Attachment 11_SOW_B1226 HVAC Renovation.pdf

PDF 846 KB Posted

Attached to
Offutt AFB Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA4600-25-R-0002
Issued by
Department of the Air Force Air Combat Command

About this file

This is a Statement of Work for an HVAC renovation project at Building 1226 at Offutt AFB, which serves as a place of worship for Family Housing units. The project involves replacing 24 existing WaterFurnace Versatec Ultra water-source heat pumps installed in 2002, reinstalling hydronic boiler heat injection for winter temperatures, and upgrading all HVAC equipment controls and controllers.

The work requires like-for-like replacement of heat pumps ranging from 0.75 to 8 tons, with specific requirements for Versatec Ultra USV models or equal for units up to 6 tons, and WaterFurnace Envision XL model NLV or equal for 8-ton units. The control system upgrade includes replacing the Honeywell XL100 DDC panel with Honeywell Tridium N4 products, migrating databases, and updating BMS graphics. Additional requirements include leak testing and cleaning of the geothermal well field, performance testing in both winter and summer conditions, and providing a 1-year warranty on materials and labor. The period of performance is 365 calendar days, and the contractor must coordinate with government occupants, providing 15 days notice for utility interruptions.

View the file

Other files for this federal contract opportunity

Other files attached to Offutt AFB Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Sol Amendment FA460025R00020004.pdf PDF
MACC QnA_11Apr25_F.xlsx XLSX spreadsheet
Attachment 5_Offutt AFB MACC SOW_r1.pdf PDF
Amendment FA460025R00020003.pdf PDF
Attachment 17_230700_THERMAL INSULATION FOR MECHANICAL SYSTEMS 2025-04-03.pdf PDF
Sol Amendment 25R00020002.pdf PDF
MACC Site Visit_18March2025.pdf PDF
Amendment FA460025R00020001.pdf PDF
MACC Site Visit_06March2025.pdf PDF
Solicitation - FA460025R0002.pdf PDF
Attachment 3_Division 1 - 01 33 01 AF66.pdf PDF
Attachment 4_Env Spec Conditions_Division 1_01 57 19_Nov24.pdf PDF
Attachment 10_21-0048 Repair Water Line Specifications.pdf PDF
Attachment 13_SGBP 22-0041 Repair HVAC B1226 Specifications.pdf PDF
AF3052_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
Attachment 2_Division 1 - 01 33 00 Section 1B_Jan21.pdf PDF
Attachment 14_SGBP 22-0041 Repair HVAC B1226_Cut Sheets.pdf PDF
Attachment 6_SOW_21-0048 Repair Water Line_F627.pdf PDF
Attachment 9_21-0048 Repair Water Line Drawings.pdf PDF
Attachment 1_Division 0 - 00 10 00 Section 1A_Mar22.pdf PDF
Attachment 5_Offutt AFB MACC SOW.pdf PDF
Attachment 7_21-0048 Project Diagram.pdf PDF
Attachment 8_21-0048 Repair Water Line Design Analysis.pdf PDF
Attachment 12_SGBP 22-0041 Repair HVAC B1226 Drawings.pdf PDF
Attachment 15_SGBP 22-0041 Repair HVAC B1226_Design Analysis.pdf PDF
Attachment 16_WD_NE20250059.pdf PDF
MACC_55 SFS Contractor Vendor NCIC Screening Pass Request.pdf PDF
Show all 27

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Project Title: B1226 HVAC Renovation NextGen Work Task #: 6976316

1. Objectives:

This scope of work is to provide a full lifecycle HVAC renovation at b1226. This includes a lifecycle replacement of the heat pumps. The existing heat pumps were installed in 2002 and have reached the end of their expected service life. Additionally, this scope includes reinstalling hydronic boiler heat injection to mitigate deep winter temperatures on the ground loop. Additionally, this scope includes a full upgraded replacement of all HVAC equipment controls and controllers. This building is the designated place of worship for the Family Housing units and personnel and supports other group functions for the Base.

