Attachment J-3 ANC ATCT TRACON Final Spec Vol 1.pdf
PDF 28 MB Posted
- Solicitation number
- 697DCK-25-R-00074
About this file
This file appears to be architectural/engineering specifications (Volume 1) for the construction of a new Airport Traffic Control Tower (ATCT) and Terminal Radar Approach Control (TRACON) facility at Ted Stevens International Airport in Anchorage. As an appendix document (Attachment J-3), it contains technical specifications and requirements for the construction project.
The Federal Aviation Administration (FAA) is seeking proposals for this major construction project through solicitation #697DCK-25-R-00074, with a Phase I proposal deadline of January 31, 2025 at 15:00 PT. A pre-proposal Zoom meeting is scheduled for January 10, 2025, and questions are due by January 17, 2025. The procurement uses a two-phase approach, with site visits planned for offerors down-selected to Phase II. Proposals must comply with Sections L and M of the solicitation, and offerors must be registered in SAM.gov. Due to file size limitations, additional design documents (Attachments J-5, J-5a, and J-5b) must be requested directly from the contracting officer.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FAA ANC New ATCT and TRACON/Base Building
Final Design Specifications – Volume 1
Division 1
June 11, 2024
Prepared for:
Federal Aviation Administration Contract No. 697DCK-22-C-00190
Prepared by:
Stantec Architecture Inc.
725 East Fireweed Lane Anchorage, Alaska 99503
Table of Contents – Volume 1 Division 1
DIVISION 01 – GENERAL REQUIREMENTS
01 00 00 General Paragraphs 01 10 00 Summary 01 10 02 Construction Administration Forms 01 10 15 Acronyms and Definitions 01 25 00 Substitution Procedures 01 31 00 Project Management and Coordination 01 32 33 Photographic Documentation 01 33 00 Submittal Procedures 01 35 29 Health, Safety, and Emergency Response Procedures Appendix: Construction Safety and Phasing Plan 01 40 00 Contractor Quality Control 01 40 10 Coordination Drawings and Building Information Modeling (BIM) 01 43 39 Mockups 01 45 29 Structural Testing and Inspections 01 45 33 Nonstructural Components and Systems Requirements 01 50 00 Temporary Facilities 01 50 10 FAA Field Representatives Office 01 55 26 Maintenance of Traffic 01 56 23 Barriers and Enclosures 01 57 13 Temporary Air and Water Pollution, Soil Erosion, and Siltation Control Appendix: Erosion and Sediment Control Plan 01 57 19 Temporary Environmental Controls 01 57 23 Handling of Incidental Petroleum Products Spillage During Construction 01 58 00 Construction Identification Signs 01 58 13 Posting of Notices 01 66 00 Government Furnished Material (GFM) 01 71 23 Surveying and Field Engineering 01 71 33.10 Protection of Work and Property 01 74 13 Construction Cleaning 01 74 19 Construction Waste Management and Disposal Attachments:
Form CWM -1 for construction waste identifications Form CWM -2 for demolition waste identifications Form CWM -3 for construction waste reduction work plan Form CWM -4 for demolition waste reduction work plan Form CWM -5 cost/revenue analysis of construction waste reduction work plan Form CWM -6 cost/revenue analysis of demolition waste reduction work plan Form CWM -7 for construction waste reduction progress report Form CWM -8 for demolition waste reduction progress report 01 77 00 Closeout Procedures 01 77 10 Final Cleaning 01 78 23 Operation and Maintenance Data 01 78 36 Warranties and Guarantees 01 78 39 Project Record Documents
01 81 09 Testing for Indoor Air Quality 01 81 13 Sustainable Design Requirements 01 91 13 General Commissioning Requirements
DIVISION 02 – EXISTING CONDITIONS
02 41 19 Selective Demolition
DIVISION 03 – CONCRETE
03 10 00 Concrete Forming and Accessories 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 45 00 Precast Architectural Concrete
DIVISION 04 – MASONRY
04 22 13 Structural Reinforced Concrete Unit Masonry
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 05 12 13 Architectural Exposed Steel Framing 05 12 50 Buckling Restrained Braces 05 31 00 Steel Decking 05 40 00 Cold-Formed Metal Framing 05 50 00 Metal Fabrications 05 51 16 Metal Floor Plate Stairs 05 51 19 Metal Grating Stairs 05 53 00 Metal Gratings 05 73 00 Decorative Metal Railings
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 Rough Carpentry 06 16 00 Sheathing 06 41 16 Plastic Laminate-Clad Architectural Cabinets 06 74 00 Composite Gratings
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 13 26 Self-Adhering Sheet Waterproofing 07 14 16 Cold Fluid Applied Waterproofing 07 21 00 Thermal Insulation 07 26 00 Vapor Retarders 07 27 27.01 Self-Adhering Water-Resistive Air Barrier Membranes 07 41 13.16 Standing Seam Metal Roof Panels 07 42 13.16 Metal Plate Wall Panels 07 53 23 Ethylene-Propylene-Diene-Monomer (EPDM) Roofing 07 62 00 Sheet Metal Flashing and Trim 07 71 00 Roof Specialties 07 72 00 Roof Accessories 07 81 00 Applied Fireproofing 07 84 13 Penetration Firestopping
