Attachment 4 - Fram Project Drawings 90 Percent.pdf

PDF 1 MB Posted

Attached to
Petersburg Office Consolidation
Solicitation number
1240BJ24R0018
Issued by

About this file

This document appears to be a set of 90% draft construction drawings for the Fram Work Center project, which is part of the Petersburg Office Consolidation and Work Center Replacement solicitation (Solicitation Number: 1240BJ24R0018) issued by the United States Department of Agriculture Forest Service.

The drawings provide details for the civil site plan, including an additive option for a parking area expansion project. Key details include:

  • Clearing and grubbing, excavation, subbase fill, and surface course for a new 3,600 SF parking pad
  • Storm drainage improvements with the installation of 24" and 18" CPEP culverts and a 48" precast stormwater catch basin
  • Driveway grading improvements, including surface course replacement and asphalt paving
  • Topsoil and seeding for revegetation of disturbed areas

The related federal contract opportunity solicits proposals for the Petersburg Office Consolidation and Work Center Replacement project located in Petersburg, Alaska on the Tongass National Forest. The pre-proposal meeting is scheduled for July 25, 2024, and the cut-off for questions is August 9, 2024. Proposals must fully respond to the Technical Evaluation Factors in Section M of the solicitation.

View the file

Other files

File Type Posted
Attachment 17_AK0514ZZ 1988-06-14 - SPRINKLERS PLANS SECTION DETAIL.pdf PDF
Attachment 19_Addendum to model change for heat pumps.pdf PDF
Attachment 18_Wage Determination AK20240001 7.19.24.pdf PDF
Amendment 3 SF30 - 1240BJ24R0018.pdf PDF
Attachment 16_087100-DR-HDWR-SETS_REVISED_240813.pdf PDF
Attachment 15_RFIs_PDO Consolidation.pdf PDF
Attachment 14_Harris 100 percent drawings addendum.pdf PDF
Amendment 2 - Summary of Changes.pdf PDF
Amendment 2 SF30 - 1240BJ24R0018.pdf PDF
Attachment 13_Fram 100 percent drawings addendum.pdf PDF
1240BJ24R0018 Amendment 1 - Solicitation Packet.pdf PDF
Attachment 12 - Guiding Principles checklist for PDO_info only.pdf PDF
Attachment 9 - Drawings_Harris Bldg Renovation 100 Percent.pdf PDF
1240BJ24R0018 Amendment 1 - SF30.pdf PDF
Attachment 11 - 01 25 00-RIB-Substitution Procedures.pdf PDF
Attachment 10 - Drawings_Fram Parking Expansion 100 Percent.pdf PDF
Attachment 3a - Harris Project Drawings 90 Percent.pdf PDF
1240BJ24R0018 Solicitation Packet.pdf PDF
Attachment 1 - PDO Project Drawings.pdf PDF
Attachment 6 - Past Performance.pdf PDF
Attachment 3b - Harris Drawings Addendum 90 Percent.pdf PDF
Attachment 8 - SF24 Bid Bond.pdf PDF
Attachment 5 - Wage Determination AK20240001.pdf PDF
Attachment 2 - PDO Project Specifications.pdf PDF
Attachment 7 - RFI Template for PDO_Harris_Fram.xlsx XLSX spreadsheet
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Juneau

ALASKA

Anchorage

Petersburg

PROJECT LOCATION

S N ord ic D r

Haugen Dr.

Fram St N th S t

DRAWING INDEX

0 - TITLESHEET

G0.00 TITLESHEET

2 - CIVIL AND LANDSCAPE

C.1 FRAM WORK CENTER - CIVIL SITE PLAN

ALASKAALASKA

PETERSBURG BOROUGHPETERSBURG BOROUGH

R10 ALASKAR10 ALASKA

TONGASS NATIONAL FORESTTONGASS NATIONAL FOREST

PETERSBURG DISTRICT OFFICEPETERSBURG DISTRICT OFFICE

United States Department of AgricultureUnited States Department of Agriculture Forest ServiceForest Service

VICINITY MAPVICINITY MAP

TRAVEL DIRECTIONS:

