Attachment_10d_-_DPAS_Implementation_Schedule.pdf
PDF 137 KB Posted
- Attached to
- Instrumentation Range Support Program Federal contract opportunity
- Solicitation number
- FA2521-18-R-0024
About this file
This synopsis and request for information concerns a future Instrumentation Range Support Program contract to provide logistics sustainment support for instrumentation tracking systems. The support is required for 26 agencies across DoD, DoE, NASA, and six foreign governments. Services include management of government-owned stock, stock replenishment, component repair and fabrication, on-site overhauls, engineering field support, system relocation, subsystem upgrades, and engineering investigations. The applicable NAICS code is 334511 with a size standard of 1250 employees. Responses were due by June 29, 2018. Interested parties must indicate their small business designation and eligibility for set-asides. The follow-on contract will be competed to re-compete the existing IRSP contract supporting ranges worldwide.
Attachment 10d DPAS Implementation Schedule
View the file
Other files for this federal contract opportunity
Show all 50
Instrumentation Range Support Program has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IRSP-INF
Tasker Number
Task Name Duration Start Finish Predecessors
Instrumentation Range Support Program (IRSP), 363 days Fri 1/1/21 Tue 5/24/22
Implementation Starting Date 0 days Fri 1/1/21 Fri 1/1/21
Contract has been modified to include the CFO report CDRL
0 days Fri 1/1/21 Fri 1/1/21 2826
Contract has been modified to include the CICP Language for PWS
0 days Fri 1/1/21 Fri 1/1/21 2826
3 Contractor has been designated as a CICP 30 days Fri 1/1/21 Thu 2/11/21
2827, 2828
Program has requested and received the RIC/DoDAACs (EB, ED and FQ series) required
90 days Fri 2/12/21
Thu 6/17/21
5a CICP has modified its IT system to send and receive DLMS transactions
1 day Fri 1/1/21 Fri 1/1/21 2828
5b CICP has a completed and signed interface control agreement (ICA) with DAAS to interface with DPAS
90 days Fri 6/18/21
Thu 10/21/21
5c CICP has completed DLMS transaction testing with DAAS and DPAS
60 days Fri 10/22/21
Thu 1/13/22
2831, 2832
6 Data cleansing activities have been completed 240 days Fri 1/1/21 Thu 12/2/21
The appropriate valuation methodology been determined for all stock numbers
60 days Fri 1/1/21 Thu 3/25/21
7a If using the deemed cost methodology, Memorandum for the Record (MFRs) have been completed to document the methodology
180 days Fri 3/26/21
Thu 12/2/21
CICP has completed a 100% inventory of assets listed on the contract within the last 90 days
90 days Tue 6/1/21
Mon 10/4/21
9 Program office has determined its’ DPAS users 90 days Fri 1/1/21 Thu 5/6/21
FA2521-19-R-A007
(REF FA2521-18-R-0024)
RFP Attachment 10d
IRSP-INF
Program has determined which GFM-A process responsibilities it will delegate to their CICP
90 days Fri 1/1/21 Thu 5/6/21
11 CICP has determined its’ DPAS users 90 days Fri 1/1/21 Thu 5/6/21
DPAS users from the program and CICP have completed the required training to perform their roles in DPAS
30 days Fri 5/7/21 Thu 6/17/21
28382840
DPAS users from the program and CICP submitted their paperwork for DPAS accounts
30 days Fri 5/7/21 Thu 6/17/21
2838, 2840
Program/CICP completed the DPAS data conversion spreadsheet
60 days Wed 9/1/21
Tue 11/23/21
DPAS data conversion spreadsheet pass validation 10 days Wed 11/24/21
Tue 12/7/21
DPAS loads data in pre-production environment 10 days Wed 12/8/21
Tue 12/21/21
The initial data load been validated for accuracy in DPAS pre-production environment
30 days Wed 12/22/21
Tue 2/1/22
DPAS moves data to DPAS production environment
10 days Wed 2/2/22
Tue 2/15/22
Financial thresholds have been set for inventory adjustments, disposal and condemnation requests by the PMO in DPAS
30 days Wed 2/16/22
Tue 3/29/22
CICP transmits beginning balances to DPAS 10 days Wed 3/30/22
Tue 4/12/22
Beginning balances have been validated for accuracy in DPAS
30 days Wed 4/13/22
Tue 5/24/22
Stock number valuations have been validated for accuracy in DPAS
30 days Wed 4/13/22
Tue 5/24/22
19 IRSP - Go-Live Date 0 days Tue 5/24/22
Tue 5/24/22
2850, 2851
IRSP-INF
File details come from the government source that posted it. Updated .