Attachment 1 Statement of Work.pdf

PDF 516 KB Posted

Attached to
Abate hazardous materials, historic buildings, WA
Solicitation number
140P8320R0008
Issued by

About this file

This is a request for proposals for hazardous materials abatement services at multiple historic buildings located at Fort Vancouver National Historic Site in Vancouver, Washington. The solicitation seeks a contractor to perform hazardous material surveys, asbestos and lead abatement, selective demolition, and minor repairs. Services include characterization and abatement of asbestos, lead, PCBs, mercury, and wildlife excrement. The small business set-aside contract has a 180-day period of performance and requires payment and performance bonds. A site visit will be held on August 13, 2020, and proposals are due on the date specified in block 13 of the SF1442 form. The government will consider both technical and price factors in a best value determination. The solicitation is designated for small businesses with average annual receipts less than $22 million over the past five years.

View the file

Other files

File Type Posted
Attachment 10 Final Clarifications_0003.pdf PDF
Sol_140P8320R0008_Amd_0003.pdf PDF
Sol_140P8320R0008_Amd_0002.pdf PDF
Sol_140P8320R0008_Amd_0001.pdf PDF
forms to return with proposal - revised 140P8320R0008_0001.docx DOCX document
Attachment 9 Site visit notes_0001.pdf PDF
Attachment 7a Revised Wage Determination_0001.pdf PDF
Attachment 3e - B748 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3a - B410 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3j - B786 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 6 Building Floor Plans_20200723.pdf PDF
Attachment 4c - B991 and B993 Asbestos Survey Field Notes.pdf PDF
Attachment 3g - B752 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3f - B749 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 4b - B993 Pre-Renovation Asbestos Survey Report.pdf PDF
Attachment 3c - B725 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3i - B754 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3h - B753 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3d - B746 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3b - B721 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 4a - B991 Pre-Renovation Asbestos Survey Report.pdf PDF
Attachment 5 Building Descriptions.pdf PDF
forms to return with proposal 140P8320R0008.docx DOCX document
Sol_140P8320R0008.pdf PDF
Attachment 2 Task List for each building.pdf PDF
FAQs for RFP 140P8320R0008.pdf PDF
Attachment 7 Wage Determination 7-3-20.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fort Vancouver National Historic Site Vancouver, Washington

SOLICITATION 140P8320R0008

Attachment 1 Statement of Work

Hazardous Materials Abatement, Selective Demolition, and Minor Repairs within Historic Buildings

July 2020

NATIONAL PARK SERVICE

PACIFIC WEST REGION

FOVA – East and South Vancouver Barracks

Attachment 1 Scope of Work

RFP# 140P8320R0008

Table of Contents

I. Background

II. Scope of Work

III. General Requirements:

IV. Emergency Precautions and Procedures

V. Radiation Safety

VI. Project Meetings

VII. Submittals

VIII. Barriers and Resource Protection Measures

IX. Temporary Controls and Facilities

X. Materials and Equipment

XI. Quality Assurance

XII. Project Closeout

XIV. Hazardous Material Survey

XV. Asbestos Abatement Requirements

XVI. Lead Remediation Requirements

XVII. Polychlorinated Biphenyl (PCB)

XVIII. Biological Remediation:

XIX. Mercury-Containing Equipment, Universal Waste, and Other Wastes

XX. Photographic Documentation

XXI. Selective Demolition

XXII. Painting

XXIII. Lighting:

XXIV. Abbreviations and Definitions

I. Background

1. Site Background Fort Vancouver National Historic Site (FOVA) is located in Vancouver, Clark County, Washington. The area was first developed by the Hudson’s Bay Company as Fort Vancouver, which existed as a trading post and support base from 1829 to the 1860s. The US Army arrived in 1849, established the Vancouver Barracks adjacent to Fort Vancouver, and used the post for a variety of purposes, including training facilities, barracks, firing ranges, and administrative and logistical support. The National Historic Site was established by the US Congress to protect the location’s rich cultural resources. These nationally significant cultural resources are listed on the National Register of Historic Places as the Vancouver National Historic Reserve National Historic District, and include historic structures, cultural landscapes, and some of the most significant and well-preserved historical archaeological sites in the Pacific Northwest.

2. Project Background The National Park Service (NPS) assumed ownership of the East and South Vancouver Barracks (ESVB) in 2011. The buildings in the ESVB were in various conditions, and had numerous renovations and alterations completed since construction of the current buildings began in the early 20th Century. This project will remove hazardous materials, to include asbestos containing materials (ACM), polychlorinated biphenyls (PCB), lead-based paints and other lead containing materials, mercury containing equipment, and biological contamination (animal feces). The project includes selective demolition of non-historic walls and specific areas needed to access and remove the hazardous materials, and repairing damage caused to the buildings by abatement and demolition to prepare these historic buildings for renovation into modern reuse.

II. Scope of Work

The contractor shall furnish all construction services, materials, supplies, labor, equipment, investigations, studies, superintendence, contract management, administration, quality assurance/control, and travel, as required, for completing the tasks required to perform a hazardous materials survey of two (2) buildings and abatement program for up to 12 buildings at FOVA. The buildings are summarized in Table 1 (next page). Note that some buildings in the table are included in the base contract and others are optional items.