07 92 00 Joint Sealants 07 92 19 Acoustical Joint Sealants 07 95 00 Expansion Control
DIVISION 08 – OPENINGS
08 11 13 Hollow Metal Doors and Frames 08 14 16 Flush Wood Doors 08 31 13 Access Doors and Frames 08 36 13 Sectional Doors 08 41 13 Aluminum Framed Entrances and Storefronts 08 41 23 Fire Rated Aluminum Framed Entrances and Storefronts 08 44 13 Glazed Aluminum Curtain Walls 08 71 00 Door Hardware 08 71 13 Automatic Door Operators 08 80 00 Glazing 08 88 58 Air Traffic Control Tower Cab Glazing 08 91 19 Fixed Louvers
DIVISION 09 – FINISHES
09 21 16.23 Gypsum Board Shaft Wall Assemblies 09 29 00 Gypsum Board 09 30 13 Ceramic Tiling 09 51 13 Acoustical Panel Ceilings 09 65 13 Resilient Base and Accessories 09 65 19 Resilient Tile Flooring 09 65 36 Static Control Resilient Flooring 09 68 13 Tile Carpeting 09 72 00 Wall Coverings 09 84 30 Sound-Absorbing Wall and Ceiling Units 09 91 13 Exterior Painting 09 91 23 Interior Painting
DIVISION 10 – SPECIALTIES
10 14 00 ATCT Signage 10 21 13.19 Plastic Toilet Compartments 10 21 23 Cubicle Curtains and Track 10 26 00 Wall and Door Protection 10 28 00 Toilet, Bath, and Laundry Accessories 10 44 00 Fire Protection Specialties 10 51 13 Metal Lockers 10 56 13 Metal Storage Shelving 10 56 17 Wall Mounted Standards and Shelving 10 73 16.13 Metal Canopies 10 73 26 Walkway Coverings 10 75 00 Flagpoles
DIVISION 11 – EQUIPMENT
11 30 13 Residential Appliances
11 33 00 Retractable Stairs 11 81 23 Façade Access Equipment
DIVISION 12 – FURNISHINGS
12 22 00 Curtains and Drapes 12 24 12 ATCT Transparent Plastic Window Shades 12 24 13 Roller Window Shades 12 35 00 Specialty Casework – Slat Wall Systems 12 36 00 Countertops 12 48 13 Entrance Floor Mats and Frames 12 51 00 Office Furnishings 12 59 00 Systems Furniture
DIVISION 13 – SPECIAL CONSTRUCTION
13 11 00 Tuned Mass Damper
DIVISION 14 – CONVEYING EQUIPMENT
14 21 50 Gearless Machine Room Less Traction Elevators 14 24 00 Hydraulic Elevators
DIVISION 21 – FIRE SUPPRESSION
21 13 13 Water-Based Fire-Suppression Systems
DIVISION 22 – PLUMBING
22 05 16 Expansion Fittings and Loops for Plumbing Piping 22 05 17 Sleeves and Sleeve Seals for Plumbing Piping 22 05 18 Escutcheons for Plumbing Piping 22 05 19 Meters and Gages for Plumbing Piping 22 05 23.12 Ball Valves for Plumbing Piping 22 05 23.13 Butterfly Valves for Plumbing Piping 22 05 23.14 Check Valves for Plumbing Piping 22 05 29 Hangers and Supports for Plumbing Piping and Equipment 22 05 33 Heat Tracing for Plumbing Piping 22 05 48 Vibration and Seismic Controls for Plumbing Piping and Equipment 22 05 53 Identification of Plumbing Piping and Equipment 22 07 19 Plumbing Piping Insulation 22 08 00 Commissioning of Plumbing 22 11 16 Domestic Water Piping 22 11 19 Domestic Water Piping Specialties 22 11 23.13 Domestic Water Packaged Booster Pumps 22 11 23.21 Inline, Domestic-Water Pumps 22 13 16 Sanitary Waste and Vent Piping 22 13 19 Sanitary Waste Piping Specialties 22 13 19.13 Sanitary Drains 22 14 13 Facility Storm Drainage 22 14 23 Storm Drainage Piping Specialties 22 14 29 Sump Pumps 22 30 00 Water Softener Systems and Reverse Osmosis Systems
22 33 00 Electric, Domestic-Water Heaters 22 34 00 Fuel-Fired, Domestic-Water Heaters 22 42 13.13 Commercial Water Closets 22 42 13.16 Commercial Urinals 22 42 16.13 Commercial Lavatories 22 42 16.16 Commercial Sinks 22 42 23 Commercial Showers 22 45 00 Emergency Plumbing Fixtures 22 47 16 Pressure Water Coolers 22 70 00 Central Vacuum Systems
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING
23 05 16 Expansion Fittings and Loops for HVAC Piping 23 05 17 Sleeves and Sleeve Seals for HVAC Piping 23 05 18 Escutcheons for HVAC Piping 23 05 19 Meters and Gauges for HVAC Piping 23 05 23.12 Ball Valves for HVAC Piping 23 05 23.13 Butterfly Valves for HVAC Piping 23 05 23.14 Check Valves for HVAC Piping 23 05 29 Hangers and Supports for HVAC Piping and Equipment 23 05 48 Vibration and Seismic Controls for HVAC 23 05 53 Identification of HVAC Piping and Equipment 23 05 66 Antimicrobial Ultraviolet Lamps Systems for HVAC 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 13 Duct Insulation 23 07 19 HVAC Piping Insulation 23 08 00 Commissioning of HVAC 23 09 23 Direct Digital Control (DDC) System for HVAC 23 09 23.11 Control Valves 23 09 23.12 Control Dampers 23 09 23.16 Gas Instruments 23 09 23.19 Moisture Instruments 23 09 23.23 Pressure Instruments 23 09 23.27 Temperature Instruments 23 11 13 Facility Fuel-Oil Piping 23 11 23 Facility Natural Gas Piping 23 12 13 Facility Fuel-Oil Pumps 23 13 23 Facility Aboveground Fuel-Oil Storage Tank 23 21 13 Hydronic Piping 23 21 13.13 Underground Hydronic Piping 23 21 16 Hydronic Piping Specialties 23 21 23 Hydronic Pumps 23 25 33 HVAC Makeup-Water Filtration Equipment 23 31 13 Metal Ducts 23 33 00 Air Duct Accessories 23 33 46 Flexible Ducts 23 34 13 Axial HVAC Fans 23 34 16 Centrifugal HVAC Fans
