This Statement of Work (SOW) details comprehensive electrical infrastructure upgrades for the Portland VA campus, spanning multiple buildings and focusing on electrical power distribution system improvements. The project involves specific electrical work across Buildings 100, 101, 103, and Building 16, including replacing and upgrading electrical switchgear, circuit breakers, transfer switches, and distribution equipment, with a comprehensive arc-flash hazard risk assessment and facility-wide ground resistance testing.

Key scope elements include replacing medium voltage (MV) "Old Switchgear" and unit substation circuit breakers, upgrading power meters and communication modules for automatic transfer switches, providing new power distribution equipment, replacing emergency generator control panel electronics, and installing spare circuit breakers. The project has a defined performance period of 545 days and is associated with VA Veterans Health Administration Veterans Integrated Service Network 20, with the specific solicitation number 36C26025R0071 for correcting electrical facility condition assessment (FCA) deficiencies.

View the file

Other files

File Type Posted
36C26025R0071 0005.docx DOCX document
F-103-1-TJC-Fire Life Safety - Bldg.103-1.pdf PDF
36C26025R0071 0004.docx DOCX document
36C26025R0071 0003.pdf PDF
F-104-R-TJC-Fire Life Safety - Bldg.104-R.pdf PDF
36C26025R0071 0002.docx DOCX document
F-104-P3-TJC-Fire Life Safety - Bldg.104-P3.pdf PDF
F-104-P2-TJC-Fire Life Safety - Bldg.104-P2.pdf PDF
F-104-2-TJC-Fire Life Safety - Bldg.104-2.pdf PDF
F-104-1-TJC-Fire Life Safety - Bldg.104-1.pdf PDF
F-103-P5-TJC-Fire Life Safety - Bldg.103-P5.pdf PDF
F-103-P4-TJC-Fire Life Safety - Bldg.103-P4.pdf PDF
F-103-P3-TJC-Fire Life Safety - Bldg.103-P3.pdf PDF
F-16-B-TJC-Fire Life Safety - Bldg.16-B.pdf PDF
Portland TJC Set Buildings 100 and 101.pdf PDF
F-16-3-TJC-Fire Life Safety - Bldg.16-3.pdf PDF
F-16-2-TJC-Fire Life Safety - Bldg.16-2.pdf PDF
Contractor sign in.pdf PDF
F-103-P2-TJC-Fire Life Safety - Bldg.103-P2.pdf PDF
F-6-2-TJC-Fire Life Safety - Bldg.6-2.pdf PDF
F-16-R-TJC-Fire Life Safety - Bldg.16-R.pdf PDF
36C26025R0071 0001.pdf PDF
F-103-2-TJC-Fire Life Safety - Bldg.103-2.pdf PDF
F-103-R-TJC-Fire Life Safety - Bldg.103-R.pdf PDF
F-6-1-TJC-Fire Life Safety - Bldg.6-1.pdf PDF
F-6-3-TJC-Fire Life Safety - Bldg.6-3.pdf PDF
F-16-1-TJC-Fire Life Safety - Bldg.16-1.pdf PDF
Attachment 10-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 8.pdf PDF
Attachment 14- VAAR 852.219-75.docx DOCX document
Attachment 5-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 3.pdf PDF
Attachment 4-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 2.pdf PDF
Attachment 15-Past Performance Questionnaire.pdf PDF
Attachment 13-Price Schedule by Division.xlsx XLSX spreadsheet
Attachment 12-Wage Determination 7-11-2025.pdf PDF
Attachment 9-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 7.pdf PDF
Attachment 7-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 5.pdf PDF
Attachment 6-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 4.pdf PDF
Attachment 3-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 1.pdf PDF
36C26025R0071_2.docx DOCX document
Attachment 11-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 9.pdf PDF
Attachment 8-648-20-119-VA OR Portland Electrical FCA DWGS STAMPED part 6.pdf PDF
Attachment 2-648-20-119-VA OR Portland Electrical FCA SPECS STAMPED.pdf PDF
Show all 42

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work: Perform the following electrical work on the Portland VA campus:

1. All buildings within scope: Replace, modify, or upgrade existing electrical power distribution equipment to provide corrections per Wiley-Wilson arc-flash report. Once all power aspects of the project have been completed, a facility wide arc-flash hazard risk assessment with report and labeling shall be performed in accordance with specification 26 05 73.

2. Buildings 100, 101, 103: Replace all MV “Old Switchgear” and unit substation circuit breakers.

3. Building 100: Facility wide ground resistance testing per VHA directive 1028-8.j(6)(e).

4. Buildings 100, 101, 103: LS & Critical automatic transfer switches power meter and communication module upgrades (7atss total).

5. Building 100: Provide power distribution equipment for delayed equipment automatic transfer switches; distribution equipment includes mv interrupter switches, mv dry-type transformer, and distribution switchboard.

6. Building 100: Replace MV ring loop feeder from MV Old Switchgear to unit substation

USNW.

7. Building 100: Replace emergency generator control panel electronics within generator master control panel and provide redundant PLC CPU within OHSU control panel, provide programming as required.

8. Buildings 100, 101, 103: Provide spare circuit breakers for mv and unit substation switchgear.

9. Building 16: Replace main electrical distribution equipment.

Period of performance is 545 days