The Contractor shall perform the requirements of this SOW to successfully complete the project with exception of those tasks specifically identified as the responsibility of the NPS or an NPS-designated representative.

Details of specific contractor tasks to be performed at each building and presence of hazardous materials are presented in Attachment 2. Hazardous materials surveys that have been performed are provided as Attachments 3a to 3j and 4a to 4c. Attachment 5 contains more detailed building descriptions and photos. Attachment 6 contains floor plans. Historic Structure Reports are available as Attachments 8a to 8k; due to large file sizes, these reports are not posted with the solicitation but are available for download. Send an email request to sarah_welch@nps.gov for FTP site link.

Table 1: Building Summary

Building Number

Address Year Built

Description Task Base or Option?

402 501 East Fifth Street, Building 402 1983 Garage Survey Base item with an option

410 801 East Fifth Street, Building 410 1935 CCC Automotive Repair Shop Abatement Option 721 800 Hatheway Road, Building 721 1904-

Gymnasium Abatement Option with an option 725 811 Hatheway Road, Building 725 1914 Mess Hall Abatement Base item 746 700 East Fifth Street, Building 746 1940, moved

Barracks Abatement Option

748 611 Fort Vancouver Way, Building 748 1918-

Motor Repair Shop Abatement Base item

749 611 Fort Vancouver Way, Building 748 1941 Shed east of 748 Abatement Base item 752 700 East Fifth Street, Building 752 1905-

Quartermaster Warehouse Abatement Option with an option 753 700 East Fifth Street, Building 753 1917 Quartermaster Storehouse Abatement Base item 754 700 East Fifth Street, Building 754 1909 Quartermaster Shop Abatement Base item 786 700 East Fifth Street, Building 786 1905-

Quartermaster Workshops Abatement Option with an option 991 991 McClellan Road 1905-

Post Headquarters Abatement Option

993 993 McClellan Road 1906-

Infantry Barracks Abatement Option

III. General Requirements:

A. The project schedule and building priorities set forth below may be unilaterally changed by NPS based on current or future tenant needs. The NPS will make every effort to provide the Contractor flexibility to conduct their operations according to their preference provided all work is completed within the period of performance. However, if NPS requires scheduling changes to task or building priority, these will not be considered changes to the contract and in general, additional funds will not be awarded based on a change in the order buildings are completed.

Planning and scheduling should be initially created so that buildings are completed in the following order:

1) 746 (Option), if exercised

2) 748

3) 749

4) 725

5) 721 (Option), if exercised

6) 753

7) 754

8) 402

9) 752 (Option)

10) 410 (Option)

11) 786 (Option)

12) 991 (Option)

13) 993 (Option)

B. The Contractor shall perform all work in accordance with the Department of the Interior’s Secretary’s Standards for Historic Preservation and building-specific plans that are developed by the contractor and submitted to NPS for approval.

C. The Contractor shall retain a third-party Certified Industrial Hygienist (CIH, “CIH Consultant”) to provide inspection, guidance, and air monitoring services during the abatement and clean-up projects. The contractor shall engage the CIH Consultant identified in their offer. Substitutions after award must be in accordance with the Key Personnel requirements of the contract. The CIH Consultant will report findings to the CO, not the Contractor. The CIH must have appropriate staff, qualifications, and/or certifications to inspect asbestos abatements in the State of Washington, for example, an Asbestos Supervisor certified by the Washington Department of Labor and Industries.

D. The Contractor shall identify personnel listed below in a letter provided to the CO that states the name, contact information, and qualifications of each individual and their role(s). Each individual must have knowledge and experience sufficient to execute these duties on a project of this complexity at a site listed on the National Registry of Historic Places.

a. Contractor Project Manager – Is responsible for managing schedules, resourcing, and communicating with the NPS CO. Substitutions in this position after award must be in accordance with the Key Personnel requirements of the contract.

b. Contractor Site Superintendent – Is responsible for project site operations in the Work Area(s) and at the historic site.

c. Contractor Quality Control – Is responsible to ensure that the Contractor meets the requirements of this SOW, as well as federal, state, and local laws and regulations and industry best practices.

The Contractor Quality Control must be onsite during all inspections or testing by the CIH Consultant.

d. Contractor Site Safety Officer – Works to ensure that the Contractor, subcontractors, employees, and visitors meet federal, state, and local health and safety standards, conform to NPS standards, industry best practices, and the Contractor’s safety plan. An alternate safety officer may also be named to cover absences of the safety officer. The site safety officer must be onsite at all times work is being conducted and may not also be the site superintendent.

E. The following NPS personnel have roles in administering the contract:

a. Contracting Officer (CO) – Is the only person who has the authority to make changes to the contract. Change orders, time extensions, modifications, notice to proceed, terminations, etc., must be signed by the CO.

b. Contracting Officer’s Representative (COR) – Is responsible for submittal approval, work in progress and day-to-day monitoring of contractor performance. The COR cannot make formal changes to the contract.

c. Inspector – Is responsible for the day-to-day inspection or monitoring of work. Will review and provide technical guidance on plans and submittals. The Inspector role may be fulfilled by the COR, the Facility Manager, an NPS employee, or a third party hired by the NPS. The Inspector cannot make formal changes to the contract.

d. Facility Manager – Is responsible for the operation and long-term maintenance of the site. Will review plans and work to ensure conformance with NPS policy, industry best practices, and future NPS capabilities. The Facility Manager cannot make formal changes to the contract.

