This document outlines specifications for lead hazard control activities for a federal contract opportunity for road rehabilitation projects with the National Park Service. The specifications cover lead-based paint inspection and abatement procedures, waste handling and disposal requirements, personnel protective equipment and training qualifications, medical monitoring, air sampling protocols, and other health and safety standards that must be followed when conducting renovation or demolition work that could expose workers or the environment to lead hazards. The contract opportunity is for road and rehabilitation projects within the National Capital Parks-East division of the National Park Service.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 02 83 13 - LEAD HAZARD CONTROL ACTIVITIES
PART 1 – GENERAL
1.1 REFERENCES
A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
B. AMERICAN INDUSTRIAL HYGIENE ASSOCIATION (AIHA)
1. AIHA Z88.6 (2006) Respiratory Protection – Respirator Use-Physical
C. U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT (HUD)
1. HUD 6780 (1995; Errata Aug 1996; Rev Ch. 7 - 1997) Guidelines for the Evaluation and
Control of Lead-Based Paint Hazards in Housing
D. U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
1. 29 CFR 1926.103 Respiratory Protection
2. 29 CFR 1926.21 Safety Training and Education
3. 29 CFR 1926.33 Access to Employee Exposure and Medical Records
4. 29 CFR 1926.55 Gases, Vapors, Fumes, Dusts, and Mists
5. 29 CFR 1926.59 Hazard Communication
6. 29 CFR 1926.62 Lead
7. 29 CFR 1926.65 Hazardous Waste Operations and Emergency Response
8. 40 CFR 260 Hazardous Waste Management System: General
9. 40 CFR 261 Identification and Listing of Hazardous Waste
10. 40 CFR 262 Standards Applicable to Generators of Hazardous Waste
11. 40 CFR 263 Standards Applicable to Transporters of Hazardous Waste
12. 40 CFR 264 Standards for Owners and Operators of Hazardous Waste
13. 40 CFR 265 Interim Status Standards for Owners and Operators of Hazardous
14. 40 CFR 268 Land Disposal Restrictions
15. 40 CFR 745 Lead-Based Paint Poisoning Prevention in Certain Residential
16. 49 CFR 178 Specifications for Packagings
E. UNDERWRITERS LABORATORIES (UL)
1. UL 586 (2009) Standard for High Efficiency Particulate Air Filter Units
1.2 DEFINITIONS
A. Action Level: Employee exposure, without regard to use of respirators, to an airborne concentration of lead of 30 micrograms per cubic meter of air averaged over an 8 hour period.
B. Area Sampling: Sampling of lead concentrations within the lead control area and inside the physical boundaries which is representative of the airborne lead concentrations but is not collected in the breathing zone of personnel (approximately 5 to 6 feet above the floor).
C. Competent Person (CP): As used in this section, refers to a person employed by the Contractor who is trained in the recognition and control of lead hazards in accordance with current federal, State, and local regulations. A United States Environmental Protection Agency (USEPA) certified
Lead Abatement Supervisor or Lead Renovator are the best choices for this project.
D. Contaminated Room: Not Applicable
E. Decontamination Shower Facility: Not Applicable
F. High Efficiency Particulate Arrestor (HEPA) Filter Equipment: Not Applicable
G. Lead: Metallic lead, inorganic lead compounds, and organic lead soaps. Excludes other forms of organic lead compounds.
H. Lead Control Area: A system of control methods to prevent the spread of lead dust, paint chips or debris to adjacent areas that may include temporary containment, floor or ground cover protection, physical boundaries, and warning signs to prevent unauthorized entry of personnel.
HEPA filtered local exhaust equipment may be used as engineering controls to further reduce personnel exposures or building/outdoor environmental contamination.
1. Demolition and renovation activities at the Site may generate lead dust. Dust control shall be used to minimize airborne lead during mechanical demolition and or renovation.
I. Lead Permissible Exposure Limit (PEL): 50 micrograms per cubic meter of air as an 8 hour time weighted average as determined by 29 CFR 1926.62. If an employee is exposed for more than eight hours in a work day, the PEL shall be determined by the following formula:
1. PEL (micrograms/cubic meter of air) = 400/No. hrs worked per day
J. Material Containing Lead/Paint with Lead (MCL/PWL): Any material, including paint, which contains lead as determined by X-Ray Fluorescence (XRF) testing. An inspection of painted building components was conducted in June 2015. The findings of this inspection are included in the Arc Environmental Lead-based Paint Inspection Report issued at that time. If other unsampled areas of the project Site are impacted by the planned renovations/demolition activities, than those components must be presumed to contain lead-based paint, given the age of the structure.
