Attachment 14_Harris 100 percent drawings addendum.pdf

PDF 107 KB Posted

Attached to
Petersburg Office Consolidation
Solicitation number
1240BJ24R0018
Issued by

About this file

This document appears to be an attachment (Attachment 14_Harris 100 percent drawings addendum.pdf) related to a federal solicitation for the Petersburg Office Consolidation and Work Center Replacement project (Solicitation 1240BJ24R0018). The attachment provides detailed specifications and requirements for the renovation and construction work, including information on existing conditions, demolition, new construction, mechanical and electrical systems, and other related items. Key details include specifications for storage shelving, garage work benches, HVAC equipment, electrical systems, and exterior building modifications. The solicitation is being issued by the U.S. Department of Agriculture Forest Service, with a virtual pre-proposal meeting scheduled for July 25, 2024 and a question submission deadline of August 9, 2024. No substitution requests will be considered prior to award, and proposals must fully respond to the technical evaluation factors outlined in Section M.

View the file

Other files

File Type Posted
Attachment 17_AK0514ZZ 1988-06-14 - SPRINKLERS PLANS SECTION DETAIL.pdf PDF
Attachment 19_Addendum to model change for heat pumps.pdf PDF
Attachment 18_Wage Determination AK20240001 7.19.24.pdf PDF
Amendment 3 SF30 - 1240BJ24R0018.pdf PDF
Attachment 16_087100-DR-HDWR-SETS_REVISED_240813.pdf PDF
Attachment 15_RFIs_PDO Consolidation.pdf PDF
Amendment 2 - Summary of Changes.pdf PDF
Amendment 2 SF30 - 1240BJ24R0018.pdf PDF
Attachment 13_Fram 100 percent drawings addendum.pdf PDF
1240BJ24R0018 Amendment 1 - Solicitation Packet.pdf PDF
Attachment 12 - Guiding Principles checklist for PDO_info only.pdf PDF
Attachment 9 - Drawings_Harris Bldg Renovation 100 Percent.pdf PDF
1240BJ24R0018 Amendment 1 - SF30.pdf PDF
Attachment 11 - 01 25 00-RIB-Substitution Procedures.pdf PDF
Attachment 10 - Drawings_Fram Parking Expansion 100 Percent.pdf PDF
Attachment 3a - Harris Project Drawings 90 Percent.pdf PDF
1240BJ24R0018 Solicitation Packet.pdf PDF
Attachment 1 - PDO Project Drawings.pdf PDF
Attachment 6 - Past Performance.pdf PDF
Attachment 3b - Harris Drawings Addendum 90 Percent.pdf PDF
Attachment 8 - SF24 Bid Bond.pdf PDF
Attachment 5 - Wage Determination AK20240001.pdf PDF
Attachment 4 - Fram Project Drawings 90 Percent.pdf PDF
Attachment 2 - PDO Project Specifications.pdf PDF
Attachment 7 - RFI Template for PDO_Harris_Fram.xlsx XLSX spreadsheet
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# 1 2 3

Sheet Detail / Section Content

1 C.1 Existing paint storage locker Dimensions are 8'x12'

2 C.2 Washdown station Provide trench for underground electrical to washdown station, per Sheet E1.00.

3 C.2 Washdown station

Provide concrete or rock retaining wall, approx. 2 ft high and 20 ft long, on east side of washdown station, to maintain integrity of adjacent swale.

4 C.6 Detail 1 -

Washdown station details

Provide stainless steel or UHMW drain strainer for the 4" slab waste drain inlet, to prevent large items from entering wastewater line. Fasten strainer to drain inlet.

5 S3.01 Detail 7 - Typ Entry Conc

Pier

Delete notes requiring embedding 4x4 posts in concrete piers. Mount posts to slab via galvanized stand-off post bases, Simpson MPB44Z or approved equal.

6 S3.01

Details 5 and 6

- Rafter to

Beam Connections

Provide cedar beams and rafters, per Architectural sheets.

A0.01, Section

10 51 13 - Metal Lockers

Part 2.1 W - Earthquake

Load Delete and replace with "See S0.01 - Structural Design Data."

8 A2.11 Demo General Note D

Replace note with the following: "All interior spaces between Grid C and Grid J, excluding Janitor 104 and Fire Cache 105: Remove and dispose all contents not specified for retention, including all workstation and systems partitions, modular furniture, non-modular furniture, and equipment not specified for retention at Harris Building."

9 A2.11 Records

Room/Garage

Add the following note: "Remove and temporarily store contents, excluding storage racks. Disassemble storage racks and shelving and move to storage yard west of the building. After new storage cage shelving is installed, move temporarily stored items to new shelving."

