Attachment J.18 CPFMD Integrated Program Schedule_Oct 2023.pdf
PDF 264 KB Posted
- Solicitation number
- DCSC-24-RFP-0170
- Issued by
- District of Columbia Government
About this file
This document contains details for a federal contract opportunity solicitation. The District of Columbia Courts is seeking qualified sources to provide construction management and quality assurance services as an integrated part of their Capital Planning and Facilities Management Division team. The selected contractor will be responsible for planning, funding, and executing the Courts' capital projects on time and within budget, developing strategies to improve project performance and resolve issues, promoting an integrated team approach throughout all project phases, and managing facility projects to support optimal judicial operations. The contractor will manage all projects regardless of delivery method from project initiation through occupancy, warranty period expiration, and transition to operations and maintenance. Services must be fully integrated program-wide to ensure projects across multiple sites and of varying scale and complexity are managed systematically and efficiently. Responses to the solicitation are due under number DCSC-24-RFP-0170.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# Activity Name Start Finish Original Duration
Responsibility
1 DC Courts Integrated Program ScheduleDC Courts Integrated Program ScheduleDC Courts Integrated Program ScheduleDC Courts Integrated Program ScheduleDC Courts Integrated Program Schedule
2 Budget Milestones Budget Milestones Budget Milestones Budget Milestones Budget Milestones
3 Receipt of FY23 Funds 01-Jan-23 A 0 BFD
4 Obligation Deadline of FY22 Funds 30-Sep-23 A 0 CPFMD
5 Receipt of FY24 Funds 01-Jan-24* 0 BFD
6 Obligation Deadline of FY23 Funds 30-Sep-24* 0 CPFMD
7 Receipt of FY25 Funds 01-Jan-25* 0 BFD
8 Obligation Deadline of FY24 Funds 30-Sep-25* 0 CPFMD
9 Obligation Deadline of FY25 Funds 30-Sep-26* 0 CPFMD
10 Renovations, Improvements & Expansions (RIE) Renovations, Improvements & Expansions (RIE) Renovations, Improvements & Expansions (RIE) Renovations, Improvements & Expansions (RIE) Renovations, Improvements & Expansions (RIE)
11 Historic Recorder of Deeds Restoration (D/B) Historic Recorder of Deeds Restoration (D/B) Historic Recorder of Deeds Restoration (D/B) Historic Recorder of Deeds Restoration (D/B) Historic Recorder of Deeds Restoration (D/B)
12 PlanningPlanningPlanningPlanningPlanning
13 DCSC-23-ESS-135 Hazardous Material RemediationDCSC-23-ESS-135 Hazardous Material RemediationDCSC-23-ESS-135 Hazardous Material RemediationDCSC-23-ESS-135 Hazardous Material RemediationDCSC-23-ESS-135 Hazardous Material Remediation
14 Award Hazardous Material Remediation 21-Jun-23 A 0 ASD
15 Aquire Permit for Hazardous Material Remediation 22-Jun-23 A 14-Jul-23 A 31 ASD
16 Selective Hazardous Material Remediation 17-Jul-23 A 23-Aug-23 A 49 ASD
17 TO 17-SG Building AssessmentTO 17-SG Building AssessmentTO 17-SG Building AssessmentTO 17-SG Building AssessmentTO 17-SG Building Assessment
18 Develop Building Assessment TRFP 07-Mar-23 A 07-Apr-23 A 23 PgM
19 Review Building Assessment TRFP 08-Apr-23 A 19-Apr-23 A 5 CPFMD
20 Revise Building Assessment TRFP 20-Apr-23 A 26-Apr-23 A 10 PgM
21 Review Building Assessment TRFP 27-Apr-23 A 03-May-23 A 2 ASD
22 Release Building Assessment TRFP 04-May-23 A 0 ASD
23 Submit Builidng Assessment Proposal 18-May-23 A 0 AEP
24 Award Building Assessment TO 25-Jul-23 A 0 ASD
25 Verify Abatement On-Site 29-Aug-23 A 29-Aug-23 A 5 AEP