F. NPS is responsible for completing the categorical exclusion under the National Environmental Policy Act (NEPA). The NPS will conduct compliance as needed for Section 106 of the National Historic Preservation Act (Section 106), The Native American Graves Protection and Repatriation Act (NAGPRA), and other Federal Regulations affecting Cultural Resources. The Contractor must comply with these regulations, which may include work stoppage in particular areas if significant cultural resources are encountered.

G. The Contractor shall establish safe viewing access (where applicable) in order for federal, state, and local agencies to conduct an evaluation of the ongoing removal, clean-up, and disposal of hazardous materials.

Since NPS cannot enter the containment area, the contractor will need to provide pictures, videos and if necessary, sketches to NPS staff to discuss situations where historic fabric is encountered, and clarifications or decisions are needed.

H. Prior to conducting any remediation, demolition, or construction activity, schedule a site walk-through with NPS Cultural Resources personnel to identify any objects of significance to be salvaged, or other historic preservation issues. This review must be requested from the NPS at least two business days in advance of the planned work. If the NPS has already completed the review, it will so state in the response to the request to schedule a review. Any objects of significance must be decontaminated by the contractor using methods approved by the NPS. If a Work Area has multiple phases of work, for example, demolition followed by construction, a review must be requested before each phase. During the abatement and selective demolition, if any objects are found (behind walls, under floors, etc.) that maybe historic – the contractor shall take a detailed picture, specifically identify location, and get a determination from the NPS Cultural Resources staff.

I. The Contractor shall submit electronic copies of the Contract Submittals for NPS and CIH Consultant approval.

J. Where conflict among requirements within the project documents (including specifications and drawings) exist, the more stringent requirements shall apply.

K. All applicable federal, state, and local regulations apply. The current issue of each regulation shall govern.

L. Industry best practices must be applied. Where the project documents, regulations, and industry best practices are inconsistent the safest legal standard shall apply.

M. If necessary, provide temporary power and lighting and ensure safe installation of temporary power sources and equipment per applicable electrical code requirements and provide ground fault interrupter circuits as power source for electrical equipment. The Contractor shall provide sufficient numbers of outlets for the exclusive use by the CIH Consultant inside and outside the work areas to power (120VAC; 20-30 amp) inspection and sampling equipment and other uses.

N. In each building, abatement shall not commence until a written Authorization to Access Building has been issued by the COR, and the following have been satisfied:

a. All required submittals have been reviewed and approved.

b. The CIH Consultant has inspected and approved the Work Area for start of abatement.

c. Arrangements have been made for securing the Work Area.

d. Sufficient capacity to securely store waste is available onsite.

O. Specific Work Area Preparation by the Contractor:

a. Isolate and/or disengage building systems, for example, heating, ventilation, and air conditioning.

Coordinate with the NPS when building systems will be isolated and returned to service.

b. Provide and post signs at all locations and approaches to the Regulated Area. The signs shall comply with regulatory requirements.

c. In buildings with fire suppression, protect systems from contamination without impacting their function.

P. The Contractor shall immediately contact the COR for evaluation of methods to deal with any suspected hazardous materials encountered that are outside the SOW. The COR will seek input from the CIH and CO.

Q. The Lead Based Paint (LBP) Abatement Contractor must use an independent National Environmental Laboratory Accreditation Program (NELAP) approved laboratory for air monitoring and analysis support.

Should the contractor change independent laboratories while the contract is in progress, the contractor shall resubmit the qualifications/certifications of the new laboratory for approval.

R. Provide daily reports as described in the submittals section.

S. Contractor shall have at least one copy each of 29 CFR 1926.1101, applicable state and local regulations, complete contract documents, and the Contractor's detailed work plan at the job site.

T. All appropriate notification for removal fees and fees associated with the removal will be paid by the contractor and included in the contract price.

U. In some locations, abatement cannot proceed without removing walls, doors, ceilings, floors, inactive equipment, debris, and/or other material. All removal or demolition of building components must be approved by the NPS and is included in the contract price.

V. Protect historic fabric that abuts or underlies areas of demolition.

W. In Buildings 410 and 991, where demolition creates holes, gaps, or similar in remaining walls, floors, or ceilings, repair wall, floor, or ceilings to match adjacent surfaces. For painted surfaces, prepare, prime and paint the patch to match abutting surface. All patches must leave the building in a safe condition, for example, a patch must not create a tripping hazard. Paint color may not need to match in all locations between adjacent surfaces, as the NPS will complete final painting to match tenant needs.