23 36 00 Air Terminal Units 23 37 13.13 Air Diffusers 23 37 13.23 Registers and Grilles 23 41 00 Particulate Air Filtration 23 51 13.16 Vent Dampers 23 51 16 Fabricated Breechings and Accessories 23 51 23 Gas Vents 23 51 33 Insulated Sectional Chimneys 23 52 23 Cast-Iron Boilers 23 57 00 Heat Exchangers for HVAC 23 64 26.16 Water-Cooled, Rotary-Screw Water Chillers 23 65 33 Liquid Coolers 23 72 23.19 Packaged Indoor Fixed Plate Energy Recovery Units 23 73 13.13 Indoor, Semi-Custom Heat Wheel Energy Recovery Units 23 73 13.16 Indoor, Semi-Custom Air-Handling Units 23 82 14 Chilled Beams 23 82 39.13 Cabinet Unit Heaters 23 82 39.19 Wall and Ceiling Unit Heaters 23 84 13.29 Self-Contained Steam Humidifiers
DIVISION 26 – ELECTRICAL
26 00 01 Provisions for GFE 26 00 02 Documentation, Testing, and Training Requirements for Government Furnished
Equipment (GFE) and Contractor Furnished Equipment (CFE) 26 00 03 List of Government Furnished Equipment (GFE) 26 05 00 Common Work Results for Electrical 26 05 05 Submittal Requirements for Lockout/Tagout Procedures 26 05 19 Low-Voltage Electrical Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangars and Supports for Electrical Systems 26 05 33 Raceway and Boxes for Electrical Systems 26 05 48 Vibration and Seismic Controls for Electrical Systems 26 05 53 Identification for Electrical Systems 26 05 73 Overcurrent Protective Device Coordination Study 26 05 74 Arc Flash Hazard Analysis 26 08 00 Commissioning of Electrical Systems 26 09 13 Electrical Power Monitoring (GFE) 26 09 23 Lighting Control Devices 26 09 43 Networked Lighting Controls 26 22 01 Low-Voltage Transformers (GFE) 26 24 14 Switchboards (GFE) 26 24 17 Panelboard (GFE) 26 25 00 Open Channel Busway 26 27 26 Wiring Devices 26 28 13 Fuses 26 28 16 Enclosed Switches Circuit Breakers 26 29 13 Enclosed Controllers 26 29 23 Variable-Frequency Motor Controllers
26 32 13 Engine Generators 26 32 14 Engine Generator Resistive Load Bank (GFE) 26 33 53 Static Uninterruptable Power Supply 26 33 54 Resistive Load Bank for Static Uninterruptable Power Supply (UPS) 26 36 00 Transfer Switches (Partial GFE) 26 36 14 Installation of Static Transfer Switches (GFE) 26 41 13 Lightning Protection for Structures 26 43 13 Surge Protective Devices for Low-Voltage Electrical Power Circuits (GFE) 26 51 00 Interior Lighting 26 55 37 Obstruction Lighting 26 56 00 Exterior Lighting
DIVISION 27 – COMMUNICATIONS
27 05 00 Common Work Results for Communications 27 05 10 Common Work Results for Audio-Video Systems 27 05 28 Pathways for Communications Systems 27 05 43 Underground Ducts and Utility Structures for Communications Systems 27 11 00 Communications Equipment Room Fittings 27 13 00 Communications Backbone Cabling 27 15 00 Communications Horizontal Cabling 27 41 16.10 Audio-Video Equipment List 27 41 16.20 Audio-Visual Narrative 27 41 16 Integrated Audio Video Systems 27 51 13 Paging Systems
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 00 Fire Detection and Alarm System
DIVISION 31 – EARTHWORK
31 20 00 Earth Moving 31 20 20 Directional Drilling 31 23 00 Structural Excavation and Fill 31 23 19 Dewatering 31 62 23 Concrete Filled Steel Pipe Piles 31 63 30 Temporary Retention System
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Paving 32 13 13 Concrete Paving 32 17 23 Pavement Markings 32 17 31 Steel Guardrail 32 31 13.53 High-Security Chain Link Fences and Gates 32 31 19 Decorative Metal Fences and Gates 32 33 00 Site Furnishings 32 90 00 Planting General 32 91 00 Planting Soil 32 92 00 Turfs and Grasses 32 93 00 Plants
32 94 00 Landscape Accessories 32 97 00 Landscape Maintenance
DIVISION 33 – UTILITIES
33 42 00 Stormwater Conveyance
MUNICIPALITY OF ANCHORAGE STANDARD SPECIFICATIONS (MASS)
20.13 Trench Excavation and Backfill
20.14 Trench Excavation, Backfill and Compaction for Service Connections
20.16 Furnish Bedding Material
20.25 Geotextile Fabric
20.26 Insulation
50.01 Standard Construction Specifications for Sanitary Sewers - General
50.02 Furnish and Install Pipe
50.04 Sanitary Sewer Pipe Connections and Extensions
60.01 Construction Specifications for Water Systems - General
60.02 Furnish and Install Pipe
60.03 Furnish and Install Valves
60.04 Furnish and Install Fire Hydrants
60.05 Water Service Lines
60.06 Furnish and Install Galvanic Anodes
60.07 Temporary Water Systems
60.08 Decommission Water System and Components
70.13 Bollards
End of Table of Contents – Volume 1
FEDERAL AVIATION ADMINISTRATION JUNE 11, 2024
ANC New ATCT & TRACON/Base Building
GENERAL PARAGRAPHS 01 00 00-1
SECTION 01 00 00 - GENERAL PARAGRAPHS
PART 1 - GENERAL
1.1 DRAWINGS, SPECIFICATIONS, AND OTHER CONTRACT DOCUMENTS
A. Drawings showing general outlines and details necessary for a comprehensive understanding of the work from a part of the Contract Documents. The total number and the titles of the drawings constituting the Drawings are given in the index of the Drawings. All work under the Contract will be performed in all respects in compliance with the requirements of the Contract Documents.
