This is an addendum document for Beaufort County, South Carolina's Buckwalter Recreation Athletic Complex Expansion project that delineates the scope of work responsibilities between the General Contractor and Musco Sports Lighting for the installation of sports lighting components at the facility. The addendum specifies that sports lighting will be contracted separately with the County rather than included in the General Contractor's bid price, as shown on the revised Concessions Building Plan Sheet E3.1. The General Contractor is responsible for providing site access using two-wheel drive equipment, locating and marking existing underground utilities and field reference points, providing disposal areas for spoils and dumpsters, and installing the Musco control and monitoring cabinet system including conduit, wiring, and connections up to 10 feet on each light pole. The General Contractor must also commission the Control-Link system by contacting Control-Link Central and maintain communication with the Musco Representative, Brian Hartman (803-904-0302), regarding project coordination and timeline.
Musco Sports Lighting's scope of work encompasses providing the complete lighting design and layout based on photometric scans, supplying all foundations, poles, electrical enclosures, wire harnesses, fixtures, and control cabinets, and managing the installation through their subcontractor. Musco is responsible for obtaining required permits, contacting 811 for public utility locates and confirming marked private utilities with the facility owner, handling equipment offloading and storage, providing security for delivered products, managing waste disposal and daily cleanup, and ensuring installation commences upon delivery without interruption. Additionally, Musco must test and aim all equipment, repair damage to marked utilities, and submit a closeout checklist with required documentation. The document emphasizes coordination between both parties to ensure seamless pole installation and site progress, with the understanding that Musco or its subcontractor will not be responsible for repairs to unmarked utilities.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The following addendum is for the removal of Sports Lighting components from the General Contractors’ bid price. Review the General Contractors’ Scope of Work items below that are to be included in the Bid Price, and as shown on the revised Concessions Building Plan Sheet E3.1.
Musco Lighting’s responsibilities and scope of work is also outlined below. These items will be contracted separately with the County.
1. General Contractors’ Scope of Work:
a. General:
i. Complete access to the site for construction utilizing 2-wheel drive rubber tire equipment.
ii. Locate existing underground utilities not covered by your local utilities. (i.e., water lines, electrical lines, irrigation systems, and sprinkler heads). Musco or Subcontractor will not be responsible for repairs to unmarked utilities.
iii. Locate and mark field reference points per Musco supplied layout.
(i.e. home plate, center of FB field) Have pole locations surveyed in and marked accordingly.
iv. Provide area on site for disposal of spoils from foundation excavation.
v. Provide area on site for dumpsters.
b. Control-Link® Control and Monitoring:
i. Provide labor, equipment, and materials to install Musco control and monitoring cabinet(s) and terminate all necessary wiring.
ii. Provide a dedicated 120 V 20 A controls circuit or a step-down transformer for 120 V control circuit if not available.
iii. Check all zones to make sure they work in both auto and manual mode.
iv. Commission Control-Link by contacting Control-Link Central™ at 877- 347-3319.
v. Run conduit and wire from service through Musco Controls and Monitoring cabinet out to each light pole (up to 10’ on each pole).
vi. Make all connections/ terminations.
vii. Communicating with Musco Representative in regard to project timeline and ensuring seamless pole installation/ site progress.
viii. If there are any further questions in regard to coordination or Musco products, please reach out to Musco Representative, Brian Hartman, at 803-904-0302.
End of General Contractor’s Scope of Work
2. Musco Sports Lighting Scope of Work:
a. General:
i. Provide design and layout for lighting system (Based off of 170390E Photometric Scans)
ii. Test and final aim equipment.
iii. Provide required foundations, poles, electrical enclosures, wire harnesses, fixtures, and control cabinets.
iv. Provide layout of pole locations and aiming diagram.
v. Provide Contract Management as required.
vi. Assist our (Musco’s) installing subcontractor and ensure our responsibilities are satisfied.
vii. Obtain any required permitting.
viii. Contact your local 811 to locate underground public utilities and then confirm they have been clearly marked.
ix. Contact the facility owner/manager to confirm the existing private underground utilities and irrigation systems have been located and are clearly marked to avoid damage from construction equipment.
x. Notify owner and repair damage to marked utilities. Notify owner and Musco regarding damage which occurred to unmarked utilities.
xi. Provide labor, equipment, and materials to offload equipment at jobsite per scheduled delivery. Control and monitoring cabinets will need to be given to on-site customer representative.
xii. Provide storage containers for materials (including electrical components enclosures) as needed.
xiii. Provide necessary waste disposal and daily cleanup.
xiv. Provide adequate security to protect Musco delivered products from theft, vandalism, or damage during the installation.
xv. Keep all heavy equipment off playing fields when possible. Repair damage to grounds which exceeds that which would be expected.
