Attachment 14a - Revised Seed RFP_SOO with Drawings Water Main Hornet and Scherz Amendment 0002-.pdf

PDF 569 KB Posted

Attached to
Simplified Acquisition of Base Engineering Requirements (SABER-IDIQ)
Solicitation number
FA303024R0004
Issued by

About this file

This document is a Statement of Objectives (SOO) for a federal contract opportunity to replace water mains, fire hydrants, and valves at Goodfellow Air Force Base. The work includes providing and installing new 6" C900 PVC piping, water control valves, fire hydrants, and associated connections and fittings. The project is divided into three sections, with the contractor responsible for demolition, excavation, plumbing, and site restoration work. Key requirements include submitting as-built drawings, test results, and other documentation. The overall federal contract opportunity is for a Simplified Acquisition of Base Engineering Requirements (SABER) Indefinite Delivery/Indefinite Quantity (IDIQ) contract at Goodfellow AFB, which is a set-aside for certified 8(a) business concerns. The anticipated Request for Proposal release date is around June 20, 2024 with a closing date of July 5, 2024. The contract has a guaranteed minimum of $750,000 and a maximum of $25,000,000 over the base period and four option years.

View the file

Other files

File Type Posted
Solicitation Amendment FA303024R00040003 SF 30.pdf PDF
Attachment 19 - FY24 SABER Q and A Worksheet Amendment 0003.pdf PDF
Attachment 12c - Seed RFP B705 - Bldg 121 Changing Rooms Photo Examples Amendment 0002-.pdf PDF
Attachment 3 - Section M Evaluation Factors -Revised Amendment 0002-.pdf PDF
Attachment 15a - Seed RFP_SOO with Drawings Water Main Lancaster and Canberra Amendment 0002-.pdf PDF
Attachment 13c - Seed RFP Construct Raised Crosswalks Topographical Drawing Amendment 0002-.pdf PDF
Attachment 19 - FY24 SABER Q and A Worksheet Amendment 0002.pdf PDF
Solicitation Amendment FA303024R00040002 SF 30 CO Signed.pdf PDF
Attachment 2 - Section L Instructions to Offerors -Revised Amendment 0002.pdf PDF
Attachment 20 - Site Visit Sign-In Sheet FY24 SABER FA303024R0004 27 June 2024.pdf PDF
Solicitation Amendment - FA303024R00040002.pdf PDF
Attachment 10 - PPQ GAFB FY24 SABER -Revised Amendment 0001-.pdf PDF
Attachment 12 - Seed RFP B705 Renovate Changing Rooms -Revised Amendment 0001-.pdf PDF
Attachment 11 Relevant Contracts FY24 SABER -Revised Amendment 0001-.pdf PDF
Attachment 2 - Section L Instructions to Offerors -Revised Amendment 0001-.pdf PDF
Attachment 3 - Section M Evaluation Factors -Revised Amendment 0001-.pdf PDF
Attachment 14 - Seed RFP Water Mains Hornet and Scherz -Revised Amendment 0001-.pdf PDF
Solicitation Amendment FA303024R00040001 SF 30.pdf PDF
Attachment 13 - Seed RFP Construct Raised Crosswalks -Revised Amendment 0001-.pdf PDF
Attachment 15 - Seed RFP Water Mains Lancaster and Canberra -Revised Amendment 0001-.pdf PDF
Solicitation Amendment - FA303024R00040001.pdf PDF
Attachment 3 - Section M Evaluation Factors.pdf PDF
Attachment 18 - NAF Standard Clauses -01May2024-.pdf PDF
Attachment 2 - Section L Instructions to Offerors.pdf PDF
Attachment 4 - SABERSPECS2024 - Updated 07May2024.pdf PDF
Attachment 6 - Wage Determination Building.pdf PDF
Attachment 1 - Section H Special Contract Requirements.pdf PDF
Attachment 12 - Seed RFP B705 Renovate Changing Rooms CO Sign.pdf PDF
Attachment 9 - Coefficient Pricing Worksheet.xlsx XLSX spreadsheet
Attachment 16 - (CUI) BAL Template 21 SEP 2022.docx DOCX document
Attachment 14b - Seed RFP Water Mains Hornet and Scherz Concept Drawing Water Main.pdf PDF
Attachment 14a - Seed RFP Water Mains Hornet and Scherz SOO.pdf PDF
Solicitation - FA303024R0004.pdf PDF
Attachment 11 Relevant Contracts FY24 SABER.pdf PDF
Attachment 15c - Seed RFP Water Mains Lancaster and Canberra Composite Utility Drawing.pdf PDF
Attachment 13b - Seed RFP Construct Raised Crosswalks Drawing Set.pdf PDF
Attachment 13a - Seed RFP Construct Raised Crosswalks SOO.pdf PDF
Attachment 13 - Seed RFP Construct Raised Crosswalks CO Sign.pdf PDF
Attachment 14 - Seed RFP Water Mains Hornet and Scherz CO Sign.pdf PDF
Attachment 15a - Seed RFP Water Mains Lancaster and Canberra SOO.pdf PDF
Attachment 12b - Seed RFP B705 Renovate Changing Rooms B705 Floor Plan.pdf PDF
Attachment 8 - Wage Determination Residential.pdf PDF
Attachment 12a - Seed RFP B705 Renovate Changing Rooms SOO.pdf PDF
Attachment 15b - Seed RFP Water Mains Lancaster and Canberra Water Drawing.pdf PDF
Attachment 7 - Wage Determination Heavy and Highway.pdf PDF
Attachment 15 - Seed RFP Water Mains Lancaster and Canberra CO Sign.pdf PDF
Attachment 10 - PPQ GAFB FY24 SABER.pdf PDF
Attachment 5 - CEREG_17June_2024.pdf PDF
Attachment 17 - Site Visit Itinerary and Map - FY24 SABER Goodfellow AFB.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PAGE (1)

