Attachment 1 - PDO Project Drawings.pdf
PDF 38 MB Posted
- Attached to
- Petersburg Office Consolidation
- Solicitation number
- 1240BJ24R0018
- Issued by
-
Department of Agriculture Forest Service
About this file
This document appears to be the Attachment 1 - PDO Project Drawings related to the federal contract opportunity for the Petersburg Office Consolidation project. The federal contract opportunity is a solicitation (Solicitation Number: 1240BJ24R0018) issued by the Department of Agriculture Forest Service for the PDO Consolidation and Work Center Replacement in Petersburg, AK; Tongass NF. Key details include:
The solicitation packet includes a virtual pre-proposal meeting scheduled for Thursday, July 25, 2024 from 1000 - 1200 (Alaska Time, ADT) via Microsoft Teams. Attendees must contact Logan Wild (logan.wild@usda.gov) by 2:00 pm ADT on 07/24/2024 to provide names and email addresses. The cut-off for questions (RFIs) to the solicitation will be close of business (1630 ADT) on Friday, August 9, 2024. No substitution requests will be considered prior to award, and offerors must respond as described in Sections L and M. Proposals that fail to provide a complete response to the Technical Evaluation Factors (Section M) may be rejected and not considered further.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTIFICATION OF POTENTIAL HAZARDS
ASBESTOS, LEAD, AND OTHER HAZARDOUS MATERIALS ARE PRESENT IN THE BUILDING
AND MAY IMPACT THE WORK OF ALL TRADES. REGULATED AIR CONTAMINANTS,
INCLUDING ASBESTOS AND LEAD, ARE ALSO PRESENT IN SETTLED AND CONCEALED
DUST IN AND ON ARCHITECTURAL, STRUCTURAL, MECHANICAL, AND ELECTRICAL
COMPONENTS OR SYSTEMS THROUGHOUT THE BUILDING. ALL TRADES SHALL
COORDINATE WITH OTHER TRADES AND CONDUCT THEIR WORK TO PREVENT WORKER
EXPOSURE OR SITE CONTAMINATION. REFER TO SPECIFICATION DIVISIONS 0, 1, AND 2
FOR SPECIFIC INFORMATION CONCERNING DISTURBING, REMOVING, AND DISPOSING OF
THESE MATERIALS AND THE INSTALLATION OF THE NEW MATERIALS OR COMPONENTS.
THIS NOTIFICATION IS PROVIDED IN ACCORDANCE WITH EPA AND OSHA REQUIREMENTS.
AK
SAL
AFOETATS
T
CETIHCRALANOISSEFOR
PDE
RE
TS
I
GE
R
No. A-140412
JUSTIN M. SCANIO
TH49
06.26.2024
N S
TR
EE
T, S
UI
TE
A N C
HO
RA
G E, A
LA
SK
A
7.
1.
E
CI
/H ye r, In c.
C
HE
C
KE
D
A
UT
HO
R:
PR
O
JE
C T N O
IS
SU
E D A
TE
RE
V
IS
IO
N
FULL SIZE PRINTED ON 22 x 34
G0.01
SH
EE
T I N
DE
X
-0 6.
C W R
JM
S
.2 6.
PE
TE
RS
BU
RG
O
FF
IC
E C O N
SO
LI
DA
TIO
N
W O
RK
C
EN
TE
R
RE
PL
A C
EM
EN
T - D
IS
TR
IC
T
O
FF
IC
E
C O N
ST
RU
C
TIO
N D O C
UM
EN
TS
0 - TITLESHEET
G0.00 TITLESHEET
1 - GENERAL
G0.01 SHEET INDEX
G1.01 GENERAL INFO & TYP MOUNTING HEIGHTS
G1.02 CODE ANALYSIS
G1.03 CODE PLANS
1 - HAZARDOUS MATERIALS
H0.1 HAZARDS ABATEMENT NOTES AND QUANTITIES
H1.0 HAZARDS ABATEMENT - PDO BUILDING FIRST FLOOR
H1.1 HAZARDS ABATEMENT - PDO BUILDING SECOND FLOOR
H1.2 HAZARDS ABATEMENT - ROOF AND PENTHOUSE
2 - CIVIL AND LANDSCAPE
C.0 PETERSBURG DISTRICT OFFICE EXISTING GENERAL NOTES, LEGEND, AND ABBREVIATIONS
C.1 PETERSBURG DISTRICT OFFICE EXISTING CONDITIONS AND DEMOLITION PLAN
C.2 PETERSBURG DISTRICT OFFICE SITE PLAN
C.3 PETERSBURG DISTRICT OFFICE GRADING PLAN
C.4 PETERSBURG DISTRICT OFFICE GRADING LAYOUT INFORMATION
C.5 PETERSBURG DISTRICT OFFICE CIVIL TYPICAL SECTIONS
C.6 PETERSBURG DISTRICT OFFICE CIVIL DETAILS (1 OF 3)
C.7 PETERSBURG DISTRICT OFFICE CIVIL DETAILS (2 OF 3)
C.8 PETERSBURG DISTRICT OFFICE CIVIL DETAILS (3 OF 3)
L1.01 SITE AND SOILS PLAN AND LANDSCAPE DEMO PLAN
L1.02 PLANTING PLAN
L5.01 DETAILS AND PLANTING SCHEDULES
L5.02 DETAILS
L5.03 DETAILS
3- STRUCTURAL
S0.01 STRUCTURAL GENERAL NOTES
S0.02 SPECIAL INSPECTIONS AND TESTING
S1.12 DEMO FLOOR FRAMING PLAN LEVEL 2
S2.13 FOUNDATION PLAN
S2.14 FLOOR FRAMING PLAN LEVEL 2
S2.15 ROOF FRAMING PLANS
S5.01 BUILDING SECTIONS
S6.01 INTERIOR CONCRETE DETAILS
S6.11 EXTERIOR CONCRETE DETAILS
S6.21 INTERIOR FRAMING DETAILS
S6.31 EXTERIOR FRAMING DETAILS
4 - ARCHITECTURAL
A1.01 ASSEMBLIES
A2.01 DEMO FLOOR PLAN LEVEL 1
A2.02 DEMO FLOOR PLAN LEVEL 2
A2.03 DEMO ROOF PLANS
A2.04 DEMO REFLECTED CEILING PLAN LEVEL 1
A2.05 DEMO REFLECTED CEILING PLAN LEVEL 2
A2.11 FLOOR PLAN LEVEL 1
A2.12 FLOOR PLAN LEVEL 2
A2.13 ROOF PLANS
A3.11 ENLARGED PLANS
A3.12 ENLARGED PLANS - TOILET ROOMS
A3.21 STAIR PLANS, SECTIONS & DETAILS
A3.22 STAIR PLANS, SECTIONS & RAILING DETAILS
A4.01 EXTERIOR ELEVATIONS EAST & WEST
A4.02 EXTERIOR ELEVATIONS NORTH & SOUTH
A5.01 BUILDING SECTIONS E-W
A5.02 BUILDING SECTIONS N-S
A6.01 WALL SECTIONS
A8.01 INTERIOR ELEVATIONS LEVEL 1
A8.02 INTERIOR ELEVATIONS LEVEL 1 CONT.
A8.03 INTERIOR ELEVATIONS LEVEL 2
A8.04 INTERIOR ELEVATIONS LEVEL 2 CONT.
A9.01 REFLECTED CEILING PLAN LEVEL 1
A9.02 REFLECTED CEILING PLAN LEVEL 2
A10.01 EXTERIOR & VESTIBULE DETAILS - SECTION
A10.02 EXTERIOR DETAILS - SECTION
A10.03 EXTERIOR DETAILS - SECTION
A10.04 EXTERIOR DETAILS - SECTION
A10.05 EXTERIOR DETAILS - SECTION
A10.11 EXTERIOR DETAILS - PLAN
A10.12 EXTERIOR DETAILS - PLAN
A10.21 EXTERIOR DETAILS - OPENINGS
A10.22 EXTERIOR DETAILS - OPENINGS
A11.01 INTERIOR DETAILS
A11.02 INTERIOR DETAILS
A11.03 INTERIOR DETAILS
A11.04 INTERIOR DETAILS
A12.01 DOOR SCHEDULE
A12.02 WINDOW SCHEDULE
A12.03 FINISH PLANS, INTERIOR ROOM AND MATERIAL SCHEDULES
A12.04 SIGNAGE AND EQUIPMENT SCHEDULE
A12.11 FURNITURE & SIGNAGE PLANS
5 - MECHANICAL
M0.01 MECHANICAL LEGEND
M0.02 MECHANICAL SCHEDULES
M0.03 MECHANICAL SCHEDULES
M0.04 MECHANICAL SCHEDULES
M1.00 UNDERFLOOR PLAN - MECHANICAL - DEMOLITION
M1.01 LEVEL 1 FLOOR PLAN - PLUMBING - DEMOLITION
M1.02 LEVEL 2 FLOOR PLAN - PLUMBING - DEMOLITION
M1.03 LEVEL 1 FLOOR PLAN - PIPING - DEMOLITION
M1.04 LEVEL 2 FLOOR PLAN - PIPING - DEMOLITION
M1.05 LEVEL 1 FLOOR PLAN - VENTILATION - DEMOLITION
M1.06 LEVEL 2 FLOOR PLAN - VENTILATION - DEMOLITION
M1.07 ROOF PLAN - MECHANICAL - DEMOLITION
M1.08 ENLARGED PENTHOUSE PLAN - DEMOLITION
M1.09 ENLARGED BOILER ROOM PLAN - DEMOLITION
M2.00 UNDERFLOOR PLAN - MECHANICAL
M2.01 LEVEL 1 FLOOR PLAN - PLUMBING
M2.02 LEVEL 2 FLOOR PLAN - PLUMBING
M2.03 LEVEL 1 FLOOR PLAN - PIPING
M2.04 LEVEL 2 FLOOR PLA N- PIPING
M2.05 LEVEL 1 FLOOR PLAN - VENTILATION
M2.06 LEVEL 2 FLOOR PLAN - VENTILATION
M2.07 ROOF PLAN - MECHANICAL
M2.08 ENLARGED PENTHOUSE PLAN
M2.09 ENLARGED BOILER ROOM PLAN
M2.10 ENLARGED PLUMBING PLANS
M3.01 DIAGRAMS - PLUMBING
M3.02 DIAGRAMS - PLUMBING
M3.03 DETAILS - PLUMBING
M3.04 DETAILS - PLUMBING
M4.01 DIAGRAMS - HEATING AND COOLING
M4.02 DIAGRAMS - HEATING AND COOLING
M4.03 DIAGRAMS - HEATING AND COOLING
M4.04 DETAILS - HEATING AND COOLING
M4.05 DETAILS - HEATING AND COOLING