IV. Emergency Precautions and Procedures A. The Contractor shall demonstrate their capabilities in advanced first aid to respond to Contractor or subcontractor employee injuries that will include, at least:

a. Basic Life Support as certified through the American Heart Association, or similar, which includes:

i. High quality cardiopulmonary resuscitation (CPR)

ii. Use of automated external defibrillators (AED)

iii. Effective ventilations using a barrier device

iv. Multi-rescuer resuscitation and effective team performance

v. Relief of foreign-body airway obstruction

vi. Control bleeding, including exsanguinating bleeds, and manage shock

b. Care for injuries, including but not limited to:

i. Eye injuries

ii. Significant skin area burns

iii. Temporary immobilization of broken bones for employee transport

c. Care for medical emergencies, including but not limited to:

i. Stroke

ii. Heat exhaustion and heat stroke

iii. Diabetic emergencies

iv. Cardiac emergencies

v. Identify special situations, such as behavioral emergencies

vi. Perform remote-location first aid B. The Contractor shall document that they have notified local entities that provide emergency services (9-1-1) of the hazardous materials being worked with during the project. Submit documentation to NPS.

C. At least one person trained in advanced first aid who is also qualified and certified to work in asbestos remediation containment, lead remediation containment, and all other types of work to be performed shall be onsite at all times work is being performed. This employee shall be identified by name, proof of training, and unique field clothing identification that shall be provided to the NPS prior to the commencement of the work of this section.

D. All employees should be trained in basic first aid, CPR, and AED use.

E. Seriously injured personnel shall be treated immediately. When an injury occurs, the Contractor shall implement asbestos-fiber reduction techniques, and/or other applicable approaches to minimize the hazards, until the injured person has been removed from the Work Area.

F. Establish emergency and fire exits from each Work Area. Display necessary signage at exits and paths to exits with representative visual aids to permit easy identification from anywhere within the Work Area. A diagram of all emergency and fire exits shall be posted in a conspicuous area proximate to the entrance to each Work Area. Exits shall be secured to prevent access from uncontaminated areas while still permitting emergency egress. Exits shall be properly sealed with polyethylene sheeting, which can be cut to permit emergency egress.

Emergency exits may lead through the worker decontamination enclosure, the waste removal airlock, or other alternative exits as required by fire officials.

G. Emergency services at FOVA are provided by the City of Vancouver and accessed by calling 9-1-1. Often 9-1- 1 calls from a cellular telephone are handled by towers in Portland, Oregon, and therefore routed to the Portland dispatch center.

When calling 9-1-1 you must request to speak with Vancouver dispatch.

H. The Contractor shall provide a means to move an injured employee from a hazardous environment to fresh air, such as a Stokes litter, Megamover, or stretcher.

I. Respiratory Protection Plan: The Contractor shall submit written documentation identifying the selection, fit testing, and use of respirators in accordance with federal, state, and local regulations, and ANSI Z88.2, Z88.6, and the manufacturer's certification that the respirators to be used in this project comply with these regulatory requirements.

J. Emergency Plan: The Contractor shall submit a plan for responding to emergencies involving:

a. Earthquake, flood, fire, accidents, medical, water leaks, Pressure Differential Unit failure, power failure, breaches in containments or spills, electrical hazards, slips, trips and falls, confined spaces, heat-related injury, emergency evacuation procedures, and the location(s) of the emergency assembly points that are located a safe distance from the hazards and are organized in a manner that facilitates an orderly headcount of employees.

b. Patient decontamination procedure for critically injured or ill patients in a hazardous environment; this procedure should be referenced to a nationally recognized standard, for example, US Department of Health and Human Services Chemical Hazards Emergency Medical Management, Patient Decontamination in a Mass Chemical Exposure Incident: National Planning Guidance for Communities (2014), or Chemical and Biological Terrorism: Research and Development to Improve Civilian Medical Response (1999).

c. Equipment failures such as cranes, backhoes, demolition claws, and other heavy equipment such as front-end loaders, earth movers, and haulers.

d. Emergency procedures shall be provided in the written languages understood by all employees working on the Project and shall be prominently posted at the work areas, including, but not limited to the entrance of the decontamination enclosure system. Prior to entering the Work Area, all parties must read and receive training on these procedures. The employees must sign a declaration to acknowledge receipt and understanding of the worksite layout, location of emergency exits, and emergency procedures.

K. In the event of non-life-threatening situations requiring medical treatment, injured or otherwise incapacitated employees shall decontaminate following normal procedures with assistance from fellow workers, if necessary, before exiting the work area.

L. In the event of life-threatening injury or illness requiring immediate medical treatment, worker decontamination shall follow a patient decontamination procedure. Provide all measures to stabilize the injured workers, remove them from the work area, and secure proper medical treatment including hazard identifications for medical workers.

M. Telephone numbers of all emergency response personnel shall be prominently posted at the entrance of the Decontamination Enclosure system, along with the location of the nearest telephone. In addition to the 9-1-1 emergency number, post the address and telephone number of the nearest emergency medical services provider, and an easily-removable printed map to their location.

N. Provide at least one (1) 2A/10BC dry chemical extinguisher in the Contractor’s Equipment Room and one (1) at each corner of contained areas in excess of 1,000 square feet. The size of each deployed extinguisher shall meet NPS or National Fire Protection Association (NFPA) minimum requirements. All workers shall be trained in the proper operation of fire extinguishers.

