Attachment 06 - Drawings - Fire Protection.pdf
PDF 3 MB Posted
- Solicitation number
- 36C25024B0031_1
About this file
This document is a set of drawings for the fire suppression system for a federal contract opportunity to construct private in-patient rooms and primary clinics in Ann Arbor, Michigan. The key details include:
The drawings provide the design for a wet-pipe fire suppression sprinkler system to cover the renovation areas, including the sprinkler layout, pipe sizing, and hazard classifications. The system will be hydraulically calculated to meet NFPA 13 requirements, including a 100 GPM hose allowance for light hazard areas and 250 GPM for ordinary hazard areas. The drawings indicate the system will tie into the existing fire suppression system and include provisions to maintain the existing system during construction. The drawings also include details on pipe hangers, penetrations through fire-rated assemblies, and requirements for quick-response sprinklers. Four bid deduct alternates are shown that would remove certain areas of work.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABBREVIATIONS
AC - AIR COMPRESSOR
ACC - ACCESS
AD - ACCESS DOOR
ADB - ACID DILUTION BASIN
ADJ - ADJUSTABLE
AFF - ABOVE FINISHED FLOOR
AFG - ABOVE FINISHED GRADE
ALT - ALTERNATE
AP - ACCESS PANEL
APPROX - APPROXIMATE
ARCH - ARCHITECT OR ARCHITECTURAL
ASSY - ASSEMBLY
BFP - BACKFLOW PREVENTER
BLDG - BUILDING
BOB - BOTTOM OF BEAM
BOD - BOTTOM OF DUCT
BOE - BOTTOM OF EQUIPMENT
BOF - BOTTOM OF FOOTING
BOG - BOTTOM OF GRILLE
BOP - BOTTOM OF PIPE
BOT - BOTTOM
BTWN - BETWEEN
CA - COMPRESSED AIR
CFCI - CONTRACTOR FURNISHED CONTRACTOR
INSTALLED
CLG - CEILING
CONN - CONNECT OR CONNECTION
CONTR - CONTRACTOR
COR - CONTRACTING OFFICER'S REPRESENTATIVE
CORR - CORRIDOR
CTR - CENTER
CWS - COMBINATION WATER SERVICE
D - DEPTH
DET - DETAIL
DIA - DIAMETER
DIM - DIMENSION
DN - DOWN
DS - SPRINKLER (DRY)
DWG - DRAWING
EA - EACH
EC - ELECTRICAL (DIVISION 26)
EJ - EXPANSION JOINT
ELEC - ELECTRICAL
ELEV - ELEVATOR
EQ - EQUAL
EQUIP - EQUIPMENT
ETR - EXISTING TO REMAIN
EQS - EQUIPMENT SUPPLIER
EXP - EXPANSION
EXT - EXTERIOR
EX - EXISTING
F - FIRE SUPPRESSION (STANDPIPE/SPRINKLER MAIN)
FCE - FIRE CONTROL EQUIPMENT
FCO - FLOOR CLEANOUT
FD - FLOOR DRAIN
FDC - FIRE DEPARTMENT CONNECTION
FDV - FIRE DEPARTMENT VALVE
FF - FINISHED FLOOR ELEVATION
FHC - FIRE HOSE CABINET
FLR - FLOOR
FPM - FEET PER MINUTE
FR - FIRE RISER
FS - FIRE SERVICE
FSC - FIRE SUPPRESSION (DIVISION 21)
FT - FEET
FTG - FOOTING
GA - GAUGE
GAL - GALLON
GALV - GALVANIZED
GC - GENERAL TRADES (DIVISION 01)
GPM - GALLONS PER MINUTE
HC - HVAC (DIVISION 23)
HD - HUB DRAIN
HP - HORSEPOWER OR HIGH POINT
HR - HOSE REEL
HT - HEAT TRACE
HVAC - HEATING, VENTILATING, AND AIR CONDITIONING
ID - INSIDE DIAMETER
