BRACE_Pricing_Table_Template_021026.xlsx
XLSX spreadsheet 30 KB Posted
- Attached to
- Buckwalter Recreation Athletic Complex Expansion
- Solicitation number
- 120925
- Issued by
- Beaufort County, South Carolina
About this file
This is a pricing table template for the Buckwalter Recreation Athletic Complex Expansion project, a comprehensive construction contract issued by Beaufort County, South Carolina. The project encompasses multiple construction phases organized into a base bid and one alternate, with detailed line items spanning site preparation and demolition, erosion control, site grading, drainage systems, utilities (sewer, water, and electric), building construction, site paving and walls, soccer fields, site furnishings, and landscaping. The base bid includes 13 major sections (A through L) covering foundational work such as site mobilization, bonds and insurance, clearing and grubbing, tree protection, and removal of existing infrastructure, followed by specialized work including the installation of artificial turf soccer fields, concrete paving, retaining walls, fencing, and comprehensive landscaping with irrigation systems. Alternate 1 (ALT 1) addresses work south of the existing traffic circle and includes similar categories with modified scope items, including a new restroom building, additional drainage infrastructure, and expanded utilities connections. The sealed bid submission deadline is December 9, 2025, at 3:00 pm EST, with a non-mandatory pre-bid conference scheduled for October 29, 2025, at 2:00 pm. The contract term is 540 days from the Notice to Proceed, with contractors required to commence work within 15 calendar days of receiving the notice.
The pricing table requires bidders to supply unit costs and quantities for each line item, with section totals and a combined base bid total calculated automatically. Notable priced items in the template include Soccer Backstop Netting at $240.00 per linear foot, Diamond Rail Fence at $540.00 per linear foot, and 4 Foot Chain Link Fence and Gates at $790.00 per linear foot. The project requires a 5% bid bond and compliance with South Carolina Department of Transportation Standard Specifications for Highway Construction (2025 Edition). Bidders must submit a Good Faith Efforts Checklist and Proposed Utilization Plan for Small and Minority Business Participation. Payment terms are structured as monthly progress payments at 90% of completed work with 10% retainage held until final completion. Liquidated damages are assessed at $600 per calendar day for project delays. Contractors must be licensed or hold Irrigation Association Certification, with irrigation systems requiring a minimum water pressure of 115 psi. Insurance requirements include worker's compensation, commercial general liability, and automobile liability coverage, with Beaufort County named as an additional insured. Project funding is derived from state, federal, and/or Beaufort County appropriations, though a specific total project budget is not identified in this pricing template.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing_Table_Template Line Item Description Unit of Measure Unit Cost Quantity Total
Base Bid Section
| A. Site Preparation and Demolition | |||
| A.1 | Site Mobilization | LS | |
| A.2 | Bonds & Insurance | LS | |
| A.3 | Construction Staking | LS | |
| A.4 | Traffic Control | LS | |
| A.5 | Asbuilt Construction Plans | LS | |
| A.6 | Tree Protection | LF | |
