39-012600 FL - Contract Modification Procedures .pdf

PDF 117 KB Posted

Attached to
2026 Maintenance Road Program - Mill and Overlay
Solicitation number
US.210836
Issued by
Washington County, Pennsylvania

View the file

Other files

File Type Posted
15-321716 FL - Manufactured Traffic-Calming Devices 1.pdf PDF
38-000101 FL - Project Title Page.pdf PDF
4-017300 FL - Execution .pdf PDF
27-C-700-Rev-1-General-Conditions-2013 .pdf PDF
3-013233 FL - Photographic Documentation .pdf PDF
6-079200 FL - Joint Sealants .pdf PDF
11-014000 FL - Quality Requirements .pdf PDF
22-C430-Bid-Bond-Penal-Sum-Form-2018 .pdf PDF
7-016000 FL - Product Requirements .pdf PDF
30-Public Works Employment Verification Form.pdf PDF
48-18532 - 2026 Paving Program Plan Set - 01.09.2026.pdf PDF
46-C-3 - Panhandle Lot - Mill and Pave.pdf PDF
29-Cover Page.pdf PDF
20-c-615 payment bond 2013 .pdf PDF
45-C-4 - Hickory Grade - Road Widening.pdf PDF
44-St list and limits VA.pdf PDF
14-C-410-Bid-Form-rev1 VA.pdf PDF
35-012900 FL - Payment Procedures-.pdf PDF
28-SFT - Standard Details - Final.pdf PDF
47-Hickory Grade Road - Line Striping Map.pdf PDF
8-017700 FL - Closeout Procedures .pdf PDF
12-Table of Contents Generated by MasterWorks .pdf PDF
19-C-200-Rev-1-Instructions-to-Bidders (pennbid 2).pdf PDF
2-2026 Bid Documents 12-31-25 VA.pdf PDF
23-c-550 notice to proceed 2013 .pdf PDF
37-010000 FL - General Requirements.pdf PDF
40-013100 FL - Project Management and Coordination.pdf PDF
25-c-940 work change directive 2013 .pdf PDF
18-c-510 (rev 1) notice of award 2013.pdf PDF
32-Non Collusion Affidavit.pdf PDF
31-coi.pdf PDF
34-004393 FL - Bid Submittal Checklist.pdf PDF
21-c-941 change order 2013 .pdf PDF
17-011000 FL - Summary.pdf PDF
43-ADDENDUM NO2 1-8-26 VA.pdf PDF
1-2026 Cape Seal Program.pdf PDF
2-013200 FL - Construction Progress Documentation .pdf PDF
13-329200 FL - Turf and Grasses .pdf PDF
16-321216 FL - Asphalt Paving .pdf PDF
33-001113 FL - Advertisement for Bids.pdf PDF
42-ADDENDUM NO1 1-6-26 VA.pdf PDF
26-c-610 performance bond 2013 .pdf PDF
41-Wages 12-30-25 VA.pdf PDF
36-012500 FL - Substitution Procedures.pdf PDF
24-C-520-Agreement-Stipulated-Price-.pdf PDF
10-012200 FL - Unit Prices PAVING .pdf PDF
1-2026 Road Maintenance Program.pdf PDF
5-013300 FL - Submittal Procedures .pdf PDF
9-015639 FL - Temporary Tree and Plant Protection .pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026 Road Maintenance Program

CONTRACT MODIFICATION PROCEDURES 012600 - 1

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

B. Related Requirements:

1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.

1.3 MINOR CHANGES IN THE WORK

A. Engineer/Owner will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by are not instructions either to stop work in progress or to execute the proposed change.

2. Within 10 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

CONTRACT MODIFICATION PROCEDURES 012600 - 2

e. Quotation Form: Use forms provided by Owner. Sample copies are included in Project Manual

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to .

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Proposal Request Form: Use forms acceptable to Owner.

1.5 ADMINISTRATIVE CHANGE ORDERS

A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.

B. Unit-Price Adjustment: See Section 012200 "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work.

1.6 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Change Proposal Request, will issue a Change Order for signatures of Owner and Contractor on form included in Project Manual.

1.7 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: may issue a Construction Change Directive on . Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

CONTRACT MODIFICATION PROCEDURES 012600 - 3

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

1.8 WORK CHANGE DIRECTIVE

A. Work Change Directive: may issue a Work Change Directive on EJCDC Document C-940.

Work Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012600

PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Engineer/Owner will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings a...
1. Work Change Proposal Requests issued by are not instructions either to stop work in progress or to execute the proposed change.
2. Within 10 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesti...
e. Quotation Form: Use forms provided by Owner. Sample copies are included in Project Manual
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to .
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesti...
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use forms acceptable to Owner.
1.5 ADMINISTRATIVE CHANGE ORDERS
A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.
B. Unit-Price Adjustment: See Section 012200 "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work.
1.6 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Change Proposal Request, will issue a Change Order for signatures of Owner and Contractor on form included in Project Manual.
1.7 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: may issue a Construction Change Directive on . Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
1.8 WORK CHANGE DIRECTIVE
A. Work Change Directive: may issue a Work Change Directive on EJCDC Document C-940. Work Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Work Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Work Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)