B. The Contract Documents provide for a complete work and may have been prepared in divisions of various crafts, trades and other categories of work. The Contractor is responsible for the performance of all work under the Contract regardless of any such divisions and will ensure that all of the work is performed and completed.
C. The FAA will provide the Contractor with one bound copy of the construction drawings and specifications for the Contractor’s use during the execution of the Contract. The Contractor may reproduce these documents for its use during the performance of the work under this Contract.
D. The Contractor will maintain at the Site at all times at least one (1) copy of Drawings, Specifications and all other Contract Documents, together with at least one (1) complete set of approved Shop Drawings and approved samples.
E. The Contractor will make available at the job site one copy of each referenced standard for the
Contractor’s and the FAA’s use during the time that work is covered by the standard.
F. The Contract, Drawings, Specifications, and all referenced standards cited are essential parts of the Contract requirements. A requirement occurring in one is as binding as though occurring in all. They are intended to be complementary and to describe and provide for a complete work.
G. The Contractor will not take advantage of any apparent error, omission, discrepancy, or ambiguity on the Drawings or Specifications. If any error, omission, discrepancy, or ambiguity is found by the Contractor in the Drawings or Specifications, the Contractor will refer the same to the Contracting Officer (CO) prior to beginning work on affected task(s), for interpretation and decision, and such decision will be final.
H. The CO will have the right to correct apparent errors or omissions in the Drawings and
Specifications and to make such interpretations as they may deem necessary for the proper fulfillment of the Contract Documents. During the course of the work, should any conflicts, ambiguities, or discrepancies be found that are not addressed or any discrepancies between the Drawings and the Specifications to which the Contractor has failed to call attention before submitting the offer, then the CO will interpret the intent of the Drawings and Specifications and the Contractor hereby agrees to abide by the CO’s interpretation and agrees to carry out the work in accordance with the decision of the CO. In such event the Contractor will be held to
GENERAL PARAGRAPHS 01 00 00-2
have included in the offer the most expensive material and/or method of construction.
I. When a material, article, or equipment is designated by a brand name, and more than one brand name is listed, it will be understood that the design is based on one of the brand name listed products. The contractor will be responsible for all coordination necessary to accommodate the material, article, or equipment actually being provided without additional cost to the government.
J. The organization of the contract Documents into divisions, sections and articles, and the arrangement of Drawings does not restrict or limit the Contractor in dividing the Work among Subcontractors or in establishing the extent of work to be performed by any trade.
K. Product and Reference Standards:
1. When descriptive catalog designations including manufacturer’s name, product brand name, or model number are referred to in the Contract Documents, such designations will be considered as being those found in industry publications of current issue on the date of the first advertisement for offers.
2. When standards of the Federal Government, State Department of Transportation, Standards Organization such as ASTM, AASHTO, AWS, or ANSI, trade societies, or trade associations are referred in the Contract Documents by specific date of issue, these will be considered a part of this Contract. When such references do not bear a date of issue, the current published edition on the date of the first advertisement for offers will be considered as part of the Contract.
3. Where in the Contract Documents an item is identified by a particular manufacturer’s name, model or other code it will be interpreted to include other manufacturers’ product of like and equal quality whether the words “or equal” are included or not.
4. Wherever a particular manufacturer’s product is required, to the exclusion of all others, appropriate language is included in the Contract Documents.
5. Wherever the terms, “as directed”, “ordered”, “permitted”, “designate”, “as approved”, “approved equal”, “or equal”, “acceptable” and other words of similar meaning which authorize an exercise of judgement are used in the Contract Documents, such judgment will be vested only in the FAA.
1.2 CONFORMITY WITH DRAWINGS AND SPECIFICATIONS
A. No deviation from the Drawings, Specifications and other Contract Documents will be permitted without the prior written approval of the Contracting Officer.
B. Wherever the term “shall” and other words of similar meaning are used in the Drawings or Specifications, such will be interpreted as a requirement on the Contractor.
1.3 SUPERVISION AND CONSTRUCTION PROCEDURES
A. At all times during performance of this contract, and until the work is completed and accepted, the Contractor will directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the CO and has the authority to act for the Contractor.
GENERAL PARAGRAPHS 01 00 00-3
B. The Contractor will supervise and direct the Work, using the Contractor's best skill and attention. The Contractor will be solely responsible for and have control over construction means, methods, techniques, sequences, and procedures and for coordinating all portions of the Work under the Contract including coordination of the duties of all trades and manufacturer’s representatives, unless the Contract Documents give other specific instructions concerning these matters.
C. The Contractor will control its operations and those of its Subcontractors and Suppliers to assure the least inconvenience to the traveling public. Under all circumstances, safety will be the most important consideration.