10 A2.11 N0604 Add "siding and sheathing" to list of items to remove and dispose at overhead door.

11 A2.11 D3201 Add "deliver planter bed soil to COR-approved location on the Fram Compound"

12 A2.11 Stairs 110 Relocate AED from alcove under stairs to Level 2

13 A2.12 Demo General Note E

Replace note with the following: "All interior spaces between Grid G and Grid J, excluding Dispatch 209, Office 211, the alcove between Rooms 207 and 211, and the two workstations along Grid G and nearest Grid 1: Remove and dispose all contents not specified for retention, including all workstation and systems partitions, modular furniture, non-modular furniture, and equipment not specified for storage at Harris Building."

14 A2.12 Gen Office 206 Retain for reinstallation the five locking metal storage cabinets belonging to SO Aviation.

15 A2.12

Opening on Grid G between grids 1 and 2

Expand opening towards Grid 2 (to the east). Opening size shown on Sheet A2.14. Includes moving the workstation, currently near Grid G/2, towards the east approximately 2 ft to align workstation partition wall with finished face of expanded opening.

16 A2.13

Cages 4 - 11, Storage 109, and Heritage

The rectangles within the cages identify storage shelving. Storage shelving is specified on Sheet A0.01, Section 10 56 13, shall be of sufficient heigh so that the top shelf is 2 ft below the ceiling height, and shall be CFOI for Option

O-1006B, and CFCI for Option O-1006F.

17 A2.13 Cages 7 and 9 Coordinate cage wall locations and storage shelving installation with existing-to-remain oil-fired heater locations.

See Mech for oil-fired heater locations.

18 A2.13 Corridor near Grid G/7

Existing oil-fired heater to remain at Grid G/7. Locate the new cage wall for Cage 8 a needed to maintain 4'-0" clearance between the front of the heater and the new cage wall.

19 A2.13 F4 tag outside Cage 5 Delete tag.

20 A2.13 N3201 at new canopy Note applies to the ramp. See Structural for slab details.

21 A2.13 Garage 107 Provide a work bench against the wall on Grid C, between the new double door and the new telecom room, to match the new work benches on other walls of the garage.

22 A2.13 Garage 107 Install Government-furnished storage racks above work benches. Underside of lowest shelf to be 8 ft above finished floor. Top shelf to be 12 ft above finished floor. Secure racks to wall and floor using OSHA-approved method.

Petersburg Office Consolidation and Work Center Replacement - Solicitation 1240BJ24R0018

Harris 100% Drawings Addendum

Section Content

Petersburg Office Consolidation and Work Center Replacement - Solicitation 1240BJ24R0018

Harris 100% Drawings Addendum

23 A2.13

Swing door on Grid D (north wall of Garage 107)

Replace door with door type B-1. Dimensions to match existing. Not fire rated. Other door and frame specifications and hardware group: Match door (N)107.

24 A2.13 Mud Room 108 Delete EQ5 on west wall. Provide gear lockers on the west wall and in the alcove below Stairs 110. Basis of design for gear lockers: Petersburg District Office ready room lockers. Submit proposed product to COR for review.

25 A2.13 Mud Room 101C Delete EQ5. Furnish and install metal storage shelving behind door (N)101C.1.

26 A2.13 N2202 Replace "plumbing" with "domestic water"

27 A2.13 N2701 Replace all instances of "Telecom" with "Switches, servers, routers and other active equipment for telecom racks."

28 A2.14 Gen Office 205 Mount relocated AED near Grid F/7.

29 A2.14 Gen Office 206 Change Cage 12 geometry so that it's formed by a single wall on Grid H, from Grid 1 to the corner of the Dispatch office. Locate cage door immediately west of the column at Grid J/2.

30 A2.14 Cage 12 and LEO Storage

The rectangles within the cage and room identify storage shelving. Storage shelving is specified on Sheet A0.01, Section 10 56 13. Height: sufficient for top shelf to be 2 ft below the ceiling height. Anchor to floor per OSHA-approved method. Option O-1006B is for the contractor to furnish the shelving. Option O-1006F is for the contractor to install the shelving.

31 A2.14 LEO Storage 207 Keynote N0901 applies to this room.

32 A2.14 Gen Office 206 Keynote N0902 applies to this room, excluding the following areas:

1. Bounded by Gridlines 1 and 3, and by Gridline G and an east-west line 12 ft north of Gridline G.

2. Alcove between Rooms 207 and 211.

33 A2.14 N1002 Replace with "Metal storage cabinets, typ. of 5. OFCI."

34 A2.15 N0505 Replace all instances of "1x2 PT WD" with "2x4 cedar."

35 A4.01 N0504 Replace with "Inspect siding and patch holes as needed. Prep and paint patch to match existing siding color.

