About this file

This is a Bid Pricing Form for the City of Portland, Oregon, for elevator modernization and maintenance services across five locations. The project encompasses modernization of six elevators total: three geared traction passenger elevators at the 1900 Building (1900 SW 4th Avenue), one hydraulic elevator at East Precinct (737 SE 106th Avenue), one hydraulic elevator at North Precinct (499 NE Emerson Street), one hydraulic elevator at Portland Communication Center (3732 SE 99th Avenue), and one hydraulic elevator at St. John's Building (7214 N. Philadelphia Avenue). The scope of work includes full modernization of elevators, electrical and fire life safety work, cab interior finishes, and two-year warranty preventive maintenance commencing upon Owner and State of Oregon Elevator Inspector acceptance. The project will be executed as a turnkey operation with construction schedules beginning at week 0 upon contract signing and Notice to Proceed, with shop drawing submission and consultant review required during initial weeks. Bids are irrevocable for sixty calendar days following the bid opening date.

The bid form requires pricing for three sections: base modernization costs, electrical and fire life safety work by others, and cab interior allowances. The 1900 Building includes a $60,000 cab interior allowance, while the four remaining locations each include $20,000 cab interior allowances, with actual costs subject to change order adjustment based on final material selections. Monthly preventive maintenance costs must be submitted for each elevator for the two-year warranty period. The Portland Communication Center form includes an Alternate 2 option for expedited schedule pricing to reduce elevator downtime. This project is subject to BOLI prevailing wage requirements using April 5, 2025 prevailing wage rates. The contractor must comply with all applicable codes, regulations, manufacturer instructions, and contract documents, with no additional change orders permitted above bid pricing except as contractually allowed.

View the file

Other files

File Type Posted
Addendum 03 ITB 00002596 Add Attachment 6.pdf PDF
Attachment 5 PPB Background Check Forms.pdf PDF
Exhibit E1 Portland Communication Center As Builts.pdf PDF
Exhibit D North Precinct Building Technical Specifications.pdf PDF
Attachment 6 - Exceptions and Deviations to the Sample Contract.docx DOCX document
Notice of Cancellation for ITB 2596.pdf PDF
Addendum 01 ITB 00002596 Update PreBid Meeting and Close Date.pdf PDF
Exhibit A Standard Goods and Services Contract.pdf PDF
Exhibit C1 City East Precinct Building As Builts.pdf PDF
Exhibit F Alternate 1 - St. Johns Building Technical Specification.pdf PDF
ITB 00002596 Elevator Modernization Construction.pdf PDF
ITB 00002596 Elevator Modernization Summary.pdf PDF
Exhibit D1 North Precinct Building As Builts.pdf PDF
Exhibit E Portland Communication Center Technical Specifications.pdf PDF
Addendum 02 ITB 00002596 Update Close Date and Documents.pdf PDF
Attachment 4 - Buyspeed Submittal Instructions.pdf PDF
Addendum 04 ITB 00002596 Scope of Work Clarifications.pdf PDF
Notice of Intent to Award ITB 2596.pdf PDF
Exhibit C City East Precinct Building Technical Specifications.pdf PDF
Exhibit B City 1900 Building Technical Specifications.pdf PDF
ITB 00002596 Elevator Modernization Bid Receipt Record.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1900 Building

ERROR:#VALUE!
1900 Building

1900 SW 4th Avenue, Portland, OR 97201

ELEVATOR MODERNIZATION & MAINTENANCE FOR THREE (3) GEARED TRACTION PASSENGER ELEVATORS
BID FORM

SECTION 1: MODERNIZATION

A.Base Bid for Full Modernization of Three (3) Geared Traction Passenger Elevators$ - 0
See technical specifications for required scope of work
Do Not Include the following in Base Bid:
*Item B below
*Item C below
*Warranty elevator preventive maintenance
B.Electrical/Fire Life Safety/Misc. Work by Others$ - 0
See technical specifications for required scope of work
C.Cab Interior Allowance$60,000
See technical specfor required scope of work. Include all labor and materials. Allowance will be adjusted based on final selection of finishes. Elevator Contractor shall provide documentation of cost after material selection by Owner, with a contract change order (additive or deductive) to reflect actual cost of the selected cab materials.

