This is a Procurement Plan memorandum from the Orange County Transportation Authority (OCTA) regarding RFP 250153 for Geographic Information Systems (GIS) Cloud Migration Hosting and Management. The procurement seeks qualified consultants to build, deploy, and manage a Microsoft Azure cloud environment supporting OCTA's desktop and enterprise GIS systems. The contract term is three and a half years, effective April 1, 2026, through September 30, 2029, with no renewal options specified. The RFP requires evaluation based on multiple criteria beyond price, necessitating a formal request for proposals rather than an invitation for bid.
The total contract value is $380,000 for the full three-and-a-half-year term. The procurement is funded through Local Measure M2 and Federal CMAQ sources. Evaluation criteria are weighted as follows: Qualifications of the Firm (30%), Staffing and Project Organization (20%), Work Plan (25%), and Cost (25%). The evaluation emphasizes that proposing firms must be Gold or Platinum Esri partners with Azure-certified staff and seven to ten years of experience with ArcGIS Enterprise cloud migrations for public agencies. The contract type is firm-fixed price due to the specific scope of work and defined deliverables. The procurement plan includes retention requirements, prevailing wage applicability, and liquidated damages provisions. Internal evaluators include Ivy Hang, Ryan Puchahes, and Steve Hossack, PE, representing Planning & Analysis, Information Systems, and GIS sections respectively. An independent cost estimate was received, and requisition R000629 was issued.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised: 07/20/2010
INTEROFFICE MEMO
Date: December 23, 2025
To: Steve Hossack, PE, Senior Section Manager, Geographic Information
Systems
From: Rhea Aninzo, Contract Administrator, CAMM
Subject: PROCUREMENT PLAN – RFP 250153 “Geographic Information
Systems (GIS) Cloud Migration Hosting and Management”
Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments.
Procurement Type: RFP IFB
Justification (explain the rationale for using the particular procurement type):
An RFP is applicable as the procurement requires evaluation criteria, in addition to price, to be used to select a firm to build, deploy, and manage a Microsoft Azure cloud environment to support OCTA’s desktop and enterprise geographic information systems (GIS).
Evaluation Criteria:
PROPOSAL WEIGHT
Qualifications of the Firm 30% Staffing/Project Organization 20% Work Plan 25% Cost 25% Justification:
Qualifications of the firm is weighted the highest at thirty percent (30%) as the scope requires a Gold or Platinum Esri partner, Azure-certified staff, and at least seven (7) to (10) years of experience with ArcGIS Enterprise cloud migrations for public agencies. Staffing and project organization is weighted at twenty percent (20%) as the proposed team must demonstrate specialized expertise necessary to architect, migrate, and manage a cloud-based GIS environment. Work plan is weighted at twenty-five (25%) as the firm’s proposed work plan should clearly demonstrate its approach to successfully completing the scope of work. Cost and price is weighted at twenty-five (25%) to ensure OCTA receives the best value for the services.
Contract Type: Time & Expense CTO-Based Firm-Fixed Price
Justification (Explain the rationale for using the particular contract type):
The contract type is firm-fixed price because the RFP has a specific Scope of Work detailing specific tasks and deliverables.
Procurement Plan, RFP 250153
Revised: 0720/2010
Retention: Yes % No N/A
Prevailing Wages: Yes $ No N/A
Liquidated Damages: Yes $ No N/A
P.M. to provide support documentation identifying how the LD amount was established.
Procurement Schedule: Attached
Suggested Evaluation Team Members:
Internal Evaluators:
Ivy Hang, Senior Transportation Analyst, Planning & Analysis Steve Hossack, PE, Senior Section Manager, Geographic Information Systems Ryan Puchahes, Senior Systems Engineer, Information Systems
Contract Term: (Include Option Years)
Three and a one-half (3 ½) years effective April 1, 2026 through September 30, 2029
Funding Source: Local Measure M2 Federal (CMAQ)
Dollar Amount: Term $380,000
Independent Cost Estimate Received: Yes No
Requisition Received: Yes #R000629 No
DBE Goal: Yes No
Project Manager Concurrence:
Steve Hossack, PE, GIS Section Manager Date
CAMM Section/Department Manager Concurrence:
Iris Deneau, Section Manager, Procurement Date