K. Personal Sampling: Sampling of airborne lead concentrations within the breathing zone of an employee to determine the 8 hour time weighted average concentration in accordance with 29
CFR 1926.62. Samples shall be representative of the employees' work tasks. Breathing zone shall be considered an area within a hemisphere, forward of the shoulders, with a radius of 6 to
9 inches and centered at the nose or mouth of an employee.
L. Physical Boundary: Area physically roped or partitioned off around lead control area to limit unauthorized entry of personnel.
1.3 DESCRIPTION
A. Description of Work
1. Construction and renovation activities impacting PWL, or material containing lead, which are covered by this specification include the renovation/demolition activities set forth in Task Order P15PD00701. Based on the Scope of Work information contained within that document, and the findings of the Arc Environmental Lead-based Paint
Inspection Report, components include but are not limited to wood trim, door components, window components, and exterior structures located throughout the Site. As previously noted, all other un-sampled areas of the project Site, which will be impacted by the planned renovations/demolition activities, should be presumed to contain lead based paint, given the age of the structure.
B. Coordination with Other Work
1. The contractor shall coordinate with work being performed in adjacent areas.
Coordination procedures shall be explained in the Plan and shall describe how the
Contractor will prevent lead exposure to other contractors and/or personnel performing work unrelated to lead activities.
1.4 SUBMITTALS
A. Occupational and Environmental Assessment Data Report (if objective data is used to justify excluding the initial occupational exposure assessment).
B. Lead Compliance Plan including CP approval (signature, date, and certification number).
C. Competent Person qualifications.
D. Training Certification of workers and supervisors.
E. Lead waste management plan.
F. Certification of Medical Examinations.
G. Occupational and Environmental Assessment Data Report.
H. Third party consultant qualifications.
I. Closeout Submittals: Waste turn-in documents or weight tickets for non-hazardous wastes that are disposed of at sanitary or construction and demolition landfills.
1.5 QUALITY ASSURANCE
A. Qualifications
1. Competent Person (CP)
a. Submit name, address, and telephone number of the CP selected to perform responsibilities specified in paragraph entitled "Competent Person (CP)
Responsibilities." Provide documented construction project-related experience with implementation of OSHA's Lead in Construction standard (29 CFR 1926.62) which shows ability to assess occupational and environmental exposure to lead, experience with the use of respirators, personal protective equipment and other exposure reduction methods to protect employee health. Submit proper documentation that the CP is trained, licensed, and certified in accordance with federal, State, and local laws.
2. Training Certification
a. Submit a certificate for each worker and supervisor, signed and dated by the accredited training provider, stating that the employee has received the required lead training specified in 29 CFR 1926.62(l) and is certified to perform or supervise renovation/demolition activities in the State of Maryland.
3. Testing Laboratory:
a. Submit the name, address, and telephone number of the testing laboratory selected to perform the air analysis and reporting of airborne concentrations of lead. Use a laboratory participating in the EPA National Lead Laboratory Accreditation
Program (NLLAP) by being accredited by either the American Association for
Laboratory Accreditation (A2LA) or the American Industrial Hygiene Association
(AIHA) and that is successfully participating in the Environmental Lead
Proficiency Analytical Testing (ELPAT) program to perform sample analysis.
Laboratories selected to perform blood lead analysis shall be OSHA approved.
B. Requirements
1. Competent Person (CP) Responsibilities
a. Verify training meets all federal, State, and local requirements.
b. Review and approve Lead Compliance Plan for conformance to the applicable referenced standards.
c. Continuously inspect PWL or MCL work for conformance with the approved plan.
d. Perform (or oversee performance of) air sampling. Recommend upgrades or downgrades (whichever is appropriate based on exposure) on the use of PPE
(respirators included) and engineering controls.
e. Ensure work is performed in strict accordance with specifications at all times.
f. Control work to prevent hazardous exposure to human beings and to the environment at all times.
g. Certify the conditions of the work as called for elsewhere in this specification.
