2026 Road Maintenance Program
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Project meetings.
B. Related Requirements:
1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule.
2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. RFI: Request for Information. Request from Owner, Engineer, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office, and in prominent location in each built facility. Keep list current at all times.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Coordination: Each contractor shall cooperate with Project coordinator who shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work. Each contractor shall coordinate its own operations with operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and scheduled activities of other contractors and direction of Project coordinator to avoid conflicts and to ensure orderly progress of the Work.
Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.6 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings.
Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade-specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.
d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.
e. Indicate required installation sequences.
f. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements.
Provide alternative sketches to Engineer indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.
2. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 013300 "Submittal Procedures."
B. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Preparation Format: PDF Version 10, operating in Microsoft Windows operating system.
3. File Submittal Format: Submit or post coordination drawing files using PDF format.
4. BIM File Incorporation: Construction Manager will incorporate Contractor's coordination drawing files into BIM established for Project.
a. Construction Manager will perform component conflict analysis as part of preparation of coordination drawings. Resolve component conflicts prior to
PROJECT MANAGEMENT AND COORDINATION 013100 - 4
submittal. Indicate where conflict resolution requires modification of design requirements by Owner/Engineer.
1.7 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Engineer will return without response those RFIs submitted to Engineer by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Engineer/Owner and Construction Manager.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms:
1. Attachments shall be electronic files in PDF format.
D. Construction Manager's Action: Construction Manager will review each RFI, determine action required, and respond. Allow seven (7) working days for Engineer's response for each RFI. RFIs received by Engineer or Construction Manager after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
PROJECT MANAGEMENT AND COORDINATION 013100 - 5
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Engineer's action may include a request for additional information, in which case Engineer's time for response will date from time of receipt by Engineer or Construction Manager of additional information.
3. Engineer's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Engineer and Construction Manager in writing within 10 days of receipt of the RFI response.
E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.
Submit log weekly 1.
1. Project name.
2. Name and address of Contractor.
3. Name and address of Engineer and Construction Manager.
4. RFI number including RFIs that were returned without action or withdrawn.
5. RFI description.
6. Date the RFI was submitted.
7. Date Engineer's and Construction Manager's response was received.
8. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.
F. On receipt of Engineer's and Construction Manager's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect and Construction Manager within seven 7 days if Contractor disagrees with response.
1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Engineer's Data Files Not Available: Engineer will not provide Engineer's BIM model CAD drawing digital data files for Contractor's use during construction.
B. PDF Document Preparation: Where PDFs are required to be submitted to Engineer, prepare as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
PROJECT MANAGEMENT AND COORDINATION 013100 - 6
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
1.9 PROJECT MEETINGS
A. General: Construction Manager will schedule and conduct meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Engineer of scheduled meeting dates and times a minimum of 5 working days prior to meeting.
2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.
3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner, Construction Manager, and Engineer, within three <3 days of the meeting.
B. Preconstruction Conference: Construction Manager will schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Engineer, but no later than 15 days after execution of the Agreement.
1. Attendees: Authorized representatives of Owner, Construction Manager, Engineer, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Phasing.
d. Critical work sequencing and long lead items.
e. Designation of key personnel and their duties.
f. Lines of communications.
g. Procedures for processing field decisions and Change Orders.
h. Procedures for RFIs.
i. Procedures for testing and inspecting.
j. Procedures for processing Applications for Payment.
k. Distribution of the Contract Documents.
l. Submittal procedures.
m. Preparation of Record Documents.
n. Use of the premises
o. Work restrictions.
p. Working hours.
q. Owner's occupancy requirements.
r. Responsibility for temporary facilities and controls.
s. Procedures for moisture and mold control.
t. Procedures for disruptions and shutdowns.
u. Construction waste management and recycling.
v. Parking availability.
w. Office, work, and storage areas.
PROJECT MANAGEMENT AND COORDINATION 013100 - 7
x. Equipment deliveries and priorities.
y. First aid.
z. Security.
aa. Progress cleaning.
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
C. Project Closeout Conference: Construction Manager will schedule and conduct a project closeout conference, at a time convenient to Owner and Architect, but no later than 90 ninety days prior to the scheduled date of Substantial Completion.
1. Conduct the conference to review requirements and responsibilities related to Project closeout.
2. Attendees: Authorized representatives of Owner, Construction Manager, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:
a. Preparation of Record Documents.
b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.
c. Procedures for completing and archiving web-based Project software site data files.
d. Submittal of written warranties.
e. Requirements for preparing operations and maintenance data.
f. Requirements for delivery of material samples, attic stock, and spare parts.
g. Requirements for demonstration and training.
h. Preparation of Contractor's punch list.
i. Procedures for processing Applications for Payment at Substantial Completion and for final payment.
j. Submittal procedures.
k. Coordination of separate contracts.
l. Owner's partial occupancy requirements.
m. Installation of Owner's furniture, fixtures, and equipment.
n. Responsibility for removing temporary facilities and controls.