D. Contractor will lay out all work well enough in advance to avoid conflicts or interferences with other work in progress so that in case of interference the layout may be altered to suit the conditions, prior to the installation of any work and without additional cost to the FAA. The contractor will be responsible to coordinate all work and take all action as required to avoid conflicts between trades. Unless specifically noted otherwise, establish the exact location of equipment based on the actual dimensions of equipment furnished. Contractor shall maintain a project “Master Document set” and ensure all design changes, field modifications, RFIs etc.; are noted and tracked on the set. In addition, the Contractor shall maintain and archive superseded drawing revisions for review purposes. Mechanical and electrical work will be coordinated so that work may proceed according to the following sequence to avoid conflict:
1. Air handling unit placement
2. Gravity Pipes (drains, sewer, storm)
3. Duct routing
4. Cable tray placement
5. Light fixture location
6. Pressure pipe routing
7. Conduit routing
1.4 CORRESPONDENCE
A. Contract correspondence will be directed to the CO with a copy to the COR. Submittals will be sent direct to the COR with a copy of the transmittal letter to the CO.
1.5 LIST OF SUBCONTRACTORS
A. The Contractor will, within 10 calendar days after award, furnish to the CO with a copy to the COR, a list of subcontractors showing the type of work each will perform. If all subcontracts have not been awarded when the initial list is submitted, the Contractor will update the list.
1.6 PRECONSTRUCTION CONFERENCE
A. The CO will arrange a conference at a location, mutually agreeable to the CO and the Contractor as soon as practicable after award of a contract. It will be mandatory that the Contractor or his designated representative attends.
GENERAL PARAGRAPHS 01 00 00-4
1.7 WORK NOT INCLUDED
A. Items noted on the drawings, details, or schedules as "N.I.C.” (Not in Contract) are not included in this contract.
1.8 SECURITY REQUIREMENTS
A. Personnel List: Contractor will provide the Contracting Officer Representative with a list of Contractor's personnel who will require access to the site. The list will be kept current during project work. The Contractor will provide all personnel with readily identifiable numbered badges during the period their access to the site is required. Badges will be worn on outer clothes at all times when at work in the site.
B. Security Investigation: Contractor's site superintendent will submit to an FAA security background check and obtain an official FAA contractor ID badge. Other Contractor personnel may be subject to security investigation by FAA. Upon request by the Contracting Officer Representative, the Contractor will promptly complete all security forms provided by the Contracting Officer Representative.
1.9 CHANGED CONDITIONS
A. Refer to Contract clauses.
1.10 EXISTING WORK
A. The disassembling, disconnecting, cutting, removal, or altering in any way of existing work will be carried on in such a manner as to prevent injury or damage to all portions of existing work, whether they are to remain in place, be re-used in the new work, or be salvaged and stored.
B. All portions of existing work which have been cut, damaged, or altered in any way during construction operations will be repaired or replaced in kind in an approved manner to match existing or adjoining work. All work of this nature will be performed by the Contractor at his expense and will be as directed. Existing work will, at the completion of all operations, be left in a condition as good as existed before the new work started.
1.11 MATERIALS AND EQUIPMENT TO BE SALVAGED
A. Except where specifically stated otherwise herein, or designated on the drawings, all existing materials and equipment which are required to be removed or disconnected to perform the work but are not indicated or specified for use in the new work, will become the property of the Contractor and will be disposed of properly. The Government may elect to salvage any or all materials removed by the Contractor by giving prior notice and pricing up materials at job site.
GENERAL PARAGRAPHS 01 00 00-5
1.12 PARTIAL OCCUPANCY OR USE
A. The FAA may occupy or use any completed or partially completed portion of the Work at any stage and, if the FAA chooses such partial occupancy, the Contractor and FAA will designate by an agreement the conditions of such partial occupancy. Such partial occupancy or use may commence whether or not the portion is substantially complete, provided the FAA and Contractor have accepted in writing the responsibilities assigned to each of them by the COR for payments, retainage if any, security, maintenance, heat, utilities, damage to the Work and insurance, and have agreed in writing concerning the period for correction of the Work and commencement of warranties required by the Contract Documents. Consent of the Contractor to partial occupancy or use by the FAA will not be unreasonably withheld.
1.13 UNCOVERING AND CORRECTION OF WORK
A. Uncovering Work
1. If any portion of the Work is covered contrary to the COR's request or to requirements specifically expressed in the Contract Documents, it must, if required in writing by the COR be uncovered for their observation and be recovered (if corrections are not required) or be corrected, if applicable, at the Contractor's expense without change in the Contract Time.
2. If a portion of the Work has been covered which the COR or any applicable governmental authority has not specifically requested to observe prior to its being covered, the COR may request to see such Work and it will be uncovered by the Contractor. If such work is in accordance with the Contract Documents, costs of uncovering and restoration will, by appropriate Change Order, be charged to the FAA. If such Work is not in accordance with the Contract Documents, the Contractor will pay such costs unless the condition was caused by the FAA or a separate contractor in which event the FAA will be responsible for payment of such costs.
B. Correction Of Work
1. The Contractor will promptly correct Work rejected by the COR or any governmental authority that fails to conform to the requirements of the Contract Documents, whether observed before or after Substantial Completion and whether or not fabricated, installed or completed. The Contractor will bear all costs of correcting such rejected Work, including additional testing and inspections and compensation for the COR's services and expenses incurred by the FAA.
2. If, within two years after the date of Substantial Completion of the Work or designated portion thereof, or after the date for commencement of warranties established above, or by terms of an applicable special warranty required by the Contract Documents, any of the work is found to be not in accordance with the requirements of the Contract Documents, the Contractor will correct it promptly after receipt of written notice from the FAA to do so unless the FAA has previously given the Contractor a written acceptance of that specific condition. This period of two years will be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance of the Work. This obligation will survive acceptance of the Work under the Contract and termination of the Contract. The
GENERAL PARAGRAPHS 01 00 00-6
FAA will give such notice within a reasonable amount of time after discovery of the condition.