M5.01 DIAGRAMS - VENTILATION
M5.02 DETAILS - VENTILATION
M5.03 DETAILS - VENTILATION
6 - ELECTRICAL
E0.01 ELECTRICAL LEGEND
E0.02 LIGHTING FIXTURES AND LIGHTING CONTROL SCHEDULES
E0.03 PANEL SCHEDULES - LEVEL 1 480V
E0.04 PANEL SCHEDULES - LEVEL 1 208V
E0.05 PANEL SCHEDULES - LEVEL 1 208V
E0.06 PANEL SCHEDULES - LEVEL 2 & PENTHOUSE
E1.00 SITE PLAN - ELECTRICAL
E1.10 OVERALL PLAN - ELECTRICAL
E1.11 OVERALL PLAN - PUBLIC ADDRESS
E1.20 LEVEL 1 FLOOR PLAN - LIGHTING - DEMO
E1.21 LEVEL 2 FLOOR PLAN - LIGHTING - DEMO
E1.30 LEVEL 1 FLOOR PLAN - POWER - DEMO
E1.31 LEVEL 2 FLOOR PLAN - POWER - DEMO
E1.40 LEVEL 1 FLOOR PLAN - SPECIAL SYSTEMS - DEMO
E1.41 LEVEL 2 FLOOR PLAN - SPECIAL SYSTEMS - DEMO
E2.00 LEVEL 1 FLOOR PLAN - LIGHTING
E2.01 LEVEL 2 FLOOR PLAN - LIGHTING
E3.00 LEVEL 1 FLOOR PLAN - POWER
E3.01 LEVEL 2 FLOOR PLAN - POWER
E4.00 LEVEL 1 FLOOR PLAN - SPECIAL SYSTEMS
E4.01 LEVEL 2 FLOOR PLAN - SPECIAL SYSTEMS
E5.01 ENLARGED PLAN - PENTHOUSE
E5.02 ENLARGED PLAN - ELECTRICAL
E6.00 DETAILS - ELECTRICAL
E7.01 DETAILS AND DIAGRAMS - SECURITY
E7.02 DIAGRAM - TELECOM ONE-LINE
E7.03 DIAGRAMS - PAGING SYSTEM
E7.04 DIAGRAMS - AV SYSTEM
E8.00 DIAGRAM - POWER ONE-LINE
SHEET INDEX
ABBREVIATIONS
ABV ABOVE
AFF ABOVE FINISH FLOOR
ALT ALTERNATE
ANO ANODIZED
ARCH ARCHITECTURAL
BD BOARD
BLDG BUILDING
BLK BLOCK
BLW BELOW
BO BOTTOM OF
BOF BOTTOM OF FINISH
BCS BABY CHANGING STATION
CIP CAST IN PLACE
CF CUBIC FOOT
CFOI CONTRACTOR FURNISHED OWNER INSTALLED
CL CENTERLINE
CONC CONCRETE
CONT CONTINUOUS
CTR CENTER
DIA DIAMETER
DIM DIMENSION
DWG DRAWING
EA EACH
EL ELEVATION
ELEC ELECTRICAL
EQ EQUAL
EQUIP EQUIPMENT
FAF FLUID APPLIED FLOORING
FD FRAME DIMENSION
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FF FINISHED FLOOR
FO FACE OF
FOC FACE OF CONCRETE
FOF FACE OF FINISH
FOS FACE OF STUD
FRT FIRE RETARDANT TREATED
FT FOOT, FEET
FURR FURRING
GA GUAGE
GALV GALVANIZED
GB GRAB BAR
INCL INCLUDE, INCLUDED
INSUL INSULATION
INT INTERIOR
LSG LAMINATED SAFETY GLAZING
LH LEFT HAND
MAX MAXIMUM
MFR MANUFACTURER
MKBD MARKERBOARD
MIN MINIMUM
MIRR MIRROR
MTL METAL
NA NOT APPLICABLE
NIC NOT IN CONTRACT
OD OUTSIDE DIAMETER
OFCI OWNER FURNISHED CONTRACTOR INSTALLED
OFOI OWNER FURNISHED OWNER INSTALLED
OH OVERHEAD
PAR PARTITION
PERF PERFORATED
PLAM PRESSURE TREATED LAMINATE
PLY PLYWOOD
PTD PAPER TOWEL DISPENSER
PT PAINT
RCP REFLECTED CEILING PLAN
REBAR/RB REINFORCING BARS
REF REFERENCE
REQD REQUIRED
RO ROUGH OPENING
SD SOAP DISPENSER
SECT SECTION
SCHED SCHEDULE
SIM SIMILAR
SND SANITARY NAPKIN DISPOSAL
SPEC SPECIFICATION
SS STAINLESS STEEL
GWB GYPSUM WALL BOARD
GYP GYPSUM WALL BOARD
HD HAND DRYER
HDWR HARDWARE
HR HOUR
HT HEIGHT
ID INSIDE DIAMETER
STD STANDARD
STL STEEL
STRUCT STRUCTURAL
TBD TO BE DETERMINED
TDWR TOWEL DISPENSER/WASTE RECEPTICAL
THERM THERMOSTAT
TOB TOP OF BEAM
TOC TOP OF CONCRETE
TOS TOP OF STEEL
TTD TOILET TISSUE DISPENSER
TSCD TOILET SEAT COVER DISPENSER
TYP TYPICAL
UL UNDERWRITERS LABORATORY CERTIFIED
UNFIN UNFINISHED
UNO UNLESS NOTED OTHERWISE
VIF VERIFY IN FIELD
WD WOOD
SYMBOLS
GRID LINE INDICATION
ROOM IDENTIFICATION
ROOM NAME
ROOM NUMBER
AREA / OCCUPANCY
A
INTERIOR / EXTERIOR ELEVATION
DASH INDICATES NO ELEVATION
BUILDING SECTION
SECTION NUMBER
SECTION SHEET
DETAIL
DETAIL NUMBER
DETAIL SHEET
DOOR NUMBER
REFER TO DOOR SCHEDULE
JJ
WINDOW TYPE
REFER TO WINDOW SCHEDULE
A1
WALL TYPE INDICATOR
REFER TO WALL LEGEND
WORK POINT
(CONTROL or DATUM POINT)
WALL SECTION
SECTION NUMBER
SECTION SHEET
FLOOR, CEILING, ROOF TYPE INDICATOR
REFER TO FLOOR, CEILING, ROOF LEGENDF1
KEYNOTE
REFER TO NOTES LISTED ON SHEET1
XXXX -
XX
XX
XX
XX
XX
XX
OFFICE
4 OCC
CEILING TYPE
REFER TO ASSEMBLIES; ELEVATION NOTED ABOVE SLAB10'-0"
C3
MATERIALS
METAL (SECTION)
WOOD, CONTINUOUS (SECTION)
WOOD, BLOCKING (SECTION)
FILL (SECTION)
PLYWOOD (SECTION)
EARTH (SECTION)
FINISH CARPENTRY (SECTION)
GYPSUM BOARD (SECTION)
INSULATION, BATT (PLAN & SECTION)
INSULATION, RIGID (PLAN & SECTION)
CONCRETE (SECTION)
STONE (PLAN)
MINERAL WOOD INSULATION (PLAN & SECTION)
1.
2.
A.
B.
C.
D.
E.
3.
4.
5.
6.
7.
8.
9.
CONSTRUCTION TO BE IN COMPLIANCE WITH ALL FEDERAL,
STATE, AND LOCAL BUILDING CODES AND REGULATIONS.
EXISTING CONDITIONS:
CONTRACTOR TO VERIFY ALL EXISTING CONDITIONS
PRIOR TO COMMENCEMENT OF WORK AND NOTIFY
CONTRACTING OFFICER OF ANY DISCREPANCIES WITH
CONDITIONS AS SHOWN IN DOCUMENTS.
ALL DIMENSIONS OF EXISTING CONSTRUCTION SHOWN
ON THE DRAWINGS ARE INTENDED AS GUIDELINES ONLY
AND MUST BE VERIFIED.
THE EXISTING CONDITIONS SHOWN ON THE DRAWINGS
ARE BASED ON EITHER LIMITED AS-BUILTS AND/OR
LIMITED ORIGINAL DRAWINGS. IF THE EXISTING
CONDITIONS DO NOT CLOSELY MATCH THE CONDITIONS
SHOWN ON THE DRAWINGS, OR IF THE EXISTING
MATERIALS ARE OF QUESTIONABLE OR SUBSTANDARD
QUALITY, NOTIFY THE CONTRACTING OFFICER PRIOR TO
COMMENCING WORK.
PROTECT ANY EXISTING CONSTRUCTION FROM DAMAGE
AT ALL TIMES DURING WORK.
SALVAGE ALL ITEMS THAT ARE TO BE REMOVED BUT
NOT REPURPOSED AND THAT ARE IN GOOD CONDITION
ARE TO BE PROTECTED AND DONATED.
ALL DIMENSIONS ARE TO GRIDLINE OR FACE OF STUD UNLESS
OTHERWISE NOTED. "CLR" REFERS TO FACE OF FINISH EACH
SIDE.
WORK AREAS TO BE LEFT CLEAN AND FREE OF ANY DEBRIS AT
THE END OF EACH SHIFT.
PROVIDE CONCEALED FRAMING WHERE HEIGHT EXCEEDS
LIMITING HEIGHT OF STUD SIZE.
PROVIDE BACKING AS REQUIRED FOR CASEWORK AND OTHER
ITEMS THAT ARE WALL SUPPORTED.
SEE MECHANICAL AND PLUMBING DRAWINGS FOR LOCATION
AND TYPE OF PLUMBING FIXTURES.
IN CASE OF A CONFLICT IN THE DOCUMENTS, THE
CONTRACTOR SHALL ASSUME THE GREATER VALUE OF SUCH
CIRCUMSTANCES.
DOORS ROUGH OPENING SHALL BE LOCATED 6" FROM
ADJACENT WALL FINISH UNLESS NOTED OTHERWISE.
GENERAL NOTES & EXISTING
CONDITIONS
1.
2.
3.
PROVIDE SOLID BACKING FOR ALL ACCESSORIES.
ELEVATIONS SHOWN HEREIN REPRESENT TYPICAL
REQUIREMENTS.
INSTALLATION OF ALL SANITARY FACILITIES ACCESSIBLE
TO THE DISABLED SHALL COMPLY WITH THIS DETAIL &
APPLICABLE REGULATORY REQUIREMENTS.
MOUNTING HEIGHT NOTES
ABA MOUNTING HEIGHTS TOILET ROOM ACCESSORIES
ACCESSIBLE
LAVATORY
COUNTER WITH UNDERMOUNT SINK
SINK
HOOK
GB48
ACCESSIBLE TOILET STALL
GB36
WC
3'-6"
6"
GB18
3'-4"
G R
IP
S
U R
FA
C
E
M
AX
-3
6" T
O
" M
IN
M
AX
AB
A
4' -0
1'-6"
DISPENSER/
WASTE RECEPTACLE
TDWR
TSCD
" M
IN
SND
TTD 2'
-1
0"
1'-6" 1'-6"
PROVIDE SEMI RIGID SOUND
INSULATION AROUND TSCD,
TYP
TO
B
O
TT
O M
M
IR
R O
R M
AX
0"
2' -1
1/
2"
3' -9
/2
1.
5"
M
IN
12" MAX
THERM
THERM-
OSTAT
LIGHT SWITCH
FEC
ELEC/TEL/DATA
OUTLET @ DOOR
MP
E/DT E/DT
ELEC/TEL/DATA
OUTLET @
WALL
LS
FIRE
EXTINGUISHER
CABINET
3'
7" 5'
0"
4'
6" T
O F
E M
O U
N T
4'
0" M
AX
T
O H
D W
R
8"
3'
7"
1'
6"
3'
7"
1'
6"
TO
P
U
SH
B U
TT
O
N
SO
AP
D
IS
P.
