Exhibit A Statement_of_Work_MAGIS-100.pdf

PDF 147 KB Posted

Attached to
MAGIS-100 Infrastructure Modifications
Solicitation number
ISD_373244_DA
Issued by

About this file

This is a Statement of Work (SOW) for construction services supporting the MAGIS-100 infrastructure modifications at Fermi National Accelerator Laboratory, effective December 9, 2025 (Revision 0). The contractor must provide all labor, materials, tools, supervision, transportation, bonding costs, safety oversight, and quality control to relocate and install utilities in the MINOS Service building shaft to accommodate the MAGIS-100 experiment installation. Specific work scope includes: demolishing and reinstalling the existing supply air duct in a new location; demolishing and relocating the sump pump discharge pipe; carefully relocating an existing stainless steel oil fill pipe with temporary supports to prevent damage; installing new chilled water taps; and installing all new utilities before demolishing existing ones to minimize downtime.

The project schedule spans 199 calendar days from Notice to Proceed, with five key milestones: (1) Day 0 – NTP issued; (2) Day 49 – Product submittals and shop drawings submitted and reviewed; (3) Day 139 – Construction complete with punch-list items remaining; (4) Day 169 – Punch-list items completed; and (5) Day 199 – Closeout documentation submitted, final invoices and retainage paid, and project complete. Major deliverables include a pre-construction meeting to confirm scope understanding, product submittals and shop drawings as specified in technical specifications, and closeout documentation upon construction completion. The work is in support of Fermi National Accelerator Laboratory's Infrastructure Services Division (ISD).

View the file

Other files

File Type Posted
Amend 03 to RFP ISD_373244_DA.pdf PDF
Exhibit T (REVISED) MAGIS-100_Drawings_Rev1.pdf PDF
SECTION 233113 (REVISED) - METAL DUCTS REV1.pdf PDF
QandA-MAGIS-100 - Fermi Responses 20260511.pdf PDF
NuMI MINOS Partial As-Built Drawings.pdf PDF
Amend 02 to RFP ISD_373244_DA.pdf PDF
Amend 01 to RFP ISD_373244_DA.pdf PDF
Pre-Proposal Sign In Sheet_MAGIS-100.pdf PDF
Exhibit Q Director Safety Letter.pdf PDF
Exhibit V FESHM_4230_CONFINED_SPACES.pdf PDF
1.0 Request for Proposal_ISD_373244_DA.pdf PDF
2.0 Price Proposal Form.pdf PDF
Exhibit F FFDG General Terms and Conditions for Construction (08.2025).pdf PDF
Exhibit I Payment Bond FL-42_FFDG.pdf PDF
Exhibit J Performance Bond FL-40_FFDG.pdf PDF
Exhibit M PUR-466_Proposal Certifications_r5_10.14.25.pdf PDF
Exhibit N SARC_Subcontractor Annual RepsCerts Rev 8.pdf PDF
Exhibit P Sample FFP Subcontract.pdf PDF
Exhibit R Fermilab Site Map-MINOS.pdf PDF
Exhibit T MAGIS-100_Drawings.pdf PDF
Exhibit C SECTION_013100_-_ESH_Requirements.pdf PDF
Exhibit D SECTION_013300_-_Submittals.pdf PDF
Exhibit H Bid Bond FL-41.pdf PDF
Exhibit K Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit L SF1413_fill-ins.pdf PDF
Exhibit S Summary of Required Solicitation Documents.pdf PDF
Exhibit W FESHM_7060_Fall_Protection_Program.pdf PDF
Business Visitor Registration Instructions and Directions-MAGIS100.pdf PDF
Exhibit B SECTION_010010_-_GENERAL_REQUIREMENTS.pdf PDF
Exhibit E SECTION_014100_-_QUALITY_REQUIREMENTS.pdf PDF
Exhibit G 2025 Construction Insurance Requirements.pdf PDF
Exhibit O General Decision IL20260008 dated 2026_0109 Mod 1.pdf PDF
Exhibit U MAGIS-100 Tech_Specs.zip ZIP file
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) – Construction Services for MAGIS-100 Infrastructure Modifications

Construction Services in support of Infrastructure Services Division (ISD)

9 December 2025 Revision 0

Subcontractor Construction Statement of Work

Fermi National Accelerator Laboratory 2

Introduction and Background

The MINOS Service building was constructed in 2002 to provide service access to the underground MINOS detector hall, absorber hall, and NuMI beamline. The MAGIS-100 experiment is currently being planned to be installed in the open shaft connecting the service building to the underground enclosure. In preparation for this experiment installation, several of the existing utilities in the shaft must be relocated by this project.

Scope

Provide all work as shown on the attached Construction Documents (drawings and technical specifications) to provide a new, fully operable plumbing/HVAC system. Furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings and technical specifications.

1. Demolish existing supply air duct and install new in location shown on plans.

2. Demolish existing sump pump discharge pipe and install new in location shown on plans.

3. Relocate existing stainless steel oil fill pipe in new location shown on plans. It is essential this piping be relocated without pinching, breaking, or otherwise damaging the piping. Temporary supports must be put in place to prevent excessive force placed on existing joints.

4. Install new chilled water taps in location shown on plans.

5. Install all new utilities prior to demolition of existing utilities to reduce utility downtime as much as possible.

Deliverables

The following is a list of major deliverable events with a description of FFDG’s expectation of the minimum requirements for accepting each deliverable.

• Pre-Construction Meeting o Confirm understanding of project scope.

• Product Submittals & Shop Drawings o Provide project Design Coordinator with product submittals and shop drawings as described in the technical specifications.

• Closeout Documentation o Provide project Design Coordinator with closeout documentation upon completion of construction as described in the technical specifications.

Schedule

The following table lists each deliverable milestone and FFDG’s expectation of scheduled calendar days for each phase. Calendar days are listed from project start. Values in parentheses are calendar days from completion of the previous listed entry.

Subcontractor Construction Statement of Work

Fermi National Accelerator Laboratory 3

Milestone Calendar

Days

Description

1 0

(+0)

Notice to Proceed (NTP). This Milestone marks the point where construction work may begin.

2 49

(+49)

All product submittals and shop drawings submitted and reviewed.

3 139

(+90)

Construction complete with punch-list items remaining.

4 169

(+30)

Punch-list items complete.

5 199

(+30)

Closeout documentation submitted. Final invoices and retainage paid.

Project complete.