2. Lead Compliance Plan
a. Submit a detailed job-specific plan of the work procedures to be used in the disturbance of PWL or MCL. The plan shall include a sketch showing the location, size, and details of lead control areas, critical barriers, physical boundaries, and location. Include a description of equipment and materials, work practices, controls and job responsibilities for each activity from which lead is emitted. Include in the plan, eating, drinking, smoking, hygiene facilities and sanitary procedures, interface of trades, sequencing of lead related work, collected waste water and dust containing lead and debris, air sampling, respirators, personal protective equipment, and a detailed description of the method of containment of the operation to ensure that lead is not released outside of the lead control area. Include occupational and environmental sampling, training and strategy, sampling and analysis strategy and methodology, frequency of sampling, duration of sampling, and qualifications of sampling personnel in the air sampling portion of the plan. Include a description of arrangements made among contractors on multi-contractor worksites to inform affected employees and to clarify responsibilities to control exposures. The plan shall be developed by the CP.
3. Occupational and Environmental Assessment Data Report
a. If initial monitoring is necessary, submit occupational and environmental sampling results to the Contracting Officer within three working days of collection, signed by the testing laboratory employee performing the analysis, the employee that performed the sampling, and the CP.
b. In order to reduce the full implementation of 29 CFR 1926.62, the Contractor shall provide documentation. Submit a report that supports the determination to reduce full implementation of the requirements of: 29 CFR 1926.62 and supporting the Lead
Compliance Plan. The initial monitoring shall represent each job classification, or if working conditions are similar to previous jobs by the same employer, provide previously collected exposure data that can be used to estimate worker exposures per 29 CFR
1926.62. The data shall represent the worker's regular daily exposure to lead for stated work. Submit worker exposure data gathered during the task based trigger operations of 29 CFR 1926.62 with a complete process description. This includes manual demolition, manual scraping, manual sanding, heat gun, power tool cleaning, rivet busting, cleanup of dry expendable abrasives, abrasive blast enclosure removal, abrasive blasting, welding, cutting and torch burning where lead containing coatings are present. The initial assessment shall determine the requirement for further monitoring and the need to fully implement the control and protective requirements including the lead compliance plan per 29 CFR 1926.62.
4. Medical Examinations
a. Initial medical surveillance as required by 29 CFR 1926.62 shall be made available to all employees exposed to lead at any time (1 day) above the action level. Full medical surveillance shall be made available to all employees on an annual basis who are or may be exposed to lead in excess of the action level for more than 30 days a year or as required by 29 CFR 1926.62. Adequate records shall show that employees meet the medical surveillance requirements of 29 CFR
1926.33, 29 CFR 1926.62 and 29 CFR 1926.103. Provide medical surveillance to all personnel exposed to lead as indicated in 29 CFR 1926.62. Maintain complete and accurate medical records of employees for the duration of employment plus
30 years.
5. Training
a. Train each employee performing work that disturbs lead, who performs MCL/PWL disposal, and air sampling operations prior to the time of initial job assignment and annually thereafter, in accordance with 29 CFR 1926.21, 29 CFR
1926.62, Commonwealth of Virginia, and local regulations where appropriate.
6. Respiratory Protection Program
a. Provide each employee required to wear a respirator a respirator fit test at the time of initial fitting and at least annually thereafter as required by 29 CFR 1926.62.
b. Establish and implement a respiratory protection program as required by AIHA
Z88.6, 29 CFR 1926.103, 29 CFR 1926.62, and 29 CFR 1926.55.
7. Hazard Communication Program
a. Establish and implement a Hazard Communication Program as required by 29 CFR
1926.59.
8. Lead Waste Management The Lead Waste Management Plan shall comply with applicable requirements of federal, State, and local hazardous waste regulations and address:
a. Identification and classification of wastes associated with the work. As previously mentioned, a lead-based paint inspection was conducted in June 2015. The findings of the inspection are included in the Arc Environmental Lead-based Paint Inspection report.
b. Estimated quantities of wastes to be generated and disposed of.
c. Names and qualifications of each contractor that will be transporting, storing, treating, and disposing of the wastes. Include the facility location [and operator] and a 24-hour point of contact.
d. Names and qualifications (experience and training) of personnel who will be working on-site with hazardous wastes.
e. List of waste handling equipment to be used in performing the work, to include cleaning, volume reduction, and transport equipment.
f. Spill prevention, containment, and cleanup contingency measures including a health and safety plan to be implemented in accordance with 29 CFR 1926.65.
g. Work plan and schedule for waste containment, removal and disposal. Proper containment of the waste includes using acceptable waste containers as well as proper marking/labeling of the containers. Wastes shall be cleaned up and containerized daily.
h. Include any process that may alter or treat waste rendering a hazardous waste non-hazardous.