O. The Accident Prevention Plan shall include an up-to-date list of all employees on site with specific designation of those employees that are trained, certified, and issued safety cards or badges and allowed to work within the isolation areas. When asked, the Contractor shall provide to the NPS and/or the CIH Consultant a current list showing the workers for the day. Per the Federal Acquisition Regulations Part 52.236-13, the operation and all associated documents will meet the following requirements:

a. The Contractor shall provide and maintain work environments and procedures which will-

i. Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities;

ii. Avoid interruptions of Government operations and delays in project completion dates; and

iii. Control costs in the performance of this contract.

b. For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall-

i. Provide appropriate safety barricades, signs, and signal lights;

ii. Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and

iii. Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.

c. Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the

Contractor or the Contractor’s representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.

d. The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.

P. Product Data: The Contractor shall submit the manufacturers’ product data for all supplies required to complete and execute the work; and the product data shall identify the following:

a. Product name and manufacturer.

b. Application specifications.

c. Application instructions.

d. HAZCOM information including the appropriate SDS.

Q. The Security Plan shall include a discussion of how the Contractor will secure equipment, waste, materials, infrastructure, buildings, and government-owned equipment secure from trespass, vandalism, and theft. It will also state the process of reporting such occurrences to the Vancouver Police Department and the NPS.

V. Radiation Safety A. Buildings with basements or concrete slabs are known to contain radon. Construction of radon mitigation systems is not part of this SOW.

B. With ventilation required for other parts of this contract, and natural ventilation in the buildings, it is not anticipated that workers will be exposed to harmful levels of radiation while working on this project. The Contractor shall verify work areas are free from harmful levels of radiation prior to starting work in that area.

In the event that an area is found to have unsafe levels of radiation, work shall immediately stop in that area, and the NPS and CIH Consultant will be notified. Work shall not resume in the area until it is safe to do so, and the NPS and CIH Consultant have concurred that work may proceed.

C. There are no known radioactive wastes in the buildings. Possible wastes include radium dials, ionization-based smoke detectors containing Americium 241, pottery glazing, or other radioactive sources. If radioactive materials are found, they must be reviewed by the NPS to determine if they are objects of historical significance prior to a waste determination being made. If the objects are significant, they must be provided in a clear plastic bag with a label stating the hazard, for example, “radioactive” or with the trefoil radiation symbol. If the object is too large for a bag, it must be marked with an NPS-approved label. It the object is not significant, a waste determination will be made by the CO, who will provide guidance on disposal.

VI. Project Meetings

A. A pre-work meeting will be scheduled and conducted by the CO prior to any on-site work. The CO will address all administrative aspects of contract performance. Participants may attend by phone or on-site.

B. Start-up Safety Meeting

a. Prior to the start of on-site work, the Contractor shall hold a start-up safety meeting for all of the

Contractor's employees that addresses at least the following issues specific for the project:

i. Safety and health hazards, including COVID-19.

ii. Procedures and work practices.

iii. Respiratory protection.

iv. Special conditions and/or work requirements.

b. In addition, provide detailed information concerning:

i. Preparation of work area and shop drawings (abatement only).

ii. Personal protective equipment, including respiratory protection and protective clothing (abatement and asbestos related disturbance if required).

iii. Employees who will participate in the project, including delineation of experience, training and assigned responsibilities during the work (abatement and asbestos related disturbance).

iv. Decontamination procedures for personnel, work area and equipment (abatement and asbestos related disturbance).

v. Abatement methods and procedures to be provided (abatement only).

vi. Required air monitoring procedures (pre-abatement and Southwest Clean Air Agency requirements (abatement only), and Occupational Safety and Health Administration (OSHA, abatement and asbestos related disturbance)).

vii. Procedures for handling and disposing of waste materials, including disposal facility abatement and asbestos related disturbance).

viii. Procedures for final Decontamination and cleanup (abatement only).

ix. A sequence of work activities and performance schedule.

x. Procedures for dealing with heat stress.

xi. Emergency procedures.

C. Every employee must attend a short meeting to be trained on NPS Cultural Resources and archaeology – including historic structures orientation and information, types of things they might find in the buildings and what may be important and what may not (bottles, graffiti, newspapers, etc). Include the “blue box” and bags for identifying. NPS may offer separate training sessions for new personnel

D. Prior to initiating work on each building, schedule and perform a Prework Site Walkthrough with NPS staff to review the historic features of the specific building, including items to be salvaged.

E. Schedule and participate in weekly coordination meetings with NPS team and appropriate subcontractors.

Prepare agenda, facilitate the meeting, take and distribute minutes, and provide teleconference line. . For in-person meetings, the NPS will provide a meeting room.

F. The Contractor shall complement the startup safety meeting with daily “tailgate” safety meetings involving all on-site employees to remind employees of potential hazards expected in the planned work for the day, methods to avoid injury, and current safety status of the on-site work to-date.

