2026 Road Maintenance Program
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1
SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:
1. Startup construction schedule.
2. Contractor's Construction Schedule.
3. Construction schedule updating reports.
4. Daily construction reports.
5. Material location reports.
6. Site condition reports.
7. Unusual event reports.
1.3 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources.
1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled.
The sum of costs for all activities must equal the total Contract Sum.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Event: The starting or ending point of an activity.
F. Float: The measure of leeway in starting and completing an activity.
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 2
1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
G. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.
1.4 INFORMATIONAL SUBMITTALS
A. Format for Submittals: Submit required submittals in the following format:
1. Working electronic copy of schedule file, where indicated.
2. PDF file.
3. <4> paper copies, of sufficient size to display entire period or schedule, as required.
B. Startup construction schedule.
1. Submittal of cost-loaded, startup construction schedule will not constitute approval of schedule of values for cost-loaded activities.
C. Startup Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities.
D. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period.
1. Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals.
E. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of preceding and succeeding activities for each activity, sorted in ascending order by activity number and then by early start date, or actual start date if known.
3. Total Float Report: List of activities sorted in ascending order of total float.
4. Earnings Report: Compilation of Contractor's total earnings from until most recent
Application for Payment.
F. Construction Schedule Updating Reports: Submit with Applications for Payment.
G. Daily Construction Reports: Submit at intervals.
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 3
H. Material Location Reports: Submit at intervals.
I. Site Condition Reports: Submit at time of discovery of differing conditions.
J. Unusual Event Reports: Submit at time of unusual event.
K. Qualification Data: For scheduling consultant.
1.5 QUALITY ASSURANCE
A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Engineer's/Owner request.
B. Prescheduling Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's Construction Schedule, including, but not limited to, the following:
1. Review software limitations and content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including .
4. Review delivery dates for Owner-furnished products.
5. Review schedule for work of Owner's separate contracts.
6. Review submittal requirements and procedures.
7. Review time required for review of submittals and resubmittals.
8. Review requirements for tests and inspections by independent testing and inspecting agencies.
9. Review time required for Project closeout and Owner startup procedures.
10. Review and finalize list of construction activities to be included in schedule.
11. Review procedures for updating schedule.
1.6 COORDINATION
A. Coordinate Contractor's Construction Schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports.
1. Secure time commitments for performing critical elements of the Work from entities involved.
2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL
A. Scheduling Consultant: Engage a consultant to provide planning, evaluation, and reporting using CPM scheduling.
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 4
1. In-House Option: Owner may waive requirement to retain a consultant if Contractor employs skilled personnel with experience in CPM scheduling and reporting techniques.
Submit qualifications.
2. Meetings: Scheduling consultant shall attend all meetings related to Project progress, alleged delays, and time impact.
B. Time Frame: Extend schedule from date established for commencement of the Notice to Proceed to date of Substantial Completion final completion.
1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.
C. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion.
1. Temporary enclosure and space conditioning.
D. Cost Correlation: Superimpose a cost correlation timeline, indicating planned and actual costs.
On the line, show planned and actual dollar volume of the Work performed as of planned and actual dates used for preparation of payment requests.
1. See Section 012900 "Payment Procedures" for cost reporting and payment procedures.
E. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues:
1. Unresolved issues.
2. Unanswered Requests for Information.
3. Rejected or unreturned submittals.
4. Notations on returned submittals.
5. Pending modifications affecting the Work and the Contract Time.
F. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.
1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.
2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.
3. As the Work progresses, indicate final completion percentage for each activity.
G. Recovery Schedule: When periodic update indicates the Work is 14 fourteen or more calendar days behind the current approved schedule, submit a separate recovery schedule indicating means by which Contractor intends to regain compliance with the schedule. Indicate changes to working hours, working days, crew sizes, equipment required to achieve compliance, and date by which recovery will be accomplished.
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 5
H. Distribution: Distribute copies of approved schedule to Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
1.8 STARTUP CONSTRUCTION SCHEDULE
A. Gantt-Chart Schedule: Submit startup, horizontal, Gantt-chart-type construction schedule within seven (7) days of date established for the Notice of Award.
1. Base schedule on the startup construction schedule and additional information received since the start of Project.
1.9 CPM SCHEDULE REQUIREMENTS
A. General: Prepare network diagrams using AON (activity-on-node) format.
B. Startup Network Diagram: Submit diagram within fourteen 14 days of date established for the Notice of Award. Outline significant construction activities for the first ninety 90 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities.
C. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the startup network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated time duration, sequence requirements, and relationship of each activity in relation to other activities. Include estimated time frames for the following activities:
a. Preparation and processing of submittals.
b. Mobilization and demobilization.
c. Purchase of materials.
d. Delivery.
e. Fabrication.
f. Utility interruptions.
g. Installation.
h. Work by Owner that may affect or be affected by Contractor's activities.
i. Testing and inspection.
j. Punch list and final completion.
k. Activities occurring following final completion.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 6
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. Format: Mark the critical path. Locate the critical path near center of network; locate paths with most float near the edges.
a. Subnetworks on separate sheets are permissible for activities clearly off the critical path.
D. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using a network fragment to demonstrate the effect of the proposed change on the overall Project schedule.
E. Initial Issue of Schedule: Prepare initial network diagram from a sorted activity list indicating straight "early start-total float." Identify critical activities. Prepare tabulated reports showing the following:
1. Contractor or subcontractor and the Work or activity.
2. Description of activity.
3. Main events of activity.
4. Immediate preceding and succeeding activities.
5. Early and late start dates.
6. Early and late finish dates.
7. Activity duration in workdays.
8. Total float or slack time.
9. Average size of workforce.
10. Dollar value of activity (coordinated with the schedule of values).
F. Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:
1. Identification of activities that have changed.
2. Changes in early and late start dates.
3. Changes in early and late finish dates.
4. Changes in activity durations in workdays.
5. Changes in the critical path.
6. Changes in total float or slack time.
7. Changes in the Contract Time.
G. Value Summaries: Prepare two cumulative value lists, sorted by finish dates.
1. In first list, tabulate activity number, early finish date, dollar value, and cumulative dollar value.
2. In second list, tabulate activity number, late finish date, dollar value, and cumulative dollar value.
3. In subsequent issues of both lists, substitute actual finish dates for activities completed as of list date.
4. Prepare list for ease of comparison with payment requests; coordinate timing with progress meetings.
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 7
a. In both value summary lists, tabulate "actual percent complete" and "cumulative value completed" with total at bottom.
b. Submit value summary printouts one week 1 week before each regularly scheduled progress meeting.
1.10 REPORTS
A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site:
1. List of subcontractors at Project site.
2. List of separate contractors at Project site.
3. Approximate count of personnel at Project site.
4. Equipment at Project site.
5. Material deliveries.
6. High and low temperatures and general weather conditions, including presence of rain or snow.
7. Testing and inspection.
8. Accidents.
9. Meetings and significant decisions.
10. Unusual events.
11. Stoppages, delays, shortages, and losses.
12. Meter readings and similar recordings.
13. Emergency procedures.
14. Orders and requests of authorities having jurisdiction.
15. Change Orders received and implemented.
16. Change Directives received and implemented.
17. Services connected and disconnected.
18. Equipment or system tests and startups.
19. Partial completions and occupancies.
20. Substantial Completions authorized.
B. Material Location Reports: At intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing materials previously reported plus items recently delivered. Include with list a statement of progress on and delivery dates for materials or items of equipment fabricated or stored away from Project site. Indicate the following categories for stored materials:
1. Material stored prior to previous report and remaining in storage.
2. Material stored prior to previous report and since removed from storage and installed.
3. Material stored following previous report and remaining in storage.
C. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing conditions, together with recommendations for changing the Contract Documents.
D. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, responses by Contractor's personnel, evaluation of results or
CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 8
effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.
1. Submit unusual event reports directly to Owner within one 1 day(s) of an occurrence.
Distribute copies of report to parties affected by the occurrence.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013200
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following: |
| 1. Startup construction schedule. |
| 2. Contractor's Construction Schedule. |
| 3. Construction schedule updating reports. |
| 4. Daily construction reports. |
| 5. Material location reports. |
| 6. Site condition reports. |
| 7. Unusual event reports. |
| 1.3 DEFINITIONS |
| A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction Project. Activities included in a construction schedule consume time and resources. |
| 1. Critical Activity: An activity on the critical path that must start and finish on the planned early start and finish times. |
| 2. Predecessor Activity: An activity that precedes another activity in the network. |
| 3. Successor Activity: An activity that follows another activity in the network. |
| B. Cost Loading: The allocation of the schedule of values for completing an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum. |
| C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of P... |
| D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float. |
| E. Event: The starting or ending point of an activity. |
| F. Float: The measure of leeway in starting and completing an activity. |
| 1. Float time is not for the exclusive use or benefit of either Owner or Contractor, but is a jointly owned, expiring Project resource available to both parties as needed to meet schedule milestones and Contract completion date. |
