Exhibit A_A003-DI-FNCL-80331A.pdf
PDF 299 KB Posted
- Attached to
- COMFRC Headquarters Technical Data Department Federal contract opportunity
- Solicitation number
- N68520-22-R-0004
About this file
This document contains a solicitation for technical data support services. The solicitation seeks proposals to award an Indefinite Delivery, Indefinite Quantity contract with Cost-Plus-Fixed-Fee and Firm-Fixed Price CLINs to provide technical data management support, technical publishing support, technical library/repository support, logistics IT support, quality assurance support, and technical data analysis to the Naval Air Systems Command Commander, Fleet Readiness Center Logistics Technical Data Department. The support is required at sites including Fleet Readiness Centers, the Naval Air Technical Data and Engineering Service Center, and Naval Air Warfare Centers. The contract would have a five year ordering period. Proposals are due by August 15, 2022 and award is anticipated for May 14, 2023. This is a 100% small business 8(a) set-aside solicitation with a NAICS code of 541330 and PSC codes of R706 and 7610.
View the file
Other files for this federal contract opportunity
Show all 50
COMFRC Headquarters Technical Data Department has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATA ITEM DESCRIPTION
Title: Funds and Man-Hours Expenditure Report
Number: DI-FNCL-80331A Approval Date: 30 OCT 2006 AMSC Number: 7618 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NS/DA02 Applicable Forms: N/A
Use/relationship:
This report provides Government visibility into contractor expenditures for labor, materials, travel and other contract charges. It tracks these expenditures against baseline values, and provides to-completion estimates.
This Data Item Description (DID) contains format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.
This DID is applicable to time and material, research and development and other contracts where use of Cost Performance Reporting (CPR) or Cost/Schedule Status Reporting (C/SSR) are not appropriate. It is not applicable on fixed-price contracts. It is acquired on a periodic basis.
It is not intended that all the requirements contained herein should be applied to every contract or program phase. Portions of this DID are subject to deletion tailoring depending on the management requirements of the solicitation/contract in which it is applied.
This DID is related to DI-A-5016, Project Planning/Actual Progress Chart (Other than fixed price contracts), and DI-FNCL-80003, Man-Hour Expenditure Chart.
This DID supersede DI-FNCL-80331.
Requirements:
1. Reference documents. None.
Downloaded from http://www.everyspec.com engineer shop, etc), burden/overhead, material/parts, travel, subsistence, fringe, DI-FNCL-80331A
2. General. The Funds and Man-Hours Expenditure Report shall contain the following data:
a. A tabular listing of funding and man-hour expenditures inclusive of the reporting period compared to original baseline values, including to-completion estimates.
b. A graphical plot of planned versus actual funding expenditures.
c. A graphical plot of planned and actual percentage of work completed.
3. Scope. Each task, job-order, sub-task, or unit of work will be separately addressed. If schedule or milestone reporting is also a reporting requirement under the contract; the breakdown of work task elements should be consistent with the reporting.
4. Format and Content. The report shall contain the following:
4.1 Funds and man-hour expenditure summary. This chart shall contain the following data elements (See Figure 1).
4.1.1 Original negotiated contract. A summary of all cost elements associated with the original negotiated contracts. This is defined as the contractor’s original cost proposal, as negotiated and accepted by the Government. It is that cost as it appears on the original contract document. Its elements shall contain the cost estimate breakdown by category (i.e., direct labor (Sr. Engineer, Jr Engineer, draftsman, General and Administration (G&A) fee, outstanding commitments, etc), as provided in the accepted proposal. Items and amounts specified in this entry shall remain constant on successive reports during the term of the contract.
4.1.2 Latest negotiated contract changes. A summary of the latest negotiated contract changes. It shall be a recapitulation of the 4.1.1 data elements reflecting all subsequent changes resulting for contract modifications. Breakdown by category shall be as provided in 4.1.1 unless altered by a contract modification. Indicated “none” if revised proposal has no effect.
4.1.3 Reporting period expenditures. Expenditure data for the current reporting period for the work task categories used in 4.1.1 or 4.1.2 (as applicable), and covering man hours, funds, and the change (new orders minus fulfilled orders) in outstanding commitments.
4.1.4 Cumulative expenditure to date. Cumulative man hour, funds and outstanding commitments expenditure data through the current reporting period for the work task categories used in 4.1.1 and 4.1.2 (as applicable). Additionally, show the cumulative costs as a percentage of the 4.1.1 of 4.1.2 costs.
4.1.5 Estimated cost-to-complete. The estimated costs required to complete the work task from the reporting date to the date of completion. This estimate shall be defined by categories as they appear in 4.1.1 of 4.1.2. All estimates shall be justified.
4.1.6 Latest cost estimate. An estimate of the final total cost at completion of the work effort. This is derived from 4.1.4 and 4.1.5. Deviations between the original contract and/or latest negotiated contract change shall be justified/explained in footnote remarks.
4.2 Funds expenditure graph. A funds expenditure graph shall be included. The graph shall be reproducible to enable periodic changes reflecting current contract funding status to be entered. The graph shall portray, on a periodic basis, the planned versus actual total dollar expenditures and the percentage of the total contract dollars that the expenditure represent (See Figure 2).
4.3 Work completed graph. A work completed graph shall be included that reflects the percentage of work completed by the contractor through the current reporting period.
The graph shall plot actual completion versus planned completion, and shall be maintained current and be fully legible and reproducible (See Figure 3).
5. END OF DI-FNCL-80331A