This document is a Statement of Objectives (SOO) for a federal contract opportunity to replace existing water mains, valves, and fire hydrants at Goodfellow Air Force Base in Texas.
The SOO outlines the project scope to include providing all labor, materials, and associated design work to install new 8-inch and 12-inch C-900 water mains and service lines, as well as replace existing valves and fire hydrants. The work involves demolition, excavation, trenching, pipe installation, paving/concrete repairs, and landscaping restoration. Key submittal requirements include as-built drawings, test results, traffic plan, and disposal/recycling reports. The contractor is responsible for all quality control testing at no additional cost to the government.
This SOO is related to a pre-solicitation for a Simplified Acquisition of Base Engineering Requirements (SABER) Indefinite Delivery/Indefinite Quantity (IDIQ) contract at Goodfellow AFB, which is set-aside for certified 8(a) business concerns. The contract has a $750,000 guaranteed minimum and a $25 million maximum over the base period and four option years.
View the file
Other files for this federal contract opportunity
Show all 49
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE (1)
SABER
STATEMENT OF OBJECTIVES (SOO)
REPLACE WATER MAINS, AND VALVES FT. GRIFFIN/W CANBERRA
Project Opportunity # 1030148
1.0 PROJECT SCOPE: The work under this task order consists of providing all labor, tools, transportation, supplies, supervision, materials, and associated design with installing new C-900 water main lines, valves, and laterals line valves. Replace existing 6-inch, 8-inch, and 10-inch mains with 8-inch and 12-inch mains along North Ft. Lancaster Ave. from B498 to Griffin Street.
This project replaces water mains, service lines, and fire lines to improve system capacity and operations. It also replaces water valves associated with water pipelines. This project involves excavating and replacing 8 inch and 12-inch water mains and service lines, as well as valves and fire hydrants; replacing existing mains and laterals with C900 PVC pipes, tape, and tracer wire;
replacing existing valves with ductile-iron, resilient, wedge-gate valves with fusion epoxy coating; replacing existing fire hydrants with 5-1/4” dry barrels; replacing other items as required to provide a complete and usable system. Replace approx. 1,032 LF of 12-inch diameter cast iron water line with C900 pipe. Replace approx. 65 LF of 8-inch cast-iron water line with C900 pipe.
Replace approx. 45 LF of 6-inch cast iron water line with C900 pipe. Project will include replacing associated fire hydrants, gates valves and all associated connecting materials. The work includes, but is not limited to all demolition, masonry, carpentry, plumbing, electrical, and associated tasks/crafts, required to successfully complete this project’s requirements. All work shall be accomplished in strict accordance with the Goodfellow AFB SABER Contract.
2.0 MATERIAL AND DEBRIS REMOVAL: All demolished materials and debris shall become the property of the Contractor. All remaining construction material shall be disposed of/or recycled off base at the Contractor’s expense in accordance with local, state, and federal environmental laws and regulations.
3.0 CONTRACTOR FURNISHED MATERIALS: Contractor shall furnish all materials to accomplish the work described in this SOO.
4.0 PROJECT DESCRIPTION: The following requirements are intended to describe the general scope of the project, but in no way limits the contract with respect to the extent of the work indicated in the specifications or on the drawing and are subject to the terms and conditions of the contract. It is the intent and meaning of this document that the Contractor shall provide new water main and laterals lines valves, fire hydrants, bores under streets, connections, sidewalks, pavement/base course repairs, and establish turf that is complete with all items and
PAGE (2)
appurtenances necessary, reasonably incidental, or customarily included, even though each item is not specifically called out.
DEMOLITION:
General requirements
1) Contractor shall demolish existing fire hydrants.
2) Contractor shall demolish concrete sidewalk where needed.
3) Contractor shall demolish concrete/asphalt paving/curbing and base course where needed.
4) Contractor shall remove existing valves as need to install new valves.
5) Contractor shall provide asphalt/concrete saw cutting.
6) Contractor shall abandon all existing water mains in place after new water main is installed.
7) Contractor shall remove any landscaping rock and reinstall after new lines are installed.
NEW WORK:
Architectural:
1) Contractor shall provide steel road plates as needed to protect roadways before asphalt repairs.
2) Contractor shall excavate for water mains and laterals connections.
3) Contractor shall compact trench with gravel bedding per SABER Spec’s.
4) Contractor shall provide new concrete sections of sidewalk/curb and gutter were removed from excavation site.
