Attachment_10d_-_DPAS_Implementation_Schedule.pdf

PDF 137 KB Posted

Attached to
Instrumentation Range Support Program Federal contract opportunity
Solicitation number
FA2521-18-R-0024
Issued by
Department of the Air Force Space Command

About this file

This synopsis and request for information concerns a future Instrumentation Range Support Program contract to provide logistics sustainment support for instrumentation tracking systems. The support is required for 26 agencies across DoD, DoE, NASA, and six foreign governments. Services include management of government-owned stock, stock replenishment, component repair and fabrication, on-site overhauls, engineering field support, system relocation, subsystem upgrades, and engineering investigations. The applicable NAICS code is 334511 with a size standard of 1250 employees. Responses were due by June 29, 2018. Interested parties must indicate their small business designation and eligibility for set-asides. The follow-on contract will be competed to re-compete the existing IRSP contract supporting ranges worldwide.

Attachment 10d DPAS Implementation Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Instrumentation Range Support Program, newest first.
File Type Posted
Attachment_L-11_TEP_Cost_Workbook_25_OCT_19.xlsx XLSX spreadsheet
Attachment_L-04_Overhaul_Work_Specification_Final.pdf PDF
Attachment_3_GFM_List.xlsx XLSX spreadsheet
Attachment_10e_-__1-Imp_Guide_Appendix_C.pdf PDF
Attachment_L-03_IRSP_Phase_Out_Plan_Final_Redacted.pdf PDF
Attachment_L-05_Sample_System_Mod_Final.pdf PDF
Attachment_10a1_1-CICP_Imp_Guide_v2_7-3_App_E.xlsx XLSX spreadsheet
Attachment_6_-_RESERVED_Labor_Rate_Fee_Rate_Listings.pdf PDF
Solicitation_-_FA2521-20-R-0006.pdf PDF
Whats_New-Bidders_Library_V9.pdf PDF
Whats_New-Bidders_Library_V8.pdf PDF
Whats_New-Bidders_Library_V6.pdf PDF
Master_Question_List_27_Sep_19_Updated.pdf PDF
Exhibit_A-P_CDRL_Portfolio.pdf PDF
Attachment_Section_M.pdf PDF
Whats_New-Bidders_Library_V5.pdf PDF
Attachment_6_-_RESERVED_Labor_Rates.pdf PDF
Attachment_Section_L.pdf PDF
Attachment_L-08_Performance_Eval_Questionnaire.pdf PDF
Attachment_L-02_Question_Template.pdf PDF
DRAFT_RFP_FA252119RA007.pdf PDF
Attachment_L-07_Logistics_Sample_6_Aug_19.pdf PDF
Attachment_8_-__Range_Resource_List.pdf PDF
Attachment_9_IRSP_SBPCD.pdf PDF
Attachment_L-12__Compliance_Matrix.pdf PDF
Attachment_L-03_IRSP_Phase_Out_Plan_Redacted.pdf PDF
Attachment_L-06_Eng_and_Obs_Sample.pdf PDF
DRAFT_Cost-Price_Workbook.xlsx XLSX spreadsheet
Whats_New-Bidders_Library_V4.pdf PDF
RFI_6_FA2521-18-R-0024.pdf PDF
Gov_Responses_to_RFI_4_Questions_Continued.pdf PDF
Draft_Section_M_6_Aug_19.pdf PDF
Attachment_L-04_Overhaul_Work_Specification.pdf PDF
Gov_Responses_to_RFI_4_Questions.pdf PDF
RFI_4_FA2521-18-R-0024.pdf PDF
Whats_New-Bidders_Library_V2.pdf PDF
Whats_New-Bidders_Library_2_July_19.pdf PDF
RFI_3_Draft_Docs-Section_L-M.zip ZIP file
RFI_3_Draft_Docs-Section_L-M.pdf PDF
Attachment_1_All_Small_Mentor_Protege_Information_Sheet.pdf PDF
Attachment_1_Industry_Day_Slide_Presentation_18_Dec_18.pdf PDF
Attachment_2_Industry_Day_Sign_In_Sheets.pdf PDF
Attach_2-_Industry_Day_Registration_Form.pdf PDF
Proposed_CLIN_Structure_11202018.pdf PDF
Attach_1_-_IRSP_III__Industry_Day_Agenda.pdf PDF
RFI_2__Past_Performance_19_Oct_18.pdf PDF
IRSP_Sources_Sought_Synopsis_15_Oct_18.docx DOCX document
Proposed_CLIN_Structure.xlsx XLSX spreadsheet
IRSP_SOW_draft.pdf PDF
RFI_06132018.pdf PDF
Show all 50

