This is a request for proposals for abatement of hazardous materials and associated demolition and repairs at historic buildings in Fort Vancouver National Historic Site in Vancouver, Washington. The National Park Service seeks a firm-fixed-price contract to remove asbestos, lead, mercury, PCBs, and wildlife excrement from multiple buildings. The contractor must complete work within 180 days of award and obtain payment and performance bonds of 100% each. Proposals are due by the date specified in any amendments on SAM.gov, where the solicitation and updates will be posted. The estimated value is $250,000 to $1,000,000 depending on option quantities. The NAICS code is 562910 and the small business size standard is $22 million average annual revenue. The government will consider both technical capability and price in a best value determination.

View the file

Other files

File Type Posted
Attachment 10 Final Clarifications_0003.pdf PDF
Sol_140P8320R0008_Amd_0003.pdf PDF
Sol_140P8320R0008_Amd_0002.pdf PDF
Sol_140P8320R0008_Amd_0001.pdf PDF
forms to return with proposal - revised 140P8320R0008_0001.docx DOCX document
Attachment 9 Site visit notes_0001.pdf PDF
Attachment 7a Revised Wage Determination_0001.pdf PDF
Attachment 3e - B748 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3a - B410 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3j - B786 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 6 Building Floor Plans_20200723.pdf PDF
Attachment 4c - B991 and B993 Asbestos Survey Field Notes.pdf PDF
Attachment 3g - B752 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3f - B749 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 4b - B993 Pre-Renovation Asbestos Survey Report.pdf PDF
Attachment 3c - B725 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3i - B754 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3h - B753 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 3b - B721 Limited Hazardous Materials Survey Report.pdf PDF
Attachment 4a - B991 Pre-Renovation Asbestos Survey Report.pdf PDF
Attachment 5 Building Descriptions.pdf PDF
forms to return with proposal 140P8320R0008.docx DOCX document
Attachment 1 Statement of Work.pdf PDF
Sol_140P8320R0008.pdf PDF
Attachment 2 Task List for each building.pdf PDF
FAQs for RFP 140P8320R0008.pdf PDF
Attachment 7 Wage Determination 7-3-20.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1011 SW Klickitat Way, Suite 104, Seattle, Washington 98134 Phone 206-381-1128 Toll Free 800-666-2959 Fax 206-254-4279

Environmental Consulting Hazardous Materials Management Industrial Hygiene Services Construction Management Indoor Air Quality

LIMITED HAZARDOUS MATERIALS SURVEY REPORT

NATIONAL PARK SERVICE

FORT VANCOUVER NATIONAL HISTORIC SITE

BUILDING 746

East Vancouver Barracks Building 746

Vancouver, Washington 98661

October 31st, 2019

Prepared For:

Mary Hazell National Park Service 612 East Reserve Street Vancouver, WA 98661 ii

Limited Hazardous Materials Survey Report

National Park Service Fort Vancouver Historic Site

East Vancouver Barracks Building 746 Vancouver, Washington 98661

EHSI Project No.: # 11295

The material and data in this report were prepared under the supervision and direction of the undersigned.

Rory Peterson Lead AHERA Building Inspector

Derica Escamilla Principal of Hazardous Materials Services iii

TABLE OF CONTENTS

Acronym List ..................................................................... iv

1.0 EXECUTIVE SUMMARY

1.1 BACKGROUND

1.2 EXTENT OF CURRENT SURVEY

1.3 ACM MATERIALS FOUND

1.4 OPINIONS AND RECOMMENDATIONS

1.5 LIMITATIONS/DISCLAIMER

2.0 LIMITED LEAD AND ASBESTOS SURVEY REPORT

2.1 BACKGROUND

2.2 BUILDING DESCRIPTION

2.3 SAMPLING METHODOLOGY

2.3.1 Asbestos-Containing Materials

2.3.2 Lead-Containing Paint/Lead-Containing Materials

2.4 SAMPLING RESULTS

2.4.1 Asbestos-Containing Materials

2.4.2 Lead-Containing Paint and Building Materials

2.4.3 Toxicity Characteristic Leaching Procedure Sampling

2.4.4 Polychlorinated Biphenyls

2.4.5 Mercury-Containing Fluorescent Light Tubes, CFL Bulbs, and thermostats

3.0 LIMITATIONS

4.0 STANDARD OF CARE

5.0 CERTIFIED AHERA BUILDING INSPECTORS

APPENDICES

A ........................ Asbestos Laboratory Reports and Field Data Forms B ........................ Lead Laboratory Reports and Field Data Forms C ........................ Toxicity Characteristic Leaching Procedure Laboratory Report and

Field Data Form D ........................ Certified AHERA Building Inspector Certificates E ........................ Laboratory Certifications for Asbestos, Lead, & TCLP Analysis F ........................ Sample Location Drawings for Asbestos, Lead, & TCLP iv

ACRONYM LIST

ACM .......................Asbestos-Containing Material ACT ........................Acoustical Ceiling Tile AHERA ....................Asbestos Hazard Emergency Response Act AHU .......................Air Handling unit AIHA ......................American Industrial Hygiene Association CFL ........................Compact Fluorescent Light CFR ........................Code of Federal Regulations Dia. ........................Diameter DOSH .....................Washington State Department of Labor and Industries, Division of

Occupational Safety and Health EA ..........................Each Ecology ...................Washington State Department of Ecology EHSI .......................EHS-International, Inc.

ELLAP .....................Environmental Lead Laboratory Accreditation Program GWB .......................Gypsum Wall Board Hg ..........................Mercury JC ..........................Joint Compound LCM ........................Lead-Containing Material LCP ........................Lead-Containing Paint L&I .........................Washington State Department of Labor and Industries mg/L ......................Milligrams Per Liter N/A ........................Not Applicable ND .........................None Detected NVL ........................NVL Laboratories, Inc.

NVLAP ....................National Voluntary Laboratory Accreditation Program OD .........................Outside Diameter OSHA .....................US Occupational Safety and Health Administration Pb ..........................Lead PCBs .......................Polychlorinated Biphenyls PLM ........................Polarized Light Microscopy ppm .......................Parts per Million QA .........................Quality Assurance RCW .......................Revised Code of Washington SACT ......................Suspended Acoustical Ceiling Tile SAT ........................Seattle Asbestos Test, LLC SF ..........................Square Feet SWCAA ...................Southwest Clean Air Agency TCLP .......................Toxicity Characteristic Leaching Procedure TSI .........................Thermal System Insulation WAC .......................Washington Administrative Code

wt. .........................Weight w/ ..........................With XRF ........................x-ray fluorescence

Fort Vancouver National Historic Site – B746

EHSI Project 11295

1.0 EXECUTIVE SUMMARY

1.1 BACKGROUND

The National Park Service (NPS) plans to renovate Building 746 (B746) at the Fort Vancouver National Historic Site (FV NHS) located at 612 E. Reserve Street, Vancouver, Washington. The NPS has contracted EHS-International, Inc. (EHSI), a hazardous materials and industrial hygiene consulting firm, to conduct a Limited Lead and Asbestos Survey of B746 in preparation for this project. The intent of the survey is to specifically identify and quantify asbestos-containing building materials (ACM), interior lead-containing paint (LCP), other interior lead-containing building materials (LCM), to collect a lead toxicity characteristic leaching procedure (TCLP) sample representative of all materials that may be in the assumed waste stream, and to inspect and quantify fluorescent light fixtures that may contain polychlorinated biphenyl (PCB)-containing ballasts, and mercury (Hg)-containing fluorescent light tubes, compact fluorescent light (CFL) bulbs, and high intensity discharge (HID) lamps, that may be impacted by renovation activities.