TOTAL MODERNIZATION COST (sum of Item A, Item B, Item C) $ 60,000.00

SECTION 2: MAINTENANCE
A.Two Year Warranty Elevator Preventive Maintenance
Warranty Preventive Maintenance will commence when all elevators have been accepted by the Owner, State of Oregon Elevator Inspector and Consultant., which also includes the Elevator Contractor’s completion of all punch list items required by the Elevator Inspector and Consultant. The scope of work required for the Warranty Elevator Preventive Maintenance shall be as stated in technical specifications - item 1.10
Total Cost per Month
Elevator 1$ - 0
Elevator 2$ - 0
Elevator 3$ - 0
SECTION 3: SCHEDULE / DURATIONS
A.Elevator Installation Schedule
The construction schedule will begin at week 0, which is when a Contract is signed and a Notice to Proceed is issued by Owner. All elevator schedules for the elevator out of service shall be approved by Owner and Consultant.
Weeks from
Duration in weeks (from NTP)NTP
Provide Shop Drawings and Submittals0
Add 1 week for consultant review1
Equipment on site0
Start Elevator 10
Complete Elevator 10
Start Elevator 2
Complete Elevator 2
Start Elevator 3
Complete Elevator 3

ADDENDA/CLARIFICATIONS

Contract Clarifications/Exceptions:Choose One
Addendums Received:Choose One
Elevator Contractor:
Name:
Phone:
Email:
Signature of Authorization for the

above price and delivery as specified:

An Offeror submitting a bid certifies that no officer, agent or employee of the City who has a pecuniary interest in this bid has participated in preparation of the bid, that the bid is made in good faith without fraud, collusion, or connection of any kind with any other Offeror of the same call for bids, and that the Offeror is competing solely in its own behalf without connection with, or obligation to any undisclosed person or firm.
END OF BID FORM
Choose One
Attached
No Exceptions/Clarifications
1
2
3
4
5
6
0
Choose One

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

This project will be a BOLI prevailing wage project and April 5, 2025 prevailing wage costs are to be used in estimating project costs. Contractor shall conform to current industry standards and shall comply with all Manufacturer’s instructions.

The undersigned having full knowledge of the specifications for the item(s) listed herein offers and agrees that this bid shall be irrevocable for at least sixty (60) calendar days after the bid opening date and time, and if accepted shall furnish any and/or all items(s) at the prices offered, all required documents, licenses and certifications, guarantees, titles and warranties as required and deliver at the designated point(s) within the time specified in the schedule.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in EXHIBIT B, DIVISION 14 SECTION 14 21 00 TECHNICAL SPECIFICATIONS FOR MODERNIZATION OF THREE (3) GEARED TRACTION PASSENGER ELEVATORS AT 1909 BUILDING, 1900 SW FOURTH AVE. PORTLAND, OR 97201

East Precinct

ERROR:#VALUE!
EAST PRECINCT

737 SE 106th Avenue, Portland, OR 97216

ELEVATOR MODERNIZATION & MAINTENANCE FOR ONE (1) HYDRAULIC PASSENGER ELEVATOR
BID FORM

SECTION 1: MODERNIZATION

A.Base Bid for Full Modernization of One (1) Hydraulic Elevator$ - 0
See technical specifications for required scope of work
Do Not Include the following in Base Bid:
*Item B below
*Item C below
*Warranty elevator preventive maintenance
B.Electrical/Fire Life Safety/Misc. Work by Others$ - 0
See technical specifications for required scope of work
C.Cab Interior Allowance$20,000
See technical specfor required scope of work. Include all labor and materials. Allowance will be adjusted based on final selection of finishes. Elevator Contractor shall provide documentation of cost after material selection by Owner, with a contract change order (additive or deductive) to reflect actual cost of the selected cab materials.

TOTAL MODERNIZATION COST (sum of Item A, Item B, Item C) $ 20,000.00

SECTION 2: MAINTENANCE
A.Two Year Warranty Elevator Preventive Maintenance
Warranty Preventive Maintenance will commence when all elevators have been accepted by the Owner, State of Oregon Elevator Inspector and Consultant., which also includes the Elevator Contractor’s completion of all punch list items required by the Elevator Inspector and Consultant. The scope of work required for the Warranty Elevator Preventive Maintenance shall be as stated in technical specifications - item 1.10
Total Cost per Month
Elevator 1$ - 0
SECTION 3: SCHEDULE / DURATIONS
A.Elevator Installation Schedule
The construction schedule will begin at week 0, which is when a Contract is signed and a Notice to Proceed is issued by Owner. All elevator schedules for the elevator out of service shall be approved by Owner and Consultant.
Weeks from
Duration in weeks (from NTP)NTP
Provide Shop Drawings and Submittals0
Add 1 week for consultant review1
Equipment on site0
Start Elevator 10
Complete Elevator 10