26 Conduct Boundary, Utility & Topographic Survey 06-Sep-23 A 07-Sep-23 A 1 AEP
27 Building Assessment Report 08-Sep-23 A 29-Sep-23 A 16 CPFMD
28 Submit Assessment Report 29-Sep-23 A 0 AEP
29 Review Assessment Report 30-Sep-23 A 12-Oct-23 A 10 AEP
30 Submit Modernization Report & Performance Requirements 27-Oct-23 A 0 AEP
31 Prepare Modernization Report & Performance Requirements 16-Oct-23 A 27-Oct-23 A 10 PgM
32 Review Modernization Report & Performance Requirements 30-Oct-23 A 03-Nov-23 5 PgM
33 Submit Preliminary IGE 17-Nov-23 0 AEP
34 Prepare Preliminary IGE 06-Nov-23 17-Nov-23 10 AEP
35 Review Preliminary IGE 20-Nov-23 01-Dec-23 10 PgM
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 1 of 12 TASK filter: All Activities
© Oracle Corporation
Responsibility
36 Submit Final IGE 15-Dec-23 0 AEP
37 Prepare Final IGE 04-Dec-23 15-Dec-23 10 AEP
38 TO 24-SG Pre-DesignTO 24-SG Pre-DesignTO 24-SG Pre-DesignTO 24-SG Pre-DesignTO 24-SG Pre-Design
39 Develop Pre-Design TRFP 24-Apr-23 A 23-May-23 A 23 PgM
40 Review Pre-Design TRFP 24-May-23 A 27-Jun-23 A 5 CPFMD
41 Revise Pre-Design TRFP 28-Jun-23 A 05-Jul-23 A 10 PgM
42 Review Pre-Design TRFP 06-Jul-23 A 21-Jul-23 A 2 ASD
43 Release Pre-Design TRFP 24-Jul-23 A 0 ASD
44 Submit Pre-Design Proposal 11-Aug-23 A 0 AEP
45 Award Pre-Design TO 04-Sep-23 A 0 ASD
46 Pre-Design (Programming) 05-Sep-23 A 01-Jan-24 67 AEP
47 Pre-Design (Space Planning, DIDs) 02-Jan-24 03-May-24 89 AEP
48 Pre-Design (35% Concept Design) 06-May-24 03-Jun-24 21 AEP
49 Complete BCD Package 03-Jun-24 0 AEP
50 Furniture Pre-DesignFurniture Pre-DesignFurniture Pre-DesignFurniture Pre-DesignFurniture Pre-Design
51 Develop Pre-Design TRFP 31-Oct-23 15-Nov-23 12 PgM
52 Review Pre-Design TRFP 16-Nov-23 01-Dec-23 12 CPFMD
53 Revise Pre-Design TRFP 04-Dec-23 08-Dec-23 5 PgM
54 Release Task Order 08-Dec-23 0 ASD
55 Submit Proposal 11-Dec-23 22-Dec-23 10 FFE
56 Negotiate Pre-Design Task Order 25-Dec-23 29-Dec-23 5 ASD
57 Award Pre-Design TO 29-Dec-23 0 ASD
58 Furniture ProcurementFurniture ProcurementFurniture ProcurementFurniture ProcurementFurniture Procurement
59 Develop TRFP 29-Mar-24 23-May-24 40 PgM
60 Review TRFP 24-May-24 20-Jun-24 20 CPFMD
61 Revise TRFP 21-Jun-24 04-Jul-24 10 PgM
62 Release Task Order 15-Jul-24 0 ASD
63 Submit Proposal 16-Jul-24 05-Aug-24 15 FFE
64 Negotiate Task Order 06-Aug-24 02-Sep-24 20 ASD
65 Award Task Order 02-Sep-24 0 ASD
66 Design-Build ProcurementDesign-Build ProcurementDesign-Build ProcurementDesign-Build ProcurementDesign-Build Procurement
67 Develop Design Build RFP 02-Jan-24* 26-Feb-24 40 PgM
68 Review Design Build RFP 27-Feb-24 25-Mar-24 20 CPFMD
69 Revise Design Build RFP 26-Mar-24 08-Apr-24 10 PgM
70 Review Design Build RFP 09-Apr-24 09-May-24 23 ASD
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 2 of 12 TASK filter: All Activities
Responsibility
71 Revise Design Build RFP 10-May-24 17-May-24 6 PgM
72 Release Design Build RFP 03-Jun-24 0 ASD
73 Solicit Design Build Contract 04-Jun-24 29-Jul-24 40 DB
74 Submit Bids 29-Jul-24 0 DB
75 Conduct SSEB 30-Jul-24 12-Aug-24 10 CPFMD
76 Negotiate Contract 13-Aug-24 02-Sep-24 15 ASD
77 Award Design Build Contract 02-Sep-24 0 ASD
78 DesignDesignDesignDesignDesign
79 Accept 65% Core & Shell Design 03-Mar-25 0 CPFMD
80 Accept 95% Interiors Construction and Finishes Design 02-Sep-25 0 CPFMD
81 Design 03-Sep-24 03-Nov-25 305 DB
82 ConstructionConstructionConstructionConstructionConstruction
83 Exercise Option - Interior Finishes 14-Jan-25 0 ASD
84 Construction - Core & Shell 03-Mar-25 26-Nov-25 193 DB