| A.7 | Clearing & Grubbing | SF | |
| A.8 | Removal & Disposal - Asphalt Paving | SF | |
| A.9 | Removal & Disposal - Concrete Sidewalks | SF | |
| A.10 | Remove and Reinstall Existing Well Pump | LS | |
| A.11 | Remove Existing 8" Sanitary Sewer Stub-out | EA | |
| A.12 | Remove Existing 3" Sanitary Sewer Force Main | LF | |
| A.13 | Miscellaneous (Provide Description and Unit) | ||
| Site Prep and Demolition Section Total | 0.00 |
| B. Erosion Control | |||
| B.1 | Silt Fence | LF | |
| B.2 | Stabilized Construction Entrance | EA | |
| B.3 | Rip Rap Outlet Protection | SY | |
| B.4 | Sediment Tube | LF | |
| B.5 | Erosion Control Blanket | SF | |
| B.6 | Concrete Washout | EA | |
| B.7 | Inlet Protection | EA | |
| B.8 | Porous Baffles | EA | |
| B.9 | Turf Reinforcement Mat | SF | |
| B.10 | Emergency Spillway | LS | |
| B.11 | Permanent Seeding | SF | |
| B.12 | Erosion Control Maintenance | LS | |
| B.13 | Miscellaneous (Provide Description and Unit) | ||
| Erosion Control Section Total | 0.00 |
| C. Site Grading | |||
| C.1 | Unsatisfactory soil removal and replacement | CY | |
| C.2 | Rough Grading (Cut) | CY | |
| C.3 | Rough Grading (Fill) | CY | |
| C.4 | Fine Grading | SY | |
| C.5 | Select Fill (Imported) | CY | |
| C.6 | Miscellaneous (Provide Description and Unit) | ||
| Site Grading Section Total | 0.00 |
| D. Site Drainage | |||
| D.1 | Infiltration Device with Overdrain | SF | |
| D.2 | 6" Field Drain Outfall w/ Pop Up Emitter | EA | |
| D.3 | 24" Nyloplast Drainage Basin w/ Concrete Collar | EA | |
| D.4 | 6" PVC Field Drain System (Perforated, Solid Pipe) | LF | |
| D.5 | 18" RCP | LF | |
| D.6 | 24" RCP | LF | |
| D.7 | 6" PVC Solid Drain Pipe | LF | |
| D.8 | 8" ACO K200 Trench Drain | LF | |
| D.9 | 3' x 3' Catch Basin | EA | |
| D.10 | General PVC Conduit for Irrigation, Lighting, Etc. | LF | |
| D.11 | 6" Perforated PVC Underdrain in Infiltration Areas | LF | |
| D.12 | Relocate Existing Catch Basin and Convert to Junction Box | EA | |
| D.13 | Miscellaneous (Provide Description and Unit) | ||
| Site Drainage Section Total | 0.00 |
| E. Utilities - Sewer | |||
| E.1 | Sanitary Sewer Cleanout | EA | |
| E.2 | 3" PVC Sewer Pipe w/ fittings | LF | |
| E.3 | 6" PVC Sewer Pipe w/ fittings | LF | |
| E.4 | 8" PVC Sewer Pipe w/ fittings | LF | |
| E.5 | Manhole | EA | |
| E.6 | Service Tie In | EA | |
| E.7 | Air Release Pedestal Assembly | EA | |
| E.8 | Miscellaneous (Provide Description and Unit) | ||
| Utilities-Sewer Section Total | 0.00 |
| F. Utilities - Water | |||
| F.1 | Relocate Existing Fire Hydrant | LS | |
| F.2 | Connect to Existing BJSWA 8" Waterline (Tee and Gate Valve w/ Box) | EA | |
| F.3 | 8" PVC Waterline with fittings | LF | |
| F.4 | Miscellaneous (Provide Description and Unit) | ||
| Utilities-Water Section Total | 0.00 |
| G. Utilities - Site Electric | |||
| G.1 | Coordination with Dominion Energy and Musco Lighting | LS | |
| G.4 | Miscellaneous (Provide Description and Unit) | ||
| Utilities-Site Electric | 0.00 |
| H. Buildings | |||
| H.1 | Concessions Building Renovations | LS | |
| H.2 | Miscellaneous (Provide Description and Unit) | ||
| Building Section Total | 0.00 |
| I. Site Paving and Walls | |||
| I.1 | Concrete Header Curb | LF | |
| I.2 | Gravel Parking Space | EA | |
| I.3 | Concrete Handicap Ramp | SF | |
| I.4 | Concrete Steps and Handrail | LS | |
| I.5 | Concrete Sidewalk | SF | |
| I.6 | Concrete Sidewalk w/ Turndown along Asphalt Pavement | SF | |
