Attachment 2d - Design Submittal Requirements.pdf

PDF 656 KB Posted

Attached to
Facility Exhaust System
Solicitation number
FA910125RB001
Issued by

About this file

Attachment 2d is a detailed Design Submittal Requirements document for the Facility Exhaust System federal contract, specifying folder format and content requirements across multiple design stages (10%, 30%, 60%, 90%, and 100%). The document outlines a comprehensive set of deliverables for each design phase, including SOO and Contractor SOW, Technical Requirements Document (TRD), site plans, hazard analyses, design narratives, design drawings, purchase items, schedules, risk registers, participant lists, approvals, and additional documentation such as Verification, Validation and Acceptance (VV&A) Plans, spare parts lists, operations and maintenance documentation, and training requirements.

Each design stage requires progressively more detailed documentation, with consistent folder structure and content expectations. Key documents include Process Flow Diagrams (PFD), Piping and Instrumentation Diagrams (P&ID), schematics, layouts, analysis, calculations, early buy specifications, risk assessment matrices, and technical review records. The requirements are part of the FA910-125-R-B001 solicitation for the Air Force Test Center Arnold Engineering Development Complex, aiming to ensure comprehensive and structured design documentation throughout the project lifecycle.

View the file

Other files

File Type Posted
Solicitation Amendment FA910125RB0010002 SF 30.pdf PDF
Attachment 2 - Technical Requirements Document_Amend2.pdf PDF
Attachment 2e - AEDC Design Review Flow and Expectations.pdf PDF
Attachment 4 Section L_Amend2.pdf PDF
Attachment 1 - Statement of Objectives_Amend2.pdf PDF
Attachment 14 Section M_Amend2.pdf PDF
Attachment 12 L-8 - Requirements Matrix_Amend2.pdf PDF
Solicitation Amendment FA910125RB0010001 SF 30.pdf PDF
FA910125RB001 Facility Exhaust System QandA 20May25.pdf PDF
Raw Water Analysis Report 7-13-12.pdf PDF
Attachment 2b - Reference Drawings.pdf PDF
Attachment 2c - SHE and Eng Standards.pdf PDF
Attachment 7 L-3 PPQ Cover Letter.pdf PDF
Attachment 10 L-6 Relevancy Matrix.xlsx XLSX spreadsheet
Attachment 11 L-7 Initial Order Pricing Sheet.xlsx XLSX spreadsheet
Solicitation - FA910125RB001.pdf PDF
Attachment 2a - Exhaust Boundary Utility Interface.pdf PDF
Facility Exhaust System RFP Cover Letter.pdf PDF
Attachment 1 - Statement of Objectives.pdf PDF
Attachment 2 - Technical Requirements Document.pdf PDF
Attachment 3 - DD1423 CDRL Template.pdf PDF
Attachment 4 Section L.pdf PDF
Attachment 6 L-2 Past and Present Performance Questionnaire.pdf PDF
Attachment 9 L-5 Subcontractor Consent Letter.pdf PDF
Attachment 13 L-9 SB Participation Commitment Document.pdf PDF
Attachment 5 L-1 PPI Tool Instructions.pdf PDF
Attachment 12 L-8 - Requirements Matrix.pdf PDF
Attachment 14 Section M.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Folder Format Requirements

01 SOO and Contractor SOW SOO and Contractor SOW with any requested revisions

02 TRD TRD with any requested revisions

03 Site Plan and/or Project Plan

Site Plan (Real Property) - Drawing of site showing project Location with Respect to Environmental boundary

04 Hazard Analyses

Hazard Analyses (HA)- Assessment with list of possible hazards, list of hazards that can be minimized or eliminated by design.

05 Design Narrative

10% Design Narrative-Includes scope with clear boundaries, initial materials selections, basic system sizing, and trade studies for the concepts considered. This would also include recommendation for the proposed concepts.

06 Design Drawings

10% Design Drawings- Include Process Flow Diagram (PFD), Piping and Instrumentation Diagram

(P&ID), schematics, single lines, layouts (major equipment / buildings), analysis, calculations performed to support design, Specifications for early buys, cut sheets of commercial off-the shelf (COTS) Products if requesting early-buy items.

