37-010000 FL - General Requirements.pdf

PDF 87 KB Posted

Attached to
2026 Maintenance Road Program - Mill and Overlay
Solicitation number
US.210836
Issued by
Washington County, Pennsylvania

View the file

Other files

File Type Posted
15-321716 FL - Manufactured Traffic-Calming Devices 1.pdf PDF
38-000101 FL - Project Title Page.pdf PDF
4-017300 FL - Execution .pdf PDF
27-C-700-Rev-1-General-Conditions-2013 .pdf PDF
3-013233 FL - Photographic Documentation .pdf PDF
6-079200 FL - Joint Sealants .pdf PDF
11-014000 FL - Quality Requirements .pdf PDF
22-C430-Bid-Bond-Penal-Sum-Form-2018 .pdf PDF
7-016000 FL - Product Requirements .pdf PDF
30-Public Works Employment Verification Form.pdf PDF
48-18532 - 2026 Paving Program Plan Set - 01.09.2026.pdf PDF
46-C-3 - Panhandle Lot - Mill and Pave.pdf PDF
29-Cover Page.pdf PDF
20-c-615 payment bond 2013 .pdf PDF
45-C-4 - Hickory Grade - Road Widening.pdf PDF
44-St list and limits VA.pdf PDF
14-C-410-Bid-Form-rev1 VA.pdf PDF
35-012900 FL - Payment Procedures-.pdf PDF
28-SFT - Standard Details - Final.pdf PDF
47-Hickory Grade Road - Line Striping Map.pdf PDF
8-017700 FL - Closeout Procedures .pdf PDF
12-Table of Contents Generated by MasterWorks .pdf PDF
19-C-200-Rev-1-Instructions-to-Bidders (pennbid 2).pdf PDF
2-2026 Bid Documents 12-31-25 VA.pdf PDF
23-c-550 notice to proceed 2013 .pdf PDF
40-013100 FL - Project Management and Coordination.pdf PDF
25-c-940 work change directive 2013 .pdf PDF
18-c-510 (rev 1) notice of award 2013.pdf PDF
32-Non Collusion Affidavit.pdf PDF
31-coi.pdf PDF
34-004393 FL - Bid Submittal Checklist.pdf PDF
21-c-941 change order 2013 .pdf PDF
17-011000 FL - Summary.pdf PDF
43-ADDENDUM NO2 1-8-26 VA.pdf PDF
1-2026 Cape Seal Program.pdf PDF
2-013200 FL - Construction Progress Documentation .pdf PDF
13-329200 FL - Turf and Grasses .pdf PDF
16-321216 FL - Asphalt Paving .pdf PDF
33-001113 FL - Advertisement for Bids.pdf PDF
42-ADDENDUM NO1 1-6-26 VA.pdf PDF
26-c-610 performance bond 2013 .pdf PDF
41-Wages 12-30-25 VA.pdf PDF
36-012500 FL - Substitution Procedures.pdf PDF
24-C-520-Agreement-Stipulated-Price-.pdf PDF
10-012200 FL - Unit Prices PAVING .pdf PDF
39-012600 FL - Contract Modification Procedures .pdf PDF
1-2026 Road Maintenance Program.pdf PDF
5-013300 FL - Submittal Procedures .pdf PDF
9-015639 FL - Temporary Tree and Plant Protection .pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026 Road Maintenance Program

GENERAL REQUIREMENTS 010000 - 1

SECTION 010000 - GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 PREVAILING WAGE REQUIREMENTS

A. Pennsylvania prevailing wage are required to be paid on this Contract.

1.2 INSPECTION SERVICES

A. Inspection services furnished by the Owner are predicated on an eight hour day, beginning not earlier than 7:00am and ending not later than 5:00 pm, prevailing time, for a five (5) day week, Monday through Friday. The Owner shall pay for these inspection services.

B. The Contractor may not elect to work overtime or on a Saturday without inspection unless authorized by the Engineer or Owner. All such additional costs for any inspection services rendered as stated herein shall be deducted from periodical or current estimates due the Contractor.

