Exhibit A_A003-DI-FNCL-80331A.pdf

PDF 299 KB Posted

Attached to
COMFRC Headquarters Technical Data Department Federal contract opportunity
Solicitation number
N68520-22-R-0004
Issued by
Department of the Navy Naval Air Systems Command

About this file

This document contains a pre-solicitation notice and draft statement of work for technical data support services. The Naval Air Systems Command seeks proposals for an 8(a) small business set-aside contract to provide technical data management, publishing, library, IT, quality assurance, and reporting support services to the Commander Fleet Readiness Centers headquarters. Services will be performed at sites including Cherry Point, Jacksonville, San Diego, Patuxent River, North Island, China Lake, and Lakehurst. The government intends to award a single IDIQ contract with both cost-plus-fixed-fee and firm-fixed-price CLINs, as well as cost reimbursement CLINs for ODCs, covering a five year ordering period starting in June 2023. Proposals are due by August 8, 2022. Questions regarding the draft RFP must be submitted by June 17, 2022 to the identified contracting officer.

View the file

Other files for this federal contract opportunity

Other files attached to COMFRC Headquarters Technical Data Department, newest first.
File Type Posted
Updated Question and Answers RFI N6852022R0004_01Jul22.pdf PDF
Question and Answers RFI N6852022R0004.pdf PDF
ATCH P6 Proposal Cost Summary.xlsx XLSX spreadsheet
Exhibit B FFP CLINs.xlsx XLSX spreadsheet
Exhibit A_A002- Status Report - TO Level 30AUG21.pdf PDF
Exhibit A_A001-Status Report - IDIQ Level.pdf PDF
ATCH 17 CPAQ.pdf PDF
Exhibit A_A003-Funds and Man-Hours Expended Report 27SEP21.pdf PDF
ATCH 10_WD-CA- Kern 15-5603 r16.pdf PDF
ATCH 14_WD-NC- Craven 15-5781 r15.pdf PDF
ATCH 09_Technical Manual Types.pdf PDF
ATCH 05_NAVAIR 00-25-604.pdf PDF
ATCH 12_WD-FL-Duval 15-4539 r15.pdf PDF
ATCH 11_WD-CA- San Diego 15-5635 r17.pdf PDF
ATCH 15_WD-NJ- Ocean 15-4195 r16.pdf PDF
ATCH 08_SOW dated 9MAY22.pdf PDF
ATCH 07_Req_ Unit Descrip for TM-FP CLINs.pdf PDF
ATCH 03_ DD254.pdf PDF
ATCH 01_Applicable Specs and Standards.pdf PDF
N6852022R0004_TDM_Draft RFP_02Jun22.pdf PDF
ATCH 18 LOE and Ordering Rates.xlsx XLSX spreadsheet
Exhibit A_A007-Technical Documentation.pdf PDF
ATCH 09_Technical_Manual Types.pdf PDF
ATCH 13_WD-MD- St. Mary's 15-4279 r15.pdf PDF
ATCH 06_NGEN IT Requirements.pdf PDF
ATCH 04_IT Potsitions Process for KTRs.pdf PDF
ATCH 02_KTR Baseline Capability Req.pdf PDF
ATCH P7 Proposal Annual Burdened Labor.xlsx XLSX spreadsheet
Exhibit A_A001-DI-FNCL-80331.pdf PDF
Exhibit A_A006-Quality Program Plan 27SEP21.pdf PDF
Exhibit A_A005 Software Development Plan 04MAY22.pdf PDF
ATCH 16 Past Performance Matrix.pdf PDF
Exhibit A_A004-DI-MGMT-80269.pdf PDF
Exhibit A_A004-GFE Status Report 27SEP21.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATA ITEM DESCRIPTION

Title: Funds and Man-Hours Expenditure Report

Number: DI-FNCL-80331A Approval Date: 30 OCT 2006 AMSC Number: 7618 Limitation: N/A DTIC Applicable: No GIDEP Applicable: No Office of Primary Responsibility: NS/DA02 Applicable Forms: N/A

Use/relationship:

This report provides Government visibility into contractor expenditures for labor, materials, travel and other contract charges. It tracks these expenditures against baseline values, and provides to-completion estimates.

