This document contains a price proposal form and solicitation for the construction of family housing at Villaggio, Vicenza, Italy. The solicitation seeks pricing for the construction of 100 housing units, a water storage building, and site work under a base CLIN, with optional pricing for additional housing units, playground construction, and shading devices. Pricing is requested for 9 CLINs, with award going to a single contractor for the base CLIN and optional CLINs as priced options. The solicitation number is N62470-21-R-0015 and is issued by the Department of the Navy Naval Facilities Engineering Command for P-91330, Phase 2 Family Housing at Vicenza, Italy.
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
60626325 ARMY FAMILY HOUSING P-91330
VICENZA, ITALY
DOCUMENT 00 22 13.00 20
SUPPLEMENTARY INSTRUCTIONS TO OFFERORS
02/14
PART 1 GENERAL
1.1 CONTRACT LINE ITEMS
The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.
Provide the Contract Line Item (CLIN) lump sum price for the following items:
CLIN 0001 - BASE PRICE. Price includes the following:
CLIN 0001AA. Price for the entire work to construct 100 Housing Units (Apartment Bldgs: 23200,23300,23400,23500,23600,26200,27400, Townhouse Block (TH30) 23105/ 23110/ 23115/ 23120/ 23125/ 23130/ 23135/ 23140/ 23145 /23150/ 23155/ 23160 /23165 and BLOCK (TH60) 26605/ 26610/ 26615/ 26620/ 26105/ 26110/ 26115/ 26120/ 26125/ 26130/ 26135/ 26140/ 26305) at Villaggio complete to the 1.5 meter line outside of the building, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs).
CLIN DESCRIPTION TOTAL PRICE FOR
CLIN 0001AA
0001AA Construction of 100 Housing Units
CLIN 0001AB. Price for the entire work to construct Water Storage Building at Villaggio complete to the 1.5 meter line, in accordance with the drawings and specifications and excludes all other contract line items (CLINs).
0001AB
0001AB Construction of the Water Storage Building
CLIN 0001AC. Price for the entire project Site Work at Villaggio, including demolition of existing structures and including site work outside the 1.5 meter line, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs).
0001AC
0001AC Site Work
CLIN 0001 TOTAL [WHICH INCLUDES: 0001AA+0001AB+0001AC] $________________
CLIN 0002 Option Item No. 1 - Price includes the following:
Price for providing all work in connection with providing (furnish and installation of) Rouladen Shading devices for the 100 housing units included in CLIN 0001AA as indicated, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs).
CLIN 0002
0002 Delete Shading devices included in the Base Bid and Provide (Furnish and Install) Rouladen Shades where indicated.
CLIN 0003 Option Item No. 2 - Price includes the following:
Price for the entire work to construct 10 Housing Units (Apartment Bldg:
24200) — at Villaggio complete to the 1.5 meter line outside of the building, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs).
CLIN 0003
0003 Construction of 10 Housing Units
CLIN 0004 Option Item No. 3 - Price includes the following:
installation of) Rouladen Shading devices for the 10 housing units included in CLIN 0003 as indicated, in accordance with the drawings and
CLIN 0004
0004 Delete Shading devices included in the CLIN 0003 and Provide
Shades where indicated
CLIN 0005 Option Item No. 4 - Price includes the following:
Price for the entire work to construct 8 Housing Units (TOWNHOUSE BLOCK (TH40) 24105/ 24110/ 24115/ 24120/ 24125/ 24130/ 24135/ 24140) — at Villaggio complete to the 1.5 meter line outside of the building, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs).
CLIN 0005
0005 Construction of 8 Housing Units
CLIN 0006 Option Item No. 5 - Price includes the following:
installation of) Rouladen Shading devices for the 8 housing units included in CLIN 0005 as indicated, in accordance with the drawings and
CLIN 0006
0006 Delete Shading devices included in the CLIN 0005 and Provide
CLIN 0007 Option Item No. 6 - Price for the entire work to construct 12 Housing Units (TOWNHOUSE BLOCK (TH40) 24305/ 24310/ 24315/ 24320/ 24325/ 24330/ 24335/ 24340/ 24345/ 24350/ 24355/ 24360) — at Villaggio complete to the 1.5 meter line outside of the building, in accordance with the drawings and specifications, and excludes all other contract line items (CLINs).
CLIN 0007
0007 Construction of 12 Housing Units
CLIN 0008 Option Item No. 7 - Price includes the following:
installation of) Rouladen Shading devices for the 12 housing units included in CLIN 0007 as indicated, in accordance with the drawings and
CLIN 0008
0008 Delete Shading devices included in the CLIN 0007 and Provide
CLIN 0009 Option Item No. 8 - Price includes the following:
Price for providing all work (furnish and install) in connection with the Venezia Neighborhood playground (refer to sheet LS401), in accordance with the drawings and specifications, and excludes all other contract line items (CLINs).
This CLIN 0009 does not include: (1) Rough and Finish grading and (2) all site utilities including electrical power to each playground light pole; these items must be priced as part of the base CLIN 0001.
CLIN 0009
0009 Price for providing all work (furnish and install) in connection with the Venezia Neighborhood playground (refer to sheet LS401)
1.2 GENERAL BID NOTES
a. Award will be made on the total sum of Contract Line Item[s] CLIN 0001 through CLIN 0009.
b. The Government intends to award a contract to a single contractor for CLIN 0001, with CLINs 0002 through CLIN 0009 as priced options.
The award of one or more options will NOT extend the contract completion date (regardless of the number of options awarded).
Offerors not submitting pricing for all CLINs will be considered nonresponsive to the solicitation and will not be evaluated.
c. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation, not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).
d. If CLINs 0002 through 0009 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all Items.
File details come from the government source that posted it. Updated .