9. Environmental, Safety and Health Compliance
a. In addition to the detailed requirements of this specification, comply with laws, ordinances, rules, and regulations of federal, State, and local authorities regarding lead. Comply with the applicable requirements of the current issue of 29 CFR 1926.62.
Submit matters regarding interpretation of standards to the Contracting Officer for resolution before starting work. Where specification requirements and the referenced documents vary, the most stringent requirement shall apply.
C. Pre-Construction Conference
1. Along with the CP, meet with the Contracting Officer to discuss in detail the Lead Waste
Management Plan and the Lead Compliance Plan, including procedures and precautions for the work.
1.6 EQUIPMENT
A. Respirators
1. Furnish appropriate respirators approved by the National Institute for Occupational
Safety and Health (NIOSH), Department of Health and Human Services, for use in atmospheres containing lead dust, fume and mist. Respirators shall comply with the requirements of 29 CFR
1926.62.
B. Special Protective Clothing
1. Furnish personnel who will be exposed to lead-contaminated dust with proper disposable protective whole body clothing, head covering, gloves, eye, and foot coverings as required by 29
CFR 1926.62. Furnish proper disposable plastic or rubber gloves to protect hands.
2. Reduce the level of protection only after obtaining approval from the CP.
C. Rental Equipment Notification
1. If rental equipment is to be used during PWL or MCL handling and disposal, notify the rental agency in writing concerning the intended use of the equipment.
D. Equipment for Authorized Personnel
1. Furnish the Contracting Officer with two complete sets of personal protective equipment
(PPE) daily, as required herein, for entry into and inspection of the lead removal work within the lead controlled area. Personal protective equipment shall include disposable whole body covering, including appropriate foot, head, eye, and hand protection. PPE shall remain the property of the Contractor. The Authorized Personnel will provide respiratory protection for the Contracting Officer.
1.7 PROJECT/SITE CONDITIONS
A. Protection of Existing Work to Remain
1. Perform work without damage or contamination of adjacent areas. Where existing work is damaged or contaminated, restore work to its original condition or better as determined by the
Contracting Officer.
PART 2 PRODUCTS: (NOT USED)
PART 3 EXECUTION
3.1 PREPARATION
A. Protection
1. Notification
a. Notify the Contracting Officer 10 days prior to the start of any lead work.
2. Lead Control Area
a. Physical Boundary - Provide physical boundaries around the lead control area by roping off the area designated in the work plan.
b. Warning Signs - Provide warning signs at approaches to lead control areas. Locate signs at such a distance that personnel may read the sign and take the necessary precautions before entering the area. Signs shall comply with the requirements of 29 CFR
1926.62.
3. Decontamination Shower Facility
a. Provide clean and contaminated change rooms and shower facilities in accordance with this specification and 29 CFR 1926.62.
4. Eye Wash Station
a. Where eyes may be exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing of the eyes shall be provided within the work area.
5. Personnel Protection
a. Personnel shall wear and use protective clothing and equipment as specified herein. Eating, smoking, or drinking or application of cosmetics is not permitted in the lead control area. No one will be permitted in the lead control area unless they have been appropriately trained and provided with protective equipment.
3.2 ERECTION
A. Lead Control Area Requirements
1. Establish a lead control area by completely establishing barriers and physical boundaries around the area or structure where PWL or MCL removal operations will be performed.
3.3 APPLICATION
A. Lead Work
1. Perform lead work in accordance with approved Lead Compliance Plan. Use procedures and equipment required to limit occupational exposure and environmental contamination with lead when the work is performed in accordance with 29 CFR 1926.62, and as specified herein. Dispose of all PWL or MCL and associated waste in compliance with federal, State, and local requirements.
B. Paint with Lead or Material Containing Lead Removal
1. Manual or power sanding or grinding of lead surfaces or materials is not permitted unless tools are equipped with HEPA attachments or wet methods. The dry sanding or grinding of surfaces that contain lead is prohibited. Provide methodology for removing lead in the Lead Compliance
Plan. Select lead removal processes to minimize contamination of work areas outside the control area with lead-contaminated dust or other lead-contaminated debris or waste and to ensure that unprotected personnel are not exposed to hazardous concentrations of lead. Describe this removal process in the Lead Compliance Plan.
