17-011000 FL - Summary.pdf

PDF 145 KB Posted

Attached to
2026 Maintenance Road Program - Mill and Overlay
Solicitation number
US.210836
Issued by
Washington County, Pennsylvania

View the file

Other files

File Type Posted
15-321716 FL - Manufactured Traffic-Calming Devices 1.pdf PDF
38-000101 FL - Project Title Page.pdf PDF
4-017300 FL - Execution .pdf PDF
27-C-700-Rev-1-General-Conditions-2013 .pdf PDF
3-013233 FL - Photographic Documentation .pdf PDF
6-079200 FL - Joint Sealants .pdf PDF
11-014000 FL - Quality Requirements .pdf PDF
22-C430-Bid-Bond-Penal-Sum-Form-2018 .pdf PDF
7-016000 FL - Product Requirements .pdf PDF
30-Public Works Employment Verification Form.pdf PDF
48-18532 - 2026 Paving Program Plan Set - 01.09.2026.pdf PDF
46-C-3 - Panhandle Lot - Mill and Pave.pdf PDF
29-Cover Page.pdf PDF
20-c-615 payment bond 2013 .pdf PDF
45-C-4 - Hickory Grade - Road Widening.pdf PDF
44-St list and limits VA.pdf PDF
14-C-410-Bid-Form-rev1 VA.pdf PDF
35-012900 FL - Payment Procedures-.pdf PDF
28-SFT - Standard Details - Final.pdf PDF
47-Hickory Grade Road - Line Striping Map.pdf PDF
8-017700 FL - Closeout Procedures .pdf PDF
12-Table of Contents Generated by MasterWorks .pdf PDF
19-C-200-Rev-1-Instructions-to-Bidders (pennbid 2).pdf PDF
2-2026 Bid Documents 12-31-25 VA.pdf PDF
23-c-550 notice to proceed 2013 .pdf PDF
37-010000 FL - General Requirements.pdf PDF
40-013100 FL - Project Management and Coordination.pdf PDF
25-c-940 work change directive 2013 .pdf PDF
18-c-510 (rev 1) notice of award 2013.pdf PDF
32-Non Collusion Affidavit.pdf PDF
31-coi.pdf PDF
34-004393 FL - Bid Submittal Checklist.pdf PDF
21-c-941 change order 2013 .pdf PDF
43-ADDENDUM NO2 1-8-26 VA.pdf PDF
1-2026 Cape Seal Program.pdf PDF
2-013200 FL - Construction Progress Documentation .pdf PDF
13-329200 FL - Turf and Grasses .pdf PDF
16-321216 FL - Asphalt Paving .pdf PDF
33-001113 FL - Advertisement for Bids.pdf PDF
42-ADDENDUM NO1 1-6-26 VA.pdf PDF
26-c-610 performance bond 2013 .pdf PDF
41-Wages 12-30-25 VA.pdf PDF
36-012500 FL - Substitution Procedures.pdf PDF
24-C-520-Agreement-Stipulated-Price-.pdf PDF
10-012200 FL - Unit Prices PAVING .pdf PDF
39-012600 FL - Contract Modification Procedures .pdf PDF
1-2026 Road Maintenance Program.pdf PDF
5-013300 FL - Submittal Procedures .pdf PDF
9-015639 FL - Temporary Tree and Plant Protection .pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026 Road Maintenance Program

SUMMARY 011000 - 1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Work under separate contracts.

4. Access to site.

5. Coordination with occupants.

6. Work restrictions.

7. Specification and Drawing conventions.

8. Miscellaneous provisions.

B. Related Requirements:

1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.3 PROJECT INFORMATION

A. Project Identification: 2026 Road Maintenance Program.

1. Project Location: 100 Township Drive, Bridgeville PA 15017.

B. Owner: South Fayette Twp.

1. Owner's Representative: Vitali Alexandrov, Director valexandrov@sftwp.com

C. Engineer's Consultants: Owner has retained the following design professionals Gibson-Thomas Engineering Co., Inc. who have prepared designated portions of the Contract Documents.

D. Contractor: <Insert name and contact information for Contractor> has been engaged as Contractor for this Project.

E. Construction Manager: Vitali Alexandrov.

1. Construction Manager has been engaged for this Project to serve as an advisor to Owner and to provide assistance in administering the Contract for construction between Owner

SUMMARY 011000 - 2

and Contractor, according to a separate contract between Owner and Construction Manager.

a. Construction Manager also serves as Project coordinator as defined in Section 011200 "Multiple Contract Summary."