VII. Submittals A. Submittals must be accompanied by a transmittal form (NPS CM-16), for NPS and CIH Consultant review.

The submittal will be provided to the NPS and the CIH Consultant concurrently. The NPS may elect to approve, request further information, or disapprove of submittals without CIH Consultant review, concurring with CIH Consultant recommendations, or contrary to CIH Consultant recommendations. The NPS has the sole authority to approve submittals. Instructions on completing the form are available from the COR.

B. Submit the following documents at least one week prior to the pre-work meeting:

a. Liability insurance certificates in accordance with the contract requirements.

b. Emergency Plan.

c. Accident Prevention Plan.

d. Respiratory Protection Plan.

e. Security Plan.

f. Waste Reduction Plan.

g. Traffic Control Plan template that discusses any temporary closures of roads or pedestrian routes and any off-road vehicle use and resource protection measures. Building-specific traffic control plans must be provided to the NPS at least 14 days prior to beginning work on the building.

Traffic control plans for the first building(s) may be provided in lieu of the template.

h. General Work Plan, the Contractor shall submit a detailed work schedule including the tools and procedures to be utilized to remain in compliance with this SOW, to identify the following:

i. Training certificates and clear photo identification of personnel assigned to work with asbestos.

ii. Isolation controls.

iii. Pre-cleaning procedures.

iv. Removal methods and procedures.

v. Final clean up and encapsulation procedures.

vi. Transportation and approved disposal methods of asbestos waste.

vii. Fiber level control methods including water management techniques

viii. Providing temporary power, emergency lighting, usage of ground fault interrupters.

ix. Lockout/Tag-out procedures for controlling hazardous energy.

x. Applicable fire codes.

C. Provide a sampling plan for buildings 402 and 405 at least 14 days prior to beginning work in those buildings.

D. Plans may be combined. If plans are combined the combination must be logical, and not interfere with the purpose or function of either plan. Combined plans must be named such that it is clear one document addresses multiple submittals, or the CM16 submittal form must state that multiple plans are being submitted as one document. The CO may disapprove of a combined plan and require individual plans.

E. Building Work Plans: Prior to commencement of the abatement work at a particular building, submit the following notices, documentation, shop drawings and product data:

a. Satisfactory proof that the required permits, site location, and arrangements for transport and disposal of asbestos containing waste materials have been completed. Permits include, but are not limited to, Notification to the State of Washington Department of Labor and Industry, Southwest Clean Air Agency Notification, and Washington State Department of Commerce notification for lead-based paint abatement. Other notifications or permits may be required.

b. Handling procedures and a list of protective equipment utilized for asbestos disposal at the landfill.

c. Satisfactory documentation that all employees, supervisors, and any other company personnel or agents who may be exposed to airborne asbestos fibers or who may be responsible for any aspects of asbestos abatement work or asbestos related disturbance have received adequate training that includes, at a minimum, information as described within this section and as required by the Asbestos Hazard Emergency Response Act (AHERA). Satisfactory documentation shall include individual numbered identification cards or badges confirming the levels of training issued by the Contractor to each employee. Each on-site employee shall carry and present this identification when working on-site and asked by the NPS or the CIH Consultant for training documentation.

d. Evidence that training in emergency response and evacuation procedures has been provided to all personnel including a signed declaration of receipt and understanding of worksite layout, location of emergency exits, and emergency procedures.

e. Documentation from a physician certifying that all employees are medically monitored and are physically capable of working while wearing the required respiratory protection without suffering adverse health effects. The certification shall state that the employee or agent is approved to work with asbestos and other hazardous materials covered within this SOW, and to wear respiratory protection without restrictions. A statement must be included that the employee has been informed by the physician of the results of the medical examination and of any medical conditions that may result from exposure to the hazards. Provide information to the examining physician about conditions in the workplace environment that may impact on the employee’s ability to perform abatement work activities. No medical examination is required of any employee if adequate records show that the employee has been examined in accordance with this paragraph within the past one-year period. The physical must be current within the length of the contract.

f. Workers engaged in the remediation of drain sludge must have training and medical monitoring consistent with workers remediating LBP and lead containing material (LCM), as outlined above, with the addition of medical monitoring for arsenic, cadmium, chromium, and mercury. They must also have training for hydrocarbons, volatile organic compounds, and the Resource Conservation and Recovery Act (RCRA) 8 heavy metals. Documentation of the training and medical monitoring must be provided to the NPS, and workers must be easily identified through an identification badge, or similar, as being trained in these additional hazards.

g. Shop drawings for layout and construction of Decontamination Enclosure Systems and barriers for isolation of the contained abatement work area as detailed in this specification and required by applicable regulations.

h. Manufacturer's certification that High Efficiency Particulate Air (HEPA) vacuums, air filtration units, and other local exhaust ventilation equipment comply with American National Standards Institute (ANSI) Z9.2-79, if they are to be used.

i. Product data verifying that all air filtration devices (i.e., air filtration units and vacuums) for use on this project have been registered or certified, as applicable, in compliance with the local Air Quality Management District rules or local Air Pollution Control District rules and all devices are clean prior to site use.

j. If rental equipment is to be used in abatement work areas or to transport asbestos-contaminated waste, the contractor must provide written notification concerning the intended use of the rental equipment to the rental agency. Submit a copy of the notification to the NPS, CIH Consultant, and any applicable regulators.