| I.7 | ADA Detectable Warnings - Grouted Pavers | SF | |
| I.8 | Concrete Curb | LF | |
| I.9 | Precast Concrete Wheel Stop w/ 24" Long #4 Rebar | EA | |
| I.10 | Pavement Markings (Space Striping, Crosswalks, ADA, Stop Bar, Etc.) | LS | |
| I.11 | Pervious Concrete Paving | SF | |
| I.12 | Asphalt Paving | SF | |
| I.13 | Observation Wells in Pervious Concrete Paving | EA | |
| I.14 | 18" Concrete Curb and Gutter | LF | |
| I.15 | 40" Max. Retaining Wall (Stucco Finish) | LF | |
| I.16 | Miscellaneous (Provide Description and Unit) | ||
| Site Paving and Walls Section Total | 0.00 |
| J. Soccer Fields | ||||
| J.1 | Artificial Turf Soccer Fields | SF | ||
| J.2 | Flush Ribbon Curb at Soccer Fields | LF | ||
| J.3 | Soccer Backstop Netting | LF | $ 240.00 | |
| J.4 | Miscellaneous (Provide Description and Unit) | |||
| Soccer Fields Section Total | 0.00 |
| K. Site Furnishings | ||||
| K.1 | Diamond Rail Fence | LF | $ 540.00 | |
| K.2 | Bike Rack | EA | ||
| K.3 | Security Bollard | EA | ||
| K.4 | Picnic Table (Square) | EA | ||
| K.5 | Backed Bench | EA | ||
| K.6 | Trash Receptacle | EA | ||
| K.7 | 4 Foot Chain Link Fence and Gates | LF | $ 790.00 | |
| K.8 | Handicap Ramp Handrail | LF | ||
| K.9 | Stop Sign | EA | ||
| K.10 | Handicapped Parking Sign | EA | ||
| K.11 | Miscellaneous (Provide Description and Unit) | |||
| Site Furnishings Section Total | 0.00 |
| L. Landscaping | |||
| L.1 | Crape Myrtle - LAIW | EA | |
| L.2 | Crape Myrtle - LAGN | EA | |
| L.3 | Southern Live Oak - QUVI | EA | |
| L.4 | Cabbage Palm - SASA | EA | |
| L.5 | Bald Cypress - TD | EA | |
| L.6 | Pinestraw Bales | EA | |
| L.7 | Centipede Sod - EROP | SF | |
| L.8 | Irrigation Well and Pump System (100% Complete & Installed) | LS | |
| L.9 | Automated Irrigation System (100% Completed & Installed) | LS | |
| L.10 | Miscellaneous (Provide Description and Unit) | ||
| Landscaping Section Total | 0.00 |
TOTAL BASE BID 0.00
ALT 1 - Area is South of the Existing Traffic Circle (See Sheet L-102 for approximate limits of work)
| AA. Site Preparation and Demolition | |||
| AA.1 | Bonds & Insurance | LS | |
| AA.2 | Construction Staking | LS | |
| AA.3 | Miscellaneous (Provide Description and Unit) | LF | |
| Site Preparation and Demolition Section Total | 0.00 |
| AB. Erosion Control | |||
| AB.1 | Concrete Washout | EA | |
| AB.2 | Inlet Protection | EA | |
| AB.3 | Porous Baffles | EA | |
| AB.4 | Turf Reinforcement Mat | SF | |
| AB.5 | Emergency Spillway | LS | |
| AB.7 | Miscellaneous (Provide Description and Unit) | ||
| Erosion Control Section Total | 0.00 |
| AC. Site Grading | |||
| AC.1 | Fine Grading | SY | |
| AC.2 | Miscellaneous (Provide Description and Unit) | ||
| Site Grading Section Total | 0.00 |
| AD. Site Drainage | |||
| AD.1 | Infiltration Device with Overdrain | SF | |
| AD.2 | 6" Field Drain Outfall w/ Pop Up Emitter | EA | |
| AD.3 | 24" Nyloplast Drainage Basin w/ Concrete Collar | EA | |
| AD.4 | 6" PVC Field Drain System (Perforated, Solid Pipe) | LF | |
| AD.5 | 18" RCP | LF | |
| AD.6 | 24" RCP | LF | |
| AD.7 | 3' x 3' Catch Basin | EA | |
| AD.8 | General PVC Conduit for Irrigation, Lighting, Etc. | LF | |
| AD.9 | 4" Perforated PVC Underdrain w/in Access Road | LF | |
| AD.10 | 6" Perforated PVC Underdrain in Infiltration Areas | LF | |
| AD.11 | Miscellaneous (Provide Description and Unit) | ||
| Site Drainage Section Total | 0.00 |
| AE. Utilities - Sewer | |||
| AE.1 | Sanitary Sewer Cleanout | EA | |