1.2 EXTENT OF CURRENT SURVEY

EHSI inspected accessible interior and exterior suspect ACM that may be potentially impacted by future projects. Accessible suspect materials were sampled including, but not limited to:

interior and exterior wall systems, window systems, and mechanical systems. The LCP and LCM survey was limited to the interior of the building only. EHSI accomplished a representative destructive inspection; however, in areas inaccessible for inspection (e.g., energized heaters and electrical equipment) suspect materials were assumed to be ACM.

1.3 ACM MATERIALS FOUND

SUMMARY OF ASBESTOS-CONTAINING MATERIALS

NATIONAL PARK SERVICE

FORT VANCOUVER BARRACKS – BUILDING 746

ASBESTOS MATERIAL DESCRIPTION LOCATION

Non-ACM beige/off-white vinyl stair tread on ACM beige/yellow/brown mastic (on wood stairs) [Sample #: 11295-B746-05]

Stairs

ACM white fibrous duct seam tape (~ every 2’-4’on 1’x1’ metal duct seams) [Sample #: 11295-B746-12, 13, 14, & 64]

1st Floor, Boiler Room and Bathroom 107 2nd Floor, Stairs, Top Landing, and Room 204

ACM white fibrous duct seam tape (~ every 2’-4’ on 2’x1’ metal duct seams above SACT, in GWB ceiling chase, and in vertical duct chase) [Sample #: 11295-B746-12, 13, 14, & 64]

Throughout

ACM white fibrous duct seam tape (~ every 2’-4’on 4’x2’ metal duct seams) [Sample #: 11295-B746-12, 13, 14, & 64]

1st Floor, Boiler Room

SUMMARY OF ASBESTOS-CONTAINING MATERIALS

NATIONAL PARK SERVICE

FORT VANCOUVER BARRACKS – BUILDING 746

ASBESTOS MATERIAL DESCRIPTION LOCATION

2’6” Dia.x7’ hot water tank w/ ACM white TSI jacket w/ non- ACM beige/off-white/gray fabric lagging [Sample #: 11295-B746-51, 52, 53]

1st Floor, Boiler Room

ACM beige/brown fibrous gasket (on old boiler expansion) [Sample #: 11295-B746-59]

1st Floor, Boiler Room

2’1”x2’5”x3’4” Trane natural gas heaters w/ assumed ACM internal components, sealant, and/or insulation 1st Floor, Boiler Room

2’ Dia.x5’ old metal boiler/tank w/ assumed ACM internal components, sealant, and/or insulation 1st Floor, Boiler Room

Small electrical panels w/ assumed ACM internal components (<1 SF in size)

1st Floor, Boiler Room

Electrical panels w/ assumed ACM internal components (1-6 SF in size)

1st Floor, Boiler Room

KEY: ACM = asbestos containing material, Dia. = diameter, OD = outer diameter, SACT = suspended acoustical ceiling tile, TSI = thermal system insulation, SF = square feet, w/ = with

1.4 OPINIONS AND RECOMMENDATIONS

EHSI recommends that all impacted ACM identified in paragraph 1.3 be removed and disposed of prior to any renovation and demolition activities.

Any suspect materials not identified as having been surveyed in this report must be treated as an ACM until determined otherwise by a Certified Asbestos Building Inspector and NVLAP certified laboratory.

Washington State Department of Labor and Industries (L&I) Division of Occupational Safety and Health (DOSH) and the US Occupational Safety and Health Administration (OSHA) require employers to conduct a hazard assessment and take appropriate worker protection precautions whenever building materials are disturbed that have detectable quantities of lead. Since the type of work planned (e.g., demolition or renovation) will disturb the LCP and LCM, the contractor will need to perform an initial exposure assessment and lead awareness training in accordance with the regulations. Special care should be taken to reduce potential employee exposure to lead when demolishing porcelain bathroom fixtures and painted metal, including reducing airborne dust (eq., water misting and use of hand tools, and/or local exhaust ventilation).

A select number of fluorescent light fixtures inspected have magnetic ballasts which are assumed to contain greater than two parts per million (> 2 ppm) PCB-dielectric fluid. Magnetic ballasts must be removed from fixtures and disposed of as Washington Department of Ecology (Ecology) Dangerous Waste. All fluorescent tubes and lamps contain mercury; any fluorescent lamps/tubes to be disturbed during the project must be recycled as (Ecology) Universal Waste.

1.5 LIMITATIONS/DISCLAIMER

This report does not represent a comprehensive hazardous materials investigation for the subject property. This investigation has been conducted by EHSI under a specific scope of work authorized by the NPS for a specific purpose. Exterior lead sampling was excluded from the scope of work. All exterior painted surfaces are assumed to have lead-containing paint.

This report and accompanying appendices include the supporting information for this executive summary.

2.0 LIMITED LEAD AND ASBESTOS SURVEY REPORT

2.1 BACKGROUND

The NPS has contracted EHSI to accomplish a pre-renovation limited hazardous materials survey of the existing structure and to collect a lead-TCLP sample representative of the anticipated demolition debris. For the limited hazardous materials survey, EHSI was tasked to use applicable federal, state, and local guidelines in the accomplishment of its survey. EHSI was further tasked to provide a written survey report including: identification of all suspect materials; a determination of whether suspect materials were: ACM, LCP, and LCM, and to provide analytical reports indicating the presence and quantity of the hazardous materials.

On August 28th and 29th, 2019, EHSI conducted a Limited Hazardous Materials Survey that meets the Washington State “Good Faith Survey” requirements as cited in Revised Code of Washington (RCW) 49.26.016 and implemented by L&I DOSH regulation, Washington Administrative Code (WAC) 296-62-07721, and Regulation Section 476-040 of the Southwest Clean Air Agency (SWCAA).

2.2 BUILDING DESCRIPTION

Building 746 is located at East Vancouver Barracks, Vancouver, Washington. The building is a two-story wood-framed barracks building with wood siding exterior walls and composite shingle roofing. B746 sits on CMU blocks and slab-on-grade for the restroom and mechanical room. Interior finishes include GWB walls and ceilings, 1’x1’ ACT on GWB walls and ceilings, SACT ceilings, vinyl cove base, wood base boards, wood slat siding, carpet flooring, hard wood floors, and painted concrete. Windows are operable wood-framed windows with counterweights in the frames. Heating and cooling is provided by a forced air HVAC (heating, ventilation, and air conditioning) system. Fluorescent light fixtures provide light to the interior of the structure.

2.3 SAMPLING METHODOLOGY

2.3.1 Asbestos-Containing Materials

The EHSI field inspectors are asbestos Building Inspectors, certified under the requirements of the United States Environmental Protection Agency (USEPA) AHERA regulation 40 Code of Federal Regulations (CFR) 763, Subpart E. Copies of their certificates are provided in Appendix D. The number of bulk samples collected and their locations are based on the AHERA regulation and the guidelines provided by the USEPA Document 560/5-85-030a, October 1985, Asbestos in Buildings: Simplified Sampling Scheme for Friable Surfacing Materials.