85 Construction - Interior Construction 02-Sep-25 02-Mar-26 130 DB
86 Construction Complete (Turnover) 28-Aug-26 0 DB
87 Construction - Interior Finishes 02-Dec-25 28-Aug-26 194 DB
88 Install FF&E 31-Aug-26 30-Nov-26 66 FFE
89 Certificate of Occupancy 30-Nov-26 0 DB
90 De-Commission Vacated Space 01-Dec-26 14-Dec-26 10 CPFMD
91 Tenant Move-in 01-Dec-26 02-Mar-27 66 CPFMD
92 100% Occupancy 02-Mar-27 0 CPFMD
93 Conract Close-OutConract Close-OutConract Close-OutConract Close-OutConract Close-Out
94 Submit O&M Manuals 25-Sep-26 0 DB
95 Submit As-Builts 25-Sep-26 0 DB
96 Contract Complete/Last day of Period of Performance 18-Dec-26 0 CM
97 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
98 One Year Warranty Period Begins 31-Aug-26 0 FM
99 Deliver Completed Close-out Documents 20-Nov-26 0 CM
100 Enter Fixed Assets into Manager Plus 18-Dec-26 0 FM
101 Enter Architectural and Furniture shop drawings to FM systems 18-Dec-26 0 FM
102 Conduct a 9-month Warranty Walk/Inspection 28-May-27 0 FM
103 One Year Warranty Period Ends 31-Aug-27 0 FM
104 Moultire Courthouse AdditionMoultire Courthouse AdditionMoultire Courthouse AdditionMoultire Courthouse AdditionMoultire Courthouse Addition
105 15-0603 HCMC Construction C Street Addition - Phase 2B (D/B/B)15-0603 HCMC Construction C Street Addition - Phase 2B (D/B/B)15-0603 HCMC Construction C Street Addition - Phase 2B (D/B/B)15-0603 HCMC Construction C Street Addition - Phase 2B (D/B/B)15-0603 HCMC Construction C Street Addition - Phase 2B (D/B/B)
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 3 of 12 TASK filter: All Activities
Responsibility
106 ConstructionConstructionConstructionConstructionConstruction
107 Issue Construction NTP 01-Jul-19 A 0 ASD
108 Install FF&E 01-Jul-22 A 31-Aug-22 A 44 FFE
109 Tenant Move-in 01-Sep-22 A 30-Sep-22 A 22 CPFMD
110 Substantial Completion - Phase 2B 12-Dec-23 0 GC
111 Construction 01-Jul-19 A 29-Dec-23 6 GC
112 Turnover Space to CPFMD 29-Dec-23 0 GC
113 100% Occupancy 29-Dec-23 0 CPFMD
114 Substantial Completion - Phase 2B.1 29-Dec-23 0 GC
115 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
116 Contract Complete/Last day of Period of Performance 10-Nov-23* 0 GC
117 Submit As-Builts 12-Dec-23 0 GC
118 Submit O&M Manuals 12-Dec-23 0 CM
119 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
120 Deliver Completed Close-out Documents 10-Nov-23 0 CM
121 Enter Architectural and Furniture shop drawings to FM systems 12-Dec-23 0 FM
122 Enter Fixed Assets into Manager Plus 12-Dec-23 0 FM
123 One Year Warranty Period Begins 01-Jan-24 0 FM
124 Conduct a 9-month Warranty Walk/Inspection 01-Oct-24 0 FM
125 One Year Warranty Period Ends 31-Dec-24 0 FM
126 DCSC-20-RFP-106 HCMC 4th Floor East Juror's Lounge Renovation (D/B)DCSC-20-RFP-106 HCMC 4th Floor East Juror's Lounge Renovation (D/B)DCSC-20-RFP-106 HCMC 4th Floor East Juror's Lounge Renovation (D/B)DCSC-20-RFP-106 HCMC 4th Floor East Juror's Lounge Renovation (D/B)DCSC-20-RFP-106 HCMC 4th Floor East Juror's Lounge Renovation (D/B)
127 ConstructionConstructionConstructionConstructionConstruction
128 Turnover Space to CPFMD 25-May-22 A 0 DB
129 Substantial Completion 25-May-22 A 0 DB
130 Install FF&E 01-Dec-22 A 30-Dec-22 A 22 FFE
131 Tenant Move-in 03-Dec-22 A 20-Jan-23 A 16 CPFMD
132 100% Occupancy 20-Jan-23 A 0 CPFMD
133 Partition Procurement 01-Nov-22 A 31-Oct-23 A 259 DB
134 Partition Installation 31-Oct-23 13-Nov-23 10 DB
135 Additional Atrium Leak Repairs 01-May-23 A 29-Dec-23 155 DB
136 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
137 Submit As-Builts 05-Jul-22 A 0 DB