ADDENDA/CLARIFICATIONS

Contract Clarifications/Exceptions:Choose One
Addendums Received:Choose One
Elevator Contractor:
Name:
Phone:
Email:
Signature of Authorization for the

above price and delivery as specified:

An Offeror submitting a bid certifies that no officer, agent or employee of the City who has a pecuniary interest in this bid has participated in preparation of the bid, that the bid is made in good faith without fraud, collusion, or connection of any kind with any other Offeror of the same call for bids, and that the Offeror is competing solely in its own behalf without connection with, or obligation to any undisclosed person or firm.
END OF BID FORM
Choose One
Attached
No Exceptions/Clarifications
1
2
3
4
5
6
0
Choose One

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

This project will be a BOLI prevailing wage project and April 5, 2025 prevailing wage costs are to be used in estimating project costs. Contractor shall conform to current industry standards and shall comply with all Manufacturer’s instructions.

The undersigned having full knowledge of the specifications for the item(s) listed herein offers and agrees that this bid shall be irrevocable for at least sixty (60) calendar days after the bid opening date and time, and if accepted shall furnish any and/or all items(s) at the prices offered, all required documents, licenses and certifications, guarantees, titles and warranties as required and deliver at the designated point(s) within the time specified in the schedule.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in EXHIBIT C, DIVISION 14 SECTION 14 24 00 TECHNICAL SPECIFICATIONS FOR MODERNIZATION OF ONE (1) HYDRAULIC PASSENGER ELEVATOR AT COP EAST PRECINCT, 737 SE 106TH AVE. PORTLAND, OR 97216

North Precinct

ERROR:#VALUE!
NORTH PRECINCT

499 NE Emerson St. Portland, OR 97211

ELEVATOR MODERNIZATION & MAINTENANCE FOR ONE (1) HYDRAULIC PASSENGER ELEVATOR
BID FORM

SECTION 1: MODERNIZATION

A.Base Bid for Full Modernization of One (1) Hydraulic Elevator$ - 0
See technical specifications for required scope of work
Do Not Include the following in Base Bid:
*Item B below
*Item C below
*Warranty elevator preventive maintenance
B.Electrical/Fire Life Safety/Misc. Work by Others$ - 0
See technical specifications for required scope of work
C.Cab Interior Allowance$20,000
See technical specfor required scope of work. Include all labor and materials. Allowance will be adjusted based on final selection of finishes. Elevator Contractor shall provide documentation of cost after material selection by Owner, with a contract change order (additive or deductive) to reflect actual cost of the selected cab materials.

TOTAL MODERNIZATION COST (sum of Item A, Item B, Item C) $ 20,000.00

SECTION 2: MAINTENANCE
A.Two Year Warranty Elevator Preventive Maintenance
Warranty Preventive Maintenance will commence when all elevators have been accepted by the Owner, State of Oregon Elevator Inspector and Consultant., which also includes the Elevator Contractor’s completion of all punch list items required by the Elevator Inspector and Consultant. The scope of work required for the Warranty Elevator Preventive Maintenance shall be as stated in technical specifications - item 1.10
Total Cost per Month
Elevator 1$ - 0
SECTION 3: SCHEDULE / DURATIONS
A.Elevator Installation Schedule
The construction schedule will begin at week 0, which is when a Contract is signed and a Notice to Proceed is issued by Owner. All elevator schedules for the elevator out of service shall be approved by Owner and Consultant.
Weeks from
Duration in weeks (from NTP)NTP
Provide Shop Drawings and Submittals0
Add 1 week for consultant review1
Equipment on site0
Start Elevator 10
Complete Elevator 10

ADDENDA/CLARIFICATIONS

Contract Clarifications/Exceptions:Choose One
Addendums Received:Choose One
Elevator Contractor:
Name:
Phone:
Email:
Signature of Authorization for the

above price and delivery as specified:

An Offeror submitting a bid certifies that no officer, agent or employee of the City who has a pecuniary interest in this bid has participated in preparation of the bid, that the bid is made in good faith without fraud, collusion, or connection of any kind with any other Offeror of the same call for bids, and that the Offeror is competing solely in its own behalf without connection with, or obligation to any undisclosed person or firm.
END OF BID FORM
Choose One
Attached
No Exceptions/Clarifications
1
2
3
4
5
6
0
Choose One

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

This project will be a BOLI prevailing wage project and April 5, 2025 prevailing wage costs are to be used in estimating project costs. Contractor shall conform to current industry standards and shall comply with all Manufacturer’s instructions.