07 Purchase Items List of buy items which will need to be procured ASAP.

08 Schedule Programmatic Documentation - Project schedule for the affected work

09 Risk Register Risk Assessment Matrix - List of cost, schedule and technical for risks and mitigations

10 Participant List

List of participants to include roles and responsibilities (This list is the personnel that participated in the meeting not a generic list of personnel)

11 Approval

AEDC-1683 Form – Technical Review Record

AEDC-1565 Form – Deficiency Summary List

99 Comments Comments sheet for design reviews

Design Review Presentation 10% Design presentation and data location for review

Facility Exhaust System 10% Design Submittal Requirements

Facility Exhaust System

FA9101-25-R-B001

Attachment 2d

01 SOO and Contractor SOW SOO and Contractor SOW with proposed revisions

02 TRD TRD with proposed Revisions

03 Site Plan and/or Project Plan

Site Plan (Real Property) - Drawing of site showing project Location with Respect to EIA boundary

04 Hazard Analyses

Hazard Analyses (HA)- Assessment with list of possible hazards, list of hazards that can be minimized or eliminated by design.

05 Design Narrative

30% Design Narrative-Includes scope with clear boundaries, initial materials selections, basic system sizing, and trade studies for the concepts considered. This would also include recommendation for the proposed concepts.

06 Design Drawings

30% Design Drawings- Include Process Flow Diagram (PFD), Piping and

Instrumentation Diagram (P&ID), schematics, single lines, layouts (major equipment

/ buildings), analysis, calculations performed to support design, Specifications for early buys, cut sheets of commercial off-the shelf (COTS) Products if requesting early-buy items.

06 Design Drawings

PDR Design Drawings- Include updated PFD and P&ID/schematics, single lines (if applicable), preliminary layouts (major equipment / buildings), preliminary analysis and/or calculations performed to support design, Specifications for early buys, cut sheets of commercial off-the shelf (COTS) Products if requesting early-buy items

07 Purchase Items List of buy items which will need to be procured ASAP.

08 Schedule Programmatic Documentation - Project schedule for the affected work

09 Risk Register

Risk Assessment Matrix - List of cost, schedule and technical for risks and mitigations

10 Participant List

List of participants to include roles and responsibilities (This list is the personnel that participated in the meeting not a generic list of personnel)

11 Approval

AEDC-1683 Form – Technical Review Record

AEDC-1565 Form – Deficiency Summary List

99 Comments Comments sheet for design reviews

Design Review Presentation 30% Design presentation and data location for review

Facility Exhaust System 30% Design Submittal Requirements

Facility Exhaust System

FA9101-25-R-B001

02 TRD TRD with proposed Revisions

03 Site Plan and/or Project Plan Site Plan (Real Property) - Drawing of site showing project Location with Respect to EIA boundary

04 Hazard Analyses

Hazard Analyses (HA)- Assessment with list of possible hazards, list of hazards that can be minimized or eliminated by design.

05 Design Narrative

60% Design Narrative-Includes scope with clear boundaries, initial materials selections, basic system sizing, and trade studies for the concepts considered. This would also include recommendation for the proposed concepts.

06 Design Drawings

60% Design Drawings- Include Process Flow Diagram (PFD), Piping and Instrumentation Diagram

(P&ID), schematics, single lines, layouts (major equipment / buildings), analysis, calculations performed to support design, Specifications for early buys, cut sheets of commercial off-the shelf (COTS) Products if requesting early-buy items.

07 Purchase Items List of buy items which will need to be procured ASAP.

08 Schedule Programmatic Documentation - Project schedule for the affected work

09 Risk Register Risk Assessment Matrix - List of cost, schedule and technical for risks and mitigations

10 Participant List

List of participants to include roles and responsibilities (This list is the personnel that participated in the meeting not a generic list of personnel)

11 Approval

AEDC-1683 Form – Technical Review Record

AEDC-1565 Form – Deficiency Summary List

99 Comments Comments sheet for design reviews

Design Review Presentation 60% Design presentation and data location for review

Facility Exhaust System 60% Design Submittal Requirements

Facility Exhaust System

FA9101-25-R-B001

02 TRD TRD with proposed Revisions

03 Site Plan and/or Project Plan Site Plan (Real Property) - Drawing of site showing project Location with Respect to EIA boundary

04 Hazard Analyses

Hazard Analyses (HA)- Assessment with list of possible hazards, list of hazards that can be minimized or eliminated by design.