INV - INVERT ELEVATION
IN - INCHES
JS - JANITOR SINK
L - LENGTH
LBS - POUNDS
MAX - MAXIMUM
MB - MOP BASIN
MC - MECHANICAL (DIVISION 23)
MEZZ - MEZZANINE
MFR - MANUFACTURER
MIN - MINIMUM
MISC - MISCELLANEOUS
MTD - MOUNTED
MTG - MOUNTING
N/C - NORMALLY CLOSED
NIC - NOT IN CONTRACT
N/O - NORMALLY OPEN
NOM - NOMINAL
NPT - NATIONAL PIPE THREAD
NTS - NOT TO SCALE
OA - OUTDOOR AIR
OD - OUTSIDE DIAMETER
OFCI - OWNER FURNISHED CONTRACTOR
INSTALLED
OFOI - OWNER FURNISHED OWNER INSTALLED
PC - PLUMBING (DIVISION 22)
OR PUMPED CONDENSATE RETURN
PIV - POST INDICATOR VALVE
PLBG - PLUMBING
PS - PRE-ACTION/DELUGE SPRINKLER
PRESS - PRESSURE
PRV - PRESSURE REGULATING VALVE
PSF - POUNDS PER SQUARE FOOT
PSI - POUNDS PER SQUARE INCH
PSV - PRESSURE SUSTAINING VALVE
PSIG - POUNDS PER SQUARE INCH GAUGE
RAD - RADIUS
REC - RECESSED
REQD - REQUIRED
RI - ROUGH IN
RPM - REVOLUTIONS PER MINUTE
S - SPRINKLER (WET)
SCH - SCHEDULE
SD - SPRINKLER DRAIN
SHT - SHEET
SK - SINK
SPEC - SPECIFICATIONS
SQ - SQUARE
STD - STANDARD
STRUC - STRUCTURAL OR STRUCTURE
SUC - SITE UTILITY CONTRACTOR
TEMP - TEMPERATURE
TOB - TOP OF BEAM
TOD - TOP OF DUCT
TOE - TOP OF EQUIPMENT
TOF - TOP OF FOOTING
TOJ - TOP OF JOIST
TOP - TOP OF PIPE
TOS - TOP OF SLAB OR TOP OF STEEL
TYP - TYPICAL
UNO - UNLESS NOTED OTHERWISE
VEL - VELOCITY
VIB - VALVE IN BOX
VOL - VOLUME
W/ - WITH
W/O - WITHOUT
WIV - WALL INDICATOR VALVE
WS - WATER SERVICE
VALVES AND FITTINGS
T
P
FOB
FOT
CONCENTRIC PIPE REDUCER
ECCENTRIC PIPE REDUCER
GAUGE - PRESSURE
GAUGE - TEMPERATURE OR THERMOMETER
UNION
CLEANOUT
STRAINER
STRAINER - WITH A BLOW DOWN VALVE AND HOSE
CONNECTION
VALVE - DRAIN WITH HOSE END CONNECTION
VALVE - PRESSURE REGULATING
VALVE - SAFETY RELIEF. PIPE DISCHARGE AIR
GAPPED TO FLOOR DRAIN UNLESS NOTED
OTHERWISE.
PLUG - PRESSURE AND TEMPERATURE TEST
TRAP PRIMER
GAUGE - VACUUM WITH STOP
CLEANOUT - TO GRADE OR FINISHED FLOOR
END CAP
MIXING FAUCET
PLUG
HOSE BIB
WALL HYDRANT
VALVE - PLUG
VALVE - SHUTOFF AND BOX
VALVE - SHUTOFF ON RISER
V
VB
TP
CO
VALVE - SOLENOID
S
P/T VALVE - PRESSURE AND TEMPERATURE SAFETY
RELIEF. PIPE DISCHARGE AIR GAPPED TO
FLOOR DRAIN UNLESS NOTED OTHERWISE.
VALVE - CHECK
VALVE - SHUTOFF: BALL, GATE, BUTTERFLY VALVE
(REFER TO SPECIFICATIONS FOR REQUIRED TYPE
BASED ON APPLICATIONS)
AUTOMATIC FLOW CONTROLLER WITH P/T PLUG IN
AND OUT
VALVE - COMBINATION SHUTOFF AND
BALANCING (REFER TO SPECIFICATIONS FOR
REQUIRED TYPE BASED ON APPLICATIONS)
A1
P1 P1OR
A1
OH
P2
B
P2
GENERAL FLOOR PLAN NOTES
RISER OR STACK NUMBER
DETAIL: B = DETAIL DESIGNATION
P2 = SHEET WHERE DETAIL IS LOCATED
FIRE SUPPRESSION HAZARD CLASSIFICATION AND
HAZARD CLASSIFICATION GROUP
SECTION: 1 = SECTION DESIGNATION
P2 = SHEET WHERE DETAIL IS LOCATED
EQUIPMENT REFERENCE. LETTER DESIGNATION
VARIES. REFER TO SCHEDULES.
