About this file
This is an educational exhibit document prepared by the National Cemetery Administration detailing Pre-Placed Crypts (PPCs) technology for cemetery development and expansion projects. The document, created by Andrew J. Walters, PE Specialist for Cemetery Development & Improvement Service on June 24, 2021, serves as instructional material for the Southern Arizona Veterans' Memorial Cemetery Expansion project (IFB PCS-25-061) managed by the Arizona Department of Veterans' Services. The exhibit provides comprehensive technical guidance on PPC construction methodology, including crypt fabrication, installation procedures, site preparation requirements, and operational processes. PPCs are thin-walled concrete vessels designed to hold four caskets per quad unit, with installation requiring only 22-inch excavation depth rather than traditional 8-foot burial depths. The construction sequence encompasses concrete pouring into steel forms, 24-hour form removal with 48-hour curing, placement onto prepared plots with drainage systems, numbering and finishing procedures, backfill and landscaping, and final burial operations using simplified casket lowering devices. The document emphasizes critical protection requirements for PPC fields during cemetery expansion construction activities.
The exhibit identifies significant risk factors that can compromise PPC structural integrity during construction and development phases. Heavy equipment restrictions are paramount, with water trucks, concrete trucks, fully-loaded dump trucks, and tall material piles prohibited from operating within 10 yards of active PPC fields. This restriction directly impacts construction planning and contractor operations for the cemetery expansion project, requiring careful equipment staging and site logistics management. The document functions as a prerequisite reference for bidders responding to the IFB PCS-25-061 procurement, with proposals due July 10, 2025. Contractors must demonstrate understanding of PPC installation requirements, drainage systems, landscaping integration, and equipment management protocols to ensure successful cemetery expansion while protecting pre-installed crypt infrastructure.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pre-Placed Crypts (PPCs) 101 Overall
June 24, 2021
Andrew J. Walters, PE Specialist, Cemetery Development & Improvement Service (41A2) National Cemetery Administration
Crypts 101 slides to date:
1. Overall
2. Inspection & Protection
3. On-site Buried Testing
4. Wall Repair
Why PPCs? Eliminates issues of 8-ft dig depth.
Besides only digging 22” to a crypt lid, this is avoided.
National Cemetery Administration
Pour fluid concrete into steel Quad crypt forms.
Remove forms in 24 hrs. Let cure for 48 hours.
Each Quad crypt has two lids and holds four caskets.
Crypts are thin-wall vessels (2” walls). Handle with care.
Excavate PPC fields, place fabric, install drain rock & piping.
Set crypts to ¼” tolerance onto 3-ft x 8-ft plots (typical).
Aerial View of same.
Lids lifted to paint crypt numbers on inside walls.
A proper inside-shelf fit. Shelf holds the 2nd casket if any.
Smooth inside walls and large floor drain holes.
Pea gravel installed into gaps between crypts
Backfill 22” over crypt lids with sand, dirt and topsoil.
Sod and lawn irrigation installed.
Dig is ONLY 22” to lid, remove lid & shelf. No 8-ft deep dig.
Ramps & Casket Lowering Device (CLD)
Lid replaced. Backfill graded dirt over lid and compacted.
Sod placed and headstones installed. Done.
So what can go wrong? Collapsed walls can happen if:
If water trucks get within 10 yds of the PPC field
If concrete trucks get within 10 yds of a PPC field.
If fully-loaded dump trucks get within 10 yds of PPC field If tall piles of material get within 10 yds of PPC field
END
| Pre-Placed Crypts (PPCs) 101� Overall � June 24, 2021��� |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
| Slide Number 16 |
| Slide Number 17 |
| Slide Number 18 |
| Slide Number 19 |
| Slide Number 20 |
| Slide Number 21 |
| Slide Number 22 |
File details come from the government source that posted it. Updated .