2026 Road Maintenance Program
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work under separate contracts.
4. Access to site.
5. Coordination with occupants.
6. Work restrictions.
7. Specification and Drawing conventions.
8. Miscellaneous provisions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.3 PROJECT INFORMATION
A. Project Identification: 2026 Road Maintenance Program.
1. Project Location: 100 Township Drive, Bridgeville PA 15017.
B. Owner: South Fayette Twp.
1. Owner's Representative: Vitali Alexandrov, Director valexandrov@sftwp.com
C. Engineer's Consultants: Owner has retained the following design professionals Gibson-Thomas Engineering Co., Inc. who have prepared designated portions of the Contract Documents.
D. Contractor: <Insert name and contact information for Contractor> has been engaged as Contractor for this Project.
E. Construction Manager: Vitali Alexandrov.
1. Construction Manager has been engaged for this Project to serve as an advisor to Owner and to provide assistance in administering the Contract for construction between Owner
SUMMARY 011000 - 2
and Contractor, according to a separate contract between Owner and Construction Manager.
a. Construction Manager also serves as Project coordinator as defined in Section 011200 "Multiple Contract Summary."
2. Construction Manager for this Project is Project's constructor. The terms "Construction Manager" and "Contractor" are synonymous.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
Project Description: Roto-milling of +/-3” of existing pavement over an approximately 33,000 S.Y. area Base repairs on asphalt streets completed as necessary. Estimated at approximately 3,000 S.Y. Grade adjustment of 46 inlets/manholes.
Install approximately 11,000 L.F. of 6”x18” bituminous wedge curbs Placement of approximately 5,100 tons of 19mm Superpave binder Installation of approximately 200 tons of fine-graded 9.5mm Superpave SCRATCH binder.
Installation of approximately 33,000 S.Y. of Superpave fine-graded fiber reinforced wearing surface. Including full depth asphalt installation on subbase prepared by others 2050 SY.
Replacement of approximately 1500 L.F. of guide rails, Mobiliza-tion/Dimobilization/Treaffic Control.
ACCESS TO SITE
B. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.
C. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
D. Use of Site: Limit use of Project site to indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
SUMMARY 011000 - 3
1.5 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
2. Notify Owner not less than seventy two 72 hours in advance of activities that will affect Owner's operations.
B. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than <48> hours' notice to Owner of activities that will affect Owner's operations.
C. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.
1. Engineer will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.
2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy.
3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work.
4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.6 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
SUMMARY 011000 - 4
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of <7> a.m. to <5> p.m., Monday through Friday, unless otherwise indicated.
1. Weekend Hours: <9:00am-6:00pm>. With Township Approval.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify not less than two 2 days in advance of proposed utility interruptions.
2. Obtain written permission before proceeding with utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify not less than two 2 days in advance of proposed disruptive operations.
2. Obtain written permission before proceeding with disruptive operations.
E. Restricted Substances: In the Township’s Park Use of tobacco and other controlled substances is not permitted.
F. Employee Identification: identification tags for Contractor personnel working on Project site.
Require personnel to use identification tags at all times.
G. Employee Screening: Comply with Owner's requirements for screening of Contractor personnel working on Project site.
1. Maintain list of approved screened personnel with Owner's representative.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations .
SUMMARY 011000 - 5
3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section Includes: |
| 1. Project information. |
| 2. Work covered by Contract Documents. |
| 3. Work under separate contracts. |
| 4. Access to site. |
| 5. Coordination with occupants. |
| 6. Work restrictions. |
| 7. Specification and Drawing conventions. |
| 8. Miscellaneous provisions. |
| B. Related Requirements: |
| 1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities. |
| 1.3 PROJECT INFORMATION |
| A. Project Identification: 2026 Road Maintenance Program. |
| 1. Project Location: 100 Township Drive, Bridgeville PA 15017. |
| B. Owner: South Fayette Twp. |
| 1. Owner's Representative: Vitali Alexandrov, Director valexandrov@sftwp.com |
| C. Engineer's Consultants: Owner has retained the following design professionals Gibson-Thomas Engineering Co., Inc. who have prepared designated portions of the Contract Documents. |
| D. Contractor: <Insert name and contact information for Contractor> has been engaged as Contractor for this Project. |
| E. Construction Manager: Vitali Alexandrov. |
| 1. Construction Manager has been engaged for this Project to serve as an advisor to Owner and to provide assistance in administering the Contract for construction between Owner and Contractor, according to a separate contract between Owner and Constru... |
| a. Construction Manager also serves as Project coordinator as defined in Section 011200 "Multiple Contract Summary." |
2. Construction Manager for this Project is Project's constructor. The terms "Construction Manager" and "Contractor" are synonymous.
| 1.4 WORK COVERED BY CONTRACT DOCUMENTS |
| A. The Work of Project is defined by the Contract Documents and consists of the following: |
| B. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project. |
| C. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section. |
| D. Use of Site: Limit use of Project site to indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated. |
| 1. Limits: Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials. |
| a. Schedule deliveries to minimize use of driveways and entrances by construction operations. |
| b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. |
E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
| 1.5 COORDINATION WITH OCCUPANTS |
| A. Full Owner Occupancy: Owner will occupy site and building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Own... |
| 1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities ha... |
| 2. Notify Owner not less than seventy two 72 hours in advance of activities that will affect Owner's operations. |
| B. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform... |
| 1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdi... |
| 2. Provide not less than <48> hours' notice to Owner of activities that will affect Owner's operations. |
| C. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not inter... |
| 1. Engineer will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work. |
| 2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy. |
| 3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems servin... |
| 4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work. |
| 1.6 WORK RESTRICTIONS |
| A. Work Restrictions, General: Comply with restrictions on construction operations. |
| 1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction. |
| B. On-Site Work Hours: Limit work in the existing building to normal business working hours of <7> a.m. to <5> p.m., Monday through Friday, unless otherwise indicated. |
| 1. Weekend Hours: <9:00am-6:00pm>. With Township Approval. |
| C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated: |
| 1. Notify not less than two 2 days in advance of proposed utility interruptions. |
| 2. Obtain written permission before proceeding with utility interruptions. |
| D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner. |
| 1. Notify not less than two 2 days in advance of proposed disruptive operations. |
| 2. Obtain written permission before proceeding with disruptive operations. |
| E. Restricted Substances: In the Township’s Park Use of tobacco and other controlled substances is not permitted. |
| F. Employee Identification: identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times. |
| G. Employee Screening: Comply with Owner's requirements for screening of Contractor personnel working on Project site. |
| 1. Maintain list of approved screened personnel with Owner's representative. |
| 1.7 SPECIFICATION AND DRAWING CONVENTIONS |
| A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows: |
| 1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase. |
| 2. Specification requirements are to be performed by Contractor unless specifically stated otherwise. |
| B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications. |
| C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products: |
| 1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections. |
| 2. Abbreviations: Materials and products are identified by abbreviations . |
| 3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual. |
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION (Not Used) |