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
D. Progress Meetings: Construction Manager will conduct progress meetings at weekly intervals.
1. Coordinate dates of meetings with preparation of payment requests.
2. Attendees: In addition to representatives of Owner, Construction Manager, and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
PROJECT MANAGEMENT AND COORDINATION 013100 - 8
3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Contractor's Construction Schedule: Review progress since the last meeting.
Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
1) Review schedule for next period.
b. Review present and future needs of each entity present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Resolution of BIM component conflicts.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site use.
9) Temporary facilities and controls.
10) Progress cleaning.
11) Quality and work standards.
12) Status of correction of deficient items.
13) Field observations.
14) Status of RFIs.
15) Status of Proposal Requests.
16) Pending changes.
17) Status of Change Orders.
18) Pending claims and disputes.
19) Documentation of information for payment requests.
4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.
a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.
E. Coordination Meetings: Construction Manager will conduct Project coordination meetings at weekly intervals. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and preinstallation conferences.
1. Attendees: In addition to representatives of Owner, Construction Manager, and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meetings shall be familiar with Project and authorized to conclude matters relating to the Work.
PROJECT MANAGEMENT AND COORDINATION 013100 - 9
2. Agenda: Review and correct or approve minutes of the previous coordination meeting.
Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.
a. Combined Contractor's Construction Schedule: Review progress since the last coordination meeting. Determine whether each contract is on time, ahead of schedule, or behind schedule, in relation to combined Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.
b. Schedule Updating: Revise combined Contractor's construction schedule after each coordination meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting.
c. Review present and future needs of each contractor present, including the following:
1) Interface requirements.
2) Sequence of operations.
3) Resolution of BIM component conflicts.
4) Status of submittals.
5) Deliveries.
6) Off-site fabrication.
7) Access.
8) Site use.
9) Temporary facilities and controls.
10) Work hours.
11) Hazards and risks.
12) Progress cleaning.
13) Quality and work standards.
14) Status of RFIs.
15) Proposal Requests.
16) Change Orders.
17) Pending changes.
3. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013100
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: |
| 1. General coordination procedures. |
| 2. Coordination drawings. |
| 3. RFIs. |
| 4. Digital project management procedures. |
| 5. Project meetings. |
| B. Related Requirements: |
| 1. Section 013200 "Construction Progress Documentation" for preparing and submitting Contractor's construction schedule. |
| 2. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points. |
| 3. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract. |
| 1.3 DEFINITIONS |
| A. RFI: Request for Information. Request from Owner, Engineer, or Contractor seeking information required by or clarifications of the Contract Documents. |
| 1.4 INFORMATIONAL SUBMITTALS |
| A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabula... |
| 1. Name, address, telephone number, and email address of entity performing subcontract or supplying products. |
| 2. Number and title of related Specification Section(s) covered by subcontract. |
| 3. Drawing number and detail references, as appropriate, covered by subcontract. |
| B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilit... |
| 1. Post copies of list in project meeting room, in temporary field office, and in prominent location in each built facility. Keep list current at all times. |
| 1.5 GENERAL COORDINATION PROCEDURES |
| A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depe... |
| 1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation. |
| 2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair. |
| 3. Make adequate provisions to accommodate items scheduled for later installation. |
| B. Coordination: Each contractor shall cooperate with Project coordinator who shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work. Each contrac... |
| 1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation. |
| 2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair. |
| 3. Make adequate provisions to accommodate items scheduled for later installation. |
| C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings. |
| 1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required. |
| D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and scheduled activities of other contractors and direction of Project coordinator to avoid conflicts and to ensure... |
| 1. Preparation of Contractor's construction schedule. |
| 2. Preparation of the schedule of values. |
| 3. Installation and removal of temporary facilities and controls. |
| 4. Delivery and processing of submittals. |
| 5. Progress meetings. |
| 6. Preinstallation conferences. |
| 7. Project closeout activities. |
| 8. Startup and adjustment of systems. |
| 1.6 COORDINATION DRAWINGS |
| A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, and additionally where installation is not completely indicated on Shop Drawings, where limited space availability necessitates coordina... |
| 1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable: |
| a. Use applicable Drawings as a basis for preparation of coordination drawings. Prepare sections, elevations, and details as needed to describe relationship of various systems and components. |
| b. Coordinate the addition of trade-specific information to coordination drawings in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review. |
| c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation. |
| d. Show location and size of access doors required for access to concealed dampers, valves, and other controls. |
| e. Indicate required installation sequences. |
| f. Indicate dimensions shown on Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternative sketches to Engineer indicating proposed resolution of such conflicts... |
2. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 013300 "Submittal Procedures."