The undersigned having full knowledge of the specifications for the item(s) listed herein offers and agrees that this bid shall be irrevocable for at least sixty (60) calendar days after the bid opening date and time, and if accepted shall furnish any and/or all items(s) at the prices offered, all required documents, licenses and certifications, guarantees, titles and warranties as required and deliver at the designated point(s) within the time specified in the schedule.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in EXHIBIT D, DIVISION 14 SECTION 14 24 00 TECHNICAL SPECIFICATIONS FOR MODERNIZATION OF ONE (1) HYDRAULIC PASSENGER ELEVATOR AT COP NORTH PRECINCT, 499 NE EMERSON ST. PORTLAND, OR 97211.

Portland Comm Center-incl Alt 2

ERROR:#VALUE!
PORTLAND COMMUNICATION CENTER

3732 SE 99th Avenue, Portland, OR 97266

ELEVATOR MODERNIZATION & MAINTENANCE FOR ONE (1) HYDRAULIC PASSENGER ELEVATOR
BID FORM

SECTION 1: MODERNIZATION

A.Base Bid for Full Modernization of One (1) Hydraulic Elevator$ - 0
See technical specifications for required scope of work
Do Not Include the following in Base Bid:
*Item B below
*Item C below
*Warranty elevator preventive maintenance
B.Electrical/Fire Life Safety/Misc. Work by Others$ - 0
See technical specifications for required scope of work
C.Cab Interior Allowance$20,000
See technical specfor required scope of work. Include all labor and materials. Allowance will be adjusted based on final selection of finishes. Elevator Contractor shall provide documentation of cost after material selection by Owner, with a contract change order (additive or deductive) to reflect actual cost of the selected cab materials.

TOTAL MODERNIZATION COST (sum of Item A, Item B, Item C) $ 20,000.00

SECTION 2: MAINTENANCE
A.Two Year Warranty Elevator Preventive Maintenance
Warranty Preventive Maintenance will commence when all elevators have been accepted by the Owner, State of Oregon Elevator Inspector and Consultant., which also includes the Elevator Contractor’s completion of all punch list items required by the Elevator Inspector and Consultant. The scope of work required for the Warranty Elevator Preventive Maintenance shall be as stated in technical specifications - item 1.10
Total Cost per Month
Elevator 1$ - 0
SECTION 3: SCHEDULE / DURATIONS
A.Elevator Installation Schedule
The construction schedule will begin at week 0, which is when a Contract is signed and a Notice to Proceed is issued by Owner. All elevator schedules for the elevator out of service shall be approved by Owner and Consultant.
Weeks from
Duration in weeks (from NTP)NTP
Provide Shop Drawings and Submittals0
Add 1 week for consultant review1
Equipment on site0
Start Elevator 10
Complete Elevator 10

SECTION 4: ALTERNATES

A.Alternate 2 - Expedited Schedule
Provide pricing for expedited work schedule to reduce elevator downtime. Include specific amount of consecutive days elevator will be out of service.
# of consecutive days that elevator will be out of service
Add alternate pricing for expedited schedule$ - 0

ADDENDA/CLARIFICATIONS

Contract Clarifications/Exceptions:Choose One
Addendums Received:Choose One
Elevator Contractor:
Name:
Phone:
Email:
Signature of Authorization for the

above price and delivery as specified:

An Offeror submitting a bid certifies that no officer, agent or employee of the City who has a pecuniary interest in this bid has participated in preparation of the bid, that the bid is made in good faith without fraud, collusion, or connection of any kind with any other Offeror of the same call for bids, and that the Offeror is competing solely in its own behalf without connection with, or obligation to any undisclosed person or firm.
END OF BID FORM
Choose One
Attached
No Exceptions/Clarifications
1
2
3
4
5
6
0
Choose One

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

This project will be a BOLI prevailing wage project and April 5, 2025 prevailing wage costs are to be used in estimating project costs. Contractor shall conform to current industry standards and shall comply with all Manufacturer’s instructions.

The undersigned having full knowledge of the specifications for the item(s) listed herein offers and agrees that this bid shall be irrevocable for at least sixty (60) calendar days after the bid opening date and time, and if accepted shall furnish any and/or all items(s) at the prices offered, all required documents, licenses and certifications, guarantees, titles and warranties as required and deliver at the designated point(s) within the time specified in the schedule.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in EXHIBIT E, DIVISION 14 SECTION 14 24 00 TECHNICAL SPECIFICATIONS FOR MODERNIZATION OF ONE (1) HYDRAULIC PASSENGER ELEVATOR AT PORTLAND COMMUNICATION CENTER, 3732 SE 99TH AVENUE, PORTLAND, OR.