138 Submit O&M Manuals 06-Jul-22 A 0 DB
139 Contract Complete/Last day of Period of Performance 31-Dec-23* 0 CM
140 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 4 of 12 TASK filter: All Activities
Responsibility
141 One Year Warranty Period Begins 25-May-22 A 0 FM
142 One Year Warranty Period Ends 25-May-23 A 0 FM
143 Deliver Completed Close-out Documents 29-Dec-23 0 CM
144 Enter Fixed Assets into Manager Plus 29-Dec-23 0 FM
145 Enter Architectural and Furniture shop drawings to FM systems 29-Dec-23 0 FM
146 DCSC-20-IFB-131 HCMC C Level NW Room C-300 RenovationDCSC-20-IFB-131 HCMC C Level NW Room C-300 RenovationDCSC-20-IFB-131 HCMC C Level NW Room C-300 RenovationDCSC-20-IFB-131 HCMC C Level NW Room C-300 RenovationDCSC-20-IFB-131 HCMC C Level NW Room C-300 Renovation
147 PermittingPermittingPermittingPermittingPermitting
148 ConstructionConstructionConstructionConstructionConstruction
149 Issue Construction NTP 07-Feb-23 A 0 ASD
150 Install FF&E 23-Aug-23 A 01-Sep-23 A 1 FFE
151 Construction 09-Feb-23 A 29-Sep-23 A 150 GC
152 Complete Punchlist Items 25-Sep-23 A 29-Sep-23 A 6 GC
153 Tenant Move-in 29-Sep-23 A 29-Sep-23 A 1 CPFMD
154 Turnover Space to CPFMD 29-Sep-23 A 0 GC
155 100% Occupancy 29-Sep-23 A 0 CPFMD
156 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
157 Submit As-Builts 29-Sep-23 A 0 GC
158 Submit O&M Manuals 29-Sep-23 A 0 GC
159 Contract Complete/Last day of Period of Performance 30-Sep-23 A 0 CM
160 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
161 One Year Warranty Period Begins 02-Oct-23 A 0 FM
162 Deliver Completed Close-out Documents to O&M Team 31-Oct-23 0 CM
163 Enter Fixed Assets into Manager Plus 31-Oct-23 0 FM
164 Enter Architectural and Furniture shop drawings to FM systems 31-Oct-23 0 FM
165 Conduct a 9-month Warranty Walk/Inspection 02-Jul-24 0 FM
166 One Year Warranty Period Ends 01-Oct-24 0 FM
167 DCSC-21-RFP-087 Migration from Gallery Place (Buildings A & B) (D/B)DCSC-21-RFP-087 Migration from Gallery Place (Buildings A & B) (D/B)DCSC-21-RFP-087 Migration from Gallery Place (Buildings A & B) (D/B)DCSC-21-RFP-087 Migration from Gallery Place (Buildings A & B) (D/B)DCSC-21-RFP-087 Migration from Gallery Place (Buildings A & B) (D/B)
168 ProcurementProcurementProcurementProcurementProcurement
169 Award Furniture Task Order 09-Jan-23 A 0 ASD
170 Award Phase 2 Construction 04-May-23 A 0 ASD
171 PermittingPermittingPermittingPermittingPermitting
172 Building Permit Approval, Building A 27-Mar-23 A 0 DOB
173 Building Permit Approval, Building B 10-Apr-23 A 0 DOB
174 DesignDesignDesignDesignDesign
175 Accept 95% Design - Rev 03 21-Mar-23 A 0 CPFMD
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 5 of 12 TASK filter: All Activities
Responsibility
176 Accept IFC/100% (corrected 95%) Construction Documents 30-Nov-23* 0 CPFMD
177 ConstructionConstructionConstructionConstructionConstruction
178 Issue NTP - Phase 2 (Full Construction) 04-May-23 A 0 ASD
179 Substantial Completion, Building A 19-Feb-24* 0 DB
180 Lease End Date at 700 6th St 31-May-24* 0 CPFMD
181 Substantial Completion, Building B, 2nd and 3rd Floors 30-Sep-24* 0 DB
182 Turnover Space to CPFMD 30-Sep-24 0 DB
183 Install FF&E 03-Sep-24 30-Sep-24 20 FFE
184 Certificate of Occupancy 30-Sep-24 0 DB
185 Tenant Move-in 01-Oct-24 28-Oct-24 20 CPFMD
186 100% Occupancy 28-Oct-24 0 CPFMD
187 De-Commission Vacated Space 29-Oct-24 11-Nov-24 10 CPFMD
188 Substantial Completion, Building B, Mechanical Room 27-Feb-25* 0 DB
189 Complete Punchlist Items 01-May-25 28-May-25 20 DB
190 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