Painting siding is not required."

36 A4.01 Detail 2 - South Elevaion Add Keynote N0504

37 A4.02 N0504 Replace with "Inspect siding and patch holes as needed. Prep and paint patch to match existing siding color.

Painting siding is not required."

38 A9.03 Detail 1, tent drying system Center pipes between Grids A and B (above aisle), to avoid storage racks.

39 A10.01 General Exterior wall penetrations for garage supply air and exhaust air ducts and louvers: Submit proposed detail for COR review.

40 A10.01 Detail 1 - (N) Roof Canopy Provide downspout and fittings for gutter.

41 A10.01 Detail 1 - (N) Roof Canopy

Lower edge detail: Provide galvanized or painted drip flashing under roofing drip edge, to lap over gutter and under roofing panels.

42 A10.01 Detail 1 - (N) Roof Canopy Upper edge detail: 2x cedar subfascia.

43 A10.01 Detail 1 - (N) Roof Canopy

Provide 1x cedar gable fascia along outside roof rafter, tight to underside of roofing panels and extending down to 1 inch below bottom edge of roof rafter. Align lap joint with joints on eave fascia. Notch tight to beams. Provide roofing panel manufacturer's recommend gable flashing product.

44 A12.01 Door and

Frame Schedule

(N)107: Provide 2 hour fire door.

45 A12.01 Door Type Legend

Type B3 (cage door): Submit shop drawing for plywood door for storage cages, to coordinate with cage wall opening.

46 M1.01 Oil-fired heaters

For reference: In addition to the oil-fired heaters shown on the drawings, there are existing-to-remain oil-fired heaters at the following locations:

1. South wall of Shop 101A, immediately west of the exterior swing door on the south elevation.

2. West wall of Storage 112, immediately south of Grid H.

3. East wall of Storage 111, immediately south of Grid G.

47 M1.01 General All mechanical items are existing-to-remain, unless noted otherwise.

48 M1.01 Demo note 1 Delete "may" from the sentence "lines may originate in the ceiling space…" The Government verifed the domestic water lines originate in the ceilings above Rooms 102 and 103.

49 M1.01 Demo note 2 Add "including exterior unit."

Section Content

Petersburg Office Consolidation and Work Center Replacement - Solicitation 1240BJ24R0018

Harris 100% Drawings Addendum

50 M1.01 Demo note 3 Add "Existing small electric heater to remain."

51 M3.01 Sheet Note 1, fifth sentence Delete "or over."

52 M4.01 Shop 101 Locate CU-1 on Grid C, between Vest 101B and Cage 3.

53 M5.01 Detail 2 - Non-freeze hose bibb

3/4" PEX CW line may be surface mounted on interior face of wall(s).

54 E0.02 P2 and P5 panel schedules

Per E6.00: Feed P5 from MDP. Feed P2 from P5.

55 E1.31 Demolition Notes

Add note 11: Relocate existing security camera system equipment to new telecom room. Intercept, extend, and reconnect existing cameras to new location, coordinate exact location with COR.

56 E1.32 Gen Office 206 Add callout for Note 7 to the two clusters of J-boxes on north side of Grid G (near Grid 1 and near Grid 3).

57 E1.32 Gen Office 201, J-boxes. Add callout for Note 7 to this cluster of J-boxes.

58 E3.01 Mud Room 101C Locate new telecom receptacle (shown elsewhere in this room) between refrigerators and the exterior door.

59 E3.01 Garage 107 Provide three additional duplex power receptacles, normal power, GFI, mounted +42" AFF along south wall (Grid C) for work bench. Feed receptacles from P5.

60 E3.01 Garage 107 Provide wireless access point.

61 E3.01 Mud Room 108 Locate new telecom receptacle (shown elsewhere in this room) between exterior doors and Grid D.

62 E3.01 Mud Room 108 Provide wireless access point.

63 E3.01 Storage 111 Provide wireless access point in eastern portion of room.

64 E3.01 Storage 112 Locate new telecom receptacle (shown elsewhere in this room) adjacent to west side of new exterior door.

65 E3.02 Gen Office 206 Add two clusters of two J-box symbols to north side of Grid G (same locations as sheet E1.32).

Comment Tracker

File details come from the government source that posted it. Updated .