This is a Procurement Plan memorandum from the Orange County Transportation Authority (OCTA) dated December 23, 2025, outlining the procurement strategy for RFP 250153 to select a qualified consultant for Geographic Information Systems (GIS) Cloud Migration Hosting and Management. OCTA seeks proposals from firms to build, deploy, and manage a Microsoft Azure cloud environment supporting the agency's desktop and enterprise GIS systems. The procurement will be conducted as a Request for Proposal (RFP) rather than an Invitation for Bid, as the selection requires evaluation criteria beyond price. The contract term is three and one-half years, effective April 1, 2026, through September 30, 2029. No specific response deadline, due date, site visit requirements, or bidder conference details are documented in the procurement plan.

The total project budget is $380,000 for the entire contract term, funded through Measure M2. The contract will be structured as a firm-fixed price agreement due to the clearly defined scope of work with specific tasks and deliverables. Evaluation will be weighted as follows: Qualifications of the Firm (30%), Staffing and Project Organization (20%), Work Plan (25%), and Cost (25%). The procurement requires that the selected firm be a Gold or Platinum Esri partner with Azure-certified staff and a minimum of seven to ten years of experience with ArcGIS Enterprise cloud migrations for public agencies. No prevailing wage, liquidated damages, retention provisions, or DBE goals apply to this procurement. An independent cost estimate has been received, and requisition R000629 has been issued. The suggested internal evaluation team includes Ivy Hang, Steve Hossack, and Ryan Puchahes from various OCTA departments.

View the file

Other files

File Type Posted
Geographic_Information_Systems_(GIS)_Cloud_Migration_Hosting_and_Management_(Addendum_#1_Revision).pdf PDF
C250153_RFP_Exhibit_A,_SOW.pdf PDF
C250153_RFP_Exhibit_B,_Proposed_Agreement.pdf PDF
C250153_RFP_Exhibit_C,_Safety_Specs.pdf PDF
C250153_RFP_Exhibit_B,_Proposed_Agreement_gmedits.pdf PDF
C250153_RFP_Exhibit_A,_SOW_gmedits.pdf PDF
C250153_PP_12-23-25-APPROVED.pdf PDF
C250153_RFP.docx DOCX document
C250153_RFP_Exhibit_A,_SOW.docx DOCX document
C250153_PP_12-23-25.pdf PDF
C250153_PP_12-23-25_idedits.docx DOCX document
C250153_R000629_idedits.pdf PDF
C250153_ICE_idedits.pdf PDF
RFP-250153-2026-01-07-11-42-48_idedits.docx DOCX document
[B]_C250153_RFP_Exhibit_B,_Proposed_Agreement_idedits.docx DOCX document
[A]_C250153_RFP_Exhibit_A,_SOW_idedits.docx DOCX document
C250153_Public_Notice_Proof.pdf PDF
C250153_Email_PP_and_PS_Info_12-22-25.pdf PDF
C250153_Insurance_Approval_by_RM_12-18-25.pdf PDF
C250153_PS_12-23-25.docx DOCX document
C250153_Public_Notice_Invoice.pdf PDF
C250153_Insurance_Approval_Request_Memo_12-15-25.pdf PDF
C250153_Form_700_Review_12-16-25.pdf PDF
C250153_ICE.pdf PDF
C250153_R000629.pdf PDF
C250153_SOW_Verification.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INTEROFFICE MEMO

Procurement Plan, RFP 250153

Date: December 23, 2025

To: Steve Hossack, PE, Senior Section Manager, Geographic Information Systems

From: Rhea Aninzo, Contract Administrator, CAMM

Subject: PROCUREMENT PLAN – RFP 250153 “Geographic Information Systems (GIS) Cloud Migration Hosting and Management”

Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.

Procurement Type: |X| RFP |_| IFB

Justification (explain the rationale for using the particular procurement type):

An RFP is applicable as the procurement requires evaluation criteria, in addition to price, to be used to select a firm to build, deploy, and manage a Microsoft Azure cloud environment to support OCTA’s desktop and enterprise geographic information systems (GIS).

Evaluation Criteria:

PROPOSAL
WEIGHT
Qualifications of the Firm
30%
Staffing/Project Organization
20%
Work Plan
25%
Cost
25%

Justification:

Qualifications of the firm is weighted the highest at thirty percent (30%) as the scope requires a Gold or Platinum Esri partner, Azure-certified staff, and at least seven (7) to (10) years of experience with ArcGIS Enterprise cloud migrations for public agencies. Staffing and project organization is weighted at twenty percent (20%) as the proposed team must demonstrate specialized expertise necessary to architect, migrate, and manage a cloud-based GIS environment. Work plan is weighted at twenty-five (25%) as the firm’s proposed work plan should clearly demonstrate its approach to successfully completing the scope of work. Cost and price is weighted at twenty-five (25%) to ensure OCTA receives the best value for the services.

Contract Type: |_| Time & Expense |_| CTO-Based |X| Firm-Fixed Price

Justification (Explain the rationale for using the particular contract type):

The contract type is firm-fixed price because the RFP has a specific Scope of Work detailing specific tasks and deliverables.

Retention:
|_| Yes
%
|X| No
|_| N/A
Prevailing Wages:
|_| Yes
$
|_| No
|X| N/A
Liquidated Damages:
|_| Yes
$
|_| No
|X| N/A

P.M. to provide support documentation identifying how the LD amount was established.

Procurement Schedule: |X| Attached

Suggested Evaluation Team Members:

Internal Evaluators:

Ivy Hang, Senior Transportation Analyst, Planning & Analysis Steve Hossack, PE, Senior Section Manager, Geographic Information Systems Ryan Puchahes, Senior Systems Engineer, Information Systems

Contract Term: (Include Option Years)

Three and a one-half (3 ½) years effective April 1, 2026 through September 30, 2029

Funding Source: |_| Local |X| Measure M2 |_| Federal (CMAQ)

Dollar Amount: |X| Term $380,000 |_| Option Term

Independent Cost Estimate Received: |X| Yes |_| No

Requisition Received: |X| Yes #R000629 |_| No

DBE Goal: |_| Yes |X| No

Project Manager Concurrence:

_____________________________________________________________
Steve Hossack, PE, GIS Section ManagerDate

CAMM Section/Department Manager Concurrence:

_____________________________________________________________
Iris Deneau, Section Manager, ProcurementDate