Ealy Site Logistics Plan.pdf

PDF 1 MB Posted

Attached to
WDS Bond Proposal Phase 1- Ealy, Middle School, Shoreline
Solicitation number
RFP WDS 270000000188 2
Issued by
Michigan

About this file

This is a Site Logistics Plan for the Ealy Elementary School construction project in Michigan, part of the WDS Bond Proposal Phase 1 initiative involving Ealy, Middle School, and Shoreline. The plan establishes construction logistics and scheduling for renovation work at Ealy Elementary, with a designated construction start date of April 2, 2027, and completion date of August 11, 2027, coordinating around the last day of school on June 4, 2027. The project includes initial boiler room demolition and roof replacement, with specific provisions for dumpster placement during both the initial demolition phase and the summer break period. The plan identifies the construction entrance and exit points, contractor parking areas, portable toilet locations, and the construction access route to minimize disruption to school operations. Clark Construction serves as the contractor with a field office located at the White Lake Community Center (541 E. Slocum Street, Whitehall, Michigan 49461).

The Site Logistics Plan document does not contain pricing information, set-asides, incumbent contractor details, or funding sources and amounts. The plan is primarily a visual and operational guide designed to coordinate construction activities during the academic calendar, ensuring that major demolition and roof replacement work occurs during the summer break period to minimize impact on the educational environment and facility operations.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TomBrennan Text Box Ealy Elementary Site Logistics Plan

TomBrennan Rectangle

TomBrennan PolyLine

TomBrennan Rectangle

TomBrennan Architect

DUMPSTER DURING INITIAL BOILER ROOM DEMOLITION AND ROOF REPLACEMENT

TomBrennan Architect

DUMPSTERS DURING SUMMER BREAK PERIOD

TomBrennan Text Box

LEGEND

DUMPSTERS

PORTABLE TOILETS

CONSTRUCTION ACCESS ROUTE

TomBrennan Rectangle

TomBrennan Switch

TomBrennan PolyLine

TomBrennan Polygon

TomBrennan Text Box

CONTRACTOR

PARKING

TomBrennan Text Box

CLARK CONSTRUCTION FIELD OFFICE

White Lake Community Center 541 E. Slocum St., Whitehall, MI 49461

TomBrennan Callout

CONSTRUCTION ENTRANCE/EXIT

TomBrennan Rectangle

TomBrennan Text Box

BOILER ROOM

(BASEMENT LEVEL)

TomBrennan Text Box

KEY DATES

Construction Start Date: 4/2/2027 Last Day of School: 6/4/2027 Construction End Date: 8/11/2027

TomBrennan Ellipse

TomBrennan Ellipse

TomBrennan Ellipse

TomBrennan Rectangle