" M
AX
2' -3
BABY CHANGING
STATION
MIRR
SD
MIRR
BCS
NOTIFICATION OF POTENTIAL HAZARDS
ASBESTOS, LEAD, AND OTHER HAZARDOUS MATERIALS ARE PRESENT IN THE BUILDING
AND MAY IMPACT THE WORK OF ALL TRADES. REGULATED AIR CONTAMINANTS,
INCLUDING ASBESTOS AND LEAD, ARE ALSO PRESENT IN SETTLED AND CONCEALED
DUST IN AND ON ARCHITECTURAL, STRUCTURAL, MECHANICAL, AND ELECTRICAL
COMPONENTS OR SYSTEMS THROUGHOUT THE BUILDING. ALL TRADES SHALL
COORDINATE WITH OTHER TRADES AND CONDUCT THEIR WORK TO PREVENT WORKER
EXPOSURE OR SITE CONTAMINATION. REFER TO SPECIFICATION DIVISIONS 0, 1, AND 2
FOR SPECIFIC INFORMATION CONCERNING DISTURBING, REMOVING, AND DISPOSING OF
THESE MATERIALS AND THE INSTALLATION OF THE NEW MATERIALS OR COMPONENTS.
THIS NOTIFICATION IS PROVIDED IN ACCORDANCE WITH EPA AND OSHA REQUIREMENTS.
AK
SAL
AFOETATS
T
CETIHCRALANOISSEFOR
PDE
RE
TS
I
GE
R
No. A-140412
JUSTIN M. SCANIO
TH49
06.26.2024
N S
TR
EE
T, S
UI
TE
A N C
HO
RA
G E, A
LA
SK
A
7.
1.
E
CI
/H ye r, In c.
C
HE
C
KE
D
A
UT
HO
R:
PR
O
JE
C T N O
IS
SU
E D A
TE
RE
V
IS
IO
N
FULL SIZE PRINTED ON 22 x 34
G1.01
G
EN
ER
A L
IN
FO
TY
P M O
UN
TIN
G H
EI
G
HT
S
-0 6.
C W R
JM
S
.2 6.
PE
TE
RS
BU
RG
O
FF
IC
E C O N
SO
LI
DA
TIO
N
W O
RK
C
EN
TE
R
RE
PL
A C
EM
EN
T - D
IS
TR
IC
T
O
FF
IC
E
C O N
ST
RU
C
TIO
N D O C
UM
EN
TS
NOTIFICATION OF POTENTIAL HAZARDS
ASBESTOS, LEAD, AND OTHER HAZARDOUS MATERIALS ARE PRESENT IN THE BUILDING
AND MAY IMPACT THE WORK OF ALL TRADES. REGULATED AIR CONTAMINANTS,
INCLUDING ASBESTOS AND LEAD, ARE ALSO PRESENT IN SETTLED AND CONCEALED
DUST IN AND ON ARCHITECTURAL, STRUCTURAL, MECHANICAL, AND ELECTRICAL
COMPONENTS OR SYSTEMS THROUGHOUT THE BUILDING. ALL TRADES SHALL
COORDINATE WITH OTHER TRADES AND CONDUCT THEIR WORK TO PREVENT WORKER
EXPOSURE OR SITE CONTAMINATION. REFER TO SPECIFICATION DIVISIONS 0, 1, AND 2
FOR SPECIFIC INFORMATION CONCERNING DISTURBING, REMOVING, AND DISPOSING OF
THESE MATERIALS AND THE INSTALLATION OF THE NEW MATERIALS OR COMPONENTS.
THIS NOTIFICATION IS PROVIDED IN ACCORDANCE WITH EPA AND OSHA REQUIREMENTS.
AK
SAL
AFOETATS
T
CETIHCRALANOISSEFOR
PDE
RE
TS
I
GE
R
No. A-140412
JUSTIN M. SCANIO
TH49
06.26.2024
N S
TR
EE
T, S
UI
TE
A N C
HO
RA
G E, A
LA
SK
A
7.
1.
E
CI
/H ye r, In c.
C
HE
C
KE
D
A
UT
HO
R:
PR
O
JE
C T N O
IS
SU
E D A
TE
RE
V
IS
IO
N
FULL SIZE PRINTED ON 22 x 34
G1.02
C O
DE
A N A
LY
SI
S
-0 6.
C W R
JM
S
.2 6.
PE
TE
RS
BU
RG
O
FF
IC
E C O N
SO
LI
DA
TIO
N
W O
RK
C
EN
TE
R
RE
PL
A C
EM
EN
T - D
IS
TR
IC
T
O
FF
IC
E
C O N
ST
RU
C
TIO
N D O C
UM
EN
TS
AUTHORITY HAVING JURISDICTION: US FOREST SERVICE
PROJECT DESCRIPTION: THIS PROJECT IS REPLACEMENT OF A
MECHANICAL SYSTEM, MODIFICATION OF EXTERIOR ENVELOPE, AND
INTERIOR REFINISHING AND RENOVATION IN A TWO-STORY BUILDING IN
DOWNTOWN PETERSBURG. THE BUILDING HAS A GROUP B OCCUPANCY,
IS TYPE V-B, AND FULLY SPRINKLERED.
OWNER: U.S. FOREST SERVICE
PROPERTY LEGAL DESCRIPTION: BLOCK 37 PETERSBURG TOWNSITE,
USSN 1252
PROPERTY ADDRESS: 12 N NORDIC DR, PETERSBURG, AK 99833
APPLICABLE CODES
PETERSBURG CITY CODE TITLE 19 - ZONING
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL FIRE CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL MECHANICAL CODE
2018 UNIFORM PLUMBING CODE
1968 ARCHITECTURAL BARRIERS ACT (GOVERNING), 2017 ICC/ANSI
A117.1, IBC CHAPTER 11 FOR ACCESSIBILITY, AND 2010 ADA
STANDARDS FOR ACCESSIBLE DESIGN
2021 NFPA
36 CFR PART 68 (SOI STANDARDS FOR THE TREATMENT OF
HISTORIC PROPERTIES)
CODE ANALYSIS
2021 INTERNATIONAL EXISTING BUILDING CODE
202 GENERAL DEFINITIONS:
ALTERATION. ANY CONSTRUCTION OR RENOVATION TO AN
EXISTING STRUCTURE OTHER THAN A REPAIR OR ADDITION. THIS
PROJECT INCLUDES ALTERATIONS TO THE EXISTING BUILDING.
PROJECT DOES NOT INCREASE BUILDING AREA CONSTITUTING AN
ADDITION.
202 GENERAL DEFINITIONS:
ALASKA SHPO HAS DETERMINED THE BUILDING IS ELIGIBLE FOR
LISTING ON THE NATIONAL REGISTER UNDER CRITERIA A AND C.
CRITERIA A:
SITES, BUILDINGS, STRUCTURES THAT ARE ASSOCIATED WITH
EVENTS THAT HAVE MADE A SIGNIFICANT CONTRIBUTION TO THE
BROAD PATTERNS OF OUR HISTORY.
CRITERIA C:
SITES, BUILDINGS, STRUCTURES THAT EMBODY THE DISTINCTIVE
CHARACTERISTICS OF A TYPE, PERIOD, OR METHOD OF
CONSTRUCTION, OR THAT REPRESENT THE WORK OF A MASTER,
OR THAT POSSESS HIGH ARTISTIC VALUES, OR THAT REPRESENT
A SIGNIFICANT AND DISTINGUISHABLE ENTITY WHOSE
COMPONENTS MAY LACK INDIVIDUAL DISTINCTION.
202 GENERAL DEFINITIONS:
REPAIR. THE RECONSTRUCTION, REPLACEMENT, OR RENEWAL OF
ANY PART OF AN EXISTING BUILDING FOR THE PURPOSE OF ITS
MAINTENANCE OR TO CORRECT DAMAGE.
THIS PROJECT CONSTITUTES REPAIRS TO EXTERIOR ELEMENTS
ON BUILDING. BROKEN OR MISSING ELEMENTS ARE BEING
REPLACED OR RECONSTRUCTED IN KIND AND EXISTING ELEMENTS
IN GOOD CONDITION ARE BEING RENEWED.
301.2 REPAIRS:
REPAIRS SHALL COMPLY WITH THE REQUIREMENTS OF CHAPTER
4. SEE DISCUSSION BELOW
301.3 ALTERATION, ADDITION, OR CHANGE OF OCCUPANCY:
PROJECT WILL USE PRESCRIPTIVE COMPLIANCE METHOD PER
301.3.1. SEE DISCUSSION BELOW.
302.3 EXISTING MATERIALS:
BUILDING CONTAINS HAZARDOUS MATERIALS. WORK WILL ONLY
DISTURB AND ABATE THOSE MATERIALS AS NECESSARY TO
COMPLETE THE WORK.
306.2 DESIGN:
BUILDING COMPLIES WITH ICC A117.1. SEE DISCUSSION BELOW.
306.3 MAINTENANCE AND REPAIR:
PROJECT WILL MAINTAIN EXISTING ACCESSIBILITY TO BUILDINGS.
SEE DISCUSSION BELOW.
TITLE 19
19.04.585 PARKING DISTRICT:
SITE IS WITHIN PARKING DISTRICT 2 - EAST AND REQUIRES 70% OF
47 PARKING SPACES BASED ON BUILDING SIZE, WHICH IS 33. SITE
PROVIDES MORE THAN MINIMUM NUMBER REQUIRED.
19.32.060 [C-1, COMMERCIAL 1 DISTRICT] LOT, YARD, AND HEIGHT:
LOT ABUTS C-1 AND C-2 ZONING DISTRICTS SO NEEDS TO ONLY
MEET REQUIRED OFF-STREET PARKING REQUIREMENTS. BUILDING
IS 27'-6" HIGH, MEASURED TO TOP OF COPING OF MECHANICAL
PENTHOUSE. BUILDING IS TWO STORIES WITH A MECHANICAL
PENTHOUSE.
19.32.080 OFF-STREET PARKING AND LOADING - OTHER REQUIREMENTS:
A. OFF-STREET PARKING AND LOADING REQUIREMENTS SHALL BE
SPECIFIED IN CHAPTER 19.64 OF THIS TITLE. B. OTHER
DEVELOPMENT REQUIREMENTS SHALL BE STATED IN CHAPTER
19.60 OF THIS TITLE (YARDS AND LOTS): SEE DISCUSSION BELOW.
19.48.020 [P-1 DISTRICT, PUBLIC USE DISTRICT] USES PERMITTED:
BUILDING HAS SOLE OCCUPANCY BY THE US FOREST SERVICE, A
DIVISION OF THE FEDERAL GOVERNMENT. SEE DISCUSSION
BELOW.
19.64.010 PARKING AREAS - REQUIREMENTS ACCORDING TO USE:
BUILDING HAS APPRAISED VALUE OF $3.734 MILLION. PROJECT
COST EXCEEDS 50% OF VALUE. BUILDING IS 11,605 SF AND
REQUIRES 47 OFF-STREET PARKING SPACES..
19.64.040 DESIGN STANDARDS:
A. EACH PARKING SPACE SHALL CONTAIN NOT LESS THAN 8 FT
WIDE BY 20 FT LONG IN AREA EXCLUSIVE OF ACCESS AND
CIRCULATION AISLES. […] C. ANY LIGHTING OF PARKING LOTS
SHALL BE ARRANGED TO REFLECT AWAY FROM PUBLIC RIGHTS-
OF-WAY AND FROM ANY ADJOINING RESIDENTIAL AREA. SEE SITE
PLAN
19.64.070 PARKING AREAS - ACCESS:
[…] NO DRIVEWAY, PARKING LOT OR CURB CUTS IN ANY DISTRICT
SHALL EXCEED […] FORTY FEET IN WIDTH FOR COMMERCIAL […]
STRUCTURES, AND DETAILED PLANS FOR ALL CURB CUTS SHALL
BE SUBMITTED TO THE CITY ENGINEERING DEPARTMENT OR
DESIGNATED REPRESENTATIVE FOR APPROVAL BEFORE A PERMIT
SHALL BE ISSUED THEREFORE. SEE SITE PLAN.