| B. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements: |
| 1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings. |
| 2. File Preparation Format: PDF Version 10, operating in Microsoft Windows operating system. |
| 3. File Submittal Format: Submit or post coordination drawing files using PDF format. |
| 4. BIM File Incorporation: Construction Manager will incorporate Contractor's coordination drawing files into BIM established for Project. |
| a. Construction Manager will perform component conflict analysis as part of preparation of coordination drawings. Resolve component conflicts prior to submittal. Indicate where conflict resolution requires modification of design requirements by Owner... |
| 1.7 REQUEST FOR INFORMATION (RFI) |
| A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified. |
| 1. Engineer will return without response those RFIs submitted to Engineer by other entities controlled by Contractor. |
| 2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors. |
| B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following: |
| 1. Project name. |
| 2. Project number. |
| 3. Date. |
| 4. Name of Contractor. |
| 5. Name of Engineer/Owner and Construction Manager. |
| 6. RFI number, numbered sequentially. |
| 7. RFI subject. |
| 8. Specification Section number and title and related paragraphs, as appropriate. |
| 9. Drawing number and detail references, as appropriate. |
| 10. Field dimensions and conditions, as appropriate. |
| 11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI. |
| 12. Contractor's signature. |
| 13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation. |
| a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches. |
| C. RFI Forms: |
| 1. Attachments shall be electronic files in PDF format. |
| D. Construction Manager's Action: Construction Manager will review each RFI, determine action required, and respond. Allow seven (7) working days for Engineer's response for each RFI. RFIs received by Engineer or Construction Manager after 1:00 p.m. w... |
| 1. The following Contractor-generated RFIs will be returned without action: |
| a. Requests for approval of submittals. |
| b. Requests for approval of substitutions. |
| c. Requests for approval of Contractor's means and methods. |
| d. Requests for coordination information already indicated in the Contract Documents. |
| e. Requests for adjustments in the Contract Time or the Contract Sum. |
| f. Requests for interpretation of Architect's actions on submittals. |
| g. Incomplete RFIs or inaccurately prepared RFIs. |
| 2. Engineer's action may include a request for additional information, in which case Engineer's time for response will date from time of receipt by Engineer or Construction Manager of additional information. |
| 3. Engineer's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures." |
| a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Engineer and Construction Manager in writing within 10 days of receipt of the RFI response. |
| E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly 1. |
| 1. Project name. |
| 2. Name and address of Contractor. |
| 3. Name and address of Engineer and Construction Manager. |
| 4. RFI number including RFIs that were returned without action or withdrawn. |
| 5. RFI description. |
| 6. Date the RFI was submitted. |
| 7. Date Engineer's and Construction Manager's response was received. |
| 8. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate. |
F. On receipt of Engineer's and Construction Manager's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect and Construction Manager within seven 7 days if Contractor disagree...