2. Construction Manager for this Project is Project's constructor. The terms "Construction Manager" and "Contractor" are synonymous.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents and consists of the following:

Project Description: Roto-milling of +/-3” of existing pavement over an approximately 33,000 S.Y. area Base repairs on asphalt streets completed as necessary. Estimated at approximately 3,000 S.Y. Grade adjustment of 46 inlets/manholes.

Install approximately 11,000 L.F. of 6”x18” bituminous wedge curbs Placement of approximately 5,100 tons of 19mm Superpave binder Installation of approximately 200 tons of fine-graded 9.5mm Superpave SCRATCH binder.

Installation of approximately 33,000 S.Y. of Superpave fine-graded fiber reinforced wearing surface. Including full depth asphalt installation on subbase prepared by others 2050 SY.

Replacement of approximately 1500 L.F. of guide rails, Mobiliza-tion/Dimobilization/Treaffic Control.

ACCESS TO SITE

B. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.

C. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.

D. Use of Site: Limit use of Project site to indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

SUMMARY 011000 - 3

1.5 COORDINATION WITH OCCUPANTS

A. Full Owner Occupancy: Owner will occupy site and building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.

2. Notify Owner not less than seventy two 72 hours in advance of activities that will affect Owner's operations.

B. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.

1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.

2. Provide not less than <48> hours' notice to Owner of activities that will affect Owner's operations.

C. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.

1. Engineer will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.

2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy.

3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work.

4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.

1.6 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

SUMMARY 011000 - 4

B. On-Site Work Hours: Limit work in the existing building to normal business working hours of <7> a.m. to <5> p.m., Monday through Friday, unless otherwise indicated.

1. Weekend Hours: <9:00am-6:00pm>. With Township Approval.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify not less than two 2 days in advance of proposed utility interruptions.

2. Obtain written permission before proceeding with utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify not less than two 2 days in advance of proposed disruptive operations.

2. Obtain written permission before proceeding with disruptive operations.

E. Restricted Substances: In the Township’s Park Use of tobacco and other controlled substances is not permitted.

F. Employee Identification: identification tags for Contractor personnel working on Project site.

Require personnel to use identification tags at all times.

G. Employee Screening: Comply with Owner's requirements for screening of Contractor personnel working on Project site.

1. Maintain list of approved screened personnel with Owner's representative.

1.7 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.

These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations .

SUMMARY 011000 - 5

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work under separate contracts.
4. Access to site.
5. Coordination with occupants.
6. Work restrictions.
7. Specification and Drawing conventions.
8. Miscellaneous provisions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.3 PROJECT INFORMATION
A. Project Identification: 2026 Road Maintenance Program.
1. Project Location: 100 Township Drive, Bridgeville PA 15017.
B. Owner: South Fayette Twp.
1. Owner's Representative: Vitali Alexandrov, Director valexandrov@sftwp.com
C. Engineer's Consultants: Owner has retained the following design professionals Gibson-Thomas Engineering Co., Inc. who have prepared designated portions of the Contract Documents.
D. Contractor: <Insert name and contact information for Contractor> has been engaged as Contractor for this Project.
E. Construction Manager: Vitali Alexandrov.
1. Construction Manager has been engaged for this Project to serve as an advisor to Owner and to provide assistance in administering the Contract for construction between Owner and Contractor, according to a separate contract between Owner and Constru...
a. Construction Manager also serves as Project coordinator as defined in Section 011200 "Multiple Contract Summary."

2. Construction Manager for this Project is Project's constructor. The terms "Construction Manager" and "Contractor" are synonymous.

1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
B. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.
C. General: Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
D. Use of Site: Limit use of Project site to indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Driveways, Walkways and Entrances: Keep driveways and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or for storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.

1.5 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy site and building(s) during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Own...
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities ha...
2. Notify Owner not less than seventy two 72 hours in advance of activities that will affect Owner's operations.
B. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform...
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdi...
2. Provide not less than <48> hours' notice to Owner of activities that will affect Owner's operations.
C. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not inter...
1. Engineer will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.
2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited Owner occupancy.
3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems servin...
4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.6 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of <7> a.m. to <5> p.m., Monday through Friday, unless otherwise indicated.
1. Weekend Hours: <9:00am-6:00pm>. With Township Approval.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify not less than two 2 days in advance of proposed utility interruptions.
2. Obtain written permission before proceeding with utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify not less than two 2 days in advance of proposed disruptive operations.
2. Obtain written permission before proceeding with disruptive operations.
E. Restricted Substances: In the Township’s Park Use of tobacco and other controlled substances is not permitted.
F. Employee Identification: identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
G. Employee Screening: Comply with Owner's requirements for screening of Contractor personnel working on Project site.
1. Maintain list of approved screened personnel with Owner's representative.
1.7 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations .
3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)