This document is a Guiding Principles checklist for sustainable design and construction for the Petersburg District Office Consolidation and Work Center Replacement project. It outlines 18 core and 12 non-core criteria across 6 categories: Integrated Design, Energy, Water, Indoor Environment, Materials, and Building Resilience. The checklist provides a framework for evaluating the project's sustainability and environmental impact, including requirements for energy efficiency, water conservation, indoor air quality, and use of recycled and biobased materials.

The related federal contract opportunity is for the Petersburg Office Consolidation project, Solicitation Number 1240BJ24R0018. The Department of Agriculture Forest Service is seeking proposals for the design and construction of a new consolidated office and work center facility in Petersburg, Alaska. Key details include a virtual pre-proposal meeting on July 25, 2024 and a question submission deadline of August 9, 2024. The solicitation notes that no substitution requests will be considered prior to award, and proposals must fully respond to the technical evaluation factors in order to be considered.

View the file

Other files

File Type Posted
Attachment 17_AK0514ZZ 1988-06-14 - SPRINKLERS PLANS SECTION DETAIL.pdf PDF
Attachment 19_Addendum to model change for heat pumps.pdf PDF
Attachment 18_Wage Determination AK20240001 7.19.24.pdf PDF
Amendment 3 SF30 - 1240BJ24R0018.pdf PDF
Attachment 16_087100-DR-HDWR-SETS_REVISED_240813.pdf PDF
Attachment 15_RFIs_PDO Consolidation.pdf PDF
Attachment 14_Harris 100 percent drawings addendum.pdf PDF
Amendment 2 - Summary of Changes.pdf PDF
Amendment 2 SF30 - 1240BJ24R0018.pdf PDF
Attachment 13_Fram 100 percent drawings addendum.pdf PDF
1240BJ24R0018 Amendment 1 - Solicitation Packet.pdf PDF
Attachment 9 - Drawings_Harris Bldg Renovation 100 Percent.pdf PDF
1240BJ24R0018 Amendment 1 - SF30.pdf PDF
Attachment 11 - 01 25 00-RIB-Substitution Procedures.pdf PDF
Attachment 10 - Drawings_Fram Parking Expansion 100 Percent.pdf PDF
Attachment 3a - Harris Project Drawings 90 Percent.pdf PDF
1240BJ24R0018 Solicitation Packet.pdf PDF
Attachment 1 - PDO Project Drawings.pdf PDF
Attachment 6 - Past Performance.pdf PDF
Attachment 3b - Harris Drawings Addendum 90 Percent.pdf PDF
Attachment 8 - SF24 Bid Bond.pdf PDF
Attachment 5 - Wage Determination AK20240001.pdf PDF
Attachment 4 - Fram Project Drawings 90 Percent.pdf PDF
Attachment 2 - PDO Project Specifications.pdf PDF
Attachment 7 - RFI Template for PDO_Harris_Fram.xlsx XLSX spreadsheet
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Guiding Principles for Sustainable Federal Buildings

Project Checklist - New Construction & Modernization (NC&M)

USFS Petersburg District Office Consolidation & Work Center Replacement

19-Jun-24

C N C N C N

4 1 4 1 1 1.1 Integrated Design and Management Core 1 X

1 1.2 Sustainable Siting Core 1 X

1 1.3 Stormwater Management Core 1 X

1 1.4 Infrastructure Utilization and Optimization Non-Core 1 X

1 1.5 Commissioning Core 1 X Required |

3 1 3 1

1 2.1 Energy Efficiency Core 1 X

1 2.2 Energy Metering Core 1 X

1 2.3 Renewable Energy Non-Core 1 X

1 2.4 Benchmarking Core 1 X

2 1 2 2 1 3.1 Indoor Water Use Core 1 X

1 3.2 Water Metering Core 1 X

1 3.3 Outdoor Water Use Non-Core 1 X

3.4 Alternative Water Non-Core 1

5 4 5 4 1 4.1 Ventilation and Thermal Comfort Core 1 X

1 4.2 Daylighting and Lighting Controls Non-Core 1 X

1 4.3 Low-Emitting Materials and Products Non-Core 1 X

1 4.4 Radon Mitigation Core 1 X

1 4.5 Moisture and Mold Control Non-Core 1 X

1 4.6 Indoor Air Quality during Construction Non-Core 1 X

1 4.7 Environmental Smoking Control Core 1 X

1 4.8 Integrated Pest Management Core 1 X

1 4.9 Occupant Health and Wellness Core 1 X

4 2 4 2 1 5.1 Materials - Recycled Content Core 1 X

1 5.2 Materials - Biobased Content Core 1 X

1 5.3 Products Non-Core 1 X

1 5.4 Ozone Depleting Substances Core 1 X

1 5.5 Hazardous Waste Core 1 X

1 5.6 Solid Waste Management Non-Core 1 X

0 0 6.0 - Assess and Consider Building Resilience 0 2

6.1 Risk Assessment Non-Core 1

6.2 Building Resilience and Adaptation Non-Core 1

A B C E F G H I J K L

18 9 TOTALS Possible Points: 18 12

Columns & Instructions:

A - Core points in design

B - Non-Core points in design

C - NC&M Criteria number

D - NC&M Criteria title

E - Core versus Non-Core Criteria

F - Core points available in Guiding Principles

G - Non-Core points available in Guiding Principles

H - Pre-Construction checkmark: Has this criterion been met during design and bidding?

I - Close-Out checkmark: Has this criterion been met throughout construction?

J - 1-Year Review checkmark: If 1-year commissioning or review is required for this criterion, has this been completed?

K - Core points at completion of project: When H, I, and J are complete, total the number of points and report in blank boxes at headers.

L - Non-Core points at completion of project: When H, I, and J are complete, total the number of points and report in blank boxes at headers.

Sustainable Federal Building: 18 Core Criteria and 9 Non-Core Criteria; 12 Non-Core Criteria points possible

Criteria Compliance Checklist

D

Pre-

Construction

Close

Out

1-Year

Review

Project Name:

Date:

5.0 - Reduce the Environmental Impact of Materials

4.0 - Enhance the Indoor Environment

3.0 - Protect and Conserve Water

2.0 - Optimize Energy Performance

1.0 - Employ Integrated Design Principles

File details come from the government source that posted it. Updated .