35-012900 FL - Payment Procedures-.pdf

PDF 95 KB Posted

Attached to
2026 Maintenance Road Program - Mill and Overlay
Solicitation number
US.210836
Issued by
Washington County, Pennsylvania

View the file

Other files

File Type Posted
15-321716 FL - Manufactured Traffic-Calming Devices 1.pdf PDF
38-000101 FL - Project Title Page.pdf PDF
4-017300 FL - Execution .pdf PDF
27-C-700-Rev-1-General-Conditions-2013 .pdf PDF
3-013233 FL - Photographic Documentation .pdf PDF
6-079200 FL - Joint Sealants .pdf PDF
11-014000 FL - Quality Requirements .pdf PDF
22-C430-Bid-Bond-Penal-Sum-Form-2018 .pdf PDF
7-016000 FL - Product Requirements .pdf PDF
30-Public Works Employment Verification Form.pdf PDF
48-18532 - 2026 Paving Program Plan Set - 01.09.2026.pdf PDF
46-C-3 - Panhandle Lot - Mill and Pave.pdf PDF
29-Cover Page.pdf PDF
20-c-615 payment bond 2013 .pdf PDF
45-C-4 - Hickory Grade - Road Widening.pdf PDF
44-St list and limits VA.pdf PDF
14-C-410-Bid-Form-rev1 VA.pdf PDF
28-SFT - Standard Details - Final.pdf PDF
47-Hickory Grade Road - Line Striping Map.pdf PDF
8-017700 FL - Closeout Procedures .pdf PDF
12-Table of Contents Generated by MasterWorks .pdf PDF
19-C-200-Rev-1-Instructions-to-Bidders (pennbid 2).pdf PDF
2-2026 Bid Documents 12-31-25 VA.pdf PDF
23-c-550 notice to proceed 2013 .pdf PDF
37-010000 FL - General Requirements.pdf PDF
40-013100 FL - Project Management and Coordination.pdf PDF
25-c-940 work change directive 2013 .pdf PDF
18-c-510 (rev 1) notice of award 2013.pdf PDF
32-Non Collusion Affidavit.pdf PDF
31-coi.pdf PDF
34-004393 FL - Bid Submittal Checklist.pdf PDF
21-c-941 change order 2013 .pdf PDF
17-011000 FL - Summary.pdf PDF
43-ADDENDUM NO2 1-8-26 VA.pdf PDF
1-2026 Cape Seal Program.pdf PDF
2-013200 FL - Construction Progress Documentation .pdf PDF
13-329200 FL - Turf and Grasses .pdf PDF
16-321216 FL - Asphalt Paving .pdf PDF
33-001113 FL - Advertisement for Bids.pdf PDF
42-ADDENDUM NO1 1-6-26 VA.pdf PDF
26-c-610 performance bond 2013 .pdf PDF
41-Wages 12-30-25 VA.pdf PDF
36-012500 FL - Substitution Procedures.pdf PDF
24-C-520-Agreement-Stipulated-Price-.pdf PDF
10-012200 FL - Unit Prices PAVING .pdf PDF
39-012600 FL - Contract Modification Procedures .pdf PDF
1-2026 Road Maintenance Program.pdf PDF
5-013300 FL - Submittal Procedures .pdf PDF
9-015639 FL - Temporary Tree and Plant Protection .pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026 Road Maintenance Program

PAYMENT PROCEDURES 012900 - 1

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Requirements:

1. Section 012200 "Unit Prices" for administrative requirements governing the use of unit prices.

2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.

3. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Engineer/Owner and paid for by Owner.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Payment Application Times: Submit Application for Payment to Engineer/Owner by the 30th of the month. The period covered by each Application for Payment is one month, ending on the Last Friday of the Month.

1. Submit draft copy of Application for Payment seven 7 days prior to due date for review by Engineer/Owner.

D. Application for Payment Forms: Use Brentwood Borough Pay Application as form for Applications for Payment.

1. Other Application for Payment forms proposed by the Contractor shall be acceptable to and Owner. Submit forms for approval with initial submittal of schedule of values.

PAYMENT PROCEDURES 012900 - 2

E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule.

Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

F. Transmittal: Submit three 3 signed and notarized original copies of each Application for Payment to the Owner by a method ensuring receipt. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Contractor's construction schedule (preliminary if not final).

3. Combined Contractor's construction schedule (preliminary if not final) incorporating

Work of multiple contracts, with indication of acceptance of schedule by each Contractor.

4. Products list (preliminary if not final).

5. Sustainable design action plans, including preliminary project materials cost data.

6. Schedule of unit prices.

7. Submittal schedule (preliminary if not final).

8. List of Contractor's staff assignments.

9. List of Contractor's principal consultants.

10. Copies of building permits.

11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

12. Initial progress report.

13. Report of preconstruction conference.

14. Certificates of insurance and insurance policies.

15. Performance and payment bonds.

16. Data needed to acquire Owner's insurance.

H. Application for Payment at Substantial Completion: After Engineer/Owner issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

PAYMENT PROCEDURES 012900 - 3

I. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. Evidence that claims have been settled.

5. Final liquidated damages settlement statement.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 012900

PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Related Requirements:
1. Section 012200 "Unit Prices" for administrative requirements governing the use of unit prices.
2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
3. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.
1.3 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Engineer/Owner and paid for by Owner.
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment Application Times: Submit Application for Payment to Engineer/Owner by the 30th of the month. The period covered by each Application for Payment is one month, ending on the Last Friday of the Month.
1. Submit draft copy of Application for Payment seven 7 days prior to due date for review by Engineer/Owner.
D. Application for Payment Forms: Use Brentwood Borough Pay Application as form for Applications for Payment.
1. Other Application for Payment forms proposed by the Contractor shall be acceptable to and Owner. Submit forms for approval with initial submittal of schedule of values.
E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.
F. Transmittal: Submit three 3 signed and notarized original copies of each Application for Payment to the Owner by a method ensuring receipt. One copy shall include waivers of lien and similar attachments if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Contractor's construction schedule (preliminary if not final).
3. Combined Contractor's construction schedule (preliminary if not final) incorporating Work of multiple contracts, with indication of acceptance of schedule by each Contractor.
4. Products list (preliminary if not final).
5. Sustainable design action plans, including preliminary project materials cost data.
6. Schedule of unit prices.
7. Submittal schedule (preliminary if not final).
8. List of Contractor's staff assignments.
9. List of Contractor's principal consultants.
10. Copies of building permits.
11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
12. Initial progress report.
13. Report of preconstruction conference.
14. Certificates of insurance and insurance policies.
15. Performance and payment bonds.
16. Data needed to acquire Owner's insurance.
H. Application for Payment at Substantial Completion: After Engineer/Owner issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
I. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. Evidence that claims have been settled.
5. Final liquidated damages settlement statement.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)