About this file

BAA 10-RD-03 High Power Microwave Technology and Electromagnetic Susceptibilty with Laboratory Applications (HPMTESLA) CALL 0011 Questions Answers (Q A) 1 This Q A includes responses to questions recieved 29 January 2015.

View the file

Other files for this federal contract opportunity

Other files attached to High Power Microwave Technology and Electromagnetic Susceptibility with Laboratory Applications (HPMTESLA), newest first.
File Type Posted
Call_Announcement.doc DOC document
BAA_10-RD-03 _Amendment_4_ _Attachment.docx DOCX document
BAA_10-RD-03 _CALL_0011_ _Attachments.pdf PDF
CALL_0009 _Q A__1.pdf PDF
BAA_10-RD-03 _CALL_0009_ _Attachments.pdf PDF
BAA_10-RD-03 _Amendment_3_ _Attachments.docx DOCX document
CALL_0008_Q A__1.pdf PDF
BAA_10-RD-03 _CALL_0008_ _Attachments.pdf PDF
CALL_0007_Q A__1.pdf PDF
CALL_0007_ _Attachments.pdf PDF
CALL 0006 QA 2.pdf PDF
BAA 10-RD-03 CALL 0006 AMENDMENT 02.pdf PDF
CALL 0006 Q A 1.pdf PDF
CALL 0006 Amendment 01 Revised SOO 1.pdf PDF
CALL0006 Attachments.pdf PDF
BAA 10-RD-03 Amendment 02 Attachments.pdf PDF
CALL 0005 Q A 2.pdf PDF
CALL 0005 Q A 1.doc DOC document
Q A.doc DOC document
Q A.doc DOC document
BAA 10-RD-03 CALL 0005 Attachments.pdf PDF
BAA 10-RD-03 CALL 0004 Attachments.pdf PDF
BAA 10-RD-03 CALL 0003 Attachments.pdf PDF
BAA 10-RD-03 CALL 0002 Attachment.pdf PDF
BAA 10-RD-03 Amendment 01 Attachments.pdf PDF
BAA 10-RD-03 CALL 0001 Attachments.pdf PDF
BAA 10-RD-03 Attachments.pdf PDF
HPMTESLA PresolicitationNotice.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

High Power Microwave Technological Electromagnetic Susceptibility with Laboratory Applications (HPMTESLA)

BAA 10-RD-03

CALL 0011 Q&A #1

Q1: Can proposals be delivered via hand carry directly from the contractor?

A1: Hand delivery of proposals will be allowed under this announcement. Proposals being hand delivered should be submitted to the Air Force Research Laboratory (AFRL) mailroom:

3550 Aberdeen Avenue Bldg. 413, Room 160 Kirtland Air Force Base, NM 87117

Q2: Anticipated Call 0011 funding is divided amongst GFY 15, 16, 17, and 18 and the award date is 5/31/15. This leaves 4 months in GFY 15 then 16, 17, and 18 add up to 36 months more for a total of 40. The Period of Performance (PoP) calls for a 39 month technical effort and a 3 month report effort totaling 42 months. How do we reconcile anticipated funding of 40 months against the total PoP of 42 months?

A2: The funding is anticipated to be available the first fiscal years in order to cover the full period of performance. The award may be fully funded on the third year to cover the remaining PoP, however billing will be done according to the award’s terms and conditions. Funding will be incrementally funded with FY 15, FY16, FY17 and FY18 funds. This is not to be confused with the period of performance.