EHSI collected samples and obtained analytical data for suspect ACM identified on the property. Once collected, each bulk sample was sealed in an unadulterated plastic bag to eliminate the possibility of cross-contamination. “Chain-of-Custody” tracking was followed to maintain sample integrity during handling and data reporting at EHSI and the analytical laboratory. As specified in 40 CFR Chapter 1 (1-1-87 edition) Part 763, Subpart F, and Appendix A, each sample was analyzed using polarized light microscopy (PLM) / dispersion staining techniques, in accordance with USEPA Method 600/R-93/116. Samples were analyzed for asbestos content by Seattle Asbestos Test, LLC (SAT) located in Seattle, Washington. SAT participates in the National Institute for Standards and Technology (NIST) National Voluntary Laboratory Accreditation Plan (NVLAP). Laboratory NVLAP certifications are included in Appendix E. Only materials containing more than 1% total asbestos were classified as “asbestos-containing” based on USEPA, state, and local regulations.

2.3.2 Lead-Containing Paint/Lead-Containing Materials

EHSI used a Niton Model XLp x-ray fluorescence (XRF) Spectrum Analyzer to measure lead content on interior paint coatings and other suspect LCM. Measurements were representative of all layers of paint and/or LCM. A summary of Lead Paint XRF results is provided in Table 3.

Bulk quality assurance samples were taken for a representative number of LBP and LCM and were sent to NVL located in Seattle, Washington, an accredited laboratory for Atomic Absorption Spectroscopy (USEPA Method-7000B) by the American Industrial Hygiene Association (AIHA) under the Environmental Lead Laboratory Accreditation Program (ELLAP).

Copies of laboratory reports and field data forms for lead are in Appendix B.

All XRF sample shots are representative of that color on that specific substrate and component. The report user shall deduce from the data in Table 3, if certain building materials throughout the entire building contain lead and should not assume that what is detected is only in the specific location identified in the Table.

2.4 SAMPLING RESULTS

2.4.1 Asbestos-Containing Materials

Ninety-one (91) bulk samples of suspect ACM were collected as part of the survey. Limited destructive inspection was conducted to identify hidden and/or concealed materials. Copies of the asbestos analytical laboratory results are included in Appendix A. Asbestos sample location drawings are provided in Appendix F. Asbestos sampling information including sample number, material description, sample location, and analytical results are summarized in Table

1. The ACM and assumed ACM identified during this survey, including the quantity and location, is summarized in Table 2. All suspect materials were accessible for sampling.

TABLE 1

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-01

1st Floor, Office 102

Layer 1: Reddish brown/white carpet Layer 2: Trace off-white internal mastic Layer 3: Beige/off-white mesh backing w/ plastic Layer 4: Yellow/tan mastic Layer 5: Brown transition strip Layer 6: Clear mastic

ND

(All Layers)

N/A (All Layers)

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-02

1st Floor, Office 104

Layer 1: Reddish brown/white carpet Layer 2: Trace off-white internal mastic Layer 3: Beige/off-white mesh backing w/ plastic Layer 4: Yellow/tan mastic Layer 5: Brown transition strip Layer 6: Clear mastic (on wood)

ND

(All Layers)

N/A (All Layers)

11295- B746-03

1st Floor, Office 106

Layer 1: Reddish brown/white carpet Layer 2: Trace off-white internal mastic Layer 3: Beige/off-white mesh backing w/ plastic Layer 4: Yellow/tan mastic Layer 5: Brown transition strip (on wood)

ND

(All Layers)

N/A (All Layers)

11295- B746-04 Stairs

Layer 1: Beige/off-white/tan vinyl stair tread Layer 2: Beige/yellow mastic Layer 3: Trace brown wood stairs (on wood)

ND

(All Layers)

N/A (All Layers)

11295- B746- 05QAx

Stairs

Layer 1: Beige/off-white vinyl stair tread Layer 2: Beige/yellow/ brown mastic (on wood stairs)

L1: ND

L2: 4%

Chrysotile

11295- B746-06

1st Floor, Main Room 108

Layer 1: 2’x4’ Beige/gray fibrous SACT (w/ small worm track & pin hole pattern) Layer 2: Beige/yellow/off-white coating on back

ND

(All Layers)

N/A (All Layers)

11295- B746-07

1st Floor, Main Room 108

Layer 1: Brown/tan paper vapor barrier w/ black mastic Layer 2: Pink fiberglass insulation (on top of SACT)

ND

(All Layers)

N/A (All Layers)

11295- B746-08

1st Floor, Main Room 108

Layer 1: 2’x4’ Beige/gray fibrous SACT (w/ small worm track & pin hole pattern) Layer 2: Beige/yellow/off-white coating on back

ND

(All Layers)

N/A (All Layers)

11295- B746-09

1st Floor, Main Room 108

Layer 1: Brown/tan paper vapor barrier w/ black mastic Layer 2: Pink fiberglass insulation (on top of SACT)

ND

(All Layers)

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-10

1st Floor, Office 103

Layer 1: 2’x4’ Beige/gray fibrous SACT (w/ small worm track & pin hole pattern) Layer 2: Beige/yellow/off-white coating on back

ND

(All Layers)

N/A (All Layers)

11295- B746-11

1st Floor, Office 103

Layer 1: Brown/tan paper vapor barrier w/ black mastic Layer 2: Pink fiberglass insulation (on top of SACT)

ND

(All Layers)

N/A (All Layers)

11295- B746-

12QA

1st Floor, Main Room

White fibrous duct seam tape w/ paint (on 2’x1’ metal duct above SACT, every 2’)

60% Chrysotile

11295- B746-13

1st Floor, Main Room

White fibrous duct seam tape w/ paint (on 2’x1’ metal duct above SACT, every 2’)

64% Chrysotile

11295- B746-14

2nd Floor, Main Room

White fibrous duct seam tape w/ paint (on 1’x1’ metal duct on GWB ceiling chase)

66% Chrysotile

11295- B746-15

1st Floor, Main Room 108

Layer 1: Gray duct tape (on newer ducts to diffusers, from older ducts) Layer 2: Gray mastic

ND

(All Layers)

N/A (All Layers)

11295- B746-16

1st Floor, Main Room 108

Layer 1: Gray/silver duct tape (on newer ducts to diffusers, from older ducts) Layer 2: Gray mastic

ND

(All Layers)

N/A (All Layers)

11295- B746-171

Composite Result <1%

1st Floor, Main Room 109

Layer 1: Texturing/JC w/ paint & paper Layer 2: GWB wall w/ paper (corner)

L1: 0.25%

L2: ND

B746-181

Composite Result <1%

1st Floor, Main Room 109

Layer 1: Trace texturing w/ paint Layer 2: GWB wall w/ paper (mid-wall)

B746-191

Composite Result <1%

1st Floor, Main Room 109

Layer 1: Trace texturing w/ paint Layer 2: GWB wall w/ paper (mid-wall)

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-20

1st Floor, Main Room 108

Layer 1: Black sealant Layer 2: Black & yellow fiberglass duct insulation Layer 3: White/off-white mastic Layer 4: White plastic (in 2’x2’ return duct)