Alternate 1 - St. John's

ERROR:#VALUE!
St. John's Building

7214 N. Philadelphia Ave, Portland, OR 97203

ELEVATOR MODERNIZATION & MAINTENANCE FOR ONE (1) HYDRAULIC PASSENGER ELEVATOR
BID FORM

tc={AA40A8DC-1433-4EAF-A396-4D7B59ABA811}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

somewhere on this form we need to note that this site's pricing is bid alternate 1

SECTION 1: MODERNIZATION

A.Base Bid for Full Modernization of One (1) Hydraulic Elevator$ - 0
See technical specifications for required scope of work
Do Not Include the following in Base Bid:
*Item B below
*Warranty elevator preventive maintenance
B.Electrical/Fire Life Safety/Misc. Work by Others$ - 0
See technical specifications for required scope of work

TOTAL MODERNIZATION COST (sum of Item A, Item B) $ - 0

SECTION 2: MAINTENANCE
A.Two Year Warranty Elevator Preventive Maintenance
Warranty Preventive Maintenance will commence when all elevators have been accepted by the Owner, State of Oregon Elevator Inspector and Consultant., which also includes the Elevator Contractor’s completion of all punch list items required by the Elevator Inspector and Consultant. The scope of work required for the Warranty Elevator Preventive Maintenance shall be as stated in technical specifications - item 1.10
Total Cost per Month
Elevator 1$ - 0
Elevator 2$ - 0
Elevator 3$ - 0
SECTION 3: SCHEDULE / DURATIONS
A.Elevator Installation Schedule
The construction schedule will begin at week 0, which is when a Contract is signed and a Notice to Proceed is issued by Owner. All elevator schedules for the elevator out of service shall be approved by Owner and Consultant.
Weeks from
Duration in weeks (from NTP)NTP
Provide Shop Drawings and Submittals0
Add 1 week for consultant review1
Equipment on site0
Start Elevator 10
Complete Elevator 10
Start Elevator 2
Complete Elevator 2
Start Elevator 3
Complete Elevator 3

ADDENDA/CLARIFICATIONS

Contract Clarifications/Exceptions:Choose One
Addendums Received:Choose One
Elevator Contractor:
Name:
Phone:
Email:
Signature of Authorization for the

above price and delivery as specified:

An Offeror submitting a bid certifies that no officer, agent or employee of the City who has a pecuniary interest in this bid has participated in preparation of the bid, that the bid is made in good faith without fraud, collusion, or connection of any kind with any other Offeror of the same call for bids, and that the Offeror is competing solely in its own behalf without connection with, or obligation to any undisclosed person or firm.
END OF BID FORM
Choose One
Attached
No Exceptions/Clarifications
1
2
3
4
5
6
0
Choose One

somewhere on this form we need to note that this site's pricing is bid alternate 1

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

FORM OF PROPOSAL FOR MODERNIZATION AND PREVENTIVE MAINTENANCE ON

VERTICAL TRANSPORTATION EQUIPMENT

This project shall be completed entirely by the Elevator Contractor as a TURNKEY project. No extra cost or change orders shall be allowed above bid pricing, except as allowed by the terms of this Contract. Elevator Contractor accepts full responsibility for the entire Elevator Project to be completed as per all Contract Documents and in full compliance with all codes, regulations and rules that are in force at the date stated on the Contract Documents.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in the Elevator Modernization and Maintenance Contract Documents.

This project will be a BOLI prevailing wage project and April 5, 2025 prevailing wage costs are to be used in estimating project costs. Contractor shall conform to current industry standards and shall comply with all Manufacturer’s instructions.

The undersigned having full knowledge of the specifications for the item(s) listed herein offers and agrees that this bid shall be irrevocable for at least sixty (60) calendar days after the bid opening date and time, and if accepted shall furnish any and/or all items(s) at the prices offered, all required documents, licenses and certifications, guarantees, titles and warranties as required and deliver at the designated point(s) within the time specified in the schedule.

The undersigned agrees to provide all engineering, tools, labor, materials and all services necessary for the completion of all work indicated and subject to all terms and conditions as stated in EXHIBIT F, DIVISION 14 SECTION 14 24 00 TECHNICAL SPECIFICATIONS FOR MODERNIZATION OF ONE (1) HYDRAULIC PASSENGER ELEVATOR AT COP ST. JOHN'S BUILDING, 7214 N. PHILADELPHIA AVE, PORTLAND, OR 97203

File details come from the government source that posted it. Updated .