19.64.080 LOADING AREAS - WHERE REQUIRED
LOADING AREA PROVIDED.
19.64.100 LOADING AREAS - ACCESS
LOADING AREA ACCESS FROM STREET VIA PARKING AREA.
306.7 ALTERATIONS
ALL NEW WORK COMPLIES WITH CHAPTER 11 OF THE IBC, ICC
A117.1, AND THE 1968 ABA, WITH THE EXCEPTION OF THE
EXTERIOR DOORS AT ENTRANCES TO THE SECOND FLOOR WHICH
DO NOT PROVIDE THE REQUIRED MANEUVERING CLEARANCES
FOR OPERATION. DOOR WIDTHS ARE INCREASED TO PROVIDE THE
MINIMUM CLEAR WIDTH OF DOORWAYS AND MECHANICAL
OPENERS ARE INSTALLED FOR THE EXTERIOR DOORS. INTERIOR
VESTIBULE DOORS MEET REQUIREMENTS FOR APPLICABLE
STANDARDS. SEE DISCUSSION BELOW FOR PLATFORM LIFTS.
306.7.8 PLATFORM LIFTS
BUILDING HAS PLATFORM LIFT. NO CHANGES PROPOSED TO LIFT.
309.2 [EXTERIOR WALL COVERINGS] ADDITIONS AND REPLACEMENTS:
PROJECT INVOLVES MODIFICATION OF EXTERIOR WALL ENVELOPE
FOR ENTIRETY OF BUILDING. NEW MATERIALS WILL COMPLY WITH
CHAPTERS 14 AND 26 OF THE IBC.
402.1 GLAZING IN HAZARDOUS LOCATIONS:
COMPLIES. GLAZING REPLACED IN ACCORDANCE WITH IBC.
501.2 FIRE-RESISTIVE RATINGS:
BUILDING IS FULLY SPRINKLERED PER THE IBC. ALL OTHER
ELEMENTS AND MATERIALS COMPLY WITH THE IBC. SEE
DISCUSSION BELOW.
503.1 [ALTERATION] GENERAL:
ALL ALTERATIONS COMPLY WITH THE IBC. EXISTING STAIR DOES
NOT COMPLY WITH SECTION 1011 OF THE IBC AND EXISTING
SPACE AND CONSTRUCTION DOES NOT ALLOW FOR
MODIFICATION. BUILDING IS HISTORIC AND STAIRWAY
CONTRIBUTES TO HISTORIC INTEGRITY. HISTORIC HANDRAIL
REMAINS UNALTERED PER EXCEPTION #2 AND SECTION 507. SEE
DISCUSSION BELOW.507.1 HISTORIC BUILDINGS:
THE PROVISIONS OF THIS CODE THAT REQUIRE IMPROVEMENTS
RELATIVE TO A BUILDING'S EXISTING CONDITION [...] SHALL NOT BE
MANDATORY FOR HISTORIC BUILDINGS UNLESS SPECIFICALLY
REQUIRED BY THIS SECTION.
507.2 LIFE SAFETY HAZARDS:
INTERIOR STAIR IS HISTORIC AND DOES NOT SERVE AS A
COMPONENT OF EGRESS AND DOES NOT APPEAR TO CONSTITUTE
A DISTINCT LIFE SAFETY HAZARD.
2021 INTERNATIONAL BUILDING CODE
202 DEFINITIONS:
AREA, BUILDING. THE AREA INCLUDED WITHIN SURROUNDING
EXTERIOR WALLS EXCLUSIVE OF VENT SHAFTS AND COURTS.
AREAS OF THE BUILDING NOT PROVIDED WITH SURROUNDING
WALLS SHALL BE INCLUDED IN THE BUILDING AREA IF SUCH AREAS
ARE INCLUDED WITHIN THE HORIZONTAL PROJECTION OF THE
ROOF OR FLOOR ABOVE.
SEE BUILDING AREA SUMMARY
302.1 [OCCUPANCY CLASSIFICATION AND USE] GENERAL:
BUILDING CONTAINS GROUP B WITH S-2 ACCESSORY SPACES AND
OCCUPANCIES. SEE BUILDING AREA TABLE FOR OCCUPANCY
CLASSIFICATIONS.
303.1.1 SMALL BUILDINGS AND TENANT SPACES:
A […] TENANT SPACE USED FOR ASSEMBLY PURPOSES WITH AN
OCCUPANT LOAD OF LESS THAN 50 PERSONS SHALL BE
CLASSIFIED AS A GROUP B OCCUPANCY.
CONFERENCE AND MEETING ROOMS USED FOR ASSEMBLY
PURPOSES HAVE OCCUPANT LOADS LESS THAN 50 AND
CLASSIFIED AS GROUP B OCCUPANCY.
304.1 BUSINESS GROUP B:
BUSINESS GROUP B OCCUPANCY INCLUDES, AMONG OTHERS, THE
USE OF A BUILDING [FOR] PROFESSIONAL SERVICES.
BUILDINGS USED FOR OFFICE PURPOSES.
311.3 LOW-HAZARD STORAGE, GROUP S-2
STORAGE ROOMS CONTAIN PRODUCTS CONSTITUTING S-2.
STORAGE OCCUPANCIES ARE ACCESSORY TO GROUP B.
502.1 ADDRESS IDENTIFICATION:
SEE NOTE ON ELEVATIONS.
503.1.2 BUILDINGS ON SAME LOT:
SITE CONTAINS STORAGE SHED. SHED AND PRIMARY BUILDING
CONSIDERED TWO SEPARATE BUILDINGS.
504.3 HEIGHT IN FEET:
SEE TABLE 504.3. BUILDING COMPLIES WITH TABLE ALLOWANCES.
SEE ELEVATIONS FOR BUILDING HEIGHT.
504.4 NUMBER OF STORIES:
SEE TABLE 504.4. BUILDING COMPLIES WITH TABLE ALLOWANCES.
506.2 ALLOWABLE AREA DETERMINATION:
SEE TABLE 506.2. BUILDING COMPLIES WITH TABLE ALLOWANCES.
SEE BUILDING AREA SUMMARY AND CODE PLANS FOR LEVEL
AREAS.
506.2.1 SINGLE-OCCUPANCY BUILDINGS:
SEE TABULATION BELOW.
BUILDING AREA (IBC CODE)
AREA TYPE NAME GROSS AREA
LEVEL 1 INTERIOR BUSINESS 5029 SF
LEVEL 1 EXTERIOR BUSINESS 310 SF
LEVEL 1 EXTERIOR BUSINESS 482 SF
101-L1-(26.25')-(E)FF 5821 SF
LEVEL 2 INTERIOR BUSINESS 5343 SF
LEVEL 2 EXTERIOR BUSINESS 21 SF
LEVEL 2 EXTERIOR BUSINESS 19 SF
201-L2-(E)FF 5383 SF
Grand total 11204 SF
TABLE 504.3: ALLOWABLE BLDG HEIGHT IN FT ABOVE GRADE PLANE
OCC CLASS SPRINKLER TYPE VALUE
B S V-B 60
TABLE 504.4: ALLOWABLE NUMBER OF STORIES ABOVE GRADE PLANE
OCC CLASS SPRINKLER TYPE VALUE
B S V-B 3
TABLE 506.2: ALLOWABLE AREA FACTOR (At) IN SQUARE FEET
OCC CLASS SPRINKLER TYPE VALUE
B SM V-B 27,000
506.2.1: MAXIMUM ALLOWABLE AREA AA IN SQUARE FEET
AA = 33,750 SF PER STORY
At = 27,000
NS = 9,000
If = 0.75
506.3.1 [FRONTAGE INCREASE] MINIMUM PERCENTAGE OF PERIMETER:
BUILDING IS 100% SURROUNDED BY OPEN SPACE OR PUBLIC WAY.
506.3.2 MINIMUM FRONTAGE DISTANCE:
ALL MINIMUM DISTANCES FOR (W) EXCEED 20 FT.
506.3.3 AMOUNT OF INCREASE:
THE AREA FACTOR INCREASE BASED ON FRONTAGE SHALL BE
DETERMINED IN ACCORDANCE WITH TABLE 506.3.3.
FACTOR IS EQUIVALENT TO 0.75.
508.2.1 [ACCESSORY] OCCUPANCY CLASSIFICATION:
BUILDING HAS STORAGE ROOMS WITH S-2 OCCUPANCIES.
PRIMARY OCCUPANCY CLASSIFICATION OF BUILDING IS GROUP B.
508.2.2 ALLOWABLE BUILDING HEIGHT:
ALLOWABLE HEIGHT AND NUMBER OF STORIES FOR GROUP B
USED PER SECTION 504.
508.2.3 ALLOWABLE BUILDING AREA:
ALLOWABLE AREA FOR GROUP B USED PER SECTION 506.
ACCESSORY OCCUPANCIES DO NOT CONSTITUTE GREATER THAN
10% OF THE FLOOR AREA OF EACH STORY AND DO NOT EXCEED
VALUES IN TABLE 506.2.
508.2.4 SEPARATION OF OCCUPANCIES:
NO SEPARATION PROVIDED.
509.2 [INCIDENTAL USES] OCCUPANCY CLASSIFICATION:
BUILDING CONTAINS INCIDENTAL USES. SEE DISCUSSION BELOW.
TABLE 509.1 INCIDENTAL USES:
BUILDING CONTAINS A BOILER ROOM REQUIRING SEPARATION.ZE
AUTOMATIC SPRINKLER PROVIDED FOR ROOM. SEE DISCUSSION
BELOW.
509.2 OCCUPANCY CLASSIFICATION:
INCIDENTAL USES CLASSIFIED AS GROUP B.
509.3 AREA LIMITATIONS:
SEE ARCHITECTURAL PLANS. INCIDENTAL USES ARE LESS THAN
10% OF BUILDING AREA OF THE STORY.
TABLE 803.13: INTERIOR WALL AND CEILING FINISH REQUIREMENTS BY
OCCUPANCY (SPRINKLERED)
GROUP: INT EXIT EXIT ACCESS ROOMS STAIRS
EXIT STAIRS/RAMPS
B B C C
OCCUPANT LOAD CALCULATION SUMMARY:
RM OCC AREA OCC AREA OCC
CLASSIFICATION (SF) LOAD FACTOR TYPE LOAD
BUSINESS: 2755 150 GROSS 18.4
ASSEMBLY (TABLES/CHAIRS): 500 15 NET 33.3
MECH/STORAGE: 1797 300 GROSS 6.0
EXTERIOR AREAS: 792 300 GROSS 2.6
LEVEL 1 TOTAL: 5844 60.3
BUSINESS: 5337 150 GROSS 35.6
MECH/STORAGE: 31 300 GROSS 0.1
EXTERIOR AREAS: 40 300 GROSS 0.1
LEVEL 2 TOTAL: 5408 35.8
MECH/STORAGE: 625 300 GROSS 2.1
LEVEL 3 TOTAL: 625 2.1
BUILDING TOTAL: 99
804.4.2 [INTERIOR FLOOR FINISH] MINIMUM CRITICAL RADIANT FLUX:
INTERIOR FLOORS HAVE MINIMUM CRITICAL RADIANT FLUX OF NOT
LESS THAN CLASS II.