ND

(All Layers)

N/A (All Layers)

11295- B746-

21QA

1st Floor, Main Room 108

Layer 1: Black sealant Layer 2: Black/green & yellow fiberglass duct insulation w/ paint Layer 3: Trace white/off-white mastic Layer 4: White plastic (in 2’x2’ metal return duct)

ND

(All Layers)

N/A (All Layers)

11295- B746-

22QA

1st Floor, Main Office 106

Layer 1: 1’x1’ Light gray fibrous ACT w/ white paint Layer 2: Brown/tan/light brown glue dots (on small worm track & pin hole pattern)

ND

(All Layers)

N/A (All Layers)

11295- B746-23

1st Floor, Office 103

Layer 1: 1’x1’ Light gray fibrous ACT w/ white paint Layer 2: Beige/tan/yellow glue dots Layer 3: GWB paper w/ paint Layer 4: Red paper spacer

ND

(All Layers)

N/A (All Layers)

11295- B746-

24QA

1st Floor, Office 105

Layer 1: 1’x1’ Light gray fibrous ACT w/ white paint Layer 2: Beige/tan/yellow glue dots Layer 3: Wood door Layer 4: Red paper spacer

ND

(All Layers)

N/A (All Layers)

11295- B746-25

1st Floor, Main Room 108

Layer 1: JC w/ paint Layer 2: GWB wall w/ paper (corner)

ND

(All Layers)

N/A (All Layers)

11295- B746-26

1st Floor, Main Room 108

Layer 1: Trace JC w/ paint Layer 2: GWB wall w/ paper (corner)

ND

(All Layers)

N/A (All Layers)

11295- B746-27

1st Floor, Main Room 108

GWB wall w/ paint and paper (mid-wall) ND N/A

11295- B746-28

1st Floor, Main Room 108

GWB wall w/ paint and paper (mid-wall) ND N/A

11295- B746-29

1st Floor, Office 106

GWB wall w/ paint and paper (mid-wall)

ND N/A

11295- B746-30

2nd Floor, Main Room

Layer 1: JC w/ paint Layer 2: GWB wall w/ paper (corner)

ND

(All Layers)

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-31

2nd Floor, Main Room

Layer 1: JC w/ paint Layer 2: Yellow seam tape (corner)

ND

(All Layers)

N/A (All Layers)

11295- B746-32

2nd Floor, Office 203

Layer 1: JC w/ paint Layer 2: GWB wall w/ paper (at seam)

ND

(All Layers)

N/A (All Layers)

11295- B746-33

2nd Floor, Office 202

GWB wall w/ paint & paper (mid-wall)

ND N/A

11295- B746-34

2nd Floor, Main Room

GWB wall w/ paint & paper (mid-wall) ND N/A

11295- B746-35

2nd Floor, Room 204

Layer 1: JC w/ paper Layer 2: GWB wall patch w/ paper

ND

(All Layers)

N/A (All Layers)

11295- B746-36

2nd Floor, Room 204

GWB wall patch w/ paper ND N/A

11295- B746-37

2nd Floor, At Top of Stairs

Layer 1: 1’x1’ Light gray fibrous ACT w/ white paint Layer 2: Dark brown glue dots (on GWB ceiling)

ND

(All Layers)

N/A (All Layers)

11295- B746-38

2nd Floor, Main Room

Layer 1: 1’x1’ Light gray fibrous ACT w/ white paint Layer 2: Dark brown glue dots (on GWB ceiling)

ND

(All Layers)

N/A (All Layers)

11295- B746-39

2nd Floor, Main Room 201

Layer 1: 1’x1’ Light gray fibrous ACT w/ white paint Layer 2: Dark brown glue dots (on GWB ceiling)

ND

(All Layers)

N/A (All Layers)

11295- B746-40 Ext. N Side White door frame caulking ND N/A

11295- B746-41 Ext. W Side

Tan/beige door frame caulking w/ paint (on wood-framed doors between trim/frame & siding)

ND N/A

11295- B746-42

Ext. W. Side

Tan/beige door frame caulking w/ paint (on wood-framed doors between trim/frame & siding)

ND N/A

11295- B746-43 Ext. E. Side

White door frame caulking w/ paint (on double door, between trim & siding)

ND N/A

11295- B746-44 Ext. E. Side

White vent cover frame caulking w/ paint (on 2’x2’ cover at boiler exhaust)

ND N/A

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-45

1st Floor, Boiler Room

Layer 1: Off-white JC w/ silver paint Layer 2: GWB ceiling w/ paper (at seam)

ND N/A

11295- B746-46

1st Floor, Boiler Room

GWB wall w/ silver paint & paper (mid-wall) ND N/A

11295- B746-47

1st Floor, Boiler Room

GWB wall w/ silver paint & paper (mid-wall)

ND

(All Layers)

N/A (All Layers)

11295- B746-48

2nd Floor, Main Room

Black coating w/ beige and silver paint (on 4” OD drainpipe)

ND N/A

11295- B746-49

2nd Floor, Main Room

Black coating w/ beige and silver paint (on 4” OD drainpipe)

ND N/A

11295- B746-50

1st Floor, Main Room 108

Black coating w/ blue and silver paint (on 4” OD drainpipe)

ND N/A

11295- B746-51

1st Floor, Boiler Room

Layer 1: Beige/off-white/gray fabric lagging w/ silver paint Layer 2: White TSI jacket (on 2’6”x7’ hot water tank)

L2: 15%

B746-52

1st Floor, Boiler Room

Layer 1: Beige/off-white/gray fabric lagging w/ silver paint Layer 2: White TSI jacket

L2: 18%

B746-53

1st Floor, Boiler Room

Layer 1: Beige/off-white/gray fabric lagging w/ silver paint Layer 2: White TSI jacket

L2: 21%

B746-54 Attic S. Side

Beige/off-white fluffy blown-in insulation ND N/A

11295- B746-55

Attic S.

Counter

Beige/off-white blown-in insulation

ND N/A

11295- B746-56

Attic N. Side Beige/off-white fluffy blown-in insulation

ND N/A

11295- B746-57 Attic S. Side

Layer 1: Gray/clear fabric vapor barrier Layer 2: Trace yellow mastic Layer 3: Black plastic (under roofing on wood slats)

ND

(All Layers)

N/A (All Layers)

11295- B746-58 Attic N. Side

Layer 1: Gray/clear fabric vapor barrier Layer 2: Black plastic (under roofing on wood slats)

ND

(All Layers)

N/A (All Layers)

11295- B746-59

1st Floor, Boiler Room

Beige/brown fibrous gasket (on old boiler expansion) 65% Chrysotile

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-60

1st Floor, Boiler Room

Layer 1: Beige/tan pipe rope Layer 2: Black asphaltic sealant w/ paint (on water line fittings)

ND

(All Layers)

N/A (All Layers)

11295- B746-61

1st Floor, Boiler Room

Beige/tan penetrations putty w/ paint (at pipes into hot water heater)

ND N/A

11295- B746-62

1st Floor, Boiler Room

8” OD Black regulator gasket w/ paint (on natural gas lines)

ND N/A

11295- B746-63

1st Floor, Boiler Room

4’x2’ white/off-white flex duct (on ducting to furnaces)

