This statement of work document outlines the requirements for a construction project to expand and renovate an outpatient mental health facility at the Tomah VA Medical Center in Tomah, Wisconsin. The project will construct a 4,500 square foot addition to infill an existing building, along with renovating three floors of the existing space. Scope of work includes demolition, site work, new construction according to provided plans and specifications, and compliance with all required codes and standards. The period of performance for the base bid is 550 days from notice to proceed. Four bid alternates are also included that would reduce the scope of work and shorten the period of performance, with the award to be made to the lowest priced responsive and responsible bidder based on available funding. Relevant agencies are the Department of Veterans Affairs and Technology Acquisition Center Austin.

View the file

Other files

File Type Posted
Amendment 0007 Attachment 33 - Wage Determination 02-02-24.pdf PDF
Amendment_0007 36C77623B0050_1 0007.pdf PDF
Amendment_0006 36C77623B0050_1 pdf.pdf PDF
Amendment_0005 Attachment 31 - VAT-MP-ADD-1 - Response to 39.pdf PDF
Amendment_0005 Attachment 25 - B404 ACM Spreadsheet Inventory 2015 - Response to 1.pdf PDF
Amendment_0005 Attachment 29 - Response to 34.pdf PDF
Amendment_0005 Attachment 32 - Replace HVAC AC B404 Record Drawings Set - Response to 38.pdf PDF
Amendment_0005 36C77623B0050_1 pdf.pdf PDF
Amendment_0005 Attachment 30 -237413 PackagedOutdoorCentral-Station Air-Handling Units_addendum 1.pdf PDF
Amendment_0005 Attachment 24 - 2431 Tomah WI ACM - Response to 1.pdf PDF
Amendment_0005 Attachment 26 - Spec Section 27 52 23 - Response to 15.pdf PDF
Amendment_0005 Attachment 27 - Spec Section 26 29 11 - Response to 16.pdf PDF
Amendment_0005 Attachment 28 - B404 TR - Response to 18.pdf PDF
Amendment_0005 Attachment 23 - Tomah Technical Questions and VA Responses.pdf PDF
Amendment_0004 36C77623B0050_1 .pdf PDF
Amendment _0003 36C77623B0050_1 .pdf PDF
Amendment_0002 Attachment 21 - Tomah Site Visit sign-in sheet.pdf PDF
Amendment_0002 36C77623B0050_1 .pdf PDF
Attachment 2 - Bid Set - Spec V1R.pdf PDF
Amendment_0001 36C77623B0050_1 pdf.pdf PDF
Amendment_0001 Attachment 20 - 676-325 Renovate B404 - Structural Pages SG-001 to SB-100.pdf PDF
Amendment_0001 Attachment 3 - Bid Set - Spec V2R revised.pdf PDF
Attachment 17 - VA Notice of Limitations on Subcontracting.pdf PDF
Attachment 15 - Drawing Part 12 676-325 Renovate B404 - Structural.pdf PDF
36C77623B0050_1.pdf PDF
Attachment 6 - Drawing Part 3 676-325 Renovate B404 - Architectural_Part2.pdf PDF
Attachment 7 - Drawing Part 4 676-325 Renovate B404 - Architectural_Part3.pdf PDF
Attachment 18 - Wage Determination 10-13-23.pdf PDF
Attachment 5 - Drawing Part 2 676-325 Renovate B404 - Architectural_Part1.pdf PDF
Attachment 4 - Drawing Part 1 676-325 Renovate B404 - Architectural.pdf PDF
Attachment 13 - Drawing Part 10 676-325 Renovate B404 - Plumbing.pdf PDF
Attachment 10 - Drawing Part 7 676-325 Renovate B404 - Fire Supression.pdf PDF
Attachment 19 - Brand Name JA Tomah.pdf PDF
Attachment 3 - Bid Set - Spec V2R.pdf PDF
Attachment 2 - Bid Set - Spec V1R.pdf PDF
Attachment 8 - Drawing Part 5 676-325 Renovate B404 - Electrical and Technology.pdf PDF
Attachment 16 - GeoTech Report.pdf PDF
Attachment 11 - Drawing Part 8 676-325 Renovate B404 - Floor Plans.pdf PDF
Attachment 12 - Drawing Part 9 676-325 Renovate B404 - Mechanical.pdf PDF
Attachment 9 - Drawing Part 6 676-325 Renovate B404 - Finishes.pdf PDF
Attachment 14 - Drawing Part 11 676-325 Renovate B404 - Site Drawings GI-001 to LS-101.pdf PDF
Show all 41

