This request for information and subsequent contract opportunity involve logistics sustainment support for instrumentation tracking systems. The proposed contract would provide management of government-owned stock, stock acquisition, component repair, fabrication, overhauls, engineering field support, system relocation, upgrades, and engineering investigations for 26 test ranges worldwide. The support covers radar, telemetry and optics systems utilized by the Department of Defense, Department of Energy, NASA, and six foreign governments. Responding firms must be U.S.-owned and indicate business size and socioeconomic program eligibility. Complete responses were due by June 29, 2018.

Attachmnet L-05 Sample System Mod

View the file

Other files

File Type Posted
Attachment_L-11_TEP_Cost_Workbook_25_OCT_19.xlsx XLSX spreadsheet
Whats_New-Bidders_Library_V11.pdf PDF
Attachment_10a1_1-CICP_Imp_Guide_v2_7-3_App_E.xlsx XLSX spreadsheet
Solicitation_-_FA2521-20-R-0006.pdf PDF
Attachment_Section_M.pdf PDF
Attachment_Section_L.pdf PDF
Attachment_L-02_Question_Template.pdf PDF
Attachment_6_-_RESERVED_Labor_Rate_Fee_Rate_Listings.pdf PDF
Attachment_10-a__1-CICP_Imp_Guide_v2_7_3_FINAL.docx DOCX document
Attachment_1_IRSP_SOW.pdf PDF
Attachment_9_IRSP_SBPCD.pdf PDF
Attachment_L-11_TEP_Cost_Workbook.xlsx XLSX spreadsheet
Attachment_10b_-__1-PMO_Imp_Guide_v2_7_3_FINAL.docx DOCX document
Attachment_10e_-__1-Imp_Guide_Appendix_C.pdf PDF
Attachment_11_-_FY_19_CFO_Report_Template.xlsx XLSX spreadsheet
Attachment_L-05_Sample_System_Mod_Final.pdf PDF
Attachment_L-04_Overhaul_Work_Specification_Final.pdf PDF
Attachment_3_GFM_List.xlsx XLSX spreadsheet
Attachment_L-03_IRSP_Phase_Out_Plan_Final_Redacted.pdf PDF
Attachment_2_GFE_List.xlsx XLSX spreadsheet
Historic_Req_by_Range_CY_2019_Jan-Aug.xlsx XLSX spreadsheet
Attachment_L-10_Sample_Consent_Letter.pdf PDF
Attachment_L-07_Logistics_Sample_Final.pdf PDF
Attachment_10d_-_DPAS_Implementation_Schedule.pdf PDF
Historic_Req_by_Range_CY_2018.xlsx XLSX spreadsheet
Attachment_7_-_Supported_Range_System_List_.pdf PDF
Attachment_L-06_Eng_and_Obs_Sample_Final.pdf PDF
Attachment_10c_-_GFE_Data_Sheet.xlsx XLSX spreadsheet
Whats_New-Bidders_Library_V10.pdf PDF
Attachment_4_DD254.pdf PDF
Exhibit_IRSP_CDRL_Portfolio_A-M.pdf PDF
Attachment_8_-__Range_Resource_List.pdf PDF
Attachment_L-12__Compliance_Matrix.pdf PDF
Attachment_L-08_Performance_Eval_Questionnaire.pdf PDF
Attachment_L-01_Historical_Info.pdf PDF
Attachment_L-09_PEQ_Cover_Letter.pdf PDF
Attachment_5_CONOPS.pdf PDF
Whats_New-Bidders_Library_V9.pdf PDF
Master_Question_List_Updated_Oct_8,_2019.pdf PDF
Whats_New-Bidders_Library_V8.pdf PDF
Master_Question_List_1_Oct_19_Updated.pdf PDF
Whats_New-Bidders_Library_V7.pdf PDF
Whats_New-Bidders_Library_V6.pdf PDF
Master_Question_List_27_Sep_19_Updated.pdf PDF
Master_Question_List_for_FBO_RELEASE_26_Sept_19.pdf PDF
Attachment_7_Supported_Range_System_List.pdf PDF
DRAFT_RFP_FA252119RA007.pdf PDF
Attachment_L-08_Performance_Eval_Questionnaire.pdf PDF
Attachment_10c_-_GFE_Data_Sheet.xlsx XLSX spreadsheet
Attachment_L-09_PEQ_Cover_Letter.pdf PDF
Show 40 more

Latest 50 of 120 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA252119RA007

(REF) FA2521-18-R-0024

RFP Attachment L-05 25 Jan 19

SAMPLE SYSTEM MODIFICATION FOR

REMOTE CONTROL OF RADAR SYSTEM

Scope: This requirement is for the remote control of a touchscreen based AN/FPS-16 radar system over a distance of 75 miles (by water), plus an additional 200 miles (by land). The radar system is configured as follows:

Elevation over Azimuth pedestal assembly 16 foot antenna and RF feed assembly 1 MW Transmitter subsystem RF receiver subsystem VME based control subsystem Angle and servo drive subsystem Console subsystem Data processing subsystem Boresite interface subsystem Optics and camera subsystem GPS Timing subsystem

Performance Specification: The system operator shall be able to have full control of all aspects of the system using a secondary radar operator’s console at a remote location, including pre and post mission, and boresite subsystem calibration abilities. The system shall be able to be operated in a real time environment, with a time latency of no greater than 150 milliseconds. The secondary console shall have all displays that are available in the local console, with an additional video display that has, in real time, an overall view of the local radar control room.

Government Furnished Equipment: Fiber optic cable exists running 75 miles (underwater) plus 200 miles (over land). There is also a Local Area Network (LAN) already in place.

The proposal shall include a design concept, basic block diagrams and flowcharts. DRAFT