806.2 COMBUSTIBLE DECORATIVE MATERIALS:
SEE FINISH SCHEDULE AND INTERIOR ELEVATIONS. DECORATIVE
MATERIALS DO NOT EXCEED 10% OF WALL OR CEILING AREA.
806.7 INTERIOR TRIM:
INTERIOR TRIM HAS A MINIMUM CLASS C FLAME SPREAD INDEX.
TRIM DOES NOT EXCEED 10% OF WALL OR CEILING AREA.
806.8 INTERIOR FLOOR-WALL BASE:
FLOORS REQUIRED TO BE CLASS II; FLOOR BASE IS LESS THAN 6"
IN HEIGHT AND IS CLASS II.
906.1 [PORTABLE FIRE EXTINGUISHERS] WHERE REQUIRED:
PORTABLE FIRE EXTINGUISHERS SHALL BE INSTALLED IN THE
FOLLOWING LOCATIONS. 1. IN GROUP B OCCUPANCIES; […] 4. ON
EACH FLOOR OF STRUCTURES UNDER CONSTRUCTION [...]; 6.
SPECIAL-HAZARD AREAS, INCLUDING BUT NOT LIMITED TO [...]
WHERE REQUIRED BY THE FIRE CODE OFFICIAL.
SEE CODE PLANS
[F] TABLE 906.3(1) FIRE EXTINGUISHERS FOR CLASS A FIRE HAZARDS:
SEE CODE PLANS. BUILDING HAS EXTINGUISHERS PROVIDED
THROUGHOUT.
912.2.2 [FIRE DEPARTMENT CONNECTIONS] EXISTING BUILDINGS:
BUILDING IS EXISTING. SEE ELEVATIONS FOR FEC LOCATION AND
SIGN.
914.1.2 INTERIOR ACCESS TO SHAFTWAYS:
SEE SIGNAGE SCHEDULE FOR SHAFTWAY IDENTIFICATION SIGNS.
1003.2 [GENERAL MEANS OF EGRESS] CEILING HEIGHT:
ALL MEANS OF EGRESS HAVE CEILING HEIGHTS EXCEEDING 7'-6"
UNLESS OTHERWISE ALLOWED TO BE LOWER BY THIS SECTION.
1003.3.1 [PROTRUDING OBJECTS] HEADROOM:
SOME PROTRUDING OBJECTS EXTEND BELOW MINIMUM CEILING
HEIGHT. THESE DO NOT COMPRISE MORE THAN 50% OF CEILING
AREA AND PROVIDE A HEADROOM OF GREATER THAN 80".
BARRIER PROVIDED AT AREAS WHERE CIRCULATION PATH HAS A
CLEARANCE LESS THAN 80".
1003.3.2 POST-MOUNTED OBJECTS:
POST-MOUNTED OBJECTS MEET THE STANDARD. SEE SIGNAGE
SCHEDULE.
1003.3.3 HORIZONTAL PROJECTIONS:
OBJECTS BETWEEN 27" AND 80" ABOVE FINISHED FLOOR DO NOT
PROJECT GREATER THAN 4" INTO THE CIRCULATION PATH.
1003.3.4 CLEAR WIDTH
PROTRUDING OBJECTS DO NOT REDUCE THE MINIMUM CLEAR
WIDTH OF ACCESSIBLE ROUTES.
1003.4 SLIP-RESISTANT SURFACE:
FLOORS IN CIRCULATION PATHS ARE NON-SLIP AND SECURELY
ATTACHED.
1004.2.1 [CUMULATIVE OCCUPANT LOADS] INTERVENING SPACES OR
ACCESSORY AREAS:
WHERE OCCUPANTS EGRESS FROM ONE OR MORE ROOMS,
AREAS, OR SPACES THROUGH OTHERS, THE DESIGN OCCUPANT
LOAD SHALL BE THE COMBINED OCCUPANT LOAD OF
INTERCONNECTED ACCESSORY OR INTERVENING SPACES.
DESIGN OF EGRESS PATH CAPACITY SHALL BE BASED ON THE
CUMULATIVE PORTION OF OCCUPANT LOADS OF ALL ROOMS,
AREAS, OR SPACES TO THAT POINT ALONG THE PATH OF EGRESS
TRAVEL.
SEE CODE PLANS
1004.5 AREAS WITHOUT FIXED SEATING:
THE NUMBER OF OCCUPANTS SHALL BE COMPUTED AT THE RATE
OF ONE OCCUPANT PER UNIT OF AREA AS PRESCRIBED IN TABLE
1004.5. […]
SEE ROOM OCCUPANT LOAD TABLE
1105.1 [ACCESSIBLE ENTRANCES] PUBLIC ENTRANCES:
BUILDING HAS ONE PUBLIC ENTRANCE. THIS ENTRANCE COMPLIES
WITH STANDARDS FOR ACCESSIBLE ENTRANCES.
1105.1.1 AUTOMATIC DOORS;
BUILDING OCCUPANT LOAD IS LESS THAN 500, THE NUMBER
REQUIRING AUTOMATIC DOOR OPERATION.
1105.1.4 RESTRICTED ENTRANCES:
ONE RESTRICTED ENTRANCE IS ACCESSIBLE.
1106.2 [PARKING AND PASSENGER LOADING FACILITIES] REQUIRED:
SEE SITE PLAN. EACH FACILITY ON-SITE PROVIDES AT LEAST ONE
ACCESSIBLE PARKING SPACE.
1106.6 VAN SPACES:
SEE SITE PLAN. AT LEAST ONE VAN-ACCESSIBLE PARKING SPACE
PROVIDED FOR EACH PARKING FACILITY.
1110.2 TOILET AND BATHING FACILITIES:
ALL TOILET ROOMS ARE ACCESSIBLE.
1110.9 LIFTS:
BUILDING IS EXISTING AND HAS EXISTING PLATFORM LIFT
PROVIDING A COMPONENT OF THE ACCESSIBLE ROUTE.
1209.3 [ACCESS TO UNOCCUPIED SPACES] MECHANICAL APPLIANCES:
ROOFTOP MECHANICAL EQUIPMENT PROVIDED ACCESS PER THE
IMC.
1511.1.1 AREA LIMITATION
PENTHOUSE DOES NOT COVER GREATER THAN ONE-THIRD AREA
OF SUPPORTING ROOF DECK.
1511.2.1 HEIGHT ABOVE ROOF DECK
PENTHOUSE IS LESS THAN 18 FEET IN HEIGHT.
1511.2.2 USE LIMITATIONS
PENTHOUSE SHALL BE USED ONLY FOR SHELTER OF MECHANICAL
AND ELECTRICAL EQUIPMENT.
1511.2.4 TYPE OF CONSTRUCTION
PENTHOUSE WALLS MEET REQUIREMENTS FOR FIRE RATING PER
TABLE 601.
2402.1 [GLAZING REPLACEMENT] GENERAL:
REPLACED GLAZING SHALL MEET REQUIREMENTS FOR NEW
INSTALLATION.
2403.3 GLASS FRAMING:
ALL WINDOWS REPLACED WITH CONTEMPORARY WINDOWS
EVOKING A SIMILAR APPEARANCE TO THE HISTORIC WINDOW WILL
COMPLY WITH THIS PROVISION. ALL DAMAGED HISTORIC
WINDOWS WILL BE REPAIRED IN A MANNER CONSISTENT WITH
THEIR ORIGINAL CONSTRUCTION PER THE IEBC AND MAY NOT
MEET THIS PROVISION.
TABLE 1020.3: MINIMUM CORRIDOR WIDTH (IN)
ANY FACILITY NOT LISTED 44
MECH ACCESS 24
<50 OCC 36
1004.7 OUTDOOR AREAS:
BUILDINGS HAVE COVERED EXTERIOR AREAS ASSOCIATED WITH
THE BUILDING USE. THESE ARE FREE AND OPEN TO A PUBLIC
WAY.
1004.9 POSTING OF OCCUPANT LOAD:
ALL BUILDINGS CONTAIN B OCCUPANCIES WITH SOME ASSEMBLY
SPACES CLASSIFIED AS B. SIGNAGE POSTED WILL PROVIDE
MAXIMUM OCCUPANT LOADS IN ROOMS OF ASSEMBLY USE OR
OCCUPANCY.
1005.3.1 STAIRWAYS:
SEE CODE PLANS. EXISTING EXTERIOR EXIT STAIRWAYS COMPLY
WITH STANDARD BUT ARE NOT MODIFIED WITH PROJECT.
1005.3.2 OTHER EGRESS COMPONENTS:
SEE CODE PLANS. EXISTING COMPONENTS OF EGRESS COMPLY
WITH STANDARD BUT WILL NOT BE MODIFIED WITH PROJECT PER
IEBC. NEW COMPONENTS OF EGRESS WILL COMPLY WITH
STANDARD.
1005.4 CONTINUITY:
COMPONENTS OF EGRESS MEET STANDARDS FOR CAPACITY.
1005.5 DISTRIBUTION OF MINIMUM WIDTH AND REQUIRED CAPACITY:
STORIES OF BUILDING AND SPACES REQUIRE MORE THAN ONE
EXIT. LOSS OF ONE EXIT DOES NOT REDUCE THE AVAILABLE
CAPACITY TO LESS THAN 50% OF THE REQUIRED CAPACITY.
1005.7.1 [ENCROACHMENT] DOORS:
SEE CODE PLANS. DOORS WHEN FULLY OPENED DO NOT REDUCE
REQUIRED WIDTH BY MORE THAN 7".
1005.7.2 OTHER PROJECTIONS:
HANDRAILS PROJECT INTO REQUIRED WIDTH PER SECTION 1014.8.
1006.2.2.1 BOILER, INCINERATOR AND FURNACE ROOMS:
MECHANICAL ROOM DOES NOT HAVE AN AREA GREATER THAN 500
SF.
1009.1 ACCESSIBLE MEANS OF EGRESS REQUIRED:
BUILDINGS ARE EXISTING AND DO NOT REQUIRE ACCESSIBLE
MEANS OF EGRESS PER IEBC. SEE DISCUSSION BELOW.
1010.1.1 SIZE OF DOORS:
ALL NEW DOORS COMPLY WITH STANDARD. EXISTING DOORS NOT
ALTERED IN THIS PROJECT COMPLY WITH STANDARD.
1010.2.2 HARDWARE:
SEE HARDWARE SCHEDULE. SEE HARDWARE SCHEDULE. ALL
DOORS MEET STANDARD.
1010.2.3 HARDWARE HEIGHT:
SEE DOOR SCHEDULE. NEW HARDWARE WILL COMPLY WITH THIS
PROVISION.
1011 STAIRWAYS:
PER IEBC EXISTING MEANS OF EGRESS MAY REMAIN UNALTERED
IF DETERMINED BY CODE OFFICIAL TO NOT POSE DANGER TO LIFE
SAFETY. STAIRWAY MAINTAINS EXISTING LEVEL OF PROTECTION.
1012.2 [RAMPS] SLOPE:
BOTTOM LANDING FOR LIFT IS 2" ABOVE ADJACENT FLOOR. SHORT
RAMP IS NOT PART OF MEANS OF EGRESS AND IS EXCLUSIVELY
USED FOR ACCESSING LIFT. RAMP SLOPE DOES NOT EXCEED 1:8.
1014.2 [HANDRAILS] HEIGHT:
HANDRAIL HEIGHT, MEASURED ABOVE STAIR TREAD NOSINGS, OR
FINISH SURFACE OF RAMP SLOPE, SHALL BE UNIFORM, NOT LESS
THAN 34" AND NOT MORE THAN 38". HANDRAIL HEIGHT OF
ALTERNATING TREAD DEVICES AND SHIP LADDERS, MEASURED
ABOVE TREAD NOSINGS, SHALL BE UNIFORM, NOT LESS THAN 30"
AND NOT MORE THAN 34". SEE STAIR SECTIONS. NEW HANDRAILS
COMPLY WITH STANDARD.