Instrumentation Range Support Program has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IRSP-INF

Tasker Number

Task Name Duration Start Finish Predecessors

Instrumentation Range Support Program (IRSP), 363 days Fri 1/1/21 Tue 5/24/22

Implementation Starting Date 0 days Fri 1/1/21 Fri 1/1/21

Contract has been modified to include the CFO report CDRL

0 days Fri 1/1/21 Fri 1/1/21 2826

Contract has been modified to include the CICP Language for PWS

0 days Fri 1/1/21 Fri 1/1/21 2826

3 Contractor has been designated as a CICP 30 days Fri 1/1/21 Thu 2/11/21

2827, 2828

Program has requested and received the RIC/DoDAACs (EB, ED and FQ series) required

90 days Fri 2/12/21

Thu 6/17/21

5a CICP has modified its IT system to send and receive DLMS transactions

1 day Fri 1/1/21 Fri 1/1/21 2828

5b CICP has a completed and signed interface control agreement (ICA) with DAAS to interface with DPAS

90 days Fri 6/18/21

Thu 10/21/21

5c CICP has completed DLMS transaction testing with DAAS and DPAS

60 days Fri 10/22/21

Thu 1/13/22

2831, 2832

6 Data cleansing activities have been completed 240 days Fri 1/1/21 Thu 12/2/21

The appropriate valuation methodology been determined for all stock numbers

60 days Fri 1/1/21 Thu 3/25/21

7a If using the deemed cost methodology, Memorandum for the Record (MFRs) have been completed to document the methodology

180 days Fri 3/26/21

Thu 12/2/21

CICP has completed a 100% inventory of assets listed on the contract within the last 90 days

90 days Tue 6/1/21

Mon 10/4/21

9 Program office has determined its’ DPAS users 90 days Fri 1/1/21 Thu 5/6/21

FA2521-19-R-A007

(REF FA2521-18-R-0024)

RFP Attachment 10d

IRSP-INF

Program has determined which GFM-A process responsibilities it will delegate to their CICP

90 days Fri 1/1/21 Thu 5/6/21

11 CICP has determined its’ DPAS users 90 days Fri 1/1/21 Thu 5/6/21

DPAS users from the program and CICP have completed the required training to perform their roles in DPAS

30 days Fri 5/7/21 Thu 6/17/21

28382840

DPAS users from the program and CICP submitted their paperwork for DPAS accounts

30 days Fri 5/7/21 Thu 6/17/21

2838, 2840

Program/CICP completed the DPAS data conversion spreadsheet

60 days Wed 9/1/21

Tue 11/23/21

DPAS data conversion spreadsheet pass validation 10 days Wed 11/24/21

Tue 12/7/21

DPAS loads data in pre-production environment 10 days Wed 12/8/21

Tue 12/21/21

The initial data load been validated for accuracy in DPAS pre-production environment

30 days Wed 12/22/21

Tue 2/1/22

DPAS moves data to DPAS production environment

10 days Wed 2/2/22

Tue 2/15/22

Financial thresholds have been set for inventory adjustments, disposal and condemnation requests by the PMO in DPAS

30 days Wed 2/16/22

Tue 3/29/22

CICP transmits beginning balances to DPAS 10 days Wed 3/30/22

Tue 4/12/22

Beginning balances have been validated for accuracy in DPAS

30 days Wed 4/13/22

Tue 5/24/22

Stock number valuations have been validated for accuracy in DPAS

30 days Wed 4/13/22

Tue 5/24/22

19 IRSP - Go-Live Date 0 days Tue 5/24/22

Tue 5/24/22

2850, 2851

IRSP-INF