B08_Attachment_8_Submittal_Log_FOWA_251994_Lighthouse_102921.xls

XLS spreadsheet 651 KB Posted

Attached to
Lighthouse Road & Rehabilitation National Capital
Solicitation number
140P3022R0030
Issued by

About this file

This document contains a submittal list template and review estimate template for a federal construction project. The templates provide guidance on submittal requirements and estimated review times for the rehabilitation of the Lighthouse Road facility for the National Park Service. Specification sections and paragraph numbers are listed along with required submittal documentation including product data, shop drawings, samples, and certification reports. An estimate of anticipated review hours is also included for architectural, civil, structural, mechanical, electrical, and other disciplines. The total estimated review time for all submittals is one hundred twenty-nine hours. This level of detail will help coordinate submittal reviews between the construction manager and design firm they engage for construction administration services.

View the file

Other files

File Type Posted
Sol_140P3022R0030_Amd_0005.pdf PDF
B09_Amendment_0005_Lead_Hazard_Control_Activities_0005.pdf PDF
Sol_140P3022R0030_Amd_0004.pdf PDF
B09_Amendment_3_Boring_Location_Plan_0003.pdf PDF
B09_Amendment_3_FOWA_852_141693_HPTC_Record_of_Treatment_2009_0003.pdf PDF
B09_Amendment_3_Q_A_FOWA_Lighthouse___Lighthouse_Road_Repair_0003.docx DOCX document
B09_Amendment_3_2017_Lighthouse_Eval_0003.pdf PDF
B09_Amendment_3_Structural_Investigaton_Fort_Washington_Lighthouse_021319_0003.pdf PDF
B09_Amendment_3_Boring_Logs_0003.pdf PDF
Sol_140P3022R0030_Amd_0003.pdf PDF
Sol_140P3022R0030_Amd_0002.pdf PDF
B09_Amendment_0002_Q_A_FOWA_Lighthouse_and_Lighthouse_Road_Repairs_8_29_22_0002.docx DOCX document
Sol_140P3022R0030_Amd_0001.pdf PDF
B08_Attachment_9_-_Biobased_Certification.docx DOCX document
B08_Attachment_12_Vaccination_Certification_Notification_to_DOI_Contractors_Template_082321_FINAL_-_signed.pdf PDF
B08_Attachment_3_FOWA_251994_Lighthouse_FINAL_CD_DRAWING_110421.pdf PDF
B08_Attachment_10_Subcontracting_Percentage_Worksheet_v1_2.docx DOCX document
B08_Attachment_5_FOWA_251994_Lighthouse_Rehab_Specs_rev1-051522.pdf PDF
B08_Attachment_4_FOWA_241555_FOWA_Resurface_Lighthouse_Rd_MDE17-SF-0104_APPROVED_PLANS_040822.pdf PDF
B08_Attachment_1_CAAC_Letter_2020-04_.pdf PDF
Sol_140P3022R0030.pdf PDF
B08_Attachment_7_FOWA_241555_Lighthouse_Rd_Submittal_Log_042922.xls XLS spreadsheet
B08_Attachment_11_Certification_of_Vaccination_Form_expires_2-28-25.pdf PDF
B08_Attachment_2_DOL_WD_MD20220109_PGco_Highway_2_25_22.pdf PDF
B08_Attachment_14_Site_Visit_FOWA_Lighthouse-VC_Aerial_Map.JPG JPG image
B08_Attachment_13_Site_Visit_Agenda_FOWA_Lighthouse_Rd___Lighthouse_Rehabilitation_8-31-22_11AM-ED.doc DOC document
B08_Attachment_6_FOWA_241555_Lighthouse_Rd_Specs_Rev-03-051522.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal List Template

SUBMITTAL LIST

Note: See tab below for Samples and Instructions. Attach to end of Specification Section 01 33 23 when complete.

FOWA LIGHTHOUSE REHABILITATION 251994D
SUBMITTALREQUIREMENTS (indicate with an "X")
Spec. Sec.Par. No.DescriptionINFORMATIONALACTION
CERT./LAB TESTREPORT/CALC.
OR PLANMfg. DATA
& INSTRUCTIONSSHOP DRAWINGSAMPLEMfg. DATA