C. Paint with Lead or Material Containing Lead - Outdoor Removal
1. Perform outdoor removal as indicated in federal, State, and local regulations and in the Lead
Compliance Plan. The worksite preparation (barriers or containments) shall be job dependent and presented in the Lead Compliance Plan.
3.4 PERSONNEL EXITING PROCEDURES
A. Whenever personnel exit the lead-controlled area, they shall perform the following procedures and shall not leave the work place wearing any clothing or equipment worn in the control area:
1. Vacuum all clothing before entering the contaminated change room.
2. Remove protective clothing in the contaminated change room, and place them in an approved impermeable disposal bag.
3. Wash hands and face at the site.
4. Change to clean clothes prior to leaving the clean clothes storage area.
3.5 FIELD QUALITY CONTROL
A. Tests
1. Air Sampling
a. Conduct sampling for lead in accordance with 29 CFR 1926.62 and as specified herein.
Air sampling shall be directed or performed by the CP.
2. The CP shall be on the job site directing the air sampling and inspecting the PWL or MCL removal work to ensure that the requirements of the contract have been satisfied during the entire
PWL or MCL operation.
a. Collect personal air samples on employees who are anticipated to have the greatest risk of exposure as determined by the CP. In addition, collect air samples on at least 25 percent of the work crew or a minimum of two employees, whichever is greater, during each work shift.
b. Submit results of air samples, signed by the CP, within 72 hours after the air samples are taken.
c. Conduct area air sampling daily, on each shift in which lead-based paint removal operations are performed, in areas immediately adjacent to the lead control area, specifically up and down-wind. Sufficient area monitoring shall be conducted to ensure unprotected personnel or area residents are not exposed at or above 30 micrograms per cubic meter of air. If 30 micrograms per cubic meter of air is reached or exceeded, stop work, correct the conditions(s) causing the increased levels. Notify the Contracting
Officer immediately. Determine if condition(s) require any further change in work methods. Removal work shall resume only after the CP and the Contracting Officer give approval.
3. Testing of Material Containing Lead Residue
a. Test residue in accordance with 40 CFR 261 for hazardous waste.
3.6 CLEANING AND DISPOSAL
A. Cleanup
1. Maintain surfaces of the lead control area free of accumulations of dust and debris.
Restrict the spread of dust and debris; keep waste from being distributed over the work area. Do not dry sweep or use pressurized air to clean up the area.
B. Disposal
1. All material, whether hazardous or non-hazardous shall be disposed in accordance with all laws and provisions and all federal, State or local regulations. Ensure all waste is properly characterized. The result of each waste characterization (TCLP for RCRA materials) will dictate disposal requirements. The Contractor shall collect one representative TCLP sample from the Site and submit it for laboratory analysis. The analytical result will provide details as to whether the generated waste can be handled and disposed of as non-hazardous or hazardous. In order for the waste stream to be considered non-hazardous, the TCLP result for lead content must be below 5 milligrams per Liter (mg/L).
2. Contractor is responsible for segregation of waste. Collect lead-contaminated waste, scrap, debris, bags, containers, equipment, and lead-contaminated clothing that may produce airborne concentrations of lead particles. Label the containers in accordance with 29 CFR 1926.62 and 40
CFR 261. If the waste stream changes at any point during the Site activities, additional TCLP samples will need to be collected in order to appropriately characterize the waste.
3. Handle, store, transport, and dispose lead or lead-contaminated waste in accordance with 40
CFR 260, 40 CFR 261, 40 CFR 262, 40 CFR 263, 40 CFR 264, and 40 CFR 265. Comply with land disposal restriction notification requirements as required by 40 CFR 268.
C. Disposal Documentation
1. Submit written evidence to demonstrate the hazardous waste treatment, storage, or disposal facility (TSD) is approved for lead disposal by the EPA, State or local regulatory agencies.
Submit one copy of the completed hazardous waste manifest, signed and dated by the initial transporter in accordance with 40 CFR 262. Contractor shall provide a certificate that the waste was accepted by the disposal facility. Provide turn-in documents or weight tickets for non-hazardous waste disposal.
D. Payment for Hazardous Waste
1. Payment for disposal of hazardous and non-hazardous waste will not be made until a signed copy of the manifest from the treatment or disposal facility certifying the amount of lead-containing materials or non-hazardous waste delivered is returned and a copy is furnished to
Contract Officer.
END OF SECTION