191 Submit As-Builts 27-Feb-25 0 DB
192 Submit O&M Manuals 27-Feb-25 0 DB
193 Contract Complete/Last day of Period of Performance 29-May-25* 0 CM
194 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
195 One Year Warranty Period Begins 27-Feb-25 0 FM
196 Deliver Completed Close-out Documents 26-Mar-25 0 CM
197 Enter Fixed Assets into Manager Plus 26-Mar-25 0 FM
198 Enter Architectural and Furniture shop drawings to FM systems 26-Mar-25 0 FM
199 Conduct a 9-month Warranty Walk/Inspection 28-Nov-25 0 FM
200 One Year Warranty Period Ends 27-Feb-26 0 FM
201 Bldg A CJDT Suite 246 RenovationBldg A CJDT Suite 246 RenovationBldg A CJDT Suite 246 RenovationBldg A CJDT Suite 246 RenovationBldg A CJDT Suite 246 Renovation
202 DesignDesignDesignDesignDesign
203 Award Design TO 28-Aug-23 A 0 ASD
204 Submit 65% Design 13-Sep-23 A 0 AEP
205 Submit 95% Design 29-Sep-23 A 0 AEP
206 Submit 100% Design 24-Oct-23 A 0 AEP
207 Review 100% Design 25-Oct-23 A 31-Oct-23 A 10 AEP
208 Construction ProcurementConstruction ProcurementConstruction ProcurementConstruction ProcurementConstruction Procurement
209 Develop Construction TRFP 31-Oct-23 13-Nov-23 10 PgM
210 Review Construction TRFP 14-Nov-23 27-Nov-23 10 CPFMD
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 6 of 12 TASK filter: All Activities
Responsibility
211 Revise Construction TRFP 28-Nov-23 04-Dec-23 5 PgM
212 Release Task Order 13-Dec-23 0 ASD
213 Submit Proposal 27-Dec-23 0 GC
214 Negotiate & Award Task Order 28-Dec-23 10-Jan-24 10 ASD
215 ConstructionConstructionConstructionConstructionConstruction
216 Issue NTP 18-Jan-24 0 ASD
217 Construction 18-Jan-24 15-May-24 85 GC
218 Install FF&E 16-May-24 29-May-24 10 FFE
219 Tenant Move-in 30-May-24 05-Jun-24 5 CPFMD
220 100% Occupancy 05-Jun-24 0 CPFMD
221 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
222 Submit As-Builts 29-May-24 0 GC
223 Submit O&M Manuals 29-May-24 0 GC
224 Contract Complete/Last day of Period of Performance 12-Jun-24 0 CM
225 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
226 One Year Warranty Period Begins 16-May-24 0 FM
227 Deliver Completed Close-out Documents 26-Jun-24 0 CM
228 Enter Fixed Assets into Manager Plus 26-Jun-24 0 FM
229 Enter Architectural and Furniture shop drawings to FM systems 26-Jun-24 0 FM
230 Conduct a 9-month Warranty Walk/Inspection 14-Feb-25 0 FM
231 One Year Warranty Period Ends 16-May-25 0 FM
232 Bldg A Crime Victims Compensation Unit Suite Suite 109 RenovationBldg A Crime Victims Compensation Unit Suite Suite 109 RenovationBldg A Crime Victims Compensation Unit Suite Suite 109 RenovationBldg A Crime Victims Compensation Unit Suite Suite 109 RenovationBldg A Crime Victims Compensation Unit Suite Suite 109 Renovation
233 Pre-DesignPre-DesignPre-DesignPre-DesignPre-Design
234 Submit Existing Condition Survey & Concept Sketches 19-Sep-23 A 0 AEP
235 Review Concept Sketches 20-Sep-23 A 29-Sep-23 A 10 CPFMD
236 Develop ROM Estimate 02-Oct-23 A 10-Oct-23 A 6 PgM
237 Authorize Project 10-Oct-23 A 13-Nov-23 6 CPFMD
238 Design ProcurementDesign ProcurementDesign ProcurementDesign ProcurementDesign Procurement
239 Develop Design TRFP 14-Nov-23 27-Nov-23 10 PgM
240 Review Design TRFP 28-Nov-23 11-Dec-23 10 CPFMD
241 Revise Design TRFP 12-Dec-23 18-Dec-23 5 PgM
242 Release Task Order 27-Dec-23 0 ASD
243 Award Design TO 05-Jan-24 0 ASD
244 DesignDesignDesignDesignDesign
245 Submit 65% Design 08-Jan-24 26-Jan-24 15 AEP
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 7 of 12 TASK filter: All Activities
Responsibility
246 Review 65% Design 29-Jan-24 16-Feb-24 15 PgM