| 2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity. |
| 3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date. |
G. Resource Loading: The allocation of manpower and equipment necessary for completing an activity as scheduled.
| 1.4 INFORMATIONAL SUBMITTALS |
| A. Format for Submittals: Submit required submittals in the following format: |
| 1. Working electronic copy of schedule file, where indicated. |
| 2. PDF file. |
| 3. <4> paper copies, of sufficient size to display entire period or schedule, as required. |
| B. Startup construction schedule. |
| 1. Submittal of cost-loaded, startup construction schedule will not constitute approval of schedule of values for cost-loaded activities. |
| C. Startup Network Diagram: Of size required to display entire network for entire construction period. Show logic ties for activities. |
| D. Contractor's Construction Schedule: Initial schedule, of size required to display entire schedule for entire construction period. |
| 1. Submit a working digital copy of schedule, using software indicated, and labeled to comply with requirements for submittals. |
| E. CPM Reports: Concurrent with CPM schedule, submit each of the following reports. Format for each activity in reports shall contain activity number, activity description, cost and resource loading, original duration, remaining duration, early start ... |
| 1. Activity Report: List of activities sorted by activity number and then early start date, or actual start date if known. |
| 2. Logic Report: List of preceding and succeeding activities for each activity, sorted in ascending order by activity number and then by early start date, or actual start date if known. |
| 3. Total Float Report: List of activities sorted in ascending order of total float. |
| 4. Earnings Report: Compilation of Contractor's total earnings from until most recent Application for Payment. |
| F. Construction Schedule Updating Reports: Submit with Applications for Payment. |
| G. Daily Construction Reports: Submit at intervals. |
| H. Material Location Reports: Submit at intervals. |
| I. Site Condition Reports: Submit at time of discovery of differing conditions. |
| J. Unusual Event Reports: Submit at time of unusual event. |
| K. Qualification Data: For scheduling consultant. |
| 1.5 QUALITY ASSURANCE |
| A. Scheduling Consultant Qualifications: An experienced specialist in CPM scheduling and reporting, with capability of producing CPM reports and diagrams within 24 hours of Engineer's/Owner request. |
| B. Prescheduling Conference: Conduct conference at Project site to comply with requirements in Section 013100 "Project Management and Coordination." Review methods and procedures related to the preliminary construction schedule and Contractor's Constr... |
| 1. Review software limitations and content and format for reports. |
| 2. Verify availability of qualified personnel needed to develop and update schedule. |
| 3. Discuss constraints, including . |
| 4. Review delivery dates for Owner-furnished products. |
| 5. Review schedule for work of Owner's separate contracts. |
| 6. Review submittal requirements and procedures. |
| 7. Review time required for review of submittals and resubmittals. |
| 8. Review requirements for tests and inspections by independent testing and inspecting agencies. |
| 9. Review time required for Project closeout and Owner startup procedures. |
| 10. Review and finalize list of construction activities to be included in schedule. |
| 11. Review procedures for updating schedule. |
| 1.6 COORDINATION |
| A. Coordinate Contractor's Construction Schedule with the schedule of values, submittal schedule, progress reports, payment requests, and other required schedules and reports. |
| 1. Secure time commitments for performing critical elements of the Work from entities involved. |
| 2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence. |
| 1.7 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL |
| A. Scheduling Consultant: Engage a consultant to provide planning, evaluation, and reporting using CPM scheduling. |
| 1. In-House Option: Owner may waive requirement to retain a consultant if Contractor employs skilled personnel with experience in CPM scheduling and reporting techniques. Submit qualifications. |
| 2. Meetings: Scheduling consultant shall attend all meetings related to Project progress, alleged delays, and time impact. |
| B. Time Frame: Extend schedule from date established for commencement of the Notice to Proceed to date of Substantial Completion final completion. |
| 1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order. |
| C. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and final completion. |
| 1. Temporary enclosure and space conditioning. |
| D. Cost Correlation: Superimpose a cost correlation timeline, indicating planned and actual costs. On the line, show planned and actual dollar volume of the Work performed as of planned and actual dates used for preparation of payment requests. |
| 1. See Section 012900 "Payment Procedures" for cost reporting and payment procedures. |
| E. Upcoming Work Summary: Prepare summary report indicating activities scheduled to occur or commence prior to submittal of next schedule update. Summarize the following issues: |
| 1. Unresolved issues. |
| 2. Unanswered Requests for Information. |
| 3. Rejected or unreturned submittals. |
| 4. Notations on returned submittals. |
| 5. Pending modifications affecting the Work and the Contract Time. |
| F. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting. |
| 1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting. |
| 2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations. |
| 3. As the Work progresses, indicate final completion percentage for each activity. |
| G. Recovery Schedule: When periodic update indicates the Work is 14 fourteen or more calendar days behind the current approved schedule, submit a separate recovery schedule indicating means by which Contractor intends to regain compliance with the sch... |
| H. Distribution: Distribute copies of approved schedule to Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility. |