There are 24 existing heat pumps requiring replacement in the building. There are 5 in the basement and 9 in the main mechanical room, with the rest distributed among the offices and other rooms. The existing units are split between vertical ducted water-source heat pumps. The manufacturer is WaterFurnace and the series is Versatec Ultra, although there is one Trane unit as well. Models and capacities are the following:

Model Capacity Qty UXV024B001CLT2SSA 2 ton 1 UXV042B301CLT2SSA 3.5 ton 1 UXV080TR301CASSA 6.5 ton 2 UXV012B001CRT2SSA 1 ton 1 UXV058B301CRT2SSA 4.5 ton 2 UXV058B301CLT2SSA 4.5 ton 5 UXV095TL301CASSA 8 ton 2 USV018TR000CBNN23N00 1.5 ton 2 CW09L023CNNASSA .75 ton 1 CC18L023CNNASSA 1.5 ton 1 CW09L023CNDASSA .75 ton 5 Trane - unknown 1 ton 1

The identified heat pump replacements will be like-for-like as much as possible in terms of cooling/heating capacity, airflow capacity, and configuration; Versatec Ultra USV models (.75, 1, 1.5, 2, 3.5, 5, and 6 ton units) or equal. The two 8 ton units shall be replaced by 8 ton WaterFurnace Envision XL model NLV or equal.

The existing control units include a Honeywell XL100 DDC panel located in the basement as well as compatible unit controllers on each heat pump. Additionally, there are two VFDs on the loop circulating pumps located in the basement which are saftronics PC10E1ST32010A1.

FA460025R0002

Attachment 11

The identified replacements shall be of like capacity in the Honeywell Tridium N4 product line.

Database and programming information shall be migrated from the old units to the new units as part of this project. The BMS (Honeywell Enterprise Building Integrator) graphics shall be revised to match all changes done. Graphics must be done by Honeywell Internarial.

The Contractor shall provide a full leak test and cleaning and flushing of the geothermal well field piping system. When the renovation is complete the Contractor shall also provide a service and report for a performance test of the loop and pump system in both winter and summer conditions to determine if any additional heat or cooling injection to the well field is needed.

The contractor shall furnish all labor, materials, transportation, equipment, special tools, expertise, supervision, and services requested to fulfill the requirements of this contract. All task specifications of this Statement of Work will herein be referred to as “requirements”. No alterations, additions, or deletions shall be made unless by prior approval of the government Project Manager and the government Procuring Contract Officer (PCO). The work shall conform to the most current applicable NFPA, IMC, IPC, ASME, and AFI, ETL, and Unified Facility Criteria Standards. Work shall be completed in a neat, substantial, and competent manner.

The contractor shall perform quality assurance activities that conform to the quality assurance processes outlined in International organization of Standards (ISO) 9001, Quality Management Systems. The Contractor shall use SOW requirements, ESE-SIT-0001, AFI 31-101, and Original Equipment manufacturer (OEM) guidelines to evaluate whether or not the equipment and systems are being installed and integrated properly.

During construction the Government will occupy the existing facilities. The contractor shall not restrict nearby pedestrian or vehicular traffic and shall coordinate with the Contracting Officer’s Representatives to facilitate usage. The Contracting Officer’s Representatives shall be notified not less than 15 calendar days in advance of any interruptions in building utilities / services, which will be described in writing.

Period of Performance: 365 Calendar Days

2. Requirements

1. The Contractor shall attend a site visit prior to beginning work in order to verify field conditions and requirements.

2. The Contractor shall provide a leak test, flush and cleaning of the well loop field to remove and contamination and to facilitate finding and leaks. The Contractor shall provide clean, filtered, and chemically balanced refill of the well loop.

3. The Contractor shall provide full replacement of heat pumps, including demolition and removal of the existing heat pumps, installation of the new units, and installation and re-routing/hookup of the new inlet and exhaust ducting, electrical connections, controls and control systems, and all process piping and any piping or ductwork insulation. If any other equipment is in the way of installation, the Contractor will temporarily move and/or reroute it to allow installation, coordinating with the Government for proper operation.

FA460025R0002

4. The Contractor shall provide full replacement of the controllers and all required interfacing components to the new HVAC equipment using the existing LON communication for the serial bus. The Contractor shall provide complete transfer of the database / control scheme, and or complete programming of the replacement equipment to match existing conditions.

5. The Contractor shall coordinate with the Government for installation and programming of the replacement equipment.

6. On-site CE shop personnel will provide coordination for needed system operation and isolation to allow the replacement.

7. The Contractor shall provide testing of the units to prove capacity and control capability and to return the units to service. The Contractor shall provide testing of the replacement controls to ensure proper operation of all equipment, components, and system on both an individual level and within the designated control sequence of operation.

8. The Contractor shall provide training on the installation configuration, maintenance, and operation of the new equipment and controls.

9. The contractor shall provide a performance test of the well field and pump system in both winter and summer after the renovation is complete. The Contractor shall analyze the conditions and results and provide a report determining if any additional heat or cooling injection is needed for peak conditions.

10. The Contractor shall dispose of all waste material offsite in accordance with Offutt AFB Environmental Special Conditions section 01 57 19.

11. The Contractor shall provide at least a 1 year warranty on all materials and labor for the project.