247 Submit 95% Design 19-Feb-24 01-Mar-24 10 AEP
248 Review 95% Design 04-Mar-24 15-Mar-24 10 PgM
249 Submit 100% Design 18-Mar-24 22-Mar-24 5 AEP
250 Construction ProcurementConstruction ProcurementConstruction ProcurementConstruction ProcurementConstruction Procurement
251 Develop Construction TRFP 25-Mar-24 05-Apr-24 10 PgM
252 Review Construction TRFP 08-Apr-24 19-Apr-24 10 CPFMD
253 Revise Construction TRFP 22-Apr-24 26-Apr-24 5 PgM
254 Release Task Order 07-May-24 0 ASD
255 Submit Proposal 21-May-24 0 GC
256 Negotiate & Award Task Order 22-May-24 04-Jun-24 10 ASD
257 ConstructionConstructionConstructionConstructionConstruction
258 Issue NTP 12-Jun-24 0 ASD
259 Construction 12-Jun-24 08-Oct-24 85 GC
260 Install FF&E 09-Oct-24 22-Oct-24 10 FFE
261 100% Occupancy 29-Oct-24 0 CPFMD
262 Tenant Move-in 23-Oct-24 29-Oct-24 5 CPFMD
263 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
264 Submit O&M Manuals 22-Oct-24 0 GC
265 Submit As-Builts 22-Oct-24 0 GC
266 Contract Complete/Last day of Period of Performance 05-Nov-24 0 CM
267 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
268 One Year Warranty Period Begins 09-Oct-24 0 FM
269 Deliver Completed Close-out Documents 19-Nov-24 0 CM
270 Enter Fixed Assets into Manager Plus 19-Nov-24 0 FM
271 Enter Architectural and Furniture shop drawings to FM systems 19-Nov-24 0 FM
272 Conduct a 9-month Warranty Walk/Inspection 10-Jul-25 0 FM
273 One Year Warranty Period Ends 09-Oct-25 0 FM
274 Bldg B Civil Suite 120 RenovationBldg B Civil Suite 120 RenovationBldg B Civil Suite 120 RenovationBldg B Civil Suite 120 RenovationBldg B Civil Suite 120 Renovation
275 Pre-DesignPre-DesignPre-DesignPre-DesignPre-Design
276 Submit Existing Condition Survey & Concept Sketches 08-Sep-23 A 0 AEP
277 Review Concept Sketches 09-Sep-23 A 27-Sep-23 A 10 PgM
278 Revise Concept Sketches 28-Sep-23 A 25-Oct-23 A 10 AEP
279 Review Concept Sketches #2 26-Oct-23 A 13-Nov-23 10 PgM
280 Develop ROM Estimate 14-Nov-23 27-Nov-23 10 PgM
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 8 of 12 TASK filter: All Activities
Responsibility
281 Authorize Project 28-Nov-23 11-Dec-23 10 CPFMD
282 Design ProcurementDesign ProcurementDesign ProcurementDesign ProcurementDesign Procurement
283 Develop Design TRFP 12-Dec-23 25-Dec-23 10 PgM
284 Review Design TRFP 26-Dec-23 08-Jan-24 10 CPFMD
285 Revise Design TRFP 09-Jan-24 15-Jan-24 5 PgM
286 Release Task Order 24-Jan-24 0 ASD
287 Award Design TO 02-Feb-24 0 ASD
288 DesignDesignDesignDesignDesign
289 Submit 65% Design 05-Feb-24 23-Feb-24 15 AEP
290 Review 65% Design 26-Feb-24 15-Mar-24 15 PgM
291 Submit 95% Design 18-Mar-24 29-Mar-24 10 AEP
292 Review 95% Design 01-Apr-24 12-Apr-24 10 PgM
293 Submit 100% Design 15-Apr-24 19-Apr-24 5 AEP
294 Construction ProcurementConstruction ProcurementConstruction ProcurementConstruction ProcurementConstruction Procurement
295 Develop Construction TRFP 22-Apr-24 03-May-24 10 PgM
296 Review Construction TRFP 06-May-24 17-May-24 10 CPFMD
297 Revise Construction TRFP 20-May-24 24-May-24 5 PgM
298 Release Task Order 04-Jun-24 0 ASD
299 Submit Proposal 18-Jun-24 0 GC
300 Negotiate & Award Task Order 19-Jun-24 02-Jul-24 10 ASD
301 ConstructionConstructionConstructionConstructionConstruction
302 Issue NTP 10-Jul-24 0 ASD
303 Construction 10-Jul-24 06-Jan-25 129 GC
304 Install FF&E 07-Jan-25 20-Jan-25 10 FFE
305 Tenant Move-in 21-Jan-25 27-Jan-25 5 CPFMD
306 100% Occupancy 27-Jan-25 0 CPFMD
307 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
308 Submit As-Builts 20-Jan-25 0 GC
309 Submit O&M Manuals 20-Jan-25 0 GC