k. National Institute for Occupational Safety and Health (NIOSH) approvals for all respiratory protective devices furnished as required by the work. Include manufacturer certification of HEPA filtration capabilities for all cartridges and filters.

l. Documentation of respirator fit testing for all employees and agents entering the abatement work area or areas where respiratory protection is required. This fit testing shall be performed in accordance with applicable regulations.

m. Samples of the forms the contractor intends to use to document required items if using forms other than those provided by the NPS or regulatory agency.

n. The Contractor shall certify in writing that all Differential Pressure and HEPA Vacuum equipment has (1) been fully decontaminated; (2) had new filter(s) installed since last use; (3) been inspected and assembled correctly with function seals in place, and; (4) has been calibrated and is fully operational in accordance with ANSI Z9.2 before being brought on site.

o. The Contractor shall document that all tools and materials used within the containment are decontaminated before they are transported through or stored in any occupied portion of a building located within the historic site. Suspect contaminated tools and materials shall be moved and stored outside the containment only in sealed bags or containers that are outwardly clean and dust free and labeled as containing “ASBESTOS CONTAINING MATERIALS” until decontaminated.

p. Step-by-Step Abatement Procedures Plan: This plan applies to contained and non-contained abatement procedures for each distinct location. This plan of action shall include the proposed LBP surface preparation methods, removal techniques, type, size, and position of barriers and signs, debris accumulation, cleanup and disposal procedures.

q. Full containment construction procedures, including drawings. Drawings will show layout of the containment, decontamination unit, load-out area, location for negative air machines, structural design of the containment and materials used in the construction of the containment.

r. Decontamination unit construction procedures (floor plans, dimensions, materials, locations, plumbing, electrical connections and method for disposal of contaminated water).

s. Encapsulation procedures (method of encapsulation and location).

t. Documentation of the qualifications for all personnel that are to work on the project. Personnel documents required per this section shall be organized by individual and include the following information: current certificates for the Contractor's Competent Person(s) and workers documenting that the individual has successfully completed a training course in abatement project supervision or abatement worker training offered by an United States Environmental Protection Agency (EPA) accredited educational institution; designate who the Competent Person(s) and Qualified Person will be for the project, and a copy of the Competent Person's certificate in First Aid and CPR; National Emission Standards for Hazardous Air Pollutants (NESHAP) provisions apply to this project.

**Training must document all forms/types of abatement**

u. Historic Preservation plan, for each historic building. All plans will include the following:

i. A detailed historic preservation work plan that includes:

1. Approximate engineering drawings for the work;

2. Description of how each task will be completed;

3. Where and how temporary containments and fixtures will be attached to the building;

4. How temporary containments and fixtures will be removed from the building; and

5. How the condition of the building will be changed.

ii. A schedule that conveys to the NPS the timing of the overall work and work at each building. The schedule should clearly show when containment areas will be constructed and removed by building.

F. Waste Handling

a. The Contractor shall provide examples of appropriate waste handling documents: including the waste label which shall include the Generator's Name, Address and Waste Manifest Number.

b. Waste Transportation: Submit the method of transport of waste including name, address, EPA identification number, and telephone number of transporters. If transportation of the waste is subcontracted, provide name, address, and phone number of subcontractor and documentation of abatement workers' medical examinations. If the transporter is to be the abatement contractor's personnel, the contractor shall submit names for those specified personnel that will be loading or unloading the lead contaminated waste.

c. Hazardous Waste Site: Submit for approval the name, class, address, EPA identification number and telephone number of hazardous waste sites to be utilized for disposal of waste.

G. Waste Reduction Plan:

a. Consistent with NPS policies to reduce waste, removed materials should be reused when possible, recycled if reuse is not possible, and disposed only as a last resort. Some of this material may have value which may be retained by the Contractor. Draft a waste reduction plan that includes:

i. List of items by building that will be reused either through donation to charities or selling for commercial reuse.

ii. List of items by building that will be recycled.

iii. Any anticipated credit to the contract through reuse and recycling.

b. At the conclusion of work in each building, amend the Waste Reduction Plan with a brief report that states the tonnage of material reused, recycled, and wasted. Waste streams and recycling should be subdivided into unregulated waste, universal waste, and hazardous waste.

H. Materials:

a. Submit each material to be used on the site with their intended application, relevant product information from the manufacturer, and safety data sheet for review by NPS, including Cultural Resources, and the CIH Consultant to ensure resource protection.

I. Submit a wiring plan prior to installing lighting in buildings.

J. Submit the Building 752 elevator characterization report including waste characterization, abatement strategy, and cost estimate.

K. Daily Submittals:

a. Submit completed daily reports on a regular schedule where the report is submitted within 2 hours of the conclusion of the 24-hour period the report covers. For example, if the reporting period for the manometer is from 08:00 hours on day one, to 08:00 hours on day two (a 24-hour period that ends at the start of shift), the daily report is due by 10:00 hours of day two. A daily report is not required on days where no work is being conducted, however, the daily report must state the reporting period it covers and forecast when the next daily report will be submitted. In the daily reports, the Contractor must document the following information:

i. Employee roster for each work shift that documents training identification number for each employee.

ii. Work area entry/exit logs for each containment.

iii. Daily Manometer report for each work area labeled with the correct time and date, signed by the Competent Person.

iv. Pre-abatement visual inspection form for each work area.

v. Final visual inspection and clearance certification form for each work area.

vi. Air monitoring sample results as described herein (permissible exposure limit and Excursion limit samples).

vii. Photos of the day’s work

viii. Report of activities performed during the day, using NPS Quality Control Report or similar format.