ND N/A

11295- B746-64

1st Floor, Boiler Room

White/off-white fibrous duct seam tape w/ silver paint (on 1’x4’ duct)

62% Chrysotile

11295- B746-65

1st Floor, Boiler Room

White duct seam sealant (on large section of ducting connected to furnace)

ND N/A

11295- B746-66

1st Floor, Boiler Room

Beige pipe rope (on natural gas line fittings) ND N/A

11295- B746-67

1st Floor, Room 107 Rest Room

Black sink drain gasket (from single ceramic sink)

ND N/A

11295- B746-68

1st Floor, Room 107 Rest Room

Black sink drain gasket (from single ceramic sink)

ND N/A

11295- B746-69

1st Floor, Room 107 Rest Room

Tank sink drain putty (from large slop sink)

ND N/A

11295- B746-70

Ext. E. Side Hard gray window glazing putty w/ paint (on 3’x10”x4’8” wood-framed window)

ND N/A

11295- B746-71

Ext. E. Side White window glazing putty patch w/ paint (on 3’x10”x4’8” wood-framed window)

ND N/A

11295- B746-

72QA

Ext. E. Side Beige/tan window glazing putty patch w/ paint (on 3’x10”x4’8” wood-framed window)

ND N/A

11295- B746-

73QA

Ext. E. Side Hard gray window glazing putty w/ paint (on 3’x10”x4’8” wood-framed window)

ND N/A

11295- B746-74

Ext. S. Side Hard gray window glazing putty w/ paint (on 3’x10”x4’8” wood-framed window)

ND N/A

11295- B746-75

Ext. S. Side White window glazing putty patch w/ paint (on 3’x10”x4’8” wood-framed window)

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-76

Ext. W. Side Gray window glazing putty patch w/ paint (on 3’10”x4’8” wood-framed window)

ND N/A

11295- B746-77

Ext. W. Side Gray window glazing putty patch w/ paint (on 3’10”x4’8” wood-framed window)

ND N/A

11295- B746-78 Ext. E. Side

Brown/tan paper vapor barrier w/ black mastic between paper layers (behind wood siding on wood)

ND N/A

11295- B746-79

Ext. E. Side

Brown/tan paper vapor barrier w/ black mastic between paper layers (behind wood siding on wood)

ND N/A

11295- B746-80

Ext. W. Side

Brown/tan paper vapor barrier w/ black mastic between paper layers (behind wood siding on wood)

ND N/A

11295- B746-81 Roof

Layer 1: Black composite shingle roofing w/ granules Layer 2: Black asphaltic tar Layer 3: Black asphaltic composite shingle roofing w/ granules Layer 4: Black asphaltic composite shingle roofing w/ granules Layer 5: Black asphaltic felt vapor barrier Layer 6: Black asphaltic felt vapor barrier Layer 7: Black plastic vapor barrier Layer 8: Black asphaltic tar Layer 9: Wood roof deck

ND

(All Layers)

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-82 Roof

Layer 1: Black asphaltic composite shingle roofing w/ granules Layer 2: Trace black asphaltic tar Layer 3: Green/black asphaltic composite shingle roofing w/ granules Layer 4: Black asphaltic tar Layer 5: Clear plastic vapor barrier Layer 6: Black asphaltic felt vapor barrier Layer 7: Black asphaltic felt vapor barrier Layer 8: Black asphaltic felt vapor barrier Layer 9: Black plastic Layer 10: Black asphaltic tar Layer 11: Black asphaltic tar Layer 12: Wood roof deck

ND

(All Layers)

N/A (All Layers)

11295- B746-83 Roof

Layer 1: Black asphaltic composite shingle roofing w/ granules Layer 2: Trace black asphaltic tar Layer 3: Green/black asphaltic composite shingle roofing w/ granules Layer 4: Black asphaltic tar Layer 5: Clear plastic vapor barrier Layer 6: Black asphaltic felt vapor barrier Layer 7: Black asphaltic felt vapor barrier Layer 8: Black asphaltic felt vapor barrier Layer 9: Black plastic Layer 10: Black asphaltic tar Layer 11: Black asphaltic tar Layer 12: Wood roof deck

ND

(All Layers)

N/A (All Layers)

11295- B746-84

Exterior NE Outside Boiler

Thick black paint/coating (on 10” OD round duct into chimney)

SUMMARY OF ASBESTOS BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

SAMPLE

LOCATION MATERIAL DESCRIPTION

ASBESTOS

TYPE OF

ASBESTOS

11295- B746-85

Exterior NE Outside Boiler

Thick black paint/coating (on 10” OD round duct into chimney)

ND N/A

11295- B746-86

Exterior NE Outside Boiler

Thick black paint/coating (on 10” OD round duct into chimney)

ND N/A

11295- B746-87

Exterior NE Outside Boiler

14” OD Black regulator gasket w/ paint (on natural gas piping to natural gas meter)

ND N/A

11295- B746-88

Exterior NE Outside Boiler

16” Square tan gaskets w/ paint (on natural gas meter)

ND N/A

11295- B746-89

Exterior NE Outside Boiler

Layer 1: Red chimney brick Layer 2: Gray mortar

ND

(All Layers)

N/A (All Layers)

11295- B746-90

2nd Floor, Main Room

Layer 1: 4” Brown cove base Layer 2: White/off-white mastic

ND

(All Layers)

N/A (All Layers)

11295- B746-91

2nd Floor, Office 202

Layer 1: 4” Brown cove base Layer 2: White/off-white mastic

ND

(All Layers)

N/A (All Layers)

KEY: ACT = acoustical ceiling tile, GWB = gypsum wall board, JC = joint compound, ND = non-detect, N/A = not applicable, OD = outside diameter, SACT = suspended acoustical ceiling tile, TSI = thermal system insulation, w/ = with

X When QA lab and primary lab sample results differed, EHSI reported the most restrictive (e.g., highest % asbestos) in Table 1. Analytical results for all analyses are provided in Appendix A.

1 Point Counted Results. Preliminary analytical reports indicated that various samples contained approximately 2% to 3% chrysotile asbestos (Sample #s 11295-B746-17, 18, and 19). EHSI re-submitted the samples reported to have greater than 1% asbestos concentration for re-analysis using the more precise EPA “Point Count” method. The “Point Count” analytical method is recommended by the EPA for samples with less than 10% asbestos. Based on the results of that re-analysis, materials found to contain less than 1% (<1%) asbestos were determined to be a non-ACM (e.g., containing < 1% asbestos fibers) and are therefore not ACM.

Only the “Point Count” re-analysis concentrations are listed in Table 1. Analytical results for all analyses are provided in Appendix A.

Samples containing <1% asbestos fibers are considered to be a non-ACM. Materials that contain <1% asbestos are not regulated for disposal purpose. However, removal of <1% asbestos materials are considered an unclassified asbestos operation by DOSH. As directed by WRD 23.30, for all other demolition of materials with <1% asbestos, employees shall have received at least two hours of asbestos awareness training as specified L&I DOSH Instruction WAC 296-62-07722(5). A list of materials with <1% asbestos is provided below

<1% asbestos texturing on non-ACM GWB walls throughout Main Room 109 on 1st Floor

Table 2 summarizes materials identified by EHSI as containing greater than 1% asbestos fibers during its survey, and un-sampled materials assumed to be ACM. The Table 2 Summary of Asbestos Containing Materials is for engineering cost estimating purposes and is not intended for bid quantifications.