SABER

STATEMENT OF OBJECTIVES (SOO)

REPLACE WATER MAINS, FIRE HYDRANT, AND VALVES HORNET AND SCHERZ

Project Opportunity # 1085841

1.0 PROJECT SCOPE: The work under this task order consists of providing all labor, tools, transportation, supplies, supervision, materials, and associated design with installing new

C900 water main lines. The project will include providing and installing new 6” C900 PVC piping, water control valves, fire hydrants, lateral line piping, as well as all associated connection fittings. The work includes, but is not limited to all excavation/demolition, plumbing, and associated tasks/crafts, required to successfully complete this project’s requirements. All work shall be accomplished in strict accordance with the Goodfellow AFB

SABER Contract.

* Section 1 – Beginning at the intersection of Scherz Blvd. and Kaydet St. and continuing

South to the intersection of Scherz Blvd. and Valiant St., replace the existing 6” main water line, existing lateral lines to bldgs., fire hydrants, and all associated water control valves.

Terminate new water line at the last live, water control valve.

* Section 2 – Beginning at the intersection of Scherz Blvd. and Hornet St. and continuing

West to Goodfellow Dr., replace existing 6” main water line, existing lateral lines to bldgs., fire hydrants, and all associated water control valves. This section will include the replacement of one (1), 2” lateral water service line with associated fittings to B800, and one

(1) water meter with associated piping from meter to main with fittings that service B818.

Terminate new water line at the last water control valve.

* Section 3 – At the intersection of Hornet St. and Ft. Stockton Ave. remove and replace the existing water control valves ONLY.

2.0 MATERIAL AND DEBRIS REMOVAL: All demolished materials and debris shall become the property of the Contractor. All remaining construction material shall be disposed of/or recycled off base at the Contractor’s expense in accordance with local, state, and federal environmental laws and regulations.

3.0 CONTRACTOR FURNISHED MATERIALS: Contractor shall furnish all materials to accomplish the work described in this SOO.

4.0 PROJECT DESCRIPTION: The following requirements are intended to describe the general scope of the project, but in no way limits the contract with respect to the extent of the work indicated in the specifications or on the drawing and are subject to the terms and conditions of the contract. It is the intent and meaning of this document that the Contractor shall provide new water main piping, lateral line piping, fittings, water control valves, excavation/boring/trenching, sidewalks, pavement/base course repairs, and establish turf that is

1591846821C Typewritten Text

UPDATED 07.2024

PAGE (2)

complete with all items and appurtenances necessary, reasonably incidental, or customarily included, even though each item is not specifically called out.

DEMOLITION:

General requirements

1) Contractor shall demolish existing fire hydrants.

(See ENLARGED Fire Hydrant Location Map)

2) Contractor shall demolish concrete sidewalk where and as needed.

3) Contractor shall demolish concrete/asphalt paving/curbing and base course where and as needed.

4) Contractor shall remove all existing valves to install new valves.

5) Contractor shall provide asphalt/concrete saw cutting.

6) Contractor shall abandon all existing water mains in place after new water main is installed.

7) Contractor shall demolish water meter and associated piping from meter to main that services

B818.

NEW WORK:

Civil:

1) Contractor shall provide steel road plates as needed to protect roadways before asphalt repairs.

2) Contractor shall excavate for water mains and laterals connections.

3) Contractor shall compact trench with gravel bedding per SABER Spec’s.

4) Contractor shall provide new concrete sections of sidewalk/curb and gutter were removed from excavation site.

5) Contractor shall provide new asphalt primer and tack material for road repairs.

6) Contractor shall provide new compacted base course material where needed.

7) Contractor shall provide new hot mix hot lay asphalt for street repair where needed.

PAGE (3)

8) Contractor shall cap existing cast iron line off main after new line is active.