310 Contract Complete/Last day of Period of Performance 03-Feb-25 0 CM
311 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
312 One Year Warranty Period Begins 07-Jan-25 0 FM
313 Deliver Completed Close-out Documents 17-Feb-25 0 CM
314 Enter Fixed Assets into Manager Plus 17-Feb-25 0 FM
315 Enter Architectural and Furniture shop drawings to FM systems 17-Feb-25 0 FM
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 9 of 12 TASK filter: All Activities
Responsibility
316 Conduct a 9-month Warranty Walk/Inspection 08-Oct-25 0 FM
317 One Year Warranty Period Ends 07-Jan-26 0 FM
318 Life Safety and Code Compliance UpgradesLife Safety and Code Compliance UpgradesLife Safety and Code Compliance UpgradesLife Safety and Code Compliance UpgradesLife Safety and Code Compliance Upgrades
319 DCSC-21-RFP-085 HCMC 4th Floor East Magistrate Judge's Renovation (D/B/B)DCSC-21-RFP-085 HCMC 4th Floor East Magistrate Judge's Renovation (D/B/B)DCSC-21-RFP-085 HCMC 4th Floor East Magistrate Judge's Renovation (D/B/B)DCSC-21-RFP-085 HCMC 4th Floor East Magistrate Judge's Renovation (D/B/B)DCSC-21-RFP-085 HCMC 4th Floor East Magistrate Judge's Renovation (D/B/B)
320 PermittingPermittingPermittingPermittingPermitting
321 Submit documents for Building Permit - Phase 2 19-Oct-22 A 0 GC
322 DOB Review of Permit Documents 19-Oct-22 A 18-Jan-23 A 147 DOB
323 Building Permit Approval 18-Jan-23 A 0 CM
324 ConstructionConstructionConstructionConstructionConstruction
325 Issue Construction NTP 12-Oct-21 A 0 ASD
326 Temporary Certificate of Occupancy 31-Aug-22 A 0 GC
327 Turnover Space to CPFMD 30-Dec-24 0 GC
328 Final Certificate of Occupancy 30-Dec-24 0 GC
329 100% Occupancy 06-Jan-25 0 CPFMD
330 De-Commission Vacated Space 07-Jan-25 20-Jan-25 10 CPFMD
331 Phase 1APhase 1APhase 1APhase 1APhase 1A
332 Construction - Phase 1A 27-Sep-21 A 31-Aug-22 A 243 GC
333 Phase 1BPhase 1BPhase 1BPhase 1BPhase 1B
334 Construction - Phase 1B 11-Jul-22 A 07-Aug-23 A 239 GC
335 Phase 2APhase 2APhase 2APhase 2APhase 2A
336 Install FF&E - Phase 2A 02-Oct-23 A 06-Oct-23 A 5 FFE
337 Construction - Phase 2A 17-Jan-23 A 16-Oct-23 A 254 GC
338 Tenant Move-in - Phase 2A 16-Oct-23 A 20-Oct-23 A 5 CPFMD
339 3120 & 31303120 & 31303120 & 31303120 & 31303120 & 3130
340 Install FF&E - 3120 & 3130 15-May-24 22-May-24 6 FFE
341 Construction - 3120 & 3130 23-Oct-23 A 01-Jul-24 179 GC
342 Tenant Move-in - 3120 & 3130 02-Jul-24 09-Jul-24 6 CPFMD
343 Phase 2BPhase 2BPhase 2BPhase 2BPhase 2B
344 Construction - Phase 2B 10-Jul-24 30-Dec-24 124 GC
345 Install FF&E - Phase 2B 23-Dec-24 30-Dec-24 6 FFE
346 Tenant Move-in - Phase 2B 31-Dec-24 06-Jan-25 5 CPFMD
347 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
348 Submit As-Builts 30-Dec-24 0 GC
349 Submit O&M Manuals 30-Dec-24 0 GC
350 Contract Complete/Last day of Period of Performance 03-Jan-25* 0 CM
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 10 of 12 TASK filter: All Activities
Responsibility
351 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
352 One Year Warranty Period Begins 31-Dec-24 0 FM
353 Deliver Completed Close-out Documents 13-Jan-25 0 CM
354 Enter Fixed Assets into Manager Plus 13-Jan-25 0 FM
355 Enter Architectural and Furniture shop drawings to FM systems 13-Jan-25 0 FM
356 Conduct a 9-month Warranty Walk/Inspection 01-Oct-25 0 FM
357 One Year Warranty Period Ends 31-Dec-25 0 FM
358 Maintain Existing Infrastructure (MEI)Maintain Existing Infrastructure (MEI)Maintain Existing Infrastructure (MEI)Maintain Existing Infrastructure (MEI)Maintain Existing Infrastructure (MEI)