TABLE 2

SUMMARY OF ASBESTOS-CONTAINING MATERIALS

NATIONAL PARK SERVICE

FORT VANCOUVER BARRACKS – BUILDING 746

ASBESTOS MATERIAL DESCRIPTION LOCATION QUANTITY

Non-ACM beige/off-white vinyl stair tread on ACM beige/yellow/brown mastic (on wood stairs) [Sample #: 11295-B746-05]

Stairs 80 SF

ACM white fibrous duct seam tape (~ every 2’-4’on 1’x1’ metal duct seams) [Sample #: 11295-B746-12, 13, 14, & 64]

1st Floor, Boiler Room and Bathroom 107 2nd Floor, Stairs, Top Landing, and Room 204

~20 EA

(seams)

ACM white fibrous duct seam tape (~ every 2’-4’ on 2’x1’ metal duct seams above SACT, in GWB ceiling chase, and in vertical duct chase) [Sample #: 11295-B746-12, 13, 14, & 64]

Throughout

~75 EA

(seams)

ACM white fibrous duct seam tape (~ every 2’-4’on 4’x2’ metal duct seams) [Sample #: 11295-B746-12, 13, 14, & 64]

1st Floor, Boiler Room

~6 EA

(seams)

2’6” Dia.x7’ hot water tank w/ ACM white TSI jacket w/ non-ACM beige/off-white/gray fabric lagging [Sample #: 11295-B746-51, 52, 53]

1st Floor, Boiler Room 1 EA

ACM beige/brown fibrous gasket (on old boiler expansion) [Sample #: 11295-B746-59]

1st Floor, Boiler Room 1 EA

2’1”x2’5”x3’4” Trane natural gas heaters w/ assumed ACM internal components, sealant, and/or insulation

1st Floor, Boiler Room

3 EA

2’ Dia.x5’ old metal boiler/tank w/ assumed ACM internal components, sealant, and/or insulation

1st Floor, Boiler Room 1 EA

Small electrical panels w/ assumed ACM internal components (<1 SF in size)

1st Floor, Boiler Room 2 EA

Electrical panels w/ assumed ACM internal components (1-6 SF in size)

1st Floor, Boiler Room

1 EA

KEY: ACM = asbestos containing material, OD = outer diameter, EA = each, SF = square feet, TSI = thermal system insulation

ACM identified in this survey should not be disturbed unless handled by personnel who are properly trained and certified in asbestos work. Demolition and/or renovation activities by contractors may expose concealed suspect ACM. Contractors should be aware of the potential for concealed suspect ACM and have pre-planned contingencies for the handling of suspect ACM discovered during renovation and/or demolition work. Any concealed suspect ACM material that was not sampled or was assumed to be ACM and included in this report, must be treated as ACM until proven otherwise by a Certified AHERA Building Inspector and a certified laboratory. Contingency plans should include stopping work on identification of concealed suspect ACM, evacuation of the area, and sampling by a Certified AHERA Building Inspector. Concealed suspect material may include, but is not limited to: spray-applied coatings, asphalt or paper vapor barriers and mastics.

2.4.2 Lead-Containing Paint and Building Materials

Seventy (70) samples were analyzed for lead using the X-Ray fluorescence (XRF) analyzer.

Results marked with “<LOD” are less than the limit of detection. XRF sample results ranged from 22.6 milligrams of lead per square centimeter (mg Pb/cm2) to < LOD. Items in Tables 3 and 4 that are bolded in red font will trigger a negative exposure assessment and lead awareness training per WAC 296-155-17609.

Table 3 summarizes XRF lead samples, including sample number, material description, substrate, color, location and analytical results.

TABLE 3

XRF SAMPLING

SUMMARY OF PAINTED COMPONENTS AND MATERIALS

VANCOUVER BARRACKS – BUILDING 746

Read

Component Substrate Color Floor Room Lead Conc.

(mg/cm2)

SELF-

CALIBRATION

N/A N/A N/A N/A 2.37

2 CALIBRATION N/A RED N/A N/A 0.9

3 CALIBRATION N/A RED N/A N/A 0.9

4 CALIBRATION N/A RED N/A N/A 1.0

5 WALL DRYWALL OFF-WHITE FIRST RM 101 2.3

6 WALL WOOD OFF-WHITE FIRST RM 101 < LOD

7 DOOR WOOD OFF-WHITE FIRST RM 101 < LOD

8 DOOR FRAME WOOD OFF-WHITE FIRST RM 101 < LOD

9 WALL DRYWALL OFF-WHITE FIRST RM 97 2.2

10 WALL ACT DARK GREEN FIRST RM 102 < LOD

11 WALL ACT BEIGE FIRST RM 102 < LOD

12 COLUMN WOOD OFF-WHITE FIRST RM 105 < LOD

13 COLUMN ACT WHITE FIRST RM 104 < LOD

14 DOOR WOOD OFF-WHITE FIRST RM 104 < LOD

15 DOOR FRAME WOOD OFF-WHITE FIRST RM 105 < LOD

16 WINDOW WOOD VARNISH FIRST RM 105 0.07

17 WALL ACT WHITE FIRST RM 106 < LOD

18 TRIM WOOD VARNISH FIRST RM 106 < LOD

19 COLUMN WOOD OFF-WHITE FIRST RM 108 0.08

20 WALL DRYWALL OFF-WHITE FIRST RM 108 3.8

21 WALL WOOD OFF-WHITE FIRST RM 108 < LOD

DRINKING

FOUNTAIN

CERAMIC WHITE FIRST RM 108 22.6

XRF SAMPLING

SUMMARY OF PAINTED COMPONENTS AND MATERIALS

VANCOUVER BARRACKS – BUILDING 746

Read

Component Substrate Color Floor Room Lead Conc.

(mg/cm2)