1.3 SUSPENSION OF WORK DUE TO NON0CONFORMANCE WITH SPECIFICATIONS

A. During the completion of the work, the Contractor’s employees must complete the contracted work in accordance with the specifications under the supervision of the foreman. If during the execution of the Contract, the Owner’s Representative determines the work is not being completed in accordance with the specifications, unnecessary damage to adjacent properties is resulting from carelessness or work outside of the limits of the project, the Owner’s Representative has been directed to administer the following procedures for resolving the matter.

B. The owner first will discuss the non-compliance of the project specifications, damage, or work beyond the project scope with the contractor’s foreman to resolve the issue. If a resolution cannot be achieved through discussion, the Owner’s Representative will mark the limit of acceptable scope of work and notify the foreman that any work beyond the defined scope of work will be at their own risk. Any work beyond the defined scope will not be a pay item and the Contractor will be responsible to pay for any damage that is outside the scope.

C. If the demarcation of the limits of work does not result in a resolution of the matter, the inspector will notify the Owner’s Engineer in Charge and/or owner of the situation and request authorization to shut the project down.

D. Once the authorization to shut the project down is given by the Owner’s Engineer in Charge and/or owner, the Inspector will issue to the foreman a Shut down Notice in which a copy will be given to the Borough and a copy forwarded to the Contractor’s office. The Shut Down notice will be very clear as to why the job is being shut down in detail and the corrections that must be completed in order for the project to proceed.

2026 Road Maintenance Program

GENERAL REQUIREMENTS 010000 - 2

E. If the foreman defies the Shut down Notice, the police will be sent to the job site to shut the job down.

F. The procedure will be reviewed at the pre-construction meeting prior to the start of work. The execution of the contract indicates the Contractor’s understanding and acceptance of this procedure.

1.4 LIQUIDATED DAMAGES

A. If the Contractor should fail to complete and have the work ready for final payment within the number of days specified in the Contract and extension thereof, liquidated damages in the amount of $500 (five hundred dollars) per calendar day will be charged against him. It is agreed that as actual damages are difficult to determine, this assessment is an equitable determination of loss to the owner and is not structured to serve as a penalty.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 010000

PART 1 - GENERAL
1.1 PREVAILING WAGE REQUIREMENTS
A. Pennsylvania prevailing wage are required to be paid on this Contract.
1.2 INSPECTION SERVICES
A. Inspection services furnished by the Owner are predicated on an eight hour day, beginning not earlier than 7:00am and ending not later than 5:00 pm, prevailing time, for a five (5) day week, Monday through Friday. The Owner shall pay for these ins...
B. The Contractor may not elect to work overtime or on a Saturday without inspection unless authorized by the Engineer or Owner. All such additional costs for any inspection services rendered as stated herein shall be deducted from periodical or curr...
1.3 SUSPENSION OF WORK DUE TO NON0CONFORMANCE WITH SPECIFICATIONS
A. During the completion of the work, the Contractor’s employees must complete the contracted work in accordance with the specifications under the supervision of the foreman. If during the execution of the Contract, the Owner’s Representative determi...
B. The owner first will discuss the non-compliance of the project specifications, damage, or work beyond the project scope with the contractor’s foreman to resolve the issue. If a resolution cannot be achieved through discussion, the Owner’s Represen...
C. If the demarcation of the limits of work does not result in a resolution of the matter, the inspector will notify the Owner’s Engineer in Charge and/or owner of the situation and request authorization to shut the project down.
D. Once the authorization to shut the project down is given by the Owner’s Engineer in Charge and/or owner, the Inspector will issue to the foreman a Shut down Notice in which a copy will be given to the Borough and a copy forwarded to the Contractor’...
E. If the foreman defies the Shut down Notice, the police will be sent to the job site to shut the job down.
F. The procedure will be reviewed at the pre-construction meeting prior to the start of work. The execution of the contract indicates the Contractor’s understanding and acceptance of this procedure.
1.4 LIQUIDATED DAMAGES
A. If the Contractor should fail to complete and have the work ready for final payment within the number of days specified in the Contract and extension thereof, liquidated damages in the amount of $500 (five hundred dollars) per calendar day will be ...
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)