1014.3 HANDRAIL GRASPABILITY:
SEE STAIR SECTIONS. NEW HANDRAILS COMPLY WITH STANDARD.
1014.4 HANDRAIL EXTENSIONS:
SEE STAIR SECTIONS. NEW HANDRAILS COMPLY WITH STANDARD.
1014.7 CLEARANCE:
NEW HANDRAILS COMPLY WITH STANDARD.
1015.3 [GUARDS] HEIGHT:
EXTERIOR STAIR LANDING IS NOT GREATER THAN 30" ABOVE
FINISHED ADJACENT GRADE. NO GUARD REQUIRED.
1016.2 EGRESS THROUGH INTERVENING SPACES:
SEE CODE PLANS. SOME EGRESS PATHS IN BUILDING PASS
THROUGH VESTIBULES OR ADJACENT ROOMS THAT ARE
ACCESSORY TO ONE OR THE OTHER. OFFICE AREAS ON FIRST
FLOOR HAVE A SECOND EXIT THAT PASSES THROUGH ADJACENT
"READY" MUD ROOM WITH CLEAR DISCERNIBLE PATH OF EGRESS.
1017.2 [EXIT ACCESS TRAVEL DISTANCE] LIMITATIONS:
TABLE 1017.2 SPECIFIES 300 FT EXIT ACCESS TRAVEL DISTANCE
MAXIMUM FOR GROUP B IN BUILDING FULLY SPRINKLERED. SEE
CODE PLANS FOR EXIT ACCESS TRAVEL DISTANCE.
1017.3 MEASUREMENT:
SEE CODE PLANS FOR EXIT ACCESS TRAVEL DISTANCE. FIRST
FLOOR OF THE BUILDING IS DIVIDED BETWEEN PUBLIC AND
OFFICE FUNCTIONS. PUBLIC AREAS WILL NOT HAVE FREE EGRESS
THROUGH OFFICE AREA AND OCCUPANT LOAD AND EXIT ACCESS
TRAVEL DISTANCE DOES NOT EXCEED LIMITS FOR HAVING ONLY
ONE EXIT. OFFICE AREAS REQUIRE ONLY ONE EXIT WHICH PASSES
THROUGH "READY" MUD ROOM.
1019.1 [EXIT ACCESS STAIRWAYS] GENERAL:
BUILDING CONTAINS INTERIOR STAIR THAT DOES NOT SERVE AS A
COMPONENT OF EGRESS.
1019.3 OCCUPANCIES OTHER THAN GROUPS I-2 AND I-3:
STAIRWAY CONNECTS ONLY TWO ADJACENT STORIES.
REQUIRED PLUMBING FIXTURES - TABLE 422.1
OCC WC REQ'D U REQ'D LAV REQ'D DF REQ'D
M F SO M M F SO
99 1 3 0 1 1 1 0 1
OTHER: 1 SERVICE SINK
CODE: 2018 UPC
TABLE 422.1 MINIMUM PLUMBING FIXTURES:
BUILDING DOES NOT CHANGE OCCUPANCY BUT PROVIDES
FACILITES PER TABLE 422.1. SEE BELOW. 2 SINGLE OCCUPANT (SO)
TOILET ROOMS PROVIDED ON LEVEL 2. ONE WATERCLOSET
REQUIRED FOR WOMEN PROVIDED IN SO TOILET ROOM SIGNED
FOR USE BY BOTH GENDERS.
601 [TYPES OF CONSTRUCTION] GENERAL:
SEE TABLE 601. BUILDING IS TYPE V-B CONSTRUCTION. SEE
DISCUSSION BELOW.
602.5 TYPE V:
BUILDING IS CONSIDERED TYPE V-B CONSTRUCTION.
TABLE 601: FIRE-RESISTANCE RATING REQUIREMENTS FOR BUILDING
ELEMENTS (HOURS)
TYPE V-B:
PRIMARY STRUCTURAL FRAME: 0 HRS
BEARING WALLS:
EXTERIOR: 0 HRS
INTERIOR: 0 HRS
NONBEARING WALLS & PARTITIONS:
EXTERIOR: SEE TBL 705.5
INTERIOR: 0 HRS
FLOOR CONSTRUCTION, ETC: 0 HRS
ROOF CONSTRUCTION, ETC: 0 HRS
717.1.2.1 DUCTS THAT PENETRATE NONFIRE-RESISTANCE-RATED
ASSEMBLIES
THE SPACE AROUND THE DUCT PENETRATING A NONFIRE-
RESISTANCE-RATED FLOOR ASSEMBLY SHALL COMPLY WITH
SECTION 717.6.3.
717.6.3 NONFIRE-RESISTANCE-RATED FLOOR ASSEMBLIES
PER METHOD 2, THE DUCTS FROM PENTHOUSE TO LEVEL 1 PASS
THROUGH ONLY 1 STORY. AS PENTHOUSE IS CONSIDERED PART
OF STORY BELOW, THE DUCTS CONNECT NO MORE THAN TWO
STORIES. DUCTS PENETRATE A NONCOMBUSTIBLE FLOOR
ASSEMBLY THAT RESISTS THE FREE PASSAGE OF FLAME AND THE
PRODUCTS OF COMBUSTION AT THE FLOOR LINE OF LEVEL 2.
ANNULAR SPACES AROUND PENETRATING DUCTS PROTECTED
WITH NONCOMBUSTIBLE MATERIAL.
TABLE 705.5: FIRE-RESISTANCE RATING REQUIREMENTS FOR EXTERIOR
WALLS BASED ON FIRE SEPARATION DISTANCE
FSD TYPE OF GROUP B, R, S-2
(FT) CONSTRUCTION
10≤X<30 V-B 0 HRS
X≥30 ALL 0 HRS
1020.2 [CORRIDORS] CONSTRUCTION:
BUILDING IS FULLY SPRINKLERED. NEW CORRIDORS PROVIDED
WITH NO FIRE-RESISTANCE RATING PER TABLE.
1020.3 WIDTH AND CAPACITY:
SEE ARCHITECTURAL DRAWINGS. NEW CORRIDORS HAVE WIDTHS
MEETING OR EXCEEDING MINIMUM WIDTH.
1020.5 DEAD ENDS:
SEE ARCHITECTURAL DRAWINGS. LENGTH OF NEW DEAD-END
DOES NOT EXCEED 20'.
1027.3 [EXTERIOR EXIT STAIRWAYS AND RAMPS] OPEN SIDE:
BUILDING HAS EXISTING EXTERIOR EXIT STAIRWAYS AND RAMPS
NOT ALTERED WITH PROJECT. ALL WORK CONDUCTED TO THESE
ELEMENTS CONSTITUTES REPAIRS. ELEMENTS CONSIDERED
CONFORMING WITH CODES ADOPTED AT TIME OF CONSTRUCTION.
EXISTING WIDTHS ACCOMMODATE REQUIRED CAPACITIES.
1028.5 ACCESS TO A PUBLIC WAY:
SEE SITE PLAN. ALL EXITS DISCHARGE TO PUBLIC WAY.
1104.1 SITE ARRIVAL POINTS:
SEE SITE PLAN. ACCESSIBLE ROUTE PROVIDED FROM ACCESSIBLE
PARKING TO ACCESSIBLE BUILDING ENTRANCES. BUILDING IS
EXISTING AND HAS ACCESSIBLE ENTRANCE NOT BEING MODIFIED
IN PROJECT. MODIFIED ENTRANCES ARE MADE ACCESSIBLE TO A
DEGREE TECHNICALLY FEASIBLE WITHOUT ALTERING BUILDING TO
ACCOMMODATE APPROACH CLEARANCES. AUTOMATIC DOOR
OPENERS PROVIDED AT ACCESSIBLE ENTRANCES.
1104.2 WITHIN A SITE:
SEE SITE PLAN. ACCESSIBLE ROUTE PROVIDED ON-SITE TO ALL
ACCESSIBLE FACILITIES, ELEMENTS, AND SPACES.
1104.3 CONNECTED SPACES:
SEE ARCHITECTURAL DRAWINGS. BUILDING HAS AN ACCESSIBLE
ROUTE TO ALL ACCESSIBLE FIRST FLOOR SPACES. SEE
DISCUSSION BELOW.
1104.4 MULTISTORY BUILDINGS AND FACILITIES:
EACH STORY HAS ACCESSIBLE SPACES AND AN ACCESSIBLE
ROUTE IS PROVIDED TO EACH STORY.
1104.5 LOCATION:
ACCESSIBLE ROUTE PROVIDED WITHIN BUILDING WITH EXISTING
WHEELCHAIR LIFT.
UP
DN
DN
DN
DN
CODE LEGEND
EXIT
GROUP B
COMMON PATH OF EGRESS
EXIT ACCESS TRAVEL DISTANCE
BEYOND COMMON PATH
F.E.*255 (545)
68.4"
OCC (REQ'D OCC)
REQ'D CAPACITY 2-A
1 HR RATED ASSEMBLY
A
B C D E F
100'-0"
'-0
20'-0" 20'-0" 20'-0" 20'-0" 20'-0"
'-0
'-0
239 SF
STORAGE S-2
5029 SF
BUSINESS
310 SF
BUSINESS
LOADING
STAIR 1
STORAGE SHED
COVERED ENTRY
482 SF
BUSINESS
11'-3"
'-3
54'-11 1/2"
117'-6 3/4"
6.3"
2.9"
LONGEST COMMON PATH
TO EXIT: 90'-0"
*2-A
*2-A
*2-A
26'-0"
10'-0"
IM
PL
IE
D P
.L.
SEPARATE BUILDING
LONGEST COMMON PATH
TO EXIT: 99'-0"
A
B C D E F
STAIR 1
5343 SF
BUSINESS
21 SF
BUSINESS
19 SF
BUSINESS
100'-0"
'-0
20'-0" 20'-0" 20'-0" 20'-0" 20'-0"
'-0
'-0
60'-0"
'-2
'-0
113'-2 1/4"
38 5.
7"38 5.
7"
*2-A *2-A
*2-A
51'-2"
B C
625 SF
BUSINESS
PENTHOUSE
2 OCC
'-0
20'-0"
'-0
'-5
'-0
'-0
NOTIFICATION OF POTENTIAL HAZARDS
ASBESTOS, LEAD, AND OTHER HAZARDOUS MATERIALS ARE PRESENT IN THE BUILDING
AND MAY IMPACT THE WORK OF ALL TRADES. REGULATED AIR CONTAMINANTS,
INCLUDING ASBESTOS AND LEAD, ARE ALSO PRESENT IN SETTLED AND CONCEALED
DUST IN AND ON ARCHITECTURAL, STRUCTURAL, MECHANICAL, AND ELECTRICAL
COMPONENTS OR SYSTEMS THROUGHOUT THE BUILDING. ALL TRADES SHALL
COORDINATE WITH OTHER TRADES AND CONDUCT THEIR WORK TO PREVENT WORKER
EXPOSURE OR SITE CONTAMINATION. REFER TO SPECIFICATION DIVISIONS 0, 1, AND 2
FOR SPECIFIC INFORMATION CONCERNING DISTURBING, REMOVING, AND DISPOSING OF
THESE MATERIALS AND THE INSTALLATION OF THE NEW MATERIALS OR COMPONENTS.
