This is a Task Assignment Change Order Form (Change Order No. 3) for DEP Contract No. BS135, issued on June 4, 2020, between the Florida Department of Environmental Protection (FDEP) and Mott MacDonald Florida, LLC. The contract involves data acquisition and inundation modeling and mapping services for dam safety assessments in Florida. Key personnel include David Skipper (Contractor Contract Manager for Mott MacDonald) and Genita Alexander (DEP Contract Manager). The contract scope encompasses work on multiple dams across Clay County (Lake Asbury South Dam, Lake Larc Dam, Lake Ryan Dam, and Lake Asbury North Dam) and Putnam County (Gibbs Avenue Dam and Ketter Causeway Dam), with support from subcontractors including Comak Group and Southeastern Surveying and Mapping Corp.
The contract requires completion of No Dam Break inundation modeling and mapping for the Lake Asbury Dam System and an updated Digital Elevation Model (DEM) for two dams in Putnam County. This change order adjusts deliverable due dates without modifying the contract amount or overall task period. The original task amount of $77,079.84 remains unchanged, with net increase/decrease of $0.00. The completion date prior to this change was July 31, 2020, and this change order maintains that same completion date with zero net increase or decrease in task period. Specific deliverable dates were modified, including Task 2.a. and 2.b. (May 1, 2020), Task 3.a. first draft (June 17, 2020), second draft (June 29, 2020), and final report (July 27, 2020). The contract is structured on a fixed-price basis with compensation tied to deliverable completion and FDEP acceptance.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT D – TASK ASSIGNMENT CHANGE ORDER FORM
DEP CONTRACT NO. BS135
Task Assignment Number: ______04____
Date: _____06/04/2020_____
Change Order No.____3___
Contractor Name:
Mott MacDonald Florida, LLC
Contractor Contract Manager: __David Skipper_____________________
Phone: _850-222-0334__________
DEP Contract Manager: ____Genita Alexander _____________
Phone: _850-245-8021____ __
Description of Change (Use Additional Sheets if necessary:
Complete No Dam Break inundation modeling and mapping for Lake Asbury Dam System and an updated Digital Elevation Model (DEM) for (2) dams in Putnam County, as described in the 03/03/2020 Scope of Services.
Deliverable due date changes follow:
Task 2.a.: May 1, 2020 Task 2.b.: May 1, 2020 Task 3.a.: 1st Draft – June17, 2020 2nd Draft – June 29, 2020 Final report – July 27, 2020
CHANGE IN TASK AMOUNT
Item Fee Schedule Cost Reimbursement
Total
Original Task Amount: $77,079.84 $77,079.84
Task Amount Prior to this Change Order: $77,079.84 $77,079.84
Net Increase/Decrease in Task Amount: $0.00 $0.00 Task Amount with all Change Orders: $77,079.84 $77,079.84
CHANGE IN TASK TIME
Original Task Completion Date: June 29, 2020 Completion Date Prior to This Change: July 31, 2020
Net Increase/Decrease in Task Period: 0 days Completion Date with all Change Orders: July 31, 2020
CONTRACTOR
FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION
Contract Manager Date Project Manager
Contract Manager
Date
Date
APPROVED:
Cost Center Administrator Date cc: DEP Procurement Section (MS93), Bureau of Finance and Accounting (MS78) – 2 copies Contract No. BS135
Digitally signed by David Skipper DN: cn=David Skipper, c=US, o=Unaffiliated, ou=A01410C0000016FC9EAEA36000089DE, email=david.skipper@mottmac.com Date: 2020.06.04 08:17:19 -05'00'
David Skipper Tracy Woods Digitally signed by Tracy Woods
Date: 2020.06.04 15:55:21 -04'00'
Genita Alexander Digitally signed by Genita Alexander Date: 2020.06.08 12:11:38 -04'00'
Rhonda Massey Digitally signed by Rhonda Massey Date: 2020.06.08 15:27:07 -04'00'
May 13, 2020
Initial: DS Initial: DS
June 4, 2020
Johnson, James J Line
Johnson, James J Line
Johnson, James J Line
Johnson, James J Line
Initial: DS
06/10/2020
06/29/2020
07/27/2020
06/17/2020
Initial: DS
Johnson, James J Line
Johnson, James J Line
Johnson, James J Line
Johnson, James J Line
Johnson, James J Line
Johnson, James J Line
File details come from the government source that posted it. Updated .