This is a Procurement Plan document prepared by the Orange County Transportation Authority (OCTA) for RFP 250153, which solicits proposals from qualified consultants to build, deploy, and manage a Microsoft Azure cloud environment supporting OCTA's desktop and enterprise geographic information systems (GIS). The project encompasses a three-and-a-half-year contract term effective April 1, 2026 through September 30, 2029. The RFP will be evaluated using four weighted criteria: Qualifications of the Firm (30%), Staffing/Project Organization (20%), Work Plan (25%), and Cost (25%). The procurement plan specifies that qualified proposers must be a Gold or Platinum Esri partner with Azure-certified staff and a minimum of seven to ten years of experience with ArcGIS Enterprise cloud migrations for public agencies.

The total contract value is $380,000 for the three-and-a-half-year term with no option years. The contract will be structured as a firm-fixed-price agreement due to the specific scope of work detailing distinct tasks and deliverables. Funding will be provided through Measure M2, and an independent cost estimate has been received along with requisition number R000629. The procurement plan includes no prevailing wage requirements, no liquidated damages provisions, no retention requirements, and no Disadvantaged Business Enterprise (DBE) goals. The suggested internal evaluation team consists of Ivy Hang (Senior Transportation Analyst, Planning & Analysis), Steve Hossack (Senior Section Manager, Geographic Information Systems), and Ryan Puchahes (Senior Systems Engineer, Information Systems).

View the file

Other files

Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

Procurement Plan, RFP 250153

Date: December 23, 2025

To: Steve Hossack, PE, Senior Section Manager, Geographic Information Systems

From: Rhea Aninzo, Contract Administrator, CAMM

Subject: PROCUREMENT PLAN – RFP 250153 “Geographic Information Systems (GIS) Cloud Migration Hosting and Management”

Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.

Procurement Type: |X| RFP |_| IFB

Justification (explain the rationale for using the particular procurement type):

An RFP is applicable as the procurement requires evaluation criteria, in addition to price, to be used to select a firm to build, deploy, and manage a Microsoft Azure cloud environment to support OCTA’s desktop and enterprise geographic information systems (GIS).

Evaluation Criteria:

PROPOSAL
WEIGHT
Qualifications of the Firm
30%
Staffing/Project Organization
20%
Work Plan
25%
Cost
25%

Justification:

Qualifications of the firm is weighted the highest at thirty percent (30%) as the scope requires a Gold or Platinum Esri partner, Azure-certified staff, and at least seven (7) to (10) years of experience with ArcGIS Enterprise cloud migrations for public agencies. Staffing and project organization is weighted at twenty percent (20%) as the proposed team must demonstrate specialized expertise necessary to architect, migrate, and manage a cloud-based GIS environment. Work plan is weighted at twenty-five (25%) as the firm’s proposed work plan should clearly demonstrate its approach to successfully completing the scope of work. Cost and price is weighted at twenty-five (25%) to ensure OCTA receives the best value for the services.

Contract Type: |_| Time & Expense |_| CTO-Based |X| Firm-Fixed Price

Justification (Explain the rationale for using the particular contract type):

The contract type is firm-fixed price because the RFP has a specific Scope of Work detailing specific tasks and deliverables.

Retention:
|_| Yes
%
|X| No
|_| N/A
Prevailing Wages:
|_| Yes
$
|_| No
|X| N/A
Liquidated Damages:
|_| Yes
$
|_| No
|X| N/A

P.M. to provide support documentation identifying how the LD amount was established.

Procurement Schedule: |X| Attached

Suggested Evaluation Team Members:

Internal Evaluators:

Ivy Hang, Senior Transportation Analyst, Planning & Analysis Steve Hossack, PE, Senior Section Manager, Geographic Information Systems Ryan Puchahes, Senior Systems Engineer, Information Systems

Contract Term: (Include Option Years)

Three and a one-half (3 ½) years effective April 1, 2026 through September 30, 2029

Funding Source: |_| Local |X| Measure M2 |_| Federal (CMAQ)

Dollar Amount: |X| Term $380,000 |_| Option Term

Independent Cost Estimate Received: |X| Yes |_| No

Requisition Received: |X| Yes #R000629 |_| No

DBE Goal: |_| Yes |X| No

Project Manager Concurrence:

_____________________________________________________________
Steve Hossack, PE, GIS Section ManagerDate

CAMM Section/Department Manager Concurrence:

_____________________________________________________________
Iris Deneau, Section Manager, ProcurementDate