| 1. Post copies in Project meeting rooms and temporary field offices. |
| 2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of cons... |
| 1.8 STARTUP CONSTRUCTION SCHEDULE |
| A. Gantt-Chart Schedule: Submit startup, horizontal, Gantt-chart-type construction schedule within seven (7) days of date established for the Notice of Award. |
| 1. Base schedule on the startup construction schedule and additional information received since the start of Project. |
| 1.9 CPM SCHEDULE REQUIREMENTS |
| A. General: Prepare network diagrams using AON (activity-on-node) format. |
| B. Startup Network Diagram: Submit diagram within fourteen 14 days of date established for the Notice of Award. Outline significant construction activities for the first ninety 90 days of construction. Include skeleton diagram for the remainder of the... |
| C. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the startup network diagram, prepare a skeleton network to identify probable critical paths. |
| 1. Activities: Indicate the estimated time duration, sequence requirements, and relationship of each activity in relation to other activities. Include estimated time frames for the following activities: |
| a. Preparation and processing of submittals. |
| b. Mobilization and demobilization. |
| c. Purchase of materials. |
| d. Delivery. |
| e. Fabrication. |
| f. Utility interruptions. |
| g. Installation. |
| h. Work by Owner that may affect or be affected by Contractor's activities. |
| i. Testing and inspection. |
| j. Punch list and final completion. |
| k. Activities occurring following final completion. |
| 2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates. |
| 3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time. |
| 4. Format: Mark the critical path. Locate the critical path near center of network; locate paths with most float near the edges. |
| a. Subnetworks on separate sheets are permissible for activities clearly off the critical path. |
| D. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using a network fragment to demonstrate the effect of the proposed change on the overall Project schedule. |
| E. Initial Issue of Schedule: Prepare initial network diagram from a sorted activity list indicating straight "early start-total float." Identify critical activities. Prepare tabulated reports showing the following: |
| 1. Contractor or subcontractor and the Work or activity. |
| 2. Description of activity. |
| 3. Main events of activity. |
| 4. Immediate preceding and succeeding activities. |
| 5. Early and late start dates. |
| 6. Early and late finish dates. |
| 7. Activity duration in workdays. |
| 8. Total float or slack time. |
| 9. Average size of workforce. |
| 10. Dollar value of activity (coordinated with the schedule of values). |
| F. Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports showing the following: |
| 1. Identification of activities that have changed. |
| 2. Changes in early and late start dates. |
| 3. Changes in early and late finish dates. |
| 4. Changes in activity durations in workdays. |
| 5. Changes in the critical path. |
| 6. Changes in total float or slack time. |
| 7. Changes in the Contract Time. |
| G. Value Summaries: Prepare two cumulative value lists, sorted by finish dates. |
| 1. In first list, tabulate activity number, early finish date, dollar value, and cumulative dollar value. |
| 2. In second list, tabulate activity number, late finish date, dollar value, and cumulative dollar value. |
| 3. In subsequent issues of both lists, substitute actual finish dates for activities completed as of list date. |
| 4. Prepare list for ease of comparison with payment requests; coordinate timing with progress meetings. |
| a. In both value summary lists, tabulate "actual percent complete" and "cumulative value completed" with total at bottom. |
| b. Submit value summary printouts one week 1 week before each regularly scheduled progress meeting. |
| 1.10 REPORTS |
| A. Daily Construction Reports: Prepare a daily construction report recording the following information concerning events at Project site: |
| 1. List of subcontractors at Project site. |
| 2. List of separate contractors at Project site. |
| 3. Approximate count of personnel at Project site. |
| 4. Equipment at Project site. |
| 5. Material deliveries. |
| 6. High and low temperatures and general weather conditions, including presence of rain or snow. |
| 7. Testing and inspection. |
| 8. Accidents. |
| 9. Meetings and significant decisions. |
| 10. Unusual events. |
| 11. Stoppages, delays, shortages, and losses. |
| 12. Meter readings and similar recordings. |
| 13. Emergency procedures. |
| 14. Orders and requests of authorities having jurisdiction. |
| 15. Change Orders received and implemented. |
| 16. Change Directives received and implemented. |
| 17. Services connected and disconnected. |
| 18. Equipment or system tests and startups. |
| 19. Partial completions and occupancies. |
| 20. Substantial Completions authorized. |
| B. Material Location Reports: At intervals, prepare and submit a comprehensive list of materials delivered to and stored at Project site. List shall be cumulative, showing materials previously reported plus items recently delivered. Include with lis... |
| 1. Material stored prior to previous report and remaining in storage. |
| 2. Material stored prior to previous report and since removed from storage and installed. |
| 3. Material stored following previous report and remaining in storage. |
| C. Site Condition Reports: Immediately on discovery of a difference between site conditions and the Contract Documents, prepare and submit a detailed report. Submit with a Request for Information. Include a detailed description of the differing condit... |
| D. Unusual Event Reports: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, responses by Contractor... |
| 1. Submit unusual event reports directly to Owner within one 1 day(s) of an occurrence. Distribute copies of report to parties affected by the occurrence. |
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION (Not Used) |