EQUIPMENT, DEVICE, OR PLUMBING FIXTURE MARK.
LETTER DESIGNATIONS REFER TO SCHEDULES.
CONNECT TO EXISTING
PLAN NOTE. APPLIES ONLY TO THE SHEET WHICH
IT IS SHOWN UNLESS NOTED OTHERWISE.
DETAIL NOTE. APPLIES ONLY TO THE ASSOCIATED DETAIL.
"UP TO" SYMBOL (ITEM ON FLOOR ABOVE)
EXISTING PIPE TO REMAIN
EXISTING PIPE TO BE REMOVED
EXPANSION JOINT
WATER METERM
PIPING SYMBOLS
BOTTOM CONNECTION (45°)
BRANCH TEE CONNECTION (NOTE:
BULLHEAD TEE'S ARE NOT PERMITTED)
DIRECTION OF PITCH
DROP
ELBOW DOWN
ELBOW UP
FLOW DIRECTION DESIGNATION
PUMP
RISE
TOP CONNECTION (45°)
TOP CONNECTION (90°)
BOTTOM CONNECTION (90°)
D
R
PIPE RISER
BC
TC
FLEX PIPING
FIRE SUPPRESSION SYMBOLS
PIPING DESIGNATIONS
FS
PIV
S
CONCEALED PENDENT SPRINKLER
FIRE HYDRANT
FLOW SWITCH
GATE VALVE OS&Y
INSTITUTIONAL PENDENT SPRINKLER
PENDENT SPRINKLER
POST INDICATOR VALVE
RECESSED PENDENT SPRINKLER
SIDE WALL SPRINKLER
SUPERVISED VALVE
UPRIGHT SPRINKLER
FIRE DEPARTMENT VALVE
SPRINKLER PIPE (DRY)
FIRE SUPPRESSION (STANDPIPE/
SPRINKLER MAIN)
FIRE SERVICE
PRE-ACTION / DELUGE SPRINKLER PIPE
SPRINKLER PIPE (WET)
SPRINKLER DRAIN PIPE
DS
F
FS
PS
S
SD
COMMMMBINATION FIRE SUPPRESSION &
DOMESTIC WATER SERVICE
CWS
DEMOLISH TO POINT INDICATED
A PROVIDE A COMPLETE FIRE SUPPRESSION SPRINKLER SYSTEM IN THE
RENOVATED AREA. MAINTAIN AND RESTORE, IF INTERRUPTED,
THE AUTOMATIC SPRINKLER SYSTEM SERVING AN UNDISTURBED AREA.
B COORDINATE WORK WITH VAMC, PHASING PLAN AND OTHER TRADES. OFFSET
AND/ OR RELOCATE EXISTING SERVICES TO ACCOMMODATE NEW WORK OF
OTHER TRADES. MAINTAIN AND RESTORE IF INTERRUPTED, THE DOMESTIC
WATER DISTRIBUTION, MEDICAL GAS AND SANITARY & VENT PIPING SYSTEMS
TO EXISTING FIXTURES LOCATED IN UNDISTURBED AREAS.
C DESIGN SERVICES SHALL FOLLOW ALL VA STANDARD DESIGN PRACTICES,
DETAILS, SPECIFICATIONS AND SITE SPECIFIC COR REQUIREMENTS AS WELL AS
WORK SHOWN ON THESE DOCUMENTS.
REFERENCE VA FIRE PROTECTION DESIGN MANUAL.
ALL DEVIATIONS FROM AFOREMENTIONED REQUIREMENTS SHALL BE APPROVED
BY THE COR.
D MAKE NECESSARY FLOW TESTS (SPECIFICATIONS 21 13 13), LAYOUT SYSTEMS,
OBTAIN APPROVALS FROM THE AUTHORITIES HAVING JURISDICTION PRIOR TO
BEGINNING ANY FABRICATION OR INSTALLATION WORK.
E VERIFY THAT THERE IS ADEQUATE SPACE TO INSTALL ALL NEW PIPING
REQUIRED TO COMPLETE THIS WORK.