| AE.2 | 3" PVC Sewer Pipe w/ fittings | LF | |
| AE.3 | 6" PVC Sewer Pipe w/ fittings | LF | |
| AE.4 | 8" PVC Sewer Pipe w/ fittings | LF | |
| AE.5 | Manhole | EA | |
| AE.6 | Service Tie In | EA | |
| AE.7 | Air Release Pedestal Assembly | EA | |
| AE.8 | Miscellaneous (Provide Description and Unit) | ||
| Utilities-Sewer Section Total | 0.00 |
| AF. Utilities - Water | |||
| AF.1 | Relocate Existing Fire Hydrant | LS | |
| AF.2 | Connect to Existing BJSWA 8" Waterline (Tee and Gate Valve w/ Box) | EA | |
| AF.3 | 8" PVC Waterline with fittings | LF | |
| AF.4 | Domestic Service #1 Assembly | LS | |
| AF.5 | Domestic Service #2 Assembly | LS | |
| AF.6 | Irrigation Service Assembly | LS | |
| AF.7 | New Fire Hyrdrant Assembly | EA | |
| AF.8 | Miscellaneous (Provide Description and Unit) | ||
| Utilities-Water Section Total | 0.00 |
| AG. Utilities - Site Electric | |||
| AG.1 | Coordination with Dominion Energy and Musco Lighting | LS | |
| AG.3 | Miscellaneous (Provide Description and Unit) | ||
| Utilities-Site Electric Section Total | 0.00 |
| AH. Buildings | |||
| AH.1 | Restroom Building | LS | |
| AH.2 | Miscellaneous (Provide Description and Unit) | ||
| Buildings Section Total | 0.00 |
| AI. Site Paving and Walls | |||
| AI.1 | Concrete Header Curb | LF | |
| AI.2 | Concrete Sidewalk | SF | |
| AI.3 | Concrete Sidewalk w/ Turndown along Asphalt Pavement | SF | |
| AI.4 | ADA Detectable Warnings - Grouted Pavers | SF | |
| AI.5 | Concrete Curb | LF | |
| AI.6 | Precast Concrete Wheel Stop w/ 24" Long #4 Rebar | EA | |
| AI.7 | Pavement Markings (Space Striping, Crosswalks, ADA, Stop Bar, Etc.) | LS | |
| AI.8 | Pervious Concrete Paving | SF | |
| AI.9 | Asphalt Paving | SF | |
| AI.10 | Observation Wells in Pervious Concrete Paving | EA | |
| AI.11 | 18" Concrete Curb and Gutter | LF | |
| AI.12 | Crushed Aggregate Service Drive w/ Steel Edging | SF | |
| AI.13 | Miscellaneous (Provide Description and Unit) | ||
| Site Paving and Walls Section Total | 0.00 |
| AJ. Soccer Fields | ||||
| AJ.1 | Artificial Turf Soccer Fields | SF | ||
| AJ.2 | Flush Ribbon Curb at Soccer Fields | LF | ||
| AJ.3 | Soccer Backstop Netting | LF | 240 | |
| AJ.4 | Miscellaneous (Provide Description and Unit) | |||
| Soccer Fields Section Total | 0.00 |
| AK. Site Furnishings | ||||
| AK.1 | Diamond Rail Fence | LF | 450 | |
| AK.2 | Bike Rack | EA | ||
| AK.3 | Security Bollard | EA | ||
| AK.4 | Backed Bench | EA | ||
| AK.5 | Trash Receptacle | EA | ||
| AK.6 | 4 Foot Chain Link Fence and Gates | LF | 790 | |
| AK.7 | Hoover Fence Vehicular Gates | EA | ||
| AK.8 | Handicap Ramp Handrail | LF | ||
| AK.9 | Stop Sign | EA | ||
| AK.10 | Handicapped Parking Sign | EA | ||
| AK.11 | Miscellaneous (Provide Description and Unit) | |||
| Site Furnishings Section Total | 0.00 |
| AL. Landscaping | |||
| AL.1 | Crape Myrtle - LAIW | EA | |
| AL.2 | Crape Myrtle - LAGN | EA | |
| AL.3 | Southern Live Oak - QUVI | EA | |
| AL.4 | Cabbage Palm - SASA | EA | |
| AL.5 | Bald Cypress - TD | EA | |
| AL.6 | Pinestraw | Bales | |
| AL.7 | Centipede Sod - EROP | SF | |
| AL.8 | Irrigation Well and Pump System (100% Complete & Installed) | LS | |
| AL.9 | Automated Irrigation System (100% Completed & Installed) | LS | |
| AL.10 | Miscellaneous (Provide Description and Unit) | ||
| Landscaping Section Total | 0.00 |
Total Alternate 0.00
&"Helvetica Neue,Regular"&12&K000000&P
File details come from the government source that posted it. Updated .