& INSTRUCTIONS

01 11 00Summary of Work
01 33 00Submittals
1.4Staff Names, Subcontractors and QualificationsX
1.6Contractor's Construction ScheduleX
01 33 10Submittal Form
01 50 00Temporary Services, Facilities, and Controls
01 70 00Execution and Closeout Requirements
1.3Inspection ProceduresX
1.4Project Record Document Submittals (As-Built Drawings)X
01 26 01Contract Modification Procedures
01 31 00Project Management and Coordination
1.2D. Construction Coordination - Division 1 documentsX
01 32 33Photo Documentation
1.2A. Construction imagesX
1.2B. CloseoutX
01 35 91Historic Preservation Treatment Procedures
1.3A. Historic Preservation Treatment PlanX
1.3B. Alternative Methods and Materials (if any)X
1.3C. Photographs or VideotapeX
01 74 19Construction Waste Management and Disposal
1.4A. Waste Management PlanX
1.4B. Progress DocumentationX
1.4C. Waste Reduction CalculationsX
1.4D. Records of DonationsX
1.4E. Records of SalesX
1.4F. Recycling and Processing Facility RecordsX
1.4G. Landfill and Incinderator Disposal RecordsX
1.4H. CloseoutX
02 42 96Historic Removal and Dismantling
04 01 20.64Brick Masonry Repointing
1.4A. Product DataX
1.4B. SamplesX
1.5B. MockupsX
06 20 13Exterior Finish Carpentry
1.5A. Product DataX
1.5B. Shop DrawingsX
1.5C. SamplesX
1.7A. Qualification Data: For Installer and fabricatorX
1.7B. Qualification Data: For historic treatment specialistX
1.7C. Wood Historic Treatment ProgramX
1.7D. Woodwork Quality Standard Compliance CertificatesX
07 62 00Sheet Metal Flashing and Trim
1.2A. Product DataX
1.2B. Shop DrawingsX
1.3B. MockupsX
08 01 52Wood Windows
1.3A. Product DataX
1.3B. Shop DrawingsX
1.3C. SamplesXX
1.4B. MockupsX
08 14 16Flush Wood Doors
1.3A. Product DataX
1.3B. Shop DrawingsX
08 91 19Fixed Louvers
1.2A. Product DataX
1.2B. Shop DrawingsX
1.2C. SamplesX
1.3A. Test ReportsX
09 91 13Painting
1.3A. Product DataX
1.3B. Shop DrawingsX
1.4A. MockupsX
DWG SHEET
S.01GENERAL NOTE
2Temp sheeting, shoring, bracing shop drawings as project conditions requireXX
CONCRETE
2A. Concrete mix designX
5Shop DrawingsX

Review Estimate Template

SUBMITTAL LIST AND REVIEW ESTIMATE
SUBMITTALS LISTACTION SUBMITTAL REVIEW ESTIMATE
Park/PMIS/Project Title(Complete this portion for AE Const. Serv. task order negotiation.)
SUBMITTALREQUIREMENTS
(indicate with an "X")A/E REVIEW TIME

(indicate number of hours)

Spec. Sec.Par. No.DescriptionINFORMATIONALACTIONARCH (hrs)CE (hrs)SE (hrs)ME (hrs)EE (hrs)PM - Coor. (hrs)LA (hrs)
CERT./LAB TESTREPORT/CALC.
OR PLANMfg. DATA
& INSTRUCTIONSSHOP DRAWINGSAMPLEMfg. DATA

& INSTRUCTIONS

Total 0 0 0 0 0 0 0

Template Instructions

SUBMITTAL LIST AND REVIEW ESTIMATE

INSTRUCTIONS

PHASE OF WORKRESPONSIBLE PARTYDESCRIPTION OF TASKS
DESIGN SERVICES
(CONSTRUCTION DOCUMENTS PHASE)Design A/E1. Fill out Park/PMIS/Project Title cell with project reference information.
2. Use this form to record construction submittal requirements for the project. Fill out the Specification Section, Paragraph number, Description columns on the left side of the form. Insert Additional rows, as required for sections containing multiple submittals.
3. In the columns designated "REQUIREMENTS", indicate the submittal requirement(s) by placing an "X" in the appropriate box(es). Insert additional columns as necessary under the headings of Informational or Action to correctly show the type of submittal. Refer to Specification Section 01 33 23 for clarification on what are Informational submittals or Action submittals. (Action submittals require Government responsive action and informational do not.) All Division 01 Specification Submittals should be shown as Informational Submittals.
4. Attach a black and white version to the end of Specification Section 01 33 23 in the project manual. Delete instructional note on the top of the page.
CONSTRUCTION SERVICES
(CONSTRUCTION PHASE)Construction COR1. Utilize the "Submittal List" form submitted with the Final Construction Documents. Copy/paste submittal information into the Submittal List and review estimate. If amendments have been issued, make adjustments to the submittal requirements if necessary.
2. Attach this form to the "A/E Construction Services" Scope of Services.
3. Utilize this form to the generate the estimated time required for the A/E to accomplish the Action submittal reviews by inserting your estimated number of hours per discipline under corresponding column headings.
4. Add discipline heading columns, as required.
5. Use the total number of hours per discipline at the bottom of the form and apply the hourly rates listed in the IDIQ contract (using appropriate option period rates) to formulate the Government estimate for submittal reviews. Refer to the sample by selecting an appropriate tab below.
6. Use the information contained within this form to negotiate the submittal review portion of the A/E Construction Services task order.
7. Provide this form to the CMR so they have an understanding of which submittals they are responsible for and which are to be forwarded to the A/E.

All Informational submittals will be reviewed by the CMR.

A/E1. Indicate level of effort required for each Action submittal review by inserting the number of hours for each discipline under the "A/E Review Time (indicate number of hours)" column.
2. All Informational submittals will be reviewed by the CMR.
3. Use the total number of hours indicated for each discipline and apply the appropriate rates from the IDIQ contract (using the appropriate option period rates) to formulate your estimate. Refer to the sample by selecting an appropriate tab below.
4. Use this estimate to negotiate the submittals review portion of the A/E Construction Services portion of the task order.