This Data Item Description (DID) contains format and content preparation instructions for the data product generated by the specific and discrete task requirement as delineated in the contract.

This DID is applicable to time and material, research and development and other contracts where use of Cost Performance Reporting (CPR) or Cost/Schedule Status Reporting (C/SSR) are not appropriate. It is not applicable on fixed-price contracts. It is acquired on a periodic basis.

It is not intended that all the requirements contained herein should be applied to every contract or program phase. Portions of this DID are subject to deletion tailoring depending on the management requirements of the solicitation/contract in which it is applied.

This DID is related to DI-A-5016, Project Planning/Actual Progress Chart (Other than fixed price contracts), and DI-FNCL-80003, Man-Hour Expenditure Chart.

This DID supersede DI-FNCL-80331.

Requirements:

1. Reference documents. None.

Downloaded from http://www.everyspec.com engineer shop, etc), burden/overhead, material/parts, travel, subsistence, fringe, DI-FNCL-80331A

2. General. The Funds and Man-Hours Expenditure Report shall contain the following data:

a. A tabular listing of funding and man-hour expenditures inclusive of the reporting period compared to original baseline values, including to-completion estimates.

b. A graphical plot of planned versus actual funding expenditures.

c. A graphical plot of planned and actual percentage of work completed.

3. Scope. Each task, job-order, sub-task, or unit of work will be separately addressed. If schedule or milestone reporting is also a reporting requirement under the contract; the breakdown of work task elements should be consistent with the reporting.

4. Format and Content. The report shall contain the following:

4.1 Funds and man-hour expenditure summary. This chart shall contain the following data elements (See Figure 1).

4.1.1 Original negotiated contract. A summary of all cost elements associated with the original negotiated contracts. This is defined as the contractor’s original cost proposal, as negotiated and accepted by the Government. It is that cost as it appears on the original contract document. Its elements shall contain the cost estimate breakdown by category (i.e., direct labor (Sr. Engineer, Jr Engineer, draftsman, General and Administration (G&A) fee, outstanding commitments, etc), as provided in the accepted proposal. Items and amounts specified in this entry shall remain constant on successive reports during the term of the contract.

4.1.2 Latest negotiated contract changes. A summary of the latest negotiated contract changes. It shall be a recapitulation of the 4.1.1 data elements reflecting all subsequent changes resulting for contract modifications. Breakdown by category shall be as provided in 4.1.1 unless altered by a contract modification. Indicated “none” if revised proposal has no effect.

4.1.3 Reporting period expenditures. Expenditure data for the current reporting period for the work task categories used in 4.1.1 or 4.1.2 (as applicable), and covering man hours, funds, and the change (new orders minus fulfilled orders) in outstanding commitments.

4.1.4 Cumulative expenditure to date. Cumulative man hour, funds and outstanding commitments expenditure data through the current reporting period for the work task categories used in 4.1.1 and 4.1.2 (as applicable). Additionally, show the cumulative costs as a percentage of the 4.1.1 of 4.1.2 costs.

4.1.5 Estimated cost-to-complete. The estimated costs required to complete the work task from the reporting date to the date of completion. This estimate shall be defined by categories as they appear in 4.1.1 of 4.1.2. All estimates shall be justified.

4.1.6 Latest cost estimate. An estimate of the final total cost at completion of the work effort. This is derived from 4.1.4 and 4.1.5. Deviations between the original contract and/or latest negotiated contract change shall be justified/explained in footnote remarks.

4.2 Funds expenditure graph. A funds expenditure graph shall be included. The graph shall be reproducible to enable periodic changes reflecting current contract funding status to be entered. The graph shall portray, on a periodic basis, the planned versus actual total dollar expenditures and the percentage of the total contract dollars that the expenditure represent (See Figure 2).

4.3 Work completed graph. A work completed graph shall be included that reflects the percentage of work completed by the contractor through the current reporting period.

The graph shall plot actual completion versus planned completion, and shall be maintained current and be fully legible and reproducible (See Figure 3).

5. END OF DI-FNCL-80331A