About this file

This attachment provides the markup rates for change orders on a federal construction contract. The contractor may elect to use the standard Navy rates for field overhead of 10% on prime contractor work, field overhead of 10% on subcontractor work, home office overhead of 3% on subcontractor work, and profit percentages on subcontractor work. The contractor must also propose rates for prime contractor home office overhead, profit, and an extended overhead rate to be used for compensable time extensions. The Navy will evaluate proposed costs using the provided form, applying a 2% markup to the base proposal for evaluation of subcontractor work and a 3% markup to the base proposal for evaluation of prime contractor home office overhead and profit. The selected extended overhead rate will also be applied for a 5-day hypothetical extension. The rates agreed upon will become part of the contract for applying to all modification costs.

This solicitation is for an indefinite delivery/indefinite quantity environmental multiple award contract for services and remedial actions at contaminated Navy and Marine Corps sites located in the Great Lakes region. The performance period is one base year with four option years not to exceed $30 million total for three to five awards. Task orders will range from $50,000 to $250,000 for studies, sampling, inspections, compliance projects, and other environmental work and corrective actions under regulations including CERCLA, RCRA, UST, and others. The contract is 100% set aside for service disabled veteran owned small businesses located in the Midwest. The Navy Facilities Engineering Command is the contracting agency.

View the file

Other files

File Type Posted
Amendment 0008.pdf PDF
Amendment 0007.pdf PDF
Amendment 0006.pdf PDF
Fig 1_Lake Michigan Sampling Locations.pdf PDF
Attachment J2 REVISED 03.09.22 Price Proposal Form.xlsx XLSX spreadsheet
UST_drawings_1.pdf PDF
Fig 2_Skokie River Sampling Locations.pdf PDF
Amendment 0005.pdf PDF
61197 - Naval Station Great Lakes - Building 1 - Great Lakes - IL - 7212021 - Final.pdf PDF
61200 - Naval Station Great Lakes - Building 3402 - Great Lakes - IL - 7222021 - Final.pdf PDF
61198 - Naval Station Great Lakes - Building 1506 - Great Lakes - IL - 7(2)21(2)2021 - Final.pdf PDF
61196 - Naval Station Great Lakes - Building 400 - Great Lakes - IL - 7212021 - Final.pdf PDF
61197 - Naval Station Great Lakes - Building 1 - Great Lakes - IL - 7212021 - Final.pdf PDF
Amendment 0004.pdf PDF
N4004821R2534 Site Visit Sign In Sheet.pdf PDF
61199 - Naval Station Great Lakes - 8150 - Final.pdf PDF
FINAL_NAVSTA Great Lakes SPCC Plan - August 2021.pdf PDF
SWPPP 2020 IEPA Submittal_FINAL.pdf PDF
157304_NSGreatLakes_AnnualSampling2021_LtrRpt_FNL.pdf PDF
REVISED Attachment J2 Price Proposal Form.xlsx XLSX spreadsheet
Amendment 0003.pdf PDF
2016EPCRA Report(Period Jan-Dec2016) Combined Appendices.pdf PDF
RY2020_Annual_TierIIReport_NavalStationGreatLakes.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
Attachment J2 Price Proposal Form.xlsx XLSX spreadsheet
ATTACHMENT J5 Key Personnel.pdf PDF
J6 SCA Wage Determination.pdf PDF
N4008521R2534.pdf PDF
ATTACHMENT J4 Responsibility Eval Form.pdf PDF
J9 PTO 001 Combined Enclosures.pdf PDF
ATTACHMENT J7 PPQ.docx DOCX document
Attachment J8 Project Data Form.docx DOCX document
J1 PTO 001 Scope of Work.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT J-3

Change Order Mark-up Rates/Extended Overhead

(The offeror may elect to propose the NAVFAC standard rates, if desired, as annotated below each item). The change order markup cost elements are awarded as part of the contract and will be used as the markups for both additive and deductive modifications after award for the term of the contract for both prime and subcontractors as listed below. In addition to the Base Price Proposal submitted, the offeror shall provide proposed modification/change order percentage rates, for Field Overhead, Home Office Overhead, and Profit, as follows:

PRIME CONTRACTOR’S WORK:

(a) Proposed field overhead rate, line 9 of Form 4330/43 ____%

(NAVFAC Standard Rate – 10%)

SUBCONTRACTOR’S WORK:

(b) Proposed field overhead rate, (subcontractor’s Work), line 19 of

Form 4330/43 (NAVFAC Standard Rate – 10%) ____%

(c) Proposed home office overhead, (subcontractor’s work), line 21 of Form 4330/43 (NAVFAC Standard Rate – 3%) ____%

(d) Proposed profit, (subcontractor’s work), line 22 of Form 4330/43 ____%

SUMMARY

(e) Proposed overhead rate on subcontractors, line 27 Form 4330/43 ____%

(NAVFAC Standard Rate – 5%)

(f) Proposed prime contractor home office overhead rate, line 28 of

Form 4330/43 (NAVFAC Standard Rate – 3%) ____%

(g) Proposed profit, line 29 of Form 4330/43 ____%

(h) Proposed extended overhead rate from Total Price Evaluation

Input Data (to be utilized in lieu of percent in Line 9 of Form

4330/43 when a contract modification results in a compensable time extension of the contract.)* $_______/day

The Government will evaluate estimated cost of changed work as follows: Using Form 4330/43 (8/88), 2% of your base proposal will be entered on Line 8 and 3% of your base price proposal will be entered on line 18. The subtotal cost (Line 30) will be calculated using the proposed rates. In the event contract modifications result in time extensions of the contract completion date due to Suspension of Work, FAR 52.242-14, the proposed Extended

Overhead rate will be used to calculate the extended overhead.

For evaluation purposes, a 5 day extension of the contract will be used. Your proposed Extended Overhead rate will be multiplied by 5 days and added to the subtotal computed on Line 30, which will be used in the Total Price

Calculation to evaluate the offer.

The above rates will become part of the successful offeror’s resultant contract and will be applied to the direct costs of all contract modifications.

Field Overhead will be evaluated as a percent mark-up and not a direct cost to the change proposal. Field overhead costs cover indirect costs incurred on this project that are chargeable only to this contract and include costs incurred on the job site incident to the performance of the work, including but not limited to, the costs of superintendent, timekeeping, clerical work, engineering, job site supervision, engineer, secretaries, tool shed keeper, temporary facilities, contractor’s office, utilities, storage shed, supplies, office supplies, temporary protection and/or maintenance, dust control, noise control, winter protection, barricades (rented), haul roads, clean-up, progress reports, equipment, superintendent’s truck, truck for clean-up, and fringe benefits for supervisory and administrative personnel.

*Extended Overhead Rate – Prior to the start of on-site work, the contractor may elect to use the extended overhead rate in lieu of the percent rates for Field Overhead shown on Line 9. If the contractor elects to use the Extended

Overhead rate, field overhead mark-ups will be allowed only in modifications that result in a compensable time extension of the contract, with the above. Extended Overhead Rate used to calculate the field overhead. If the contractor does not elect to use the Extended Overhead Rate in lieu of the percentage rates for Field Overhead shown on Line 9, the extended overhead rate will be used only on modifications to the contract that results in a compensable time extension of the contract due to Suspension of Work, FAR 52.242-14.

File details come from the government source that posted it. Updated .