3. The Contractor will remove from the site portions of the Work that are not in accordance with the requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the FAA.
4. If the Contractor fails to correct nonconforming Work within a reasonable time, the FAA may correct it in accordance with General Provisions. If the Contractor does not proceed with correction of such nonconforming Work within a reasonable time fixed by written notice from the COR, the FAA may correct or remove such nonconforming work and all costs for such corrections or removals will be assessed against the Contractor.
5. The Contractor will bear the cost of correcting destroyed or damaged Work, whether completed or partially completed, of the FAA or separate contractors caused by the Contractor's performing correction or removal of Work which is not in accordance with the requirements of the Contract Documents.
6. Nothing contained herein will be construed to establish a period of limitation with respect to other obligations that the Contractor might have under the Contract Documents.
Establishment of the time period of two years as described above relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability and damages with respect to the Contractor's obligations other than specifically to correct the Work.
C. Acceptance Of Nonconforming Work
1. If the FAA prefers to accept Work that is not in accordance with the requirements of the
Contract Documents, the FAA may do so instead of requiring its removal or correction.
If the FAA accepts the Work under such circumstances, the Total Contract Price will be reduced in an equitable manner as determined by the Contracting Officer, whether or not final payment has been made.
D. Terms and Conditions” and “Contract Clauses”
1. Wherever a reference to a clause of the General Provisions or General Conditions occurs in a section of the specifications, it will be taken to mean the “Terms and Conditions” and “Contract Clauses” having the same title as the referenced General Provisions or General Conditions clause.
1.14 UNDERGROUND UTILITIES
A. Utilities Encountered - Efforts have been taken to locate all the underground utilities and cables on the contract drawings; however, unforeseen utilities and underground cables may be encountered. Actual cable locations will be verified in the field by the Contractor by hand digging a minimum of five (5') on each side of the cable. FAA owned cable will be marked by the FAA prior to the start of work by the Contractor.
1.15 LOCATION OF SERVICES
GENERAL PARAGRAPHS 01 00 00-7
A. The FAA does not guarantee the accuracy or the completeness of the location information relating to existing utility services, facilities, or structures that may be shown on the drawings.
Any inaccuracy or omission in such information will not relieve Contractor of its responsibility to protect such existing features from damage or unscheduled interruption of service.
1.16 COOPERATE WITH OTHER ENTITIES
A. Cooperate with the FAA, the Airport Authority, and other public or private utility services, or a utility service of another government agency that may be authorized by the FAA to construct, reconstruct, or maintain such utility services or facilities during the progress of the work.
Control operations to prevent the unscheduled interruption of such utility services and facilities.
1.17 NOTICE TO FAA/OPERATORS
A. Prior to commencing the work in the general vicinity of an existing utility service or facility, Contractor will notify each FAA/operator in writing of activities that might affect its interests.
If, in Contractor’s opinion, the FAA/operator’s assistance is needed to locate the utility service or facility or the presence of a representative of the FAA/operator is desirable to observe the work, such advice should be included in the notification. Furnish a copy of such written notices to COR.
1.18 DAMAGE TO SERVICES
A. Should Contractor damage or interrupt the operation of a utility service or facility by accident or otherwise, it will immediately notify in writing the FAA/operator, appropriate public safety authorities, and the COR and will take all reasonable measures to prevent further damage or interruption of service. Cooperate with the utility service or facility FAA and the COR continuously until such damage has been repaired and service restored.
1.19 FAILURE TO PROTECT PROPERTY
A. Contractor will not be entitled to any extension of time or compensation on account of Contractor’s failure to protect all facilities, equipment, materials and other property as described herein. All costs in connection with any Improvements or restoration necessary or required by reason of unauthorized obstruction, damage, or use will be borne by Contractor.
1.20 UTILITY CONTRACTOR LICENSING REQUIREMENTS
A. Contractor will comply with all state and local requirements for construction of utilities.
1.21 ASBESTOS AND LEAD FREE CERTIFICATION
A. FAA policy is to construct all new facilities without asbestos or lead containing products. The
GENERAL PARAGRAPHS 01 00 00-8
Contractor will provide a letter on his company’s standard letterhead stating that to the best of his knowledge no product or material used on this project contains asbestos or lead. The statement will include the name of the project and the contract number and will be signed by an officer of the company. The statement will be furnished within 10 calendar days of the Substantial Completion date. Submission of this statement is a condition for final payment under the contract.
B. Verification: If the FAA suspects the presence of asbestos or lead, tests will be performed on the material or product at the FAA’s expense. If it is determined that the product or material does contain asbestos or lead, then the contractor will remove the product or material and replace at his own expense including the expense of the testing and any retesting that may be necessary.
C. Non – Compliance: If the Contractor fails to provide the above statement, then the FAA will have a complete building survey performed by a qualified testing firm and the costs deducted from the contractor’s final payment.
1.22 MATERIAL SAFETY DATA SHEETS (MSDS):
A. The Contractor will submit to the Contracting Officer Representative Material Safety Data Sheets (MSDS) for all materials and/or products utilized during the course of the project accomplishment. During the course of the project, both the Contracting Officer Representative and the Contractor will routinely check products utilized on-site to ensure only products which have had MSDS submitted are utilized. Copies of all MSDS will be turned over to the local FAA office for their records.