THIS NOTIFICATION IS PROVIDED IN ACCORDANCE WITH EPA AND OSHA REQUIREMENTS.
AK
SAL
AFOETATS
T
CETIHCRALANOISSEFOR
PDE
RE
TS
I
GE
R
No. A-140412
JUSTIN M. SCANIO
TH49
06.26.2024
N S
TR
EE
T, S
UI
TE
A N C
HO
RA
G E, A
LA
SK
A
7.
1.
E
CI
/H ye r, In c.
C
HE
C
KE
D
A
UT
HO
R:
PR
O
JE
C T N O
IS
SU
E D A
TE
RE
V
IS
IO
N
FULL SIZE PRINTED ON 22 x 34
G1.03
C O
DE
P
LA
N S
-0 6.
C W R
JM
S
.2 6.
PE
TE
RS
BU
RG
O
FF
IC
E C O N
SO
LI
DA
TIO
N
W O
RK
C
EN
TE
R
RE
PL
A C
EM
EN
T - D
IS
TR
IC
T
O
FF
IC
E
C O N
ST
RU
C
TIO
N D O C
UM
EN
TS
1/16" = 1'-0"1 LEVEL 1 CODE PLAN
1/16" = 1'-0"2 LEVEL 2 CODE PLAN
1/16" = 1'-0"3 LEVEL 3 CODE PLAN
NOTE: CONFERENCE AND HUDDLE ROOMS CONSIDERED
NON-CONCENTRATED ASSEMBLY FOR DETERMINING
NUMBER OF OCCUPANTS
ESTIMATED QUANTITIES TO BE REMOVED (PDO BUILDING)
INCIDENTAL QUANTITIES OF MATERIALS, INCLUDING LEAD-CONTAINING MATERIALS, THAT ARE REQUIRED TO BE REMOVED TO COMPLETE THE WORK, BUT OTHERWISE ARE TO REMAIN, ARE NOT INCLUDED HERE, AS THEY WILL VARY DEPENDING ON THE CONTRACTOR'S CHOICE OF MEANS AND METHODS.
26,850 SQUARE FEET OF GYPSUM WALLBOARD WITH ASBESTOS-CONTAINING JOINT COMPOUND, INCLUDING GYPSUM WALL BOARD SUBSTRATE TO GLUED-ON CEILING TILES
225 SQUARE FEET OF CEMENT ASBESTOS BOARD INSULATED INFILL PANELS, INCLUDING THE SEALANTS AT THE PERIMETER FRAMES.
2,185 SQUARE FEET OF 12" X 24 " ASBESTOS-CONTAINING ASPHALTIC FLOOR TILES AND ASBESTOS-CONTAINING MASTICS TO BE COMPLETELY REMOVED.
4,390 SQUARE FEET OF VARIOUS COLORS OF 9" X 9" VINYL ASBESTOS FLOOR TILES AND ASBESTOS-CONTAINING MASTICS TO BE COMPLETELY REMOVED.
80 SQUARE FEET OF VARIOUS COLORS OF 12" X 12" VINYL COMPOSITE TILE CONTAMINATED BY ASBESTOS-CONTAINING MASTICS TO BE COMPLETELY REMOVED.
1,750 LINEAR FEET OF DUCTWORK WITH ASBESTOS-CONTAINING GRAY-GREEN SEALANTS TO BE COMPLETELY REMOVED.
100* ALLOWANCE FOR REQUIRED REMOVAL OF GLOBS OF INSULATION PIN MASTIC FROM ROUGH CONCRETE SURFACE. THE INSULATION PINS ARE HOLDING RIGID FIBERGLASS PANEL INSULATION TO EXTERIOR WALLS, AND UNDER ENTRY ALCOVES AND ARE ONLY REQUIRED TO BE REMOVED WHERE NECESSARY TO COMPLETE THE WORK. THE VAST MAJORITY OF THE MASTIC OF THE INSULATION PINS ARE TO REMAIN IN PLACE AND HAVE THE PINS CLIPPED OFF OF THE PERFORATED 2" SQUARE METAL PIN PLATES.
2,100 LINEAR FEET OF PIPING, FIBERGLASS INSULATION AND ASBESTOS-CONTAINING "HARD-FITTING" INSULATION AT VALVES, FITTINGS, HANGARS, ETC. TO BE REMOVED.
380 EACH ASBESTOS-CONTAINING "HARD-FITTINGS" AND FIBERGLASS INSULATION TO BE REMOVED FROM ROOF DRAIN PIPING, PIPING TO REMAIN, AND BE RE-INSULATED.
1 LOT ASBESTOS-CONTAINING GASKETS AND VALVE PACKINGS ON PIPING.
3 EACH WOOD FIRE DOORS WITH ASBESTOS-CONTAINING DOOR INSULATION.
1 EACH BOILER WITH ASBESTOS-CONTAINING GASKETS, SEALANTS AND REFRACTORY INSULATION AT BOILER BASE.
40 LINEAR FEET OF SITE ERECTED BOILER STACK WITH ASBESTOS-CONTAINING INSULATION AND METAL JACKET, INCLUDING THROUGH ROOF AND REMOVAL OF THE ENCLOSURE ABOVE THE ROOF IF
NECESSARY FOR COMPLETE REMOVAL OF THE STACK AND INSULATION.
20* SQUARE FOOT ALLOWANCE FOR REMOVAL OF ASSUMED ASBESTOS-CONTAINING TARRY DAMP-PROOFING AT EXTERIOR FOUNDATION WALL.
50* SQUARE FOOT ALLOWANCE FOR REMOVAL OF REMNANTS OF ASSUMED ASBESTOS-CONTAINING BUILT-UP ROOFING OR VAPOR BARRIER ON SURFACE OF ROOF DECK TO BE REMOVED FOR NEW
PENETRATIONS AND EQUIPMENT MOUNTING.
430 MERCURY-CONTAINING FLUORESCENT LAMPS AND COMPACT FLUORESCENT LAMPS
15 SELF ILLUMINATING EXIT RADIOACTIVE SIGNS
15 EMERGENCY LIGHTS OR OTHER EQUIPMENT WITH UNIVERSAL WASTE BATTERIES
1 MERCURY-CONTAINING THERMOSTATS
2,180 LINEAR FEET OF ASBESTOS-CONTAINING SEALANTS AT WINDOWS AND DOORS
GENERAL NOTES
1. THE HAZARDS ABATEMENT PORTION OF THIS PROJECT INCLUDES THE DISTURBANCE AND/OR REMOVAL AND DISPOSAL OF SELECTED ASBESTOS-CONTAINING MATERIALS, POLYCHLORINATED BIPHENYL
(PCB) CONTAINING LIGHT BALLASTS, MERCURY-CONTAINING MATERIALS, LEAD-CONTAINING MATERIALS AND ITEMS CONTAINING RADIOACTIVE COMPOUNDS. THE PURPOSE OF THE HAZARDS ABATEMENT PORTION OF THE WORK IS TO REMOVE THESE MATERIALS FROM THE PDO BUILDING PRIOR TO RENOVATION OR DEMOLITION SO THAT PERSONNEL CAN SAFELY PERFORM THEIR WORK WITHOUT CREATING
HAZARDS TO HEALTH OR THE ENVIRONMENT.
2. THE WORK IN THE PDO BUILDING DOES NOT INCLUDE REMOVAL OF ALL HAZARDOUS MATERIALS IN THE BUILDING. REMOVE HAZARDOUS MATERIALS COORDINATING WITH OTHER TRADES, AS SPECIFIED AND/OR INDICATED ON THE DRAWINGS, OUTLINED IN THE SPECIFICATIONS, AND AS REQUIRED TO COMPLETE THE WORK. "REMOVAL" INCLUDES PROPER HANDLING, PACKAGING AND DISPOSAL OF
MATERIALS REMOVED.
3. POTENTIALLY HAZARDOUS MATERIALS SUCH AS MERCURY-CONTAINING LAMPS AND THERMOSTATS, SELF ILLUMINATING EXIT SIGNS CONTAINING RADIOACTIVE COMPONENTS, METALLIC LEAD ITEMS, REFRIGERANTS, HEATING SYSTEM GLYCOL AND PCB CONTAINING BALLASTS AFFECTED BY THE PROJECT ARE TO BE REMOVED AND DISPOSED OF PROPERLY. REFER TO SPECIFICATIONS AND THE CONTRACTOR'S APPROVED WORK PLAN FOR HAZARDOUS MATERIALS REMOVAL, DISTURBANCE, CLEARANCE, AND DISPOSAL PROCEDURES.
4. LEAD-BASED PAINTS (PAINT CONTAINING EQUAL TO OR GREATER THAN 1.0 mg/cm²) WERE IDENTIFIED DURING THE LIMITED LEAD TESTING SHOWN IN THE HAZMAT SURVEY, AND LEAD-BASED PAINTS MAY BE PRESENT AT OTHER LOCATIONS. LOW LEVELS OF LEAD FOUND BY XRF TESTING DOES NOT MEAN THE PAINTS ARE FREE OF LEAD, THE PAINTS MAY CONTAIN MEASURABLE AMOUNTS OF LEAD.
LEAD-CONTAINING MATERIALS INCLUDE ALL PAINTED SURFACES, CERAMIC TILES, AND METALLIC LEAD, AS WELL AS LEAD-CONTAINING DUSTS. THIS IS NOT A LEAD ABATEMENT PROJECT, AND ALL TRADES WILL LIKELY DISTURB SOME LEAD-CONTAINING MATERIALS. CONTROL WORKER EXPOSURES USING LEAD-SAFE WORK PRACTICES AND CHOICE OF MEANS AND METHODS OF CONDUCTING THE WORK TO
COMPLY WITH 29 CFR 1926.62 AND TO AVOID CONTAMINATION OF THE WORK AREA AND SITE.
5. PERFORM INITIAL AIR MONITORING TESTS ON ALL TASKS THAT DISTURB ASBESTOS OR LEAD-CONTAINING MATERIALS, DUST OR PAINT TO DETERMINE THE APPROPRIATE WORKER AND SITE PROTECTION PROCEDURES REQUIRED. DUE TO THE AGE OF THE BUILDINGS, METALLIC LEAD IS ASSUMED PRESENT IN BELL AND SPIGOT PIPE JOINTS AND IN SOLDER ON COPPER PIPES.
6. SETTLED AND CONCEALED DUST ON ARCHITECTURAL, STRUCTURAL, ELECTRICAL AND MECHANICAL COMPONENTS THROUGHOUT THE PROJECT AREA(S) IS ASSUMED TO CONTAIN REGULATED AIR CONTAMINANTS INCLUDING ASBESTOS AND LEAD. WORK OF ALL TRADES MAY INCLUDE DISTURBANCE OF ASBESTOS AND LEAD AND MAY RESULT IN WORKER EXPOSURE TO ASBESTOS AND LEAD ABOVE THE OSHA ACTION LEVEL OR PERMISSIBLE EXPOSURE LIMITS FOR ASBESTOS OR LEAD IF PROPER WORK PRACTICES AND/OR ENGINEERING CONTROLS ARE NOT USED. IT IS THE CONTRACTOR'S RESPONSIBILITY TO CHOOSE APPROPRIATE WORKER AND SITE PROTECTION PROCEDURES SO THAT THEIR WORKERS ARE NOT EXPOSED ABOVE THOSE LIMITS AND THAT WORK IS PERFORMED IN ACCORDANCE WITH ALL APPLICABLE REGULATIONS. THE PRESENCE OF ASBESTOS OR LEAD IN DUSTS DOES NOT NECESSARILY MAKE THEM A HAZARD TO WORKERS OR A HAZARDOUS WASTE.