Indentations caused by heavy equipment traveling over dry ground would be an example of expected damage. Ruts and sod damage caused by equipment traveling over wet ground would be an example of damage requiring repair.
xvi. Installation to commence upon delivery and proceed without interruption until complete. Notify Musco immediately of any breaks in schedule or delays.
xvii. Complete and submit Musco provided closeout checklist including required pictures.
b. Foundations, Poles, and Luminaires:
i. Confirm pole locations per the aiming drawing provided and surveyed/ marked locations from General Contractor. If there are any issues, immediately notify your Musco Project Manager.
ii. Provide labor, materials, and equipment to install LSS foundations as specified on Layout and per the stamped foundation drawings, if applicable.
iii. Remove spoils and dispose of off-site.
iv. Provide labor, materials, and equipment to assemble Musco TLC-LED fixtures, electrical enclosures, poles, and pole harnesses.
v. Provide labor, equipment, and materials to erect dressed LSS Poles and aim utilizing the pole alignment beam.
End of Musco Sports Lighting Scope of Work
| 1. General Contractors’ Scope of Work: |
| a. General: |
| i. Complete access to the site for construction utilizing 2-wheel drive rubber tire equipment. |
| ii. Locate existing underground utilities not covered by your local utilities. (i.e., water lines, electrical lines, irrigation systems, and sprinkler heads). Musco or Subcontractor will not be responsible for repairs to unmarked utilities. |
| iii. Locate and mark field reference points per Musco supplied layout. (i.e. home plate, center of FB field) Have pole locations surveyed in and marked accordingly. |
| iv. Provide area on site for disposal of spoils from foundation excavation. |
| v. Provide area on site for dumpsters. |
| b. Control-Link® Control and Monitoring: |
| i. Provide labor, equipment, and materials to install Musco control and monitoring cabinet(s) and terminate all necessary wiring. |
| ii. Provide a dedicated 120 V 20 A controls circuit or a step-down transformer for 120 V control circuit if not available. |
| iii. Check all zones to make sure they work in both auto and manual mode. |
| iv. Commission Control-Link by contacting Control-Link Central™ at 877-347-3319. |
| v. Run conduit and wire from service through Musco Controls and Monitoring cabinet out to each light pole (up to 10’ on each pole). |
| vi. Make all connections/ terminations. |
| vii. Communicating with Musco Representative in regard to project timeline and ensuring seamless pole installation/ site progress. |
| viii. If there are any further questions in regard to coordination or Musco products, please reach out to Musco Representative, Brian Hartman, at 803-904-0302. |
| End of General Contractor’s Scope of Work |
| 2. Musco Sports Lighting Scope of Work: |
| a. General: |
| i. Provide design and layout for lighting system (Based off of 170390E Photometric Scans) |
| ii. Test and final aim equipment. |
| iii. Provide required foundations, poles, electrical enclosures, wire harnesses, fixtures, and control cabinets. |
| iv. Provide layout of pole locations and aiming diagram. |
| v. Provide Contract Management as required. |
| vi. Assist our (Musco’s) installing subcontractor and ensure our responsibilities are satisfied. |
| vii. Obtain any required permitting. |
| viii. Contact your local 811 to locate underground public utilities and then confirm they have been clearly marked. |
| ix. Contact the facility owner/manager to confirm the existing private underground utilities and irrigation systems have been located and are clearly marked to avoid damage from construction equipment. |
| x. Notify owner and repair damage to marked utilities. Notify owner and Musco regarding damage which occurred to unmarked utilities. |
| xi. Provide labor, equipment, and materials to offload equipment at jobsite per scheduled delivery. Control and monitoring cabinets will need to be given to on-site customer representative. |
| xii. Provide storage containers for materials (including electrical components enclosures) as needed. |
| xiii. Provide necessary waste disposal and daily cleanup. |
| xiv. Provide adequate security to protect Musco delivered products from theft, vandalism, or damage during the installation. |
| xv. Keep all heavy equipment off playing fields when possible. Repair damage to grounds which exceeds that which would be expected. Indentations caused by heavy equipment traveling over dry ground would be an example of expected damage. Ruts and sod d... |
| xvi. Installation to commence upon delivery and proceed without interruption until complete. Notify Musco immediately of any breaks in schedule or delays. |
| xvii. Complete and submit Musco provided closeout checklist including required pictures. |
| b. Foundations, Poles, and Luminaires: |
| i. Confirm pole locations per the aiming drawing provided and surveyed/ marked locations from General Contractor. If there are any issues, immediately notify your Musco Project Manager. |
| ii. Provide labor, materials, and equipment to install LSS foundations as specified on Layout and per the stamped foundation drawings, if applicable. |
| iii. Remove spoils and dispose of off-site. |
| iv. Provide labor, materials, and equipment to assemble Musco TLC-LED fixtures, electrical enclosures, poles, and pole harnesses. |
| v. Provide labor, equipment, and materials to erect dressed LSS Poles and aim utilizing the pole alignment beam. |
End of Musco Sports Lighting Scope of Work