23 VENT PIPE METAL OFF-WHITE FIRST RM 108 < LOD

24 WINDOW TRIM WOOD VARNISH FIRST RM 108 0.05

25 FLOOR WOOD VARNISH FIRST RM 108 < LOD

26 WINDOW WOOD VARNISH FIRST RM 109 0.05

27 WALL DRYWALL OFF-WHITE FIRST RM 109 < LOD

28 FA PANEL METAL RED FIRST RM 109 < LOD

29 DOOR WOOD VARNISH FIRST RM 107 0.09

30 WINDOW WOOD LIGHT BLUE FIRST RM 107 2.8

31 TRIM WOOD LIGHT BLUE FIRST RM 107 1.6

32 WALL WOOD OFF-WHITE FIRST RM 107 5.1

33 DRAINPIPE METAL OFF-WHITE FIRST RM 107 4.6

34 WINDOW WOOD GRAY FIRST

RM 107

SHOWER

3.9

35 WINDOW TRIM WOOD GRAY FIRST RM 107

SHOWER

6.9

36 WALL METAL GRAY FIRST

RM 107

SHOWER < LOD

37 SLOP SINK METAL WHITE FIRST

RM 107

SHOWER

4.7

38 TOILET CERAMIC WHITE FIRST

RM 107

SHOWER

3.7

39 STALL METAL BEIGE FIRST RM 107

SHOWER

< LOD

40 CEILING WOOD OFF-WHITE FIRST RM 107 6.3

41 BEAM WOOD OFF-WHITE FIRST RM 107 4.8

42 WALL WOOD OFF-WHITE SECOND STAIRWELL 4.6

43 WALL DRYWALL OFF-WHITE SECOND RM 204 < LOD

44 WINDOW WOOD VARNISH SECOND RM 204 0.05

45 DOOR WOOD VARNISH SECOND RM 204 0.03

46 WALL HATCH WOOD VARNISH SECOND RM 204 < LOD

47 WALL WOOD OFF-WHITE SECOND RM 204 3.5

48 WALL DRYWALL LIGHT BLUE SECOND RM 201 < LOD

49 WALL DRYWALL OFF-WHITE SECOND RM 201 < LOD

50 WALL ACT WHITE SECOND RM 202 < LOD

51 DOOR FRAME WOOD OFF-WHITE SECOND RM 202 < LOD

52 WALL DRYWALL LIGHT BLUE SECOND RM 203 < LOD

53 COLUMN WOOD LIGHT BLUE SECOND RM 201 3.5

54 COLUMN WOOD OFF-WHITE SECOND RM 201 5.3

XRF SAMPLING

SUMMARY OF PAINTED COMPONENTS AND MATERIALS

VANCOUVER BARRACKS – BUILDING 746

Read

Component Substrate Color Floor Room Lead Conc.

(mg/cm2)

55 TRIM WOOD VARNISH SECOND RM 201 < LOD

56 WALL DRYWALL OFF-WHITE SECOND RM 201 0.7

57 ATTIC HATCH WOOD OFF-WHITE SECOND RM 201 2.3

58 DUCT METAL OFF-WHITE SECOND RM 201 < LOD

59 WALL DRYWALL SILVER FIRST BOILER ROOM 7.4

60 CEILING DRYWALL SILVER FIRST BOILER ROOM 6.4

61 DUCT METAL SILVER FIRST BOILER ROOM < LOD

62 ELECTRICAL

PANEL

METAL GRAY FIRST BOILER ROOM < LOD

ELECTRICAL

PANEL METAL GRAY FIRST BOILER ROOM < LOD

64 AHU METAL BEIGE_TAN FIRST BOILER ROOM < LOD

HOT WATER

TANK

METAL BEIGE FIRST BOILER ROOM < LOD

66 HOT WATER

TANK

METAL BROWN FIRST BOILER ROOM 0.1

67 EXPANSION TANK INSULATION SILVER FIRST BOILER ROOM < LOD

EXPANSION TANK

STAND

METAL SILVER FIRST BOILER ROOM < LOD

EXPANSION

TANK PIPING

METAL BLACK FIRST BOILER ROOM 0.19

70 TANK METAL SILVER FIRST BOILER ROOM 0.16

71 TRIM WOOD SILVER FIRST BOILER ROOM 0.28

72 TRIM WOOD SILVER FIRST BOILER ROOM 0.29

73 DOOR_FRAME WOOD SILVER FIRST BOILER ROOM 0.4

74 DOOR_FRAME WOOD SILVER FIRST BOILER ROOM 9.8

75 CALIBRATION N/A RED N/A N/A 1.0

76 CALIBRATION N/A RED N/A N/A 0.9

77 CALIBRATION N/A RED N/A N/A 0.9

Key: ACT = acoustical ceiling tile, N/A = not applicable, RM = room, <LOD = less than limit of detection

All XRF sample shots are representative of that color on that specific substrate and component.

The report user shall deduce from the data in Table 3, if certain building materials throughout the entire building contain lead and should not assume that what is detected is only in the specific location identified in the Table.

In addition to the XRF samples, EHSI collected three (3) bulk QA samples for laboratory analysis. The bulk sample results ranged from 0.011 to 10.0 percent lead by weight (%Pb/wt.). Building materials and paint containing detectable levels of lead are considered regulated by DOSH.

Table 4 summarizes bulk QA lead sample, including sample number, material description, substrate, color, location, and analytical results. Copies of the analytical laboratory report and field data forms for lead paint are included in Appendix B of this report.

TABLE 4

SUMMARY OF LEAD BULK SAMPLING AND ANALYTICAL RESULTS

FORT VANCOUVER BARRACKS – BUILDING 746

SAMPLE

NUMBER

LOCATION COMPONENT/

SUBSTRATE

COLOR

RESULTS

% Pb by

WT

11295-B746- Pb01

1st Floor, main Room 108 Wall/GWB Beige on multiple layers

3.6

11295-B746- Pb02 1st Floor, Bathroom 107 Wall/Wood

Beige on tan 10.0

11295-B746- Pb03 1st Floor, Exterior E. Side

Chimney/Brick & Mortar Red & gray 0.011

Key: GWB = gypsum wall board, Pb = lead, WT = weight

L&I DOSH requires employers to conduct a hazard assessment and take appropriate worker protection precautions whenever disturbing materials that have detectable quantities of lead.

Since the type of work planned (e.g., sawing, grinding, select demolition) may disturb the lead-containing materials, the contractor will need to conduct lead awareness training and perform an initial exposure assessment in accordance with the regulations.

In addition to XRF and bulk samples, EHSI observed two (2) lead-acid batteries inside the fire alarm control panel during the inspection. These batteries must be disposed of in accordance with the Washington State Department of Ecology (Ecology) dangerous waste regulations or recycled at an approved facility.

2.4.3 Toxicity Characteristic Leaching Procedure Sampling

At the request of NPS, EHSI accomplished TCLP sampling and analysis of the assumed waste stream for the project and Table 5 summarizes the analytical results. EHSI collected and composited a representative sample of the assumed waste stream for renovation activities that may impact interior building finishes, that included proportionate quantities of all materials expected to be included in the waste stream. Note: Painted metals were not included in the assumed waste stream sampling, because they are expected to be recycled and because there is no limit on metals containing paint on metals being recycled.

Ecology requires testing using the “toxicity characteristic leaching procedure” (TCLP) and segregation of construction debris if it is potentially contaminated with dangerous waste (e.g., hazardous metals-containing paint/hazardous metals-containing materials). Ecology has set a dangerous waste threshold at 5.0 milligrams per liter (mg/L), for arsenic, chromium, lead, and silver, 1.0 Mg/L for cadmium, 100 mg/L for barium and .2 mg/L for mercury.

The TCLP sample for the Project was analyzed for Lead (Pb) only. Copies of the analytical laboratory report and field data forms for the TCLP sample are included in Appendix C of this report.

TABLE 5

SUMMARY OF TCLP SAMPLING AND ANALYTICAL RESULTS

NATIONAL PARK SERVICE

FORT VANCOUVER BARRACKS – BUILDING 746

Sample # Elements RL in mg/L Results in mg/L

Results in ppm

11295- B746-

TCLP-01

Sample Description:

49% Painted GWB wall & ceilings w/ wood framing;

20% Painted 1’x1’ ACT w/ glue dots;

13% Composite shingle roofing;

7% Painted 2’x4’ SACT;

3% Silver paint on GWB wall & ceiling;

3% Painted “Orange Peel” texturing on GWB wall;

2% Red/brown carpet;

1% Painted wood building skirt;

1% Wood baseboards; and 1% Beige vinyl stair tread.

