2026 Road Maintenance Program
MANUFACTURED TRAFFIC-CALMING DEVICES 321716 - 1
SECTION 321716 - MANUFACTURED TRAFFIC-CALMING DEVICES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes manufactured traffic-calming devices.
B. Detour Plan.
C. Notification Requirements.
1.3 DEFINITIONS
A. Penn DOT: Pennsylvania Department of Transportation.
PART 2 - PRODUCTS
2.1 MANUFACTURED TRAFFIC-CALMING DEVICES
A. All traffic control signs and warning devises shall meet specifications set forth in the current edition of Penn DOT’s publication 203 and 408.
PART 3 - EXECUTION
3.1 SIGNS AND TRAFFIC CONTROL DEVICES
A. The contractor shall install all required signs and traffic control devices to maintain proper traffic control. All signs and devices shall be installed in accordance with the current edition of Penn DOT’s publication 203 for road closure or single lane closure.
B. The contractor shall install all traffic control signs a minimum of one (1) week prior to starting construction.
2026 Road Maintenance Program
MANUFACTURED TRAFFIC-CALMING DEVICES 321716 - 2
C. The contractor shall maintain all traffic control signs and devices during the life of the project.
D. The contractor shall remove all traffic control signs and devises a maximum of two (2) weeks after final acceptance of the project.
E. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 DETOUR PLAN
A. The contractor shall prepare and submit a detour plan for road closure to the Engineer/Owner for review and approval.
B. The contractor shall install all of the required signs and devices in accordance with the Traffic Control Plan included in the contract documents.
C. The contractor shall make arrangements ahead of time with local school district and Port Authority whenever their buses will be inconvenienced during the life of the project.
3.3 INSTALLATION
A. Install manufactured traffic-calming devices according to manufacturer's written instructions unless otherwise indicated.
END OF SECTION 321716
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section includes manufactured traffic-calming devices. |
| B. Detour Plan. |
| C. Notification Requirements. |
| 1.3 DEFINITIONS |
| A. Penn DOT: Pennsylvania Department of Transportation. |
| PART 2 - PRODUCTS |
| 2.1 MANUFACTURED TRAFFIC-CALMING DEVICES |
| A. All traffic control signs and warning devises shall meet specifications set forth in the current edition of Penn DOT’s publication 203 and 408. |
| PART 3 - EXECUTION |
| 3.1 SIGNS AND TRAFFIC CONTROL DEVICES |
| A. The contractor shall install all required signs and traffic control devices to maintain proper traffic control. All signs and devices shall be installed in accordance with the current edition of Penn DOT’s publication 203 for road closure or single... |
| B. The contractor shall install all traffic control signs a minimum of one (1) week prior to starting construction. |
| C. The contractor shall maintain all traffic control signs and devices during the life of the project. |
| D. The contractor shall remove all traffic control signs and devises a maximum of two (2) weeks after final acceptance of the project. |
| E. Proceed with installation only after unsatisfactory conditions have been corrected. |
| 3.2 DETOUR PLAN |
| A. The contractor shall prepare and submit a detour plan for road closure to the Engineer/Owner for review and approval. |
| B. The contractor shall install all of the required signs and devices in accordance with the Traffic Control Plan included in the contract documents. |
| C. The contractor shall make arrangements ahead of time with local school district and Port Authority whenever their buses will be inconvenienced during the life of the project. |
| 3.3 INSTALLATION |
| A. Install manufactured traffic-calming devices according to manufacturer's written instructions unless otherwise indicated. |