05 Design Narrative

90% Design Narrative-Includes scope with clear boundaries, initial materials selections, basic system sizing, and trade studies for the concepts considered. This would also include recommendation for the proposed concepts.

06 Design Drawings

90% Design Drawings- Include Process Flow Diagram (PFD), Piping and Instrumentation Diagram

(P&ID), schematics, single lines, layouts (major equipment / buildings), analysis, calculations performed to support design, Specifications for early buys, cut sheets of commercial off-the shelf (COTS) Products if requesting early-buy items.

07 Purchase Items List of buy items which will need to be procured ASAP.

08 Schedule Programmatic Documentation - Project schedule for the affected work

09 Risk Register Risk Assessment Matrix - List of cost, schedule and technical for risks and mitigations

10 Participant List

List of participants to include roles and responsibilities (This list is the personnel that participated in the meeting not a generic list of personnel)

11 Approval

AEDC-1683 Form – Technical Review Record

AEDC-1565 Form – Deficiency Summary List

13 VV&A

Verification, Validation and Acceptance Plan (VV&A) – 60% draft plan with verification events, success criteria.

16 Outage Requests

Outage request(s) as required for AEDC system tie-in related outages (if applicable for the subsystem under CDR review).

17 Spare Parts List of recommended spare parts with quantities, lead-times, extended cost and justification

19 Operations & Maintenance O&M Documentation – O&M Plan

20 Training Requirements Training requirements and plan in high level draft format

99 Comments Comments sheet for design reviews

Design Review Presentation 90% Design presentation and data location for review

Facility Exhaust System 90% Design Submittal Requirements

Facility Exhaust System

FA9101-25-R-B001

02 TRD TRD with proposed Revisions

03 Site Plan and/or Project Plan Site Plan (Real Property) - Drawing of site showing project Location with Respect to EIA boundary

04 Hazard Analyses

Hazard Analyses (HA)- Assessment with list of possible hazards, list of hazards that can be minimized or eliminated by design.

05 Design Narrative

100% Design Narrative-Includes scope with clear boundaries, initial materials selections, basic system sizing, and trade studies for the concepts considered. This would also include recommendation for the proposed concepts.

06 Design Drawings

100% Design Drawings- Include Process Flow Diagram (PFD), Piping and Instrumentation Diagram

(P&ID), schematics, single lines, layouts (major equipment / buildings), analysis, calculations performed to support design, Specifications for early buys, cut sheets of commercial off-the shelf

(COTS) Products if requesting early-buy items.

07 Purchase Items List of remaining procurement items

08 Schedule Programmatic Documentation - Project schedule for the affected work

09 Risk Register Risk Assessment Matrix - List of cost, schedule and technical for risks and mitigations

10 Participant List

List of participants to include roles and responsibilities (This list is the personnel that participated in the meeting not a generic list of personnel)

11 Approval

AEDC-1683 Form – Technical Review Record

AEDC-1565 Form – Deficiency Summary List

13 VV&A

Verification, Validation and Acceptance Plan (VV&A) – 90% draft plan with verification events, success criteria.

16 Outage Requests

Outage request(s) as required for AEDC system tie-in related outages (if applicable for the subsystem under CDR review).

17 Spare Parts List of recommended spare parts with quantities, lead-times, extended cost and justification

19 Operations & Maintenance O&M Documentation – O&M Plan

20 Training Requirements Training requirements and plan in high level draft format

99 Comments Comments sheet for design reviews

Design Review Presentation 100% Design presentation and data location for review

Facility Exhaust System 100% Design Submittal Requirements

Facility Exhaust System

FA9101-25-R-B001

File details come from the government source that posted it. Updated .