9) Contractor shall provide new topsoil and dry seed in all areas disturbed by installing new water main.

Plumbing:

1) Contractor shall provide and install new 6” C-900 pipe.

2) Contractor shall provide and install new 6” resilient wedge-gate valves with fusion epoxy coating and cast-iron valve boxes.

3) Contractor shall provide thrust blocking at all three-way valves (as needed or required).

4) Contractor shall provide new gravel bedding for 6” C-900 water main.

5) Contractor shall provide and install new connections and valves on lateral lines.

6) Contractor shall provide boring or trenching under curbs for new water main lines.

7) Contractor shall provide steel case for pipe borings (as needed or if required).

8) Contractor shall provide new uni-lugs bolts on all C-900 fittings and valves.

9) Contractor shall provide all disinfectant on new water lines.

10) Contractor shall provide all water testing and test results.

11) Contractor shall provide new water line marking tape on new water main.

12) Contractor shall provide and install new 5 1/4 fire hydrants.

13) Contractor shall provide hydronic testing to new water main.

14) Contractor shall provide and install joint restraints at each connection.

15) Contractor shall provide and install new lateral water line from new main to building 800.

Electrical: N/A

5.0 SPECIAL CONSIDERATIONS: Work shall be performed in a manner to create minimum disturbance and inconvenience to the Goodfellow AFB, the personnel visiting, and working around the construction areas. As a minimum the Contractor shall give the Contracting

Officer advance 14- day notice in writing for any utility outages affecting buildings, any part of

GAFB. This project can be completed in several phases so there is minimum disturbance and

PAGE (4)

inconvenience to Goodfellow AFB personnel. CE can provide water outages during normal duty hour to support this water main project.

6.0 GENERAL QUALITY CONTROL TESTING: The Contractor is responsible for all quality control testing. All testing shall be performed at no additional cost to the Government.

No work requiring testing will be permitted until the required tests have been identified and approved by the Contracting Officer.

7.0 SUBMITTALS: The Contractor shall provide the following submittals to the Contracting

Officer for approval/disapproval:

1) As-Built Drawings

2) C-900 pipe and connectors

3) Concrete strength/slump tests and asphalt, prime coat, and base material.

4) DD Form 1354 Checklist

5) Water Main Valves

6) Fire Hydrants

7) Water Test Results

8) Traffic Plan

9) Compaction and asphalt results

10) C & D Disposal Reports/ Recycle in Pounds

11) Hazmat Usage

END OF STATEMENT OF OBJECTIVE

dc dc dc dc dc dc dc dc dc dc dcdcdc dc dc dc dc dc dc dc dcdc dcdc dcdc dc dc dc dc dcdc dc dc dc dc dcdc dc dc dc dc dc dc dc dc dcdc dc dc dc dc dcdcdcdcdc dc dcdc dc dc dc dc dc dc dc dcdc dc dc dc dc dc dc dc dc dc dc dcdc dcdc dcdc dc dc dc dcdc dcdc dc dcdc dc dc dc dc dc dc dcdc dcdc dc dc dc dc dcdcdcdc dc dc dcdc dc dc dc dc dc dc dc dc dc dc dc dcdc dc dc dc dc dcdcdcdcdcdcdc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dcdc dc dc dc dc dc dc dc dc dcdc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dc dcdc dc dc dc dc dc dc dc dcdc dc dc dc dc dcdc dc dc dc dcdc dc dc dc dcdc dcdc dc dcdc dc

!U

W

W

W

WW

W

W

W

W

W W

W

Ballfield #2

China BeachSwimming Pool

McGarr Swimming

Pool

SCHERZ BLVD.

FARR

O

W

STREET

H O

R N

E

T STR

EET

K

AYD

ET STR

EET

FT. STOCKTON AVENUE

FT. PHANTOM HILL AVENUE

PO

LLA

R D

S

TR

EET

G O

O D

FELLO

W

DR

IVE

TEXA

N

S

TR

EET

FT. LANCASTER AVENUE

810 745

1591846821C Typewritten Text

* Section 1 - Kaydet St to Valiant St - Replace Existing 6" DI Water Line, All Existing Water Control Valves, and Identified Fire Hydrants.

Provide and Install New 6" C900 PVC Piping, New Water Control Valves, and New Fire Hydrants.

* Section 2 - Scherz Blvd to Goodfellow Dr - Replace Existing 6" DI Water Line, All Existing Water Control Valves, and Identified Fire Hydrants.

Provide and Install New 6" C900 PVC Piping, New Water Control Valves, and New Fire Hydrants.

* Section 3 - Ft Stockton Ave / Hornet St - Remove and Replace Existing Water Control Valves ONLY, at this Location.