1.23 INITIAL SUBMITTALS
A. The following submittals are required to have FAA approval prior to Notice to Proceed.
1. Section 01 32 01 PROJECT SCHEDULE SCHEDULE
2. Section 01 35 29 HEALTH, SAFETY, AND EMERGENCY RESPONSE
PROCEDURES
3. Section 01 40 00 CONTRACTOR QUALITY CONTROL
4. Section 01 50 10 FAA FIELD REPRESENTATIVE OFFICE
5. Section 01 57 13 TEMPORARY AIR AND WATER POLLUTION, SOIL
EROSION, AND SILTATION CONTROL
6. Division 03 TOWER FOUNDATION REBAR AND PILES
1.30 KNOWLEDGE SHARING NETWORK (KSN) SITE
The FAA maintains a joint use internet site for the purpose of electronic communication with its Contractors. If it is a requirement to use this KSN site for submittals, RFI’s and other communications with the government, the government will provide access and required passwords to allow access to this site.
1.31 UTILITY CONTACTS
GENERAL PARAGRAPHS 01 00 00-9
Contractor will be responsible for establishing and maintaining a list of the local utility contacts.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION 01 00 00
GENERAL PARAGRAPHS 01 00 00-10
SUMMARY 01 10 00-1
SECTION 01 10 00 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Work under Owner's separate contracts.
5. Owner-furnished/Contractor-installed (OFCI) products.
6. Contractor's use of site and premises.
7. Coordination with occupants.
8. Work restrictions.
9. Specification and Drawing conventions.
1.2 DEFINITIONS
A. Contracting Officer’s Representative (COR): Individual authorized to receive and distribute information on the behalf of the Contracting Officer. Also referred to as the Contracting Officer’s Technical Representative (COTR) and/or Resident Engineer (RE) in some instances.
1.3 ENVIRONMENTAL GOALS
A. Support implementation goals of federal policy and programs for sustainable building, in accordance with Executive Order 13423 – Strengthening Federal Environmental, Energy, and Transportation Management.
B. Comply with Guiding Principles for Federal Leadership in High Performance and Sustainable Buildings.
1. Employ Integrated Design Principles.
a. Integrated Design.
b. Commissioning.
2. Optimize Energy Performance
a. Energy Efficiency.
b. Measurement and Verification.
3. Protect and Conserve Water.
a. Indoor Water (conservation)
SUMMARY 01 10 00-2
4. Enhance Indoor Environmental Quality
a. Ventilation and Thermal Comfort.
b. Moisture Control.
c. Daylighting.
d. Low-Emitting Materials.
e. Protect Indoor Air Quality during Construction.
5. Reduce Environmental Impact of Materials.
a. Recycled Content.
b. Biobased Content.
c. Construction Waste.
d. Ozone Depleting Compounds.
1.4 PROJECT INFORMATION
A. Project Identification: ANC - Airport Traffic Control Tower and TRACON Base Building (A11) including utilities, and fiber optics transmission system (FOTS) loop. Anchorage, Alaska
B. FAA's Lead Project Engineer: Jon Ikeda, P.E., Lead Engineer, Terminal Engineering, AJW2- 11A, Western Service Area, 2200 S. 216th St. Des Moines, WA 98198-6547.
C. CO (FAA Contracting Officer): Katherine Fogle, Regional Acquisitions, 1701 Columbia Avenue, College Park, GA 30337.
1.5 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and consists of the following:
1. Site Clearing and Earthwork
2. Airport Traffic Control Tower (ATCT)
3. TRACON Base Building
4. Roadway and Parking
5. Utility Relocations
6. Utilities and Ancillary Site Components.
7. Landscaping
8. Security Systems
9. Fiber Optic Transmission System
B. Type of Contract:
1. Project will be constructed under a single prime contract.
1.6 WORK PHASES
A. The Work shall be conducted in 20 phases. Construction of the ATCT and TRACON base building will occur in a single phase. Construction of the FOTS system will occur in 19 phases across the AOA. Phases are lined out in the Construction Safety and Phasing Plan (CSPP). The
SUMMARY 01 10 00-3
Contractor will be responsible for determining the sequence of operation to maintain security of the airport and the construction site while complying with the requirement of the CSPP.
B. Before commencing Work, submit a schedule showing the sequence, commencement and completion dates, and move -in dates of FAA's personnel for all of the Work.
C. Construction Work stages at the ATCT/TRACON site shall be defined by the Contractor. The following sequence is provided as General Information Only. Portions of Stages may be simultaneous.
Stage Action
1. Establish and make FAA Field Representatives’ (COR) office trailer fully operational
2. Secure site and install erosion control devices
3. Complete site clearing
4. Existing duct bank relocation
5. Rough grade site
6. Construct permanent and temporary storm drain
7. Construct foundations
8. Construct ATCT and Base Building
9. Construct utilities and fiber optics
10. Construct roadways and parking areas
11. Construct final fence and perimeter security
12. Landscape
13. Remove Temporary Structures and Devices
1.7 WORK UNDER SEPARATE CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying Work under this Contract or other contracts.
Coordinate the Work of this Contract with work performed under separate contracts.
1.8 BUY AMERICAN REQUIREMENTS
A. Contractor shall comply with requirements set forth by 49 U.S.C.ꝣ50101., for purchase of steel and manufactured goods which are produced in the United States.
1.9 CONTRACTOR'S USE OF PREMISES
A. General: Contractor shall have full use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by FAA's right to perform work or to retain other contractors on portions of Project.
B. Use of Site: Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
SUMMARY 01 10 00-4
1.10 FAA’S OCCUPANCY REQUIREMENTS
A. FAA Occupancy of Completed Areas of Construction: FAA reserves the right to occupy and to place and install equipment in completed areas of building, before Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total Work.