Submittal List Sample

SUBMITTAL LIST
Death Valley National Park, PMIS 06660, Rehabilitate Maintenance Facilities
SUBMITTALREQUIREMENTS

(indicate with an "X")

INFORMATIONALACTION
Spec. Sec.Par. No.DescriptionCERT./LAB TESTREPORT/CALC.
OR PLANMfg. DATA
& INSTRUCTIONSSHOP DRAWINGSAMPLEMfg. DATA

& INSTRUCTIONS

21101.3Excavation safety planX
21201.4Signed copies of manifestX
23201.2Procedures for trench dewateringX
25011.3Water and sewer test accuracy cert.X
25021.2Water line marking tape sampleX
25171.2Fire Hydrants
Manufactures information: x-sectionX
Certification with AWWA C502-94X
27251.2Aggregate base courseX
27781.2Walks, curbs and gutters, mix designXX
33001.3Cast in-Place Concrete
Steel placement shop drawingX
Batching and hauling planX
Rebar certificationX
41001.2Mortar
Cured mortar sampleX
Material certification & test reportsX
42011.3Masonry Work
Shop drawingsX
Masonry unit sampleX
Mfg. information on admixturesX
51201.4Structural steelX
53111.3Steel roof deck shop drawingsX
54001.3Cold Formed Metal Framing
Shop drawings and erection diagramsX
Mill certificatesX
Welder certificatesX
64021.3Interior architectural woodworkXXX
71001.4Cold Fluid Applied Waterproofing
Product dataX
Shop drawingsX
Installer certificationX
Product test reportsX
72601.2Vapor retarder mfg. installation instructionsX
76101.3Sheet metal roofingXXX
81101.3Steel Doors and Frames
Shop drawingsX
Catalog cuts and install instructionsX
Door scheduleX
85201.3Aluminum windowsXX
87101.2Finish hardware scheduleX
93101.6Ceramic Tile
SampleX
Mfg. literatureX
CertificationX
99011.4Painting
Mfg. color chartX
Paint sample applied to like materialX
Mfg. informationX
108001.7Toilet and bath acc.mfg.infoX
114521.2Kitchen appliances, product dataX
125001.3Horizontal louver blindsX
150601.4Piping and accessoriesXXX
158001.3DuctworkXX
164701.4Panel boardsXXX

Review Estimate Sample

SUBMITTAL LIST AND REVIEW ESTIMATE
SUBMITTAL LISTSUBMITTAL REVIEW ESTIMATE
Death Valley National Park, PMIS 06660, Rehabilitate Maintenance Facilities(Complete this portion for AE Const. Serv. task order negotiation)
SUBMITTALREQUIREMENTS
(indicate with an "X")A/E REVIEW TIME

(indicate number of hours)

INFORMATIONALACTIONARCH (hrs)CE (hrs)SE (hrs)ME (hrs)EE (hrs)PM - Coor. (hrs)LA (hrs)
Spec. Sec.Par. No.DescriptionCERT./LAB TESTREPORT/CALC.
OR PLANMfg. DATA
& INSTRUCTIONSSAMPLESHOP DRAWINGMfg. DATA

& INSTRUCTIONS

21101.3Excavation safety planX
21201.4Signed copies of manifestX
23201.2Procedures for trench dewateringX
25011.3Water and sewer test accuracy cert.X
25021.2Water line marking tape sampleX2
25171.2Fire Hydrants
Manufactures information: x-sectionX
Certification with AWWA C502-94X
27251.2Aggregate base courseX
27781.2Walks, curbs and gutters, mix designXX32
33001.3Cast in-Place Concrete
Steel placement shop drawingX12
Batching and hauling planX1
Rebar certificationX
41001.2Mortar
cured mortar sampleX11
Material certification & test reportsX
42011.3Masonry Work
Shop drawingsX4
Masonry unit sampleX1
Mfg. information on admixturesX1
51201.4Structural steelX4
53111.3Steel roof deck shop drawingsX4
54001.3Cold Formed Metal Framing
Shop drawings and erection diagramsX4
Mill certificatesX
Welder certificatesX
64021.3Interior architectural woodworkXXX6
71001.4Cold Fluid Applied Waterproofing
Product dataX
Shop drawingsX2
Installer certificationX
Product test reportsX
72601.2Vapor retarder mfg. installation instructionsX
76101.3Sheet metal roofingXXX32
81101.3Steel Doors and Frames
Shop drawingsX3
Catalog cuts and install instructionsX
Door scheduleX
85201.3Aluminum windowsXX6
87101.2Finish hardware scheduleX
93101.6Ceramic Tile
SampleX2
Mfg. literatureX
CertificationX
99011.4Painting
Mfg. color chartX3
Paint sample applied to like materialX2
Mfg. informationX
108001.7Toilet and bath acc.mfg.infoX
114521.2Kitchen appliances, product dataX
125001.3Horizontal louver blindsX
150601.4Piping and accessoriesXXX3
158001.3DuctworkXX3
164701.4Panel boardsXXX3
Total297246300