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

676-325 Expand/Renovate B404 for Outpatient Mental Health- Construction 10/20/2023

Tomah VA Medical Center

Expand/Renovate B404 for Outpatient Mental Health 676-325 (C )

STATEMENT OF WORK

I. GENERAL:

This project will construct a planned design to expand and renovate B404 for outpatient mental health office space. The 4,500 square foot expansion will infill the southeast corner of the building with three levels and a mechanical space on the roof. The first floor is rebar reinforced slab-on-grade. The expansion will house large meeting rooms and two new elevators. The renovation of the three main floors will consist predominantly of full gut of the building with the exception of selected walls throughout, the east end of the first floor, and IT closets. The renovation of the space includes all new finishes, mechanical ducting and equipment, plumbing, electrical, fire suppression and alarms, data, and communications infrastructure. The exterior renovation is limited. The north, main entrance will be reworked, a new southeast entrance added to accommodate the addition, and south of the building will receive a rain garden to assist with stormwater drainage. All window fenestrations will be removed and replaced. Exterior brick and lintel work will be removed to accept the new addition. Roofs are not included except where the new addition adjoins the existing building.

II. SCOPE OF WORK

This project includes all work elements defined by the drawings and specifications prepared by CB Design Group Architects and Engineers, Alexandria, VA. The construction contractor shall:

A. Provide for and furnish all labor, materials, equipment, temporary protection, qualified supervision, overtime, and other items designated in the specifications and as shown on the drawings for the expansion and renovation of B404.

B. General Note:

The Contractor shall verify all existing dimensions and conditions. The route of all buried utility lines and their route shall be clearly delineated prior to and during the construction activity.

C. Removal/Demolition Work

1. Removal of the existing trees as shown in the plans

2. Removal of asphalt and concrete as shown in the plans.

3. Removal of the existing topsoil and stockpile on site for site finishing.

4. Prepare the existing surface in preparation for the expansion and other improvements.

5. Comply with waste separation and recycling goals as stated in Specification 01 74 19

Construction Waste Management.

6. Protect existing landscaping and improvements within and accessing the construction area and existing construction not a part of demolition.

D. New Work

1. New work will be completed according to the plans and specifications published for this project.

2. Provide and maintain a cost weighted, critical path defined, construction schedule in accordance with Specification 01 32 16.15 Project Schedules.

3. Submittal requirements include:

a. Submittals shall be provided to the VA and the CPS Contractor via Submittal Exchange a minimum of 30-days prior to the start of work for that work item. Fifteen days are required for submittal review and return to the construction contractor. No work shall commence until submittals have been approved.

b. Submittals shall include manufacturer’s literature, hardware, access controls, and installation/operation instructions according to the specifications for this project.

Submittal requirements are outlined in Specification 01 33 23.

c. Material Safety Data Sheets (MSDS) for all hazardous materials to be used/kept on the contract site.

d. Waste recycling reports must be provided with monthly invoices.

4. No work shall proceed on Federal Holidays unless special permission has been obtained from the COR.

5. Work shall be scheduled as approved materials are available, delivered on site and ready for installation.

E. Additional Requirements

1. Normal working hours are between 7:00 am to 4:30 pm.

2. Contractor shall be required to comply with the General Requirements, Specification 01 00

00.

3. The contractor will be responsible for organizing, scheduling, and facilitating the progress of work and coordinate with the COR and coordinate with the construction period services contractor.

4. Contractors shall be required to obtain, wear, and return VA Contractor badges.

5. Contractors and sub-contractors shall wear proper PPE including safety shoes, safety glasses, and hardhat and additional PPE as required by the task being completed.

6. Contractors shall obtain the 2023-24 flu vaccination when available and as appropriate during the period of performance. Evidence of inoculation will be required.

7. The work area shall be clean and picked up at the end of each day’s work.

8. The VA anticipates lead and asbestos abatement in the project. The Basis of Design provides a preliminary asbestos sampling and testing report. Prior to asbestos abatement, the contractor shall provide additional identification and testing of suspect material in areas previously in accessible such as within walls, in crawlspaces and steam tunnel passages, paying special attention to pipe insulation in these previously inaccessible areas.

III. CODES, STANDARDS, AND EXECUTIVE ORDERS

VA has adopted the latest edition of the following codes and standards as a minimum for all projects performed in the modernization, alteration, addition, or improvement of its real property and the construction of new structures. VA design Manuals and Master Specifications specify other codes and standards that VA follows on its projects. This project shall be constructed in accordance with the design drawings and specifications based on the following codes:

• VA Directives, Design Manuals, Master Specifications, VA National CAD Standard Application

Guide, and other Guidance on the Technical Information Library (TIL) (www.cfm.va.gov/til/).

