About this file
This is a Final Plan Approval Letter issued by the Town of Bluffton, South Carolina, for a public development project at the Buckwalter Recreation Center. The project, identified as Development Plan Application DP-10-23-018587, involves the construction of four new artificial turf soccer fields, a new restroom building, renovations to an existing restroom facility, new parking areas, driveways, sidewalks, storm water management facilities, associated utilities, site and sports lighting, site furnishings, and landscaping on approximately 142.9 acres within the Buckwalter Planned Unit Development. The approval, effective April 8, 2025, and expiring April 8, 2027, was issued to Eric Walsnovich of Wood and Partners, Inc., on behalf of property owner Town of Bluffton. The project received required approvals including MS4 approval on April 24, 2024, and an NPDES Permit on February 13, 2025. Prior to commencing horizontal construction, the applicant must schedule and host a pre-construction meeting with Town staff, the design engineer, the site general contractor, and other necessary personnel. Following this meeting, the applicant will receive a Conditional Notice to Proceed authorizing installation of tree protection fencing and erosion control devices. After Town approval of pre-clearing and stormwater inspections, the applicant will receive a Notice to Proceed authorizing commencement of construction.
The approval letter establishes the procedural framework for project implementation but does not specify pricing, contract terms, or funding sources within this document. These details are addressed in the associated Beaufort County Invitation for Bid (IFB #120925), which requires sealed bids to be submitted by December 9, 2025, at 3:00 pm EST, with a non-mandatory pre-bid conference scheduled for October 29, 2025. The contract time is 540 days from Notice to Proceed, with contractors required to commence work within 15 calendar days of receiving notice. Bidders must provide a 5% bid bond and comply with South Carolina Department of Transportation Standard Specifications. The project funding will be provided through state, federal, and/or Beaufort County appropriations, with monthly progress payments at 90% of completed work and 10% retainage held until final completion. Liquidated damages are assessed at $600 per calendar day for project delays.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF BLUFFTON
FINAL PLAN APPROVAL
APPLICATION NO.: DP-10-23-018587
APPLICATION TYPE: Development Plan
PARCEL NO.: R610 038 000 0053 0000
PROPERTY ADDRESS: 800 BUCKWALTER PARKWAY,
BLUFFTON SC 29910
ZONING DISTRICT:
ISSUE DATE: 04/08/2025
APPROVAL DATE: 04/08/2025
EXPIRATION DATE: 04/08/2027
Eric Walsnovich Wood and Partners, Inc.
Stephen Steese Town of Bluffton
APPLICANT: OWNER:
DESCRIPTION:A request by Eric Walsnovich of Wood + Partners, Inc, on behalf of the property owner, Town of Bluffton, for approval of a public project. The project proposes the construction of four new soccer fields; a new restroom building; renovations to the existing restroom building; new parking areas, driveways and sidewalks; storm water management facilities; associated utilities; lighting; site furnishings and landscaping. The property is zoned Buckwalter Planned Unit Development and consists of approximately
142.9 acres identified by tax map number R610 038 000 0053 0000 located within the Buckwalter Recreation Center Master Plan.
Status: Comments on the public project were reviewed at the November 15, 2023, meeting of the DRC.
Status 4/24/24: The Public Project received MS4 approval.
Status 2/13/25: The Public Project received NPDES Permit.
Status 3/25/25: The Applicant resubmitted for FDP Approval.
Status 4/8/25: The Public Project is APPROVED.
TOWN OF BLUFFTON APPROVAL SIGNATURE DATE
The Applicant must schedule and host a Pre-Construction Meeting with Town Staff, the design engineer, the site general contractor, and any other necessary personnel involved in the horizontal construction. After the this meeting is conducted, the Applicant will be provided a Conditional Notice to Proceed authorizing the installation of tree protection fencing and erosion control devices. Upon installation of such fencing and devices, the Applicant must schedule Pre-Clearing and Stormwater Inspections of the completed work. Once approved by the Town, the Applicant will be provided a Notice to Proceed authorizing the commencement of horizontal construction as depicted in this Final Plan Approval.
Theodore D. Washington Municipal Building 20 Bridge Street P.O. Box 386 Bluffton, South Carolina 29910
Telephone (843) 706-4522 Fax (843) 706-4518 Town Web Site www.townofbluffton.sc.gov
Email- growthmanagementcs@townofbluffton.com
4/8/25
File details come from the government source that posted it. Updated .