5) Contractor shall provide new asphalt primer and tack material for road repairs.
6) Contractor shall provide new compacted base course material where needed.
7) Contractor shall provide new hot mix hot lay asphalt for street repair where needed.
8) Contractor shall cap existing cast iron line off main after new line is active.
PAGE (3)
9) Contractor shall provide new topsoil and dry seed in all areas disturbed by installing new water main.
10) Contractor shall paint all new valve covers blue.
Plumbing:
1) Contractor shall provide and install new 6”, 8” and 12” C-900 pipe.
2) Contractor shall provide and install new 6” and 8” resilient wedge-gate valves with fusion epoxy coating and cast-iron valve boxes.
3) Contractor shall provide thrust blocking at all three-way valves (as needed or required).
4) Contractor shall provide new gravel bedding for 6”, 8” and 12” C-900 water main.
5) Contractor shall provide and install new connections and valves on lateral lines.
6) Contractor shall provide boring or trenching under curbs and gutters for new water main lines.
7) Contractor shall provide steel case for pipe borings (as needed or if required).
8) Contractor shall provide new uni-lugs bolts on all C-900 fittings and valves.
9) Contractor shall provide all disinfectant on new water lines.
10) Contractor shall provide all water testing (Bac-T) and test results.
11) Contractor shall provide new water line marking tape on new water main.
12) Contractor shall provide and install 5 new 5 ¼” fire hydrants.
13) Contractor shall provide hydronic testing to new water main.
14) Contractor shall provide and install joint restraints at each connection.
15) Contractor shall provide and install new painted road marking as needed.
Electrical: N/A
5.0 SPECIAL CONSIDERATIONS: Work shall be performed in a manner to create minimum disturbance and inconvenience to the Goodfellow AFB, the personnel visiting, and working around the construction areas. As a minimum the Contractor shall give the Contracting
PAGE (4)
Officer advance 14- day notice in writing for any utility outages affecting buildings, any part of GAFB. This project can be completed in several phases so there is minimum disturbance and inconvenience to Goodfellow AFB personnel. CE can provide water outages during normal duty hour to support this water main project.
6.0 GENERAL QUALITY CONTROL TESTING: The Contractor is responsible for all quality control testing. All testing shall be performed at no additional cost to the Government.
No work requiring testing will be permitted until the required tests have been identified and approved by the Contracting Officer.
7.0 SUBMITTALS: The Contractor shall provide the following submittals to the Contracting Officer for approval/disapproval:
1) As-Built Drawings
2) C-900 pipe and connectors.
3) Concrete strength/slump tests and asphalt, prime coat, and base material.
4) DD Form 1354 Checklist
5) Water Main Valves
6) Fire Hydrants
7) Water Test Results
8) Traffic Plan
9) Compaction and asphalt results
10) C & D Disposal Reports/ Recycle in Pounds
11) Hazmat Usage
12) Bedding material
13) Base material
14) Asphalt material
END OF STATEMENT OF OBJECTIVE
PAGE (5)
| SABER |
| STATEMENT OF OBJECTIVES (SOO) |
| REPLACE WATER MAINS, AND VALVES FT. GRIFFIN/W CANBERRA |
| Project Opportunity # 1030148 |
| 1.0 PROJECT SCOPE: The work under this task order consists of providing all labor, tools, transportation, supplies, supervision, materials, and associated design with installing new C-900 water main lines, valves, and laterals line valves. Replace e... |
| 2.0 MATERIAL AND DEBRIS REMOVAL: All demolished materials and debris shall become the property of the Contractor. All remaining construction material shall be disposed of/or recycled off base at the Contractor’s expense in accordance with local, sta... |
| 3.0 CONTRACTOR FURNISHED MATERIALS: Contractor shall furnish all materials to accomplish the work described in this SOO. |
| 4.0 PROJECT DESCRIPTION: The following requirements are intended to describe the general scope of the project, but in no way limits the contract with respect to the extent of the work indicated in the specifications or on the drawing and are subjec... |
| DEMOLITION: |
| General requirements |
| NEW WORK: |
| Architectural: |
| 7.0 SUBMITTALS: The Contractor shall provide the following submittals to the Contracting Officer for approval/disapproval: |
| 1) As-Built Drawings |
| 2) C-900 pipe and connectors. |
| 3) Concrete strength/slump tests and asphalt, prime coat, and base material. |
| 4) DD Form 1354 Checklist |
END OF STATEMENT OF OBJECTIVE