This document represents answers to technical questions received in response to solicitation number 140P3022R0030 issued by the National Park Service for Lighthouse Road & Rehabilitation work at Fort Washington Park. The solicitation seeks contractors to perform repairs to the Fort Washington Lighthouse and Lighthouse Road. The last date for contractors to submit technical questions is September 9, 2022. All questions will be answered in an amendment to the solicitation. The document clarifies that the requirement is for 10 years of trade experience in each of the four identified trades rather than 10 years of corporate experience. Contractors are referred to page 4/64 of the RFP for budget magnitude disclosure in accordance with FAR 36.204.

View the file

Other files

File Type Posted
Sol_140P3022R0030_Amd_0005.pdf PDF
B09_Amendment_0005_Lead_Hazard_Control_Activities_0005.pdf PDF
Sol_140P3022R0030_Amd_0004.pdf PDF
B09_Amendment_3_Boring_Location_Plan_0003.pdf PDF
B09_Amendment_3_FOWA_852_141693_HPTC_Record_of_Treatment_2009_0003.pdf PDF
B09_Amendment_3_Q_A_FOWA_Lighthouse___Lighthouse_Road_Repair_0003.docx DOCX document
B09_Amendment_3_2017_Lighthouse_Eval_0003.pdf PDF
B09_Amendment_3_Structural_Investigaton_Fort_Washington_Lighthouse_021319_0003.pdf PDF
B09_Amendment_3_Boring_Logs_0003.pdf PDF
Sol_140P3022R0030_Amd_0003.pdf PDF
Sol_140P3022R0030_Amd_0002.pdf PDF
Sol_140P3022R0030_Amd_0001.pdf PDF
B08_Attachment_9_-_Biobased_Certification.docx DOCX document
B08_Attachment_12_Vaccination_Certification_Notification_to_DOI_Contractors_Template_082321_FINAL_-_signed.pdf PDF
B08_Attachment_3_FOWA_251994_Lighthouse_FINAL_CD_DRAWING_110421.pdf PDF
B08_Attachment_10_Subcontracting_Percentage_Worksheet_v1_2.docx DOCX document
B08_Attachment_5_FOWA_251994_Lighthouse_Rehab_Specs_rev1-051522.pdf PDF
B08_Attachment_4_FOWA_241555_FOWA_Resurface_Lighthouse_Rd_MDE17-SF-0104_APPROVED_PLANS_040822.pdf PDF
B08_Attachment_1_CAAC_Letter_2020-04_.pdf PDF
Sol_140P3022R0030.pdf PDF
B08_Attachment_8_Submittal_Log_FOWA_251994_Lighthouse_102921.xls XLS spreadsheet
B08_Attachment_7_FOWA_241555_Lighthouse_Rd_Submittal_Log_042922.xls XLS spreadsheet
B08_Attachment_11_Certification_of_Vaccination_Form_expires_2-28-25.pdf PDF
B08_Attachment_2_DOL_WD_MD20220109_PGco_Highway_2_25_22.pdf PDF
B08_Attachment_14_Site_Visit_FOWA_Lighthouse-VC_Aerial_Map.JPG JPG image
B08_Attachment_13_Site_Visit_Agenda_FOWA_Lighthouse_Rd___Lighthouse_Rehabilitation_8-31-22_11AM-ED.doc DOC document
B08_Attachment_6_FOWA_241555_Lighthouse_Rd_Specs_Rev-03-051522.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

National Capital Parks-East (NACE) Fort Washington Park (FOWA) RFP 140P3022R0030 FOWA Lighthouse & Light House Road Repairs Amendment 2 – Question & Answer Issued:8/29/2022 The last date for contractor to submit any technical questions is 9/9/2022 at 12:00 PM ED. Any questions received after this date will not be addressed. ALL technical questions must be submitted in writing only to brian_dankmeyer@nps.gov. All questions received by the due date and time will be answered in an amendment to the solicitation as soon as practicable after the due date and time. Any questions received after the due date and time will not be addressed through any Amendment.

This document represents answers to all technical question that were received on or before 8/24/2022 at 3:30 PM ED.

1. I have located the site visit information but am having difficulty finding the budget.?

a. Refer to pg 4/64 of the RFP for magnitude disclosure IAW FAR 36.204

2. Subfactor 2b of the proposal states that “the offeror shall be able to show a minimum of 10 years experience in each of the following trades” but also goes on to describe the technical requirements of three projects to demonstrate that experience. Would it be possible to eliminate the requirement for 10 years of corporate experience, but maintain the technical requirements for the trades and the three relevant projects?

a. There is no requirement for “10-years of corporate experience.” Only 10-year trade experience in each of the four trades identified in the solicitation.