7. THE CONTRACTOR'S INDEPENDENT LABORATORY SHALL PROVIDE ALL INSPECTIONS, MONITORING, SAMPLING, ANALYSES AND REPORTING SERVICES AS SPECIFIED. CLEARANCE AIR MONITORING IN THE PDO BUILDING SHALL BE CONDUCTED IN ACCORDANCE WITH 40 CFR 763. REFER TO SPECIFICATIONS FOR ADDITIONAL INFORMATION ON SAMPLING.
8. LOCATIONS OF MATERIALS SHOWN ON THESE DRAWINGS ARE SCHEMATIC AND APPROXIMATE. FIELD VERIFY AND COORDINATE CONSTRUCTION DETAILS, DIMENSIONS, WORK CONDITIONS, AND LOCATIONS WHICH WILL AFFECT THE REMOVAL OR DISTURBANCE OF HAZARDOUS MATERIALS. HAZARDOUS MATERIALS MAY HAVE COME LOOSE AND FALLEN ONTO FLOORS, CEILINGS, CHASES, OR WALL CAVITIES. THE QUANTITIES SHOWN IN THE SHEET SUMMARY ARE APPROXIMATE AND MAY VARY DEPENDING ON THE CONTRACTOR'S MEANS AND METHODS. REQUIRE ALL TRADES TO COORDINATE WITH EACH OTHER AND TO CONDUCT THEIR WORK TO PREVENT WORKER EXPOSURE OR SITE CONTAMINATION, SEE DRAWINGS OF ALL DISCIPLINES FOR ADDITIONAL INFORMATION RELATING TO HAZARDOUS MATERIALS.
IMMEDIATELY COMMUNICATE ALL DISCREPANCIES IN QUANTITIES TO THE OWNER. REFER TO HAZARDOUS MATERIALS ASSESSMENT FOR MORE INFORMATION ABOUT POTENTIALLY HAZARDOUS MATERIALS THAT ARE NOT SCHEDULED FOR DISTURBANCE BY THIS PROJECT. FURNISH ALL WORK AND MATERIALS REQUIRED FOR A FINISHED PROJECT AS DESCRIBED IN THE CONTRACT DOCUMENTS. QUANTITIES LISTED WITH A * MAY VARY DEPENDING ON THE CONTRACTOR'S MEANS AND METHODS. CONTRACTOR'S MEANS AND METHODS RESULTING IN ADDITIONAL MATERIALS REMOVAL SHALL NOT RESULT IN
ADDED CONTRACT COSTS TO THE OWNER.
9. BUILDINGS TO BE RENOVATED OR DEMOLISHED INCLUDE STORED MATERIALS AND CHEMICALS, SUCH AS PAINTS, CLEANING COMPOUNDS, THINNERS, SOLVENTS, ETC. THE OWNER WILL REMOVE AND SALVAGE MATERIALS FOR THEIR CONTINUED USE. THE CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF ALL STORED MATERIALS AND CHEMICALS THAT THE OWNER CHOOSES TO LEAVE IN PLACE
IN THE BUILDINGS.
10. PROVIDE ALL WASTE TESTING, PACKAGING, HANDLING, TRANSPORTATION AND DISPOSAL. ALL COSTS FOR DISPOSAL SHALL BE BORNE BY THE CONTRACTOR. PERFORM TOXICITY CHARACTERISTIC LEACHING PROCEDURE (TCLP) TEST(S) OF WASTE(S) CONTAINING LEAD OR PAINTED WITH LEAD-CONTAINING PAINT TO CHARACTERIZE THE WASTE(S) AS HAZARDOUS OR NON-HAZARDOUS PRIOR TO DISPOSAL. PERFORM TOXICITY CHARACTERISTIC LEACHING PROCEDURE (TCLP) TEST(S) OF HEAT TRANSFER FLUIDS (GLYCOL OR WATER) IN HEATING SYSTEM TO CHARACTERIZE THE WASTE(S) AS HAZARDOUS OR NON-HAZARDOUS PRIOR TO DISPOSAL. COORDINATE REQUIREMENTS OF LANDFILL(S) REGARDING MATERIALS PACKAGING, HANDLING, AND DISPOSAL REQUIREMENTS PRIOR TO SUBMITTING
BID.
H0.1
HA
ZA
RD
S
A
BA
TE
M
EN
T N
O
TE
S A
N D
Q
UA
N
TI
TIE
S
N S
TR
EE
T, S
UI
TE
A N
C
HO
RA
G
E, A
LA
SK
A
7.
1.
E
CI
/H ye r, In c.
C
HE
C
KE
D
A
UT
HO
R:
PR
O
JE
C
T N
O
RA
F
RA
F
IS
SU
E D
A
TE
:0 5.
.2
RE
V
IS
IO
N
EH
S-
A
LA
SK
A
BU
SI
N
ES
S
BO
UL
EV
A
RD
, S
UI
TE
EA
G
LE
R
IV
ER
, A
LA
SK
A
.6
.1
FULL SIZE PRINTED ON 22 x 34
P
R
E
L
I
M
I
N
A
R
Y
N
O
T
F
R
C
O
N
S
T
R
U
C
T
I
O
N
PE
TE
RS
BU
RG
O
FF
IC
E C
O N
SO
LI
DA
TIO
N
W O
RK
C
EN
TE
R
RE
PL
A
C
EM
EN
T
DI
ST
RI
C T
O
FF
IC
E
C O
N
ST
RU
C
TIO
N
D O
C
UM
EN
TS
NOTIFICATION OF POTENTIAL HAZARDS
ASBESTOS, LEAD, AND OTHER HAZARDOUS MATERIALS ARE PRESENT IN THE BUILDING
AND MAY IMPACT THE WORK OF ALL TRADES. REGULATED AIR CONTAMINANTS,
INCLUDING ASBESTOS AND LEAD, ARE ALSO PRESENT IN SETTLED AND CONCEALED
DUST IN AND ON ARCHITECTURAL, STRUCTURAL, MECHANICAL, AND ELECTRICAL
COMPONENTS OR SYSTEMS THROUGHOUT THE BUILDING. ALL TRADES SHALL
COORDINATE WITH OTHER TRADES AND CONDUCT THEIR WORK TO PREVENT WORKER
EXPOSURE OR SITE CONTAMINATION. REFER TO SPECIFICATION DIVISIONS 0, 1, AND 2
FOR SPECIFIC INFORMATION CONCERNING DISTURBING, REMOVING, AND DISPOSING OF
THESE MATERIALS AND THE INSTALLATION OF THE NEW MATERIALS OR COMPONENTS.
THIS NOTIFICATION IS PROVIDED IN ACCORDANCE WITH EPA AND OSHA REQUIREMENTS.
-0
SHEET NOTES
HAZARDS ABATEMENT DRAWINGS DO NOT SHOW ALL DETAILS OF WORK REQUIRED. ALL TRADES SHALL EXAMINE DRAWINGS OF OTHER TRADES AND COORDINATE WITH EACH OTHER TO DETERMINE EXTENT, TIMING AND LOCATIONS OF MATERIALS AFFECTED BY THE PROJECT.
1 REMOVE GYPSUM WALL BOARD ON WALLS AND CEILINGS WITH ASBESTOS-CONTAINING JOINT COMPOUND. GYPSUM WALL BOARD CEILING AT SECOND FLOOR IS MOSTLY COVERED WITH A GLUED-ON ACOUSTIC CEILING TILES WHICH HAD MASTICS WHICH CONTAINED LESS THAN 1 PERCENT ASBESTOS, BUT ARE CONTAMINATED BY THE ASBESTOS-CONTAINING JOINT COMPOUND. ALL GYPSUM WALL
BOARD IS TO BE REMOVED FROM THE PDO BUILDING.
2 REMOVE CEMENT ASBESTOS BOARD (CAB) "GLASWELD" INSULATED INFILL PANELS, ALUMINUM FRAMES, AND ASSUMED CONCEALED ASBESTOS-CONTAINING SEALANTS FROM CONCRETE WALLS.
3 REMOVE CARPETING, SHEET VINYL, VINYL ASBESTOS TILE AND COMPLETELY REMOVE ASBESTOS-CONTAINING OR CONTAMINATED MASTIC, INCLUDING UNDER WALLS SCHEDULED FOR DEMOLITION.
LOCATIONS OF DIFFERENT TYPES AND MULTIPLE LAYERS OF ACM SHOWN BY LEGEND AND REFER TO SHEET SUMMARY.
4 REMOVE DUCTWORK WITH GRAY-GREEN ASBESTOS-CONTAINING SEALANTS. REFER TO MECHANICAL FOR LOCATIONS. MOSTLY FOUND IN PENTHOUSE FAN ROOM, BUT ASSUMED TO BE LOCATED
THROUGHOUT THE BUILDING.
5 REMOVE ASBESTOS-CONTAINING GREEN MASTIC OF PERFORATED METAL PINS HOLDING FIBERGLASS INSULATION BOARDS TO THE EXTERIOR WALLS, AND UNDERNEATH THE SECOND FLOOR ENTRY
ALCOVES ONLY AS NECESSARY TO COMPLETE THE WORK.
6 REMOVE HEATING AND DOMESTIC WATER PIPING WITH FIBERGLASS INSULATION ON RUNS AND ASBESTOS-CONTAINING INSULATION ON FITTINGS, VALVES, ETC. PIPING IS EXPOSED AND CONCEALED ABOVE CEILINGS AND INSIDE WALLS. REMOVE ASBESTOS-CONTAINING GASKETS AND VALVE PACKINGS, ETC., INCLUDING ON SPRINKLER PIPING.
7 REMOVE ASBESTOS-CONTAINING INSULATION FROM ROOF DRAIN PIPING. PIPING IS EXPOSED AND CONCEALED ABOVE CEILINGS AND INSIDE WALLS. PIPING TO REMAIN AND BE RE-INSULATED.
8 REMOVE FIRE DOORS WITH ASBESTOS-CONTAINING INSULATION.
9 REMOVE BOILER WITH ASBESTOS-CONTAINING GASKETS, SEALANTS, AND ASSUMED ASBESTOS-CONTAINING REFRACTORY AND INSULATION AT THE BOILER BASE.
10 CREATE PENETRATIONS IN FOUNDATION WALLS WITH ASSUMED ASBESTOS-CONTAINING TARRY DAMPPROOFING AS NECESSARY TO COMPLETE PLANNED WORK.
11 CREATE PENETRATIONS AND REMOVE REMNANTS OF ORIGINAL ASBESTOS-CONTAINING BUILT-UP ROOFING WHICH IS ASSUMED TO BE PRESENT UNDER NEWER, NON-ASBESTOS ROOFING MATERIALS (INSTALLED IN 2011) AND REMOVE ASBESTOS-CONTAINING PATCHING TARS WHICH MAY BE PRESENT ON THE NON-ASBESTOS ROOFING MATERIALS, ONLY AS NECESSARY TO COMPLETE THE WORK.
12 REMOVE FLUORESCENT LIGHT FIXTURES WITH PCB-CONTAINING BALLASTS AND MERCURY-CONTAINING LIGHT TUBES. REMOVE THERMOSTATS, SWITCHES AND OTHER ELECTRICAL DEVICES CONTAINING
MERCURY.
13 REMOVE HID LIGHT FIXTURES WITH ASSUMED PCB-CONTAINING BALLASTS AND…