VIII. Barriers and Resource Protection Measures A. The historic site is open to the public and has over 1 million visitors per year. Fence all exterior work areas to prevent entry. Post signage as required by regulation and this document.

B. Public Pathways, sidewalks, roads, and parking will remain open and should be passable at all times.

Temporary closures and detours are allowed with prior COR approval. Closures and detours will be adequately signed, as determined by the NPS. All signage will be provided by the Contractor.

C. Drive slowly and safely. The speed limit on historic site roads is 15 miles per hour, the Contractor may need to drive slower than the speed limit. Follow all federal, state, and local traffic laws.

D. Provide a traffic control plan for each building. Coordinate all truck traffic and vehicle routes with the COR to establish safe and coordinated plans to minimize impact on NPS operations. Vehicles (or vehicle and trailer) must be of a size and design so that deliveries and other work can be performed at a site designed to obfuscate vehicle operators and impede vehicular access, this may include the need to shuttle debris from the point of generation or a satellite accumulation area to an area where it can be removed by the transporter. Alvord Road will not be available as a driving route. Transportation of waste shall use vehicles that conform to work within existing roads and turning radii. Since this is an archaeological site, all equipment, wheeled or tracked, must be operated on either an existing hard surface or plywood of sufficient size and thickness to prevent disturbances and damage in nearby grass, natural areas, or soils adjacent or below that will remain after the project is complete. Vehicles with steel tracks are not allowed on hard surfaces (e.g., asphalt or concrete). The use of vehicles with steel tracks off hard surfaces must be approved in advance by the CO. Plywood is to be provided and laid down in unpaved work areas by the Contractor. The Contractor should ensure precautions are taken to protect buildings, utilities, and features to remain, including plants and vegetation, and ensure no damage.

E. Ensure that vehicle covers and proper vehicle decontamination and tracking control is operational so that contamination is not spread outside of the work area during operations and transport. If applicable, install appropriate stormwater pollution prevention measures, such as silt fencing, to minimize erosion and movement of soil during storm events, excavation, and soil handling activities.

F. Eliminate fugitive dust emissions by laying down water spray or similarly effective method during any work outdoors to conform to applicable EPA regulations.

G. Keep all equipment and work-related items within the described and approved work area and staging area at all times.

H. The Contractor may move hazardous materials around on the staging area site to facilitate stockpiling for later transport with written concurrence from the CO. The contractor will be required to ensure that contamination is not spread while materials are moved or stockpiled.

I. Archaeological Protection

a. General

i. Summary

1. The work of this section consists of protecting archeological resources contained in soil deposits. The project area is within a highly sensitive archeological site. The area may contain historically significant buried features or artifacts. The Contractor shall strictly limit and control the depth and/or extent of excavations, minimizing them to the greatest extent possible.

ii. Definitions

1. Archeological Resources: Archeological resources are the physical evidences of past human activity, including evidences of the effects of that activity on the environment. Archeological resources represent both prehistoric and historic time periods. They are found above and below ground and under water.

2. Archeologically Sensitive Areas: Areas that have the potential to contain significant (National Register eligible) archeological resources. If National Register eligible or listed archeological resources cannot be avoided, an appropriate mitigation strategy shall be developed in consultation with the state historic preservation officer and, if necessary, associated American Indian tribes.

3. Non-sensitive Areas: Areas with little, if any, potential of containing significant (National Register eligible) archeological resources. Fort Vancouver National Historic Site is within a National Historic District and contains no non-sensitive areas.

4. Archeological Monitor: Representative of the Government designated to oversee construction activities that could disturb archeological resources.

iii. Submittals

1. Daily Work Schedule; Submit a Daily work Schedule detailing construction. Submit to Contracting Officer 30 days before start of ground disturbing site work. This information shall be included in the 3-week look-ahead schedule with notes identifying any ground disturbing activities within 30 days of the weekly meeting.

iv. Quality Assurance

1. At least one week before on-site work begins, Contractor shall meet with Contracting

Officer and Archeological Monitor to discuss Daily Work Schedule and equipment and special methods to be used. Contractor shall ensure that approved Daily Work Schedule is followed throughout construction. Special methods may include hand digging in especially sensitive locations.

b. Products

i. Daily Work Schedule

1. A Daily Work Schedule is required for all ground-disturbing activities. Include all work that is to occur within the area and key the schedule to the drawings to include the following:

a. Starting and ending dates of ground-disturbing activities.

b. Locations of temporary facilities, such as barriers, field offices, staging areas, sanitary facilities, borrow pits, and haul and access roads.

c. Types of construction, such as clearing, topsoil stripping, structure or trench excavation, pole or post removal, augering, landscaping, and…