1. Subparagraphs below describe procedures and requirements necessary before partial occupancy of portions of Project.
2. COR will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied before FAA occupancy.
3. Before partial FAA occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, FAA will operate mechanical and electrical systems serving occupied portions of building. Contractor shall provide maintenance for one year after date of Substantial Completion.
4. On occupancy, FAA will assume responsibility for custodial service for occupied portions of building. Contractor shall provide maintenance for one year after date of Substantial Completion.
1.11 WORK RESTRICTIONS
A. Normal working hours are 0700 to 1600, Monday through Friday (except U.S. Federal holidays). Contractor requests to work outside normal working hours require COR approval.
However, the COR has full discretion to approve or disapprove, or withdraw approval of requests. If the contractor desires to work outside normal hours (including Saturdays, Sundays, and holidays), he shall submit his written request to the COR at least 48 hours in advance.
Some typical constraints on working outside normal working hours are:
1. The Contractor’s request must be made at least two days in advance (e.g., request received by close of business Wednesday for work on following Saturday). Prior to submitting the request, the Contractor must coordinate as needed (such as utility outages) and have all required people and materials for the work that will be performed.
2. A Contractor with quality or safety problems (as determined by the COR) will be restricted to normal working hours. Contractors may also not work time outside of normal working hours if they are not present on the job site during normal working hours.
3. A Contractor who fails to correct deficiencies within a reasonable time (as determined by the COR) will be restricted to normal working hours or may be allowed to work outside normal working hours only to correct those deficiencies.
4. The Contractor shall schedule his work to cause the least amount of interference to normal activities.
B. Airport Work: This project will require work in the Airport Operations Area (AOA).
Restrictions, safety, and security requirements for work on the AOA are outlined in the approved CSPP which is appended to 01 35 29 “HEALTH, SAFETY AND EMERGENCY RESPONSE PROCEDURES”. Hours of this work must be coordinated by the Contractor with the FAA and Airport Authority. Those hours may be limited to night or other hours not shown above. The Contractor acknowledges responsibility for badges and fees for all workers and vehicles requiring access to the AOA. The construction schedule and cost proposal must account for any lead time and fees required to obtain necessary badges and permits.
SUMMARY 01 10 00-5
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by FAA or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by FAA or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated: Notify FAA COR not less than 10 days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without FAA and utility company written permission.
D. Nonsmoking Building: Smoking is not permitted inside the buildings or within 25 feet of the building entrances, operable windows or openings, outdoor air intakes throughout the duration of the construction.
E. Limits on Operations: The FAA has established moratorium dates for construction activity at critical facilities including the ANC. The intent is to minimize the possibility of any activity that may have an adverse impact on the ability of FAA to perform its operational activities.
Moratorium dates may change without notice. The moratorium dates are generally:
May – Wednesday before Memorial Day through Tuesday after Memorial Day July – Few days before and after July 4 September – Wednesday prior to Labor Day through Tuesday after Labor Day November – Friday before Thanksgiving through Monday after Thanksgiving December/January – Friday before Christmas through Monday after New Years Comply with all ANC Airport Authority local moratoriums
All construction activity during moratorium periods must be approved in advance by the FAA.
Submit items of work to be performed during moratorium dates no later than forty-five (45) days prior to the moratorium dates. Activities that have, in the sole opinion of the FAA, potential to negatively impact FAA operations will not be approved. A written waiver will be provided by FAA to the Contractor outlining the allowable work items. No additional time or cost will be allowed for such denial.
1.12 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 50-division format and CSI/CSC's "MasterFormat" numbering system.
1. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Sections in these Specifications are in numeric sequence; however, the sequence is incomplete because all available Section numbers are not used. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of Sections in the Contract Documents.
2. Division 01: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
SUMMARY 01 10 00-6
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the Specifications. Unless otherwise indicated, linked information is not part of the Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
1.13 PERMITS AND FEES
A. Contractor is responsible for applying for utility services, obtaining required permits, and payment for any associated fees. Compliance is required with the conditions of all permits that have been issued. All fees must be paid by the Contractor. The contractor shall include on his bid base an allowance of $250,000.00 to pay for all the utility services charges to obtain requiring permits, including water appurtenances required by the Authority Having Jurisdiction; this allowance ($250,000) it is not for temporary utility connections need by the contractor to perform his work, the contractor shall include fees for temporary utilities connections on their base bid as a separate item.
B. Contractor is responsible for paying all utility service charges associated with the construction of the project. This includes temporary and permanent utilities, permits, inspection fees, connection fees and equipment to be installed by utility companies. This allocation of financial responsibility applies to all utilities as well as Municipal and State agencies and entities. Contractor is responsible for follow up with the issuing authority after submittal.
C. Listed below are the agencies that govern this project. Unless otherwise noted, Contractor is responsible for applying for utility services, obtaining required permits, and payment for any associated fees. Compliance is required with the conditions of all permits that have been issued.
Additional permits may need to be obtained by the Contractor and all fees must be paid by the Contractor.
1. Anchorage Water and Wastewater Utility (water and sewer utilities) – Contractor to comply with requirements of application and permitting process for main line relocation and utility connections. Contractor will not be required to obtain a construction permit.
Contractor will pay for connection fees and establish customer service which will be transferred to FAA at no cost at completion of construction contract.
2. Alaska Department of Environmental Conservation (water and sewer utilities) - Contractor to comply with requirements of application and permitting process for main line relocation. Contractor will not be required to obtain a construction permit.
3. Alaska Pollutant Discharge Elimination System (APDES) – Contractor will be provided an Erosion and Sediment Control plan for use in…