F ALL SPRINKLER PIPING IS LOCATED ABOVE THE CEILING (AT THE BOTTOM OF
STRUCTURE IN EXPOSED STRUCTURAL AREAS), UNLESS OTHERWISE INDICATED.
G THE BASIS OF DESIGN OF SPACING AND SIZING FOR THE COMPLETE FIRE
SUPPRESSION SPRINKLER SYSTEM SHALL BE FOR A WET PIPE SYSTEM
HYDRAULICALLY CALCULATED FOR A:
1 LIGHT HAZARD AREA LIMITED TO A MAXIMUM OF 225 SQ. FT. PER SPRINKLER
WITH THE DENSITY OF 0.10 GPM/SQ. FT. PROVIDE AN ADDITION OF 100 GPM
HOSE ALLOWANCE.
2 ALL MECHANICAL, ELECTRICAL AND SIMILAR SPACE AREAS SHALL BE
ORDINARY HAZARD (GROUP 1) LIMITED TO A MAXIMUM OF 130 SQ. FT. PER
SPRINKLER WITH A DENSITY OF 0.15 GPM/SQ. FT. PROVIDE AN ADDITION OF
250 GPM HOSE ALLOWANCE.
3 ALL STORAGE, TRASH, FILE STORAGE AND SIMILAR SPACE AREAS SHALL BE
ORDINARY HAZARD (GROUP 2) LIMITED TO A MAXIMUM OF 130 SQ. FT. PER
SPRINKLER WITH A DENSITY OF 0.20 GPM/ SQ. FT. PROVIDE AN ADDITION OF
250 GPM HOSE ALLOWANCE.
NOTE: ALL AREAS ARE LIGHT HAZARD UNLESS OTHERWISE NOTED.
H PROVIDE SPRINKLER LOCATIONS, PIPING LAYOUTS AND SIZING. SPRINKLER
PIPING SHALL BE MINIMUM 1" SIZE. PROVIDE HYDRAULIC CALCULATIONS AND
STAMPED DRAWINGS PER SPECIFICATION REQUIREMENTS.
I ALL SPRINKLER LOCATIONS MUST BE COORDINATED WITH ALL EQUIPMENT
KINDRED TO OTHER TRADES. SPRINKLER LOCATIONS MUST BE APPROVED BY
THE ARCHITECT BEFORE WORK COMMENCES. ALL PENDENT TYPE SPRINKLERS
LOCATED IN SUSPENDED CEILING TILE AREAS SHALL BE LOCATED IN THE CENTER
OF THE CEILING TILE. REFER TO THE ARCHITECTURAL DRAWINGS REFLECTIVE
CEILING PLANS FOR ADDITIONAL INFORMATION ON ALL CEILING TYPES, HEIGHTS
AND OTHER ARCHITECTURAL FEATURES.
J SPRINKLERS SHALL BE "QUICK RESPONSE" TYPE IN ALL AREAS EXCEPT HIGH
TEMPERATURE AREAS, TELECOMMUNICATION, ELECTRICAL SWITCHGEAR,
ELEVATOR EQUIPMENT ROOMS AND ELEVATOR SHAFTS.
SPRINKLERS (UNLESS OTHERWISE NOTED):
EXPOSED AREAS - UPRIGHT OR PENDENT TYPE - STANDARD BRASS
CEILING AREAS - RECESSED PENDENT TYPE
CONCEALED SPRINKLERS ARE NOT PERMITTED
ALL HEADS SHALL BE UL LISTED AND FM APPROVED.
K SPRINKLER SYSTEM PIPING AND FITTINGS SHALL BE IN ACCORDANCE WITH
NFPA 13.
1 PIPING SIZES 2" AND SMALLER SHALL BE BLACK STEEL SCHEDULE 40
WITH THREADED END CONNECTIONS.
2 PIPING SIZES 2.5" AND LARGER SHALL BE BLACK STEEL SCHEDULE 10
WITH GROOVED CONNECTIONS. GROOVES IN SCHEDULE 10 PIPING SHALL BE
ROLLED GROOVED ONLY.
L ACOUSTICAL CEILINGS ACCESS IDENTIFICATION MARKERS: COLORED MARKERS
WITH PRESSURE SENSITIVE ADHESIVE ON ONE SIDE, PAPER OR PLASTIC, 6 TO
9 MM (1/4 TO 3/8 INCH) DIAMETER.
REFER TO SPECIFICATION 09 51 00 SECTION 2.6.C.