Lead (Pb) 0.5 0.8 0.8 KEY: ACT = acoustic ceiling tile, GWB = gypsum wall board, mg/L = milligram per liter, Pb = Lead, ppm = part per million, RL = Reporting Limit, SACT = suspended acoustic ceiling tile, w/ = with

Based on the representative waste stream that was submitted for TCLP by EHSI, this waste stream passed TCLP testing for lead (did not exceed the threshold of 5.0 ppm). If the client were to have a waste stream with similar percentages as indicated above, the waste stream would likely pass.

It should be noted that this TCLP was done on behalf of NPS for disposal cost estimating purposes. It is recommended that the contractor take their own TCLP test of their demolition waste stream including the option to not TCLP specific materials based on the ability to recycle metal and concrete painted building materials.

2.4.4 Polychlorinated Biphenyls

Ballasts

EHSI inspected a representative number of each type of fluorescent fixture for PCB-containing ballasts. A select number of fixtures were found to contain magnetic ballasts. Any magnetic ballasts found, which are assumed to contain greater than two parts per million (> 2 ppm) PCB-dielectric fluid, must be removed from fixtures and disposed of as Washington Department of Ecology (Ecology) Dangerous Waste. All fluorescent tubes and lamps contain mercury; any fluorescent lamps/tubes to be disturbed during the project must be recycled as (Ecology) Universal Waste.

2.4.5 Mercury-Containing Fluorescent Light Tubes, CFL Bulbs, and thermostats

All fluorescent light tubes quantified in Table 6 are assumed to contain Hg. Hg wastes are regulated as “universal wastes” under Ecology’s regulation WAC 173-303. Hg-containing building materials must be recycled or disposed of as hazardous waste. Hg-containing fluorescent light tubes are quantified in Table 6.

TABLE 6

SUMMARY OF LIGHT FIXTURE INSPECTION RESULTS

NATIONAL PARK SERVICE

FORT VANCOUVER BARRACKS – BUILDING 746

LIGHT TYPE FIXTURES

LIGHT TUBES/

BULBS

MAGNETIC

BALLASTS

16”x8’ Mounted light fixture w/ 2 8’ bulbs & 1 large magnetic ballast 2 4 2

2’x4’ Mounted light fixture w/ 4 bulbs & 2 magnetic ballasts

2 8 4

2’x4’ Mounted light fixture w/ 2 bulbs & 2 magnetic ballasts

22 44 22

1’x4’ Mounted light fixture w/ 2 bulbs & 1 electronic ballast 32 64 0

HID light fixtures 2 2 2

TOTAL IMPACTED 60 122 30

Key: HID = high intensity discharge, w/ = with

3.0 LIMITATIONS

This survey was limited to those materials accessible using standard survey methods. Limited representative destructive inspection was accomplished. All suspect materials present were accessible for sampling.

This survey was limited to the chemicals and materials identified herein. No effort was made to identify hazardous materials in soil, water, or air, other than those listed herein. Any survey regardless of how extensive can miss concealed materials. Contractors should be aware of the potential that demolition activities may expose concealed suspect ACM and should have preplanned contingencies for handling these materials when discovered during demolition work. Any concealed, suspect ACM material that was not sampled or that was assumed to be ACM by this survey report when encountered must be treated as ACM until sampled by a Certified AHERA Building Inspector and analyzed by a certified laboratory. Exterior lead sampling was excluded from the scope of work. All exterior painted surfaces are assumed to have lead-containing paint.

4.0 STANDARD OF CARE

The recommendations and conclusions contained in this report represent the professional opinions of EHSI. These opinions are derived in accordance with federal, state, and local environmental and health and safety laws and regulations. This survey was accomplished in accordance with applicable federal, state, and local regulations and industry standards in effect at the time. Other than this, no other warranty is implied or intended.

5.0 CERTIFIED AHERA BUILDING INSPECTORS

The Certified AHERA Building Inspectors listed below surveyed Building 746 on August 28th- 29th, 2018, in accordance with federal, state, and local requirements.

Rory Peterson Brett Racine Certified AHERA Building Inspector Certified AHERA Building Inspector Certificate Number: 174271 Certificate Number: 173936 Expiration Date: August 7, 2020 Expiration Date: July 10, 2020

Appendix A

APPENDIX A

Asbestos Analytical Laboratory Report and Field Data Forms

Matt Macfarlane, Asbestos Lab Supervisor

Client Project: 11295-01 Location: NPS Fort Vancouver B746

Dear Mr. Peterson, Enclosed please find test results for the 7 sample(s) submitted to our laboratory for analysis on 8/30/2019.

Examination of these samples was conducted for the presence of identifiable asbestos fibers using polarized light microscopy (PLM) with dispersion staining in accordance with both EPA 600/M4-82-020, Interim Method for the Determination of Asbestos in Bulk Insulation Samples and EPA 600/R-93/116 Method for the Determination of Asbestos in Bulk Building Materials.

For samples containing more than one separable layer of materials, the report will include findings for each layer (labeled Layer 1 and Layer 2, etc. for each individual layer). The asbestos concentration in the sample is determined by calibrated visual estimation.

For those samples with asbestos concentrations between 1 and 10 percent based on visual estimation, the EPA recommends a procedure known as point counting (NESHAPS, 40 CFR Part 61). Point counting is a statistically more accurate means of quantification for samples with low concentrations of asbestos.

The detection limit for the calibrated visual estimation is <1%, 400 point counts is 0.25% and 1000 point counts is 0.1%

Samples are archived for two weeks following analysis. Samples that are not retrieved by the client are discarded after two weeks.

Thank you for using our laboratory services. Please do not hesitate to call if there is anything further we can assist you with.

Sincerely, Enc.: Sample Results

September 10, 2019

Rory Peterson EHS International 1011 SW Klickitat Way. Suite 104 Seattle, WA 98134

RE: Bulk Asbestos Fiber Analysis; NVL Batch # 1918948.00

< Client:

Address:

Attention: Mr. Rory Peterson NPS Fort Vancouver B746

Client Project #: 11295-01

Samples Received: 7

By Polarized Light Microscopy Bulk Asbestos Fibers Analysis

EHS International 1011 SW Klickitat Way. Suite 104 Seattle, WA 98134

Method: EPA/600/R-93/116

& EPA/600/M4-82-020

Samples Analyzed: 7 Project Location:

Batch #: 1918948.00

Date Received: 8/30/2019

19105712Lab ID: Client Sample #:

Location: NPS Fort Vancouver B746

11295-B746-05QA

Layer 1 of 2 Description: Tan vinyl material Non-Fibrous Materials: Other Fibrous Materials:% Asbestos Type: %

Vinyl/Binder, Fine particles NDNone Detected None Detected ND Layer 2 of 2 Description: Brown brittle mastic

Non-Fibrous Materials: Other Fibrous Materials:% Asbestos Type: % Mastic/Binder, Fine particles NDNone Detected Chrysotile 4%

19105713Lab ID: Client Sample #:

Location: NPS Fort Vancouver B746

11295-B746-12QA

Layer 1 of 1 Description: Gray fibrous…