* NO Water Line Replacement work to be performed from Goodfellow Dr. to Ft Stockton Ave

1591846821C

Proj. #1085841 ENLARGED Water Distribution Map of Project Location

Refer to SOO for project scope

1591846821C Text Box

VALIANT ST

1591846821C Polygon

1591846821C Text Box

SECTION - 3

1591846821C Text Box

GOODFELLOW DR

1591846821C Polygon

1591846821C Text Box

SECTION - 1

1591846821C Text Box

SECTION - 1

1591846821C Text Box

SECTION - 2

1591846821C Typewritten Text NOTE: This map is being provided to identify the project location ONLY.

The Contractor shall be responsible for verifying the existing site conditions.

To include footages and quantities of equipment to be removed and replaced.

** Cloud denotes Areas of Work **

SCHERZ BLVD.

CO

UR

T

H O

R N

ET STR

EET

K

AYD

ET STR

EET

FT. STOCKTON AVENUE

FT. PHANTOM HILL AVENUE

PO

LLA

R D

STR

EETG

O O

DFE

L LOW DRIVE

TEXA

N

STR

EET

M

ITC

H

ELL STR

EET

FT. LANCASTER AVENUE

Ballfield #2

China BeachSwimmingPool

McGarr Swimming

Pool

2-1 2-51-91-5

1-1 9-5 9-2

9-3

9-1

8-6 8-7

8-5

9-6 9-4

3-6

7-4 7-5

7-10 7-7 7-67-8

7-9

8-3

8-4

8-2

7-12

8-1

3-1

8-8

8-9

703705

718719

250 25

742750

1591846821C Polygon

1591846821C Typewritten Text

* Demo\remove existing Fire Hydrants - 7-8, 7-12, 8-2, 8-3, & 8-6

* Provide and Install a New 5 1/4" Fire Hydrant at locations 7-8, 7-12, 8-2, 8-3, & 8-6

Polygon

1591846821C Polygon

1591846821C Typewritten Text

VALIANT STREET

1591846821C Typewritten Text Proj. #1085841 ENLARGED Fire Hydrant Locations

1591846821C Polygon

Polygon dc dc dc dc dc dc dc dc dc dc dc dcdc dc dc dc dc dc dcdc dc dcdc dc dcdc dc dc dc dc dc dc dc dc dc dc dc dcdcdcdc dc dc dc dc dc dc dc dc dc dcdc dc dc dcdc dc dc dc dc dc

!R

!R

!R

!R !R

!R

!R

!R

!R

!R

!R

!R

!R

BBC

VBC

VBC

BBC

Ballfield #2

China BeachSwimming Pool

McGarr Swimming

Pool

SCHERZ BLVD.

H O

R N

E

T STR

EET

K

AYD

ET STR

EET

FT. STOCKTON AVENUE

FT. PHANTOM HILL AVENUE

PO

LLA

R D

S

TR

EET

G O

O D

FELLO

W

DR

IVE

TEXA

N

S

TR

EET

M

ITC

H

ELL STR

EET

FT. LANCASTER AVENUE

4 22

810 745

1591846821C Typewritten Text Proj. #1085841 ENLARGED Natural Gas Distribution Map

NOTE: This map is being provided to identify the project location and other utilities within the project work site ONLY.

The Contractor shall be responsible for verifying the existing site conditions.

To include footages and quantities of equipment to be removed and replaced.

1591846821C Polygon

1591846821C Polygon

1591846821C Text Box

SECTION - 1

1591846821C Text Box

SECTION - 1

1591846821C Text Box

SECTION - 2

1591846821C Text Box

SECTION - 3

1591846821C Typewritten Text

** NO NATURAL GAS LINE WORK IS INVOLVED IN THIS PROJECT**

1591846821C

"i

BBC

BC

BC

BBC

T

Ballfield #2

China BeachSwimming Pool

McGarr Swimming

Pool

SCHERZ BLVD.

H O

R N

ET STR

EET

K

AYD

ET STR

E

ET

FT. STOCKTON AVENUE

FT. PHANTOM HILL AVENUE

PO

LLA

R D

STR

EE

T

G O

O D

FELLO

W

DR

IVE

TEXA

N

STR

EET

M

ITC

H E

LL STR

EET

FT. LANCASTER AVENUE

810 745

1591846821C Typewritten Text Proj. #1085841 ENLARGED Sanitary Sewer Map

1591846821C Polygon

1591846821C Polygon

1591846821C Text Box

SECTION - 1

1591846821C Text Box

SECTION - 2

1591846821C Text Box

SECTION - 1

1591846821C Text Box

SECTION - 3

1591846821C Typewritten Text

** NO SANITARY SEWER WORK IS INVOLVED IN THIS PROJECT**

1591846821C Typewritten Text NOTE: This map is being provided to identify the project location and other utilities within the project work site ONLY.

The Contractor shall be responsible for verifying the existing site conditions.

To include footages and quantities of equipment to be removed and replaced.