1. COLOR CODE: PROVIDE THE FOLLOWING COLOR MARKERS FOR
SERVICE IDENTIFICATION:
• RED - SPRINKLER SYSTEM: VALVES AND CONTROLS.
M ANNULAR SPACE AT PIPE AND OTHER SIMILAR PENETRATION OF FIRE RATED
ASSEMBLIES SHALL BE FIRE STOPPED. IN ADDITION, PENETRATIONS THROUGH
0-HOUR RATED WALLS & FLOOR SHALL BE SEALED TO RETARD THE PASSAGE
OF SMOKE. REFER TO SPECIFICATIONS FOR FIRESTOPPING.
N REFER TO ARCHITECTURAL DRAWINGS FOR SMOKE COMPARTMENTS, SMOKE
PARTITIONS, FIRE BARRIERS, LOCATIONS AND FIRE RATINGS OF NEW AND
EXISTING WALL ASSEMBLIES. ALL PENETRATIONS THROUGH FIRE RATED
ASSEMBLIES SHALL BE PROTECTED AND/ OR FIRE STOPPED AS REQUIRED TO
MAINTAIN FIRE RATINGS INDICATED. COORDINATE WITH ALL TRADES TO ENSURE
FIRE RATED PENETRATION REQUIREMENTS AND DETAILS ARE MET.
ALLSPRINKLER ZONES SHALL MATCH SMOKE COMPARTMENTS.
O ALL REMOVED MATERIAL AND EQUIPMENT SO DESIGNATED BY THE COR,
SHALL BE TURNED OVER AND PLACED WHERE DIRECTED. ALL MATERIAL AND
EQUIPMENT, WHICH THE OWNER DOES NOT WISH TO RETAIN, SHALL BECOME
THE PROPERTY OF THE CONTRACTOR RESPONSIBLE FOR THE REMOVAL
P ANY RENOVATION WORK REQUIRED "OUTSIDE" OF THE BOUNDARIES/ EXTENTS
OF A SPECIFIC PHASE OF WORK (OR TEMPORARY CONSTRUCTION WALLS
SHALL BE BID AS "NIGHT WORK" AND SHALL BE AS DIRECTED BY THE COR.
Q ALL CORE DRILLS AND PIPE EXTENSIONS THRU THE EXISTING STRUCTURAL
FLOOR SLAB OR STRUCTURAL WALL SHALL BE X-RAYED TO DETERMINE THE
EXACT LOCATION OF THE "REBAR" IN THE STRUCTURAL SLAB. DO NOT CUT
THE LOWER (BOTTOM REBAR) IN THE STRUCTURAL FLOOR SLAB.
R WORK IN EXISTING AREAS WITH NO/ LIMITED ARCHITECTURAL SCOPE, THE
CONTRACTOR SHALL PROVIDE ALL REQUIRED FLOOR/ WALL PROTECTION (AS
REQUIRED) AND REPLACE ANY DAMAGED CEILING TILES WITH NEW. RETURN
AREA BACK TO ORIGINAL CONDITION UPON COMPLETION OF WORK.
S PHASING: REFER TO ARCHITECTURAL DRAWINGS FOR AN OUTLINE OF PROJECT
PHASING. ADDITIONAL NOTES DESCRIBING PHASING DETAILS MAY BE INCLUDED
THROUGHOUT THIS DRAWING SET. INCLUDE ALL LABOR AND MATERIAL TO
ACCOMMODATE PHASING.
T BID ITEMS: REFER TO ARCHITECTURAL DRAWING AND SPECIFICATION SECTION
01 00 00 FOR AN OUTLINE OF BID ITEMS. ADDITIONAL NOTES DESCRIBING BID
ITEM DETAILS MAY BE INCLUDED THROUGHOUT THIS DRAWING SET.
FIRE SUPPRESSION DESIGN NOTES
HANGER ROD
INSULATION (VAPOR
BARRIER TYPE IS
REQUIRED FOR LOW
TEMPERATURE PIPE)
PROVIDE HIGH COMPRESSIVE
STRENGTH INSULATION (9 PSF MIN.