359 General ImprovementsGeneral ImprovementsGeneral ImprovementsGeneral ImprovementsGeneral Improvements
360 HCMC MR-1000 Chilled Water Upgrade (D/B/B)HCMC MR-1000 Chilled Water Upgrade (D/B/B)HCMC MR-1000 Chilled Water Upgrade (D/B/B)HCMC MR-1000 Chilled Water Upgrade (D/B/B)HCMC MR-1000 Chilled Water Upgrade (D/B/B)
361 ConstructionConstructionConstructionConstructionConstruction
362 Issue NTP 16-Nov-22 A 0 ASD
363 Substantial Completion 05-Jan-24* 0 GC
364 Commissioning 31-Oct-23* 19-Feb-24 80 CX
365 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
366 Submit As-Builts 01-Feb-24 0 GC
367 Submit O&M Manuals 01-Feb-24 0 GC
368 Contract Complete/Last day of Period of Performance 07-Mar-24* 0 CM
369 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
370 One Year Warranty Period Begins 05-Jan-24 0 FM
371 Deliver Completed Close-out Documents 15-Feb-24 0 CM
372 Enter Fixed Assets into Manager Plus 15-Feb-24 0 FM
373 Enter Architectural and Furniture shop drawings to FM systems 15-Feb-24 0 FM
374 Conduct a 9-month Warranty Walk/Inspection 07-Oct-24 0 FM
375 One Year Warranty Period Ends 06-Jan-25 0 FM
376 HCMC Penthouse Generator Communications UpgradeHCMC Penthouse Generator Communications UpgradeHCMC Penthouse Generator Communications UpgradeHCMC Penthouse Generator Communications UpgradeHCMC Penthouse Generator Communications Upgrade
377 DesignDesignDesignDesignDesign
378 Award Design TO 01-Jun-23 A 0 ASD
379 Submit 35% Design 07-Oct-23 A 0 AEP
380 Conduct Equipment Testing & Submit Report 02-Nov-23* 08-Nov-23 5 FM
381 Submit 95% Design 28-Nov-23 0 AEP
382 Review 95% Design 29-Nov-23 05-Dec-23 5 FM
383 Submit 100% Design 06-Dec-23 0 AEP
384 Review 100% Design 07-Dec-23 20-Dec-23 10 FM
385 Construction ProcurementConstruction ProcurementConstruction ProcurementConstruction ProcurementConstruction Procurement
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 11 of 12 TASK filter: All Activities
Responsibility
386 Develop Construction RFP 06-Dec-23 02-Jan-24 20 PgM
387 Review Construction RFP 03-Jan-24 16-Jan-24 10 FM
388 Revise Construction RFP 17-Jan-24 30-Jan-24 10 PgM
389 Review Construction RFP 31-Jan-24 01-Mar-24 23 ASD
390 Revise Construction RFP 04-Mar-24 11-Mar-24 6 PgM
391 Release Construction RFP 11-Mar-24 0 ASD
392 Solicit Construction Contract 12-Mar-24 22-Apr-24 30 ASD
393 Submit Bids 22-Apr-24 0 GC
394 Conduct SSEB 23-Apr-24 06-May-24 10 FM
395 Negotiate Contract 07-May-24 27-May-24 15 ASD
396 Award Construction Contract 27-May-24 0 ASD
397 ConstructionConstructionConstructionConstructionConstruction
398 Issue NTP 28-May-24 0 ASD
399 Construction 28-May-24 03-Feb-25 180 GC
400 Contract Close-OutContract Close-OutContract Close-OutContract Close-OutContract Close-Out
401 Submit As-Builts 17-Feb-25 0 GC
402 Submit O&M Manuals 17-Feb-25 0 GC
403 Contract Complete/Last day of Period of Performance 03-Mar-25 0 CM
404 Project Close-OutProject Close-OutProject Close-OutProject Close-OutProject Close-Out
405 One Year Warranty Period Begins 04-Feb-25 0 FM
406 Deliver Completed Close-out Documents 17-Mar-25 0 CM
407 Enter Fixed Assets into Manager Plus 17-Mar-25 0 FM
408 Enter Architectural and Furniture shop drawings to FM systems 17-Mar-25 0 FM
409 Conduct a 9-month Warranty Walk/Inspection 05-Nov-25 0 FM
410 One Year Warranty Period Ends 04-Feb-26 0 FM
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2024 2025
DC Courts Integrated Program Schedule October 2023 Update 01-Nov-23
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
2nd Baseline Milest...
Milestone
Page 12 of 12 TASK filter: All Activities