FOREST LOCATIONFOREST LOCATION

FOREST ENGINEER

RECOMMENDED BY:RECOMMENDED BY:

DISTRICT RANGER

FOREST SUPERVISOR

RO FACILITIES PROGRAM MANAGER

APPROVED:APPROVED:

DIRECTOR OF ENGINEERING DATE

DATE

DATE

DATE

DATE

SHEET 001 OF 002SHEET 001 OF 002

DIRECTOR OF RECREATION DATE

PETERSBURG OFFICE CONSOLIDATIONPETERSBURG OFFICE CONSOLIDATION

& WORK CENTER REPLACEMENT -& WORK CENTER REPLACEMENT -

FRAM WORK CENTERFRAM WORK CENTER

FROM THE USFS PETERSBURG RANGER DISTRICT OFFICE, TRAVEL EAST ON HAUGEN DRIVE, TURN LEFT NORTHBOUND ON N 3RD STREET, TURN RIGHT EASTBOUND ON FRAM STREET, TAKE THE FIRST RIGHT

TURN AT 402 FRAM STREET, PETERSBURG, AK 99833. 56°48'41.7"N 132°57'05.3"W

ADDITIVE OPTION #5 - PARKING EXPANSION

PROVIDE BID FOR EXPANSION OF PARKING AREA PER SCOPE OF WORK DESCRIPTION (NOTE ALL QUANTITIES

PROVIDED ARE APPROXIMATE):

CONSTRUCTION OF A NEW PARKING PAD AREA

CLEARING AND GRUBBING: 3,600 SF

ORGANICS EXCAVATION (1’ MAXIMUM): 100 CY

NFS SUBBASE FILL: 260 CY

SURFACE COURSE (6” THICK): 40 CY

ADDITIVE OPTION:

REPLACE SURFACE COURSE W/:

ASPHALT CONCRETE PAVEMENT (3” THICK): 2200 SF

BASE COURSE: 20 CY

STORM DRAINAGE IMPROVEMENTS:

MINOR GRADING OF DITCHES AND SWALES AT UPSTREAM AND DOWNSTREAM ENDS OF

CULVERTS TO FACILITATE DRAINAGE.

FURNISH & INSTALL CPEP CULVERTS

24” CPEP: 90 LF

18” CPEP: 70 LF

FURNISH & INSTALL ONE (1) 48” PRECAST STORMWATER CATCH BASIN W/ 24 ” DOME INLET

5TH STREET DRIVEWAY GRADING IMPROVEMENTS:

SURFACE COURSE REPLACEMENT AND DRIVEWAY REGRADING BETWEEN ASPHALT PARKING

AREA AND ASPHALT DRIVEWAY TIE-IN ON 5TH STREET.

EXCAVATION OF 22 CY OF EXISTING GRAVEL SURFACING MATERIAL

SURFACE COURSE (6” THICK): 22 CY

ADDITIVE OPTION:

REPLACE SURFACE COURSE W/

ASPHALT CONCRETE PAVEMENT (3” THICK): 1,170 SF

BASE COURSE: 11 CY

SAW CUTTING TACK COATING OF ASPHALT AT EXISTING ASPHALT JOINT TIE-INS

TOPSOIL & SEEDING (OR PLACEMENT OF SALVAGED GRUBBED ORGANIC SOILS) FOR

REVEGETATION OF ALL DISTURBED AREAS.

connors Polygon connors Polygon connors Callout

RED SHADED AREAS: APPROXIMATE EXTENTS OF PROPOSED FILL & SURFACE COURSE

connors Line connors Typewritten Text

PROPOSED STORM DRAIN

connors Line connors Typewritten Text

PROPOSED STORM DRAIN

connors Ellipse connors Callout

SD CATCH BASIN

connors Typewritten Text

CIVIL SITE PLAN

connors Typewritten Text

& CWR

connors Typewritten Text 07.18.2024 connors Typewritten Text

90% DRAFT CONSTRUCTION DOCUMENTS

connors Typewritten Text

& JMS

connors Rectangle connors Callout

ADDITIVE OPTION #5 - PARKING EXPANSION

File details come from the government source that posted it. Updated .