| 1.8 DIGITAL PROJECT MANAGEMENT PROCEDURES |
| A. Engineer's Data Files Not Available: Engineer will not provide Engineer's BIM model CAD drawing digital data files for Contractor's use during construction. |
| B. PDF Document Preparation: Where PDFs are required to be submitted to Engineer, prepare as follows: |
| 1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item. |
| 2. Name file with submittal number or other unique identifier, including revision identifier. |
| 3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated. |
| 1.9 PROJECT MEETINGS |
| A. General: Construction Manager will schedule and conduct meetings and conferences at Project site unless otherwise indicated. |
| 1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Engineer of scheduled meeting dates and times a minimum of 5 working days prior to meeting. |
| 2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees. |
| 3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner, Construction Manager, and Engineer, within three <3 days of the m... |
| B. Preconstruction Conference: Construction Manager will schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Engineer, but no later than 15 days after execution of the Agreement. |
| 1. Attendees: Authorized representatives of Owner, Construction Manager, Engineer, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the ... |
| 2. Agenda: Discuss items of significance that could affect progress, including the following: |
| a. Responsibilities and personnel assignments. |
| b. Tentative construction schedule. |
| c. Phasing. |
| d. Critical work sequencing and long lead items. |
| e. Designation of key personnel and their duties. |
| f. Lines of communications. |
| g. Procedures for processing field decisions and Change Orders. |
| h. Procedures for RFIs. |
| i. Procedures for testing and inspecting. |
| j. Procedures for processing Applications for Payment. |
| k. Distribution of the Contract Documents. |
| l. Submittal procedures. |
| m. Preparation of Record Documents. |
| n. Use of the premises |
| o. Work restrictions. |
| p. Working hours. |
| q. Owner's occupancy requirements. |
| r. Responsibility for temporary facilities and controls. |
| s. Procedures for moisture and mold control. |
| t. Procedures for disruptions and shutdowns. |
| u. Construction waste management and recycling. |
| v. Parking availability. |
| w. Office, work, and storage areas. |
| x. Equipment deliveries and priorities. |
| y. First aid. |
| z. Security. |
| aa. Progress cleaning. |
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
| C. Project Closeout Conference: Construction Manager will schedule and conduct a project closeout conference, at a time convenient to Owner and Architect, but no later than 90 ninety days prior to the scheduled date of Substantial Completion. |
| 1. Conduct the conference to review requirements and responsibilities related to Project closeout. |
| 2. Attendees: Authorized representatives of Owner, Construction Manager, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall... |
| 3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following: |
| a. Preparation of Record Documents. |
| b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance. |
| c. Procedures for completing and archiving web-based Project software site data files. |
| d. Submittal of written warranties. |
| e. Requirements for preparing operations and maintenance data. |
| f. Requirements for delivery of material samples, attic stock, and spare parts. |
| g. Requirements for demonstration and training. |
| h. Preparation of Contractor's punch list. |
| i. Procedures for processing Applications for Payment at Substantial Completion and for final payment. |
| j. Submittal procedures. |
| k. Coordination of separate contracts. |
| l. Owner's partial occupancy requirements. |
| m. Installation of Owner's furniture, fixtures, and equipment. |
| n. Responsibility for removing temporary facilities and controls. |
4. Minutes: Entity conducting meeting will record and distribute meeting minutes.
| D. Progress Meetings: Construction Manager will conduct progress meetings at weekly intervals. |
| 1. Coordinate dates of meetings with preparation of payment requests. |
| 2. Attendees: In addition to representatives of Owner, Construction Manager, and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activ... |
| 3. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project. |
| a. Contractor's Construction Schedule: Review progress since the last meeting. Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind sche... |
| 1) Review schedule for next period. |
| b. Review present and future needs of each entity present, including the following: |
| 1) Interface requirements. |
| 2) Sequence of operations. |
| 3) Resolution of BIM component conflicts. |
| 4) Status of submittals. |
| 5) Deliveries. |
| 6) Off-site fabrication. |
| 7) Access. |
| 8) Site use. |
| 9) Temporary facilities and controls. |
| 10) Progress cleaning. |
| 11) Quality and work standards. |
| 12) Status of correction of deficient items. |
| 13) Field observations. |
| 14) Status of RFIs. |
| 15) Status of Proposal Requests. |
| 16) Pending changes. |
| 17) Status of Change Orders. |
| 18) Pending claims and disputes. |
| 19) Documentation of information for payment requests. |
| 4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information. |
| a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting. |
| E. Coordination Meetings: Construction Manager will conduct Project coordination meetings at weekly intervals. Project coordination meetings are in addition to specific meetings held for other purposes, such as progress meetings and preinstallation co... |
| 1. Attendees: In addition to representatives of Owner, Construction Manager, and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activ... |
| 2. Agenda: Review and correct or approve minutes of the previous coordination meeting. Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project. |
| a. Combined Contractor's Construction Schedule: Review progress since the last coordination meeting. Determine whether each contract is on time, ahead of schedule, or behind schedule, in relation to combined Contractor's construction schedule. Determi... |
| b. Schedule Updating: Revise combined Contractor's construction schedule after each coordination meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with report of each meeting. |
| c. Review present and future needs of each contractor present, including the following: |
| 1) Interface requirements. |
| 2) Sequence of operations. |
| 3) Resolution of BIM component conflicts. |
| 4) Status of submittals. |
| 5) Deliveries. |
| 6) Off-site fabrication. |
| 7) Access. |
| 8) Site use. |
| 9) Temporary facilities and controls. |
| 10) Work hours. |
| 11) Hazards and risks. |
| 12) Progress cleaning. |
| 13) Quality and work standards. |
| 14) Status of RFIs. |
| 15) Proposal Requests. |
| 16) Change Orders. |
| 17) Pending changes. |
3. Reporting: Record meeting results and distribute copies to everyone in attendance and to others affected by decisions or actions resulting from each meeting.
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION (Not Used) |