• International Building Code (IBC) (Only when specifically referenced in VA Design Documents, see notes below)

• NFPA 101 Life Safety Code (see notes below)

• NFPA National Fire Codes, with the exception of NFPA 5000 and NFPA 900

• Occupational, Safety and Health Administration (OSHA) Standards.

• VA Seismic Design Requirements, H-18-8

• National Electrical Code (NEC)

• International Plumbing Code (IPC)

• Safety Code for Elevators and Escalators, American Society of Mechanical Engineers (ASME)

A 17.1.

• ASME Boiler and Pressure Vessel Code

• ASME Code for Pressure Piping

• Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier

Free Design Guide (PG-18-13)

• Building Code Requirements for Reinforced Concrete, American Concrete Institute and

Commentary (ACI 318)

• Manual of Steel Construction, Load and Resistance Factor Design Specifications for Structural

Steel Buildings, American Institute of Steel Construction (AISC)PG 18-3 – DESIGN AND CONSTRUCTION PROCEDURES September 2013 CODES, STANDARDS & EXECUTIVE

ORDERS 1-2

• Energy Policy Act of 2005 (EPAct)

• DOE Interim Final Rule: Energy Conservation Standards for New Federal, Commercial and

Multi-Family High-Rise Residential Buildings and New Low-Rise Residential Buildings, 10 CFR Parts 433, 434 and 435.

• Federal Leadership in High Performance and Sustainable Buildings: Memorandum of Understanding (MOU)

• Executive Order 13693: Planning for Federal Sustainability in the Next Decade - 2015.

• The Provisions for Construction and Safety Signs. Stated in the General Requirements Section

01010 of the VA Master Construction Specification.

• Ventilation for Acceptable Indoor Air Quality – ASHRAE Standard 62.1- 2019.

• Safety Standard for Refrigeration Systems – ASHRAE Standard 15 – 2019.

IV. BID Alternates Bid alternates shall be implemented as necessary and as funding permits. Detailed bid alternate descriptions are shown in the drawings. In summary:

All Inclusive Base Bid: Furnish all labor, materials, equipment, and supervision in accordance with construction documents, drawings and specifications to complete Project 676-325 Expand/Renovate B404 for Outpatient Mental Health, Tomah VAMC, Tomah, WI.

The bid alternates are detailed on drawing sheet BD101.

Bid Alternate #1: Remove 3rd floor addition from the Base Bid. This area will become roofing, refer to drawing sheets BD102, BD103, and BD104. Period of Performance is 550 days.

Bid Alternate #2: ALTERNATE 1, additionally delete the 3rd floor renovation area. No demolition on the western portion of 3rd floor area as indicated on drawing BD101. Existing finishes should remain. The contractor shall tie services to existing systems. Period of Performance is 500 days.

Bid Alternate #3: ALTERNATES 1 & 2, additionally delete the remaining portion of the 3rd floor as indicated on drawing BD101. Existing finishes should remain. The contractor shall tie services to existing systems. The period of performance is 475 days.

Bid Alternate #4: ALTERNATES 1, 2, & 3, additionally delete the 2nd floor addition. Refer to ALTERNATE 1 for roof details for similar conditions. The period of performance is 450 days.

NOTICE TO BIDDERS:

•A single award will be made on the Base Bid, subject to available funding. In the event bids on the Base Bid exceed available funding, a single award will be made exclusively on the amount of funding available in the following order: Bid Alternate Total #1, Bid alternate Total #2, Bid alternate Total #3, or Bid alternate Total #4. Award will be made to the lowest priced, responsive, and responsible bidder.

•BIDDERS MUST BID ON ALL BID ITEMS. ONLY ONE AWARD WILL BE MADE AS ARESULT

OF THIS SOLICITATION.

V. PERIOD OF PERFORMANCE:

The period for construction activities from the date of the Notice to Proceed:

T1 = Notice To Proceed, T1 + 15 days = Pre-construction Kick-Off Meeting scheduled, including all sub-contractors, T1 + 225 days = 50% complete, T1 + 550 days = 100% complete, T1 + 580 days = Project closeout.

VI. Other:

The C&A requirements do not apply, and a Security Accreditation Package is not required.

END OF DOCUMENT

Appendix

1. Basis of Design

a. Includes preliminary Asbestos Sampling and Testing Results

2. Specifications

3. Drawing Sheets