2026 Road Maintenance Program
PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Related Requirements:
1. Section 012200 "Unit Prices" for administrative requirements governing the use of unit prices.
2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
3. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.
1.3 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Engineer/Owner and paid for by Owner.
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment Application Times: Submit Application for Payment to Engineer/Owner by the 30th of the month. The period covered by each Application for Payment is one month, ending on the Last Friday of the Month.
1. Submit draft copy of Application for Payment seven 7 days prior to due date for review by Engineer/Owner.
D. Application for Payment Forms: Use Brentwood Borough Pay Application as form for Applications for Payment.
1. Other Application for Payment forms proposed by the Contractor shall be acceptable to and Owner. Submit forms for approval with initial submittal of schedule of values.
PAYMENT PROCEDURES 012900 - 2
E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule.
Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.
F. Transmittal: Submit three 3 signed and notarized original copies of each Application for Payment to the Owner by a method ensuring receipt. One copy shall include waivers of lien and similar attachments if required.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Contractor's construction schedule (preliminary if not final).
3. Combined Contractor's construction schedule (preliminary if not final) incorporating
Work of multiple contracts, with indication of acceptance of schedule by each Contractor.
4. Products list (preliminary if not final).
5. Sustainable design action plans, including preliminary project materials cost data.
6. Schedule of unit prices.
7. Submittal schedule (preliminary if not final).
8. List of Contractor's staff assignments.
9. List of Contractor's principal consultants.
10. Copies of building permits.
11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
12. Initial progress report.
13. Report of preconstruction conference.
14. Certificates of insurance and insurance policies.
15. Performance and payment bonds.
16. Data needed to acquire Owner's insurance.
H. Application for Payment at Substantial Completion: After Engineer/Owner issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
PAYMENT PROCEDURES 012900 - 3
I. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. Evidence that claims have been settled.
5. Final liquidated damages settlement statement.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 012900
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment. |
| B. Related Requirements: |
| 1. Section 012200 "Unit Prices" for administrative requirements governing the use of unit prices. |
| 2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract. |
| 3. Section 013200 "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule. |
| 1.3 APPLICATIONS FOR PAYMENT |
| A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Engineer/Owner and paid for by Owner. |
| B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement. |
| C. Payment Application Times: Submit Application for Payment to Engineer/Owner by the 30th of the month. The period covered by each Application for Payment is one month, ending on the Last Friday of the Month. |
| 1. Submit draft copy of Application for Payment seven 7 days prior to due date for review by Engineer/Owner. |
| D. Application for Payment Forms: Use Brentwood Borough Pay Application as form for Applications for Payment. |
| 1. Other Application for Payment forms proposed by the Contractor shall be acceptable to and Owner. Submit forms for approval with initial submittal of schedule of values. |
| E. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. will return incomplete applications without action. |
| 1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made. |
| 2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment. |
| 3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application. |
| 4. Indicate separate amounts for work being carried out under Owner-requested project acceleration. |
| F. Transmittal: Submit three 3 signed and notarized original copies of each Application for Payment to the Owner by a method ensuring receipt. One copy shall include waivers of lien and similar attachments if required. |
| 1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application. |
| G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following: |
| 1. List of subcontractors. |
| 2. Contractor's construction schedule (preliminary if not final). |
| 3. Combined Contractor's construction schedule (preliminary if not final) incorporating Work of multiple contracts, with indication of acceptance of schedule by each Contractor. |
| 4. Products list (preliminary if not final). |
| 5. Sustainable design action plans, including preliminary project materials cost data. |
| 6. Schedule of unit prices. |
| 7. Submittal schedule (preliminary if not final). |
| 8. List of Contractor's staff assignments. |
| 9. List of Contractor's principal consultants. |
| 10. Copies of building permits. |
| 11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work. |
| 12. Initial progress report. |
| 13. Report of preconstruction conference. |
| 14. Certificates of insurance and insurance policies. |
| 15. Performance and payment bonds. |
| 16. Data needed to acquire Owner's insurance. |
| H. Application for Payment at Substantial Completion: After Engineer/Owner issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete. |
| 1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum. |
| 2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work. |
| I. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following: |
| 1. Evidence of completion of Project closeout requirements. |
| 2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid. |
| 3. Updated final statement, accounting for final changes to the Contract Sum. |
| 4. Evidence that claims have been settled. |
| 5. Final liquidated damages settlement statement. |
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION (Not Used) |
File details come from the government source that posted it. Updated .