DENSITY) UNDER INSULATION SHIELD
INSULATION SHEILD
AT HANGER
WELD
SADDLE
ADJUSTABLE CLEVIS HANGER TYPE 1 -
SEE SPECIFICATIONS
ADJUSTABLE CLEVIS HANGER TYPE 43 -
SEE SPECIFICATIONS
PROVIDE INSULATION SHEILD
& INSERT FOR ALL PIPING
(200mm [8"] MIN.)
15mm [½"] DIA.
HANGER RODS WITH
900mm [36"] MAX.
SPACING ON EACH
CHANNEL
BAND
43mm [1-⅝"] 12 GAUGE CHANNEL OR 50x50x6.4mm [2"x2"x¼"] ANGLE m m [1
M
A X
SIDE VIEW TRAPEZE HANGER FOR UP TO
453KG [1000lb.] UNIFORM LOAD
[1]
[1¼]
THRU 20
[THRU ¾]
[1½]
[2½]
[2]
[3]
[4]
[5]
[6]
[10]
[10]
[12]
[14]
[16]
[18]
[20]
[24]NOM. SIZE
[7]
[7]
[7]
[9]
[11]
[10]
[12]
[14]
[16]
[17]
[19]
[22]
[23]
[25]
[27]
[28]
[30]
[32]PIPE
[6]
[7]
[5]
[8]
[9]
[8]
[10]
[12]
[13]
[14]
[16]
-TUBING
mm
[IN]
mm
[FT]
mm
[FT]
NOTE: FOR TRAPEZE HANGER TAKE SPACING OF SMALLEST SIZE ON TRAPEZE.
MAXIMUM PIPE/TUBING SUPPORT SPACING
NOTE:
SEE SPECIFER FOR DETAILED HANGER REQUIREMENTS
6" [1 m m
1" [2
5m m
6" [1 m m
INSULATE
PIPE OR DUCT
PIPE SLEEVE
WHERE SPECIFIED
FLOOR
WELD
1/4" [6.4mm]
ANCHOR ROD FOR
NEW CONSTRUCTION
FIRESTOP MATERIAL
3/4" [19mm]
APPROVED FIRESTOP
INSULATION WITH
VAPOR BARRIER
3/4" [19mm] APPROVED
FIRESTOP INSULATION WITH
VAPOR BARRIER 6"
[150mm]
MASONRY
PARTITION INSULATED
PIPE OR
DUCT
6" [150mm]
FIRESTOP
MATERIAL
DRYWALL PARTITION
PARTITION SUPPORT
FLOOR OR DECK PENETRATION
6" [150mm]
6" [150mm]
PARTITION OR CHASE PENETRATION
NOTE:
1. APPLICABLE TO PENETRATIONS OF
ALL FIRE RATED MEMBRANES, IN
ACCORDANCE WITH NRPA 101.
REFER TO SPECIFICATIONS SECTION
07 84 00, FIRE STOPPING
SYSTEMS.
MOUNTING PLATE
REFER TO MANUFACTURER'S
MINIMUM EXPOSURE
DIMENSION TO OBTAIN FM
APPROVED QUICK RESPONSE
LISTING.
1" [2
5.
4m m
1/
4" [3
1.
8m m
1/ 8"
[3 m m
MOUNTING
SURFACE
ADJUSTABLE OUTER
CUP/ ESCUTCHEON
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
Project Schedule Date
Schematic Design 15% 02.16.2021
Schematic Design 35% 04.16.2021
Design Development 65% 09.24.2021
Construction Documents 95% 10.26.2023
Bid Documents 100% 12.15.2023
Design Development 65% (Re-submittal) 11.15.2021
/1 /2
:0
:4
P M
Construct Private In-Patient Rooms & Primary Clinics
12/15/2023
ABBREVIATIONS, SYMBOLS &
INDEX OF DRAWINGS
F001
RLCEWL
506-334
Ann Arbor, Michigan (506)
B01W
JEFF MEANS
BID DOCUMENTS 100%
20014.00
INDEX OF DRAWINGS - FIRE SUPPRESSION
SHEET NUMBER SHEET NAME
F001 ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS
F002 BID DEDUCT ALTERNATE 01 & 02
F003 BID DEDUCT ALTERNATE 03 & 04
FX103 PARTIAL THIRD FLOOR PLAN
FX104 PARTIAL FOURTH FLOOR PLAN
FX105 PARTIAL FIFTH FLOOR PLAN
SCALE: NONE
PIPE HANGERS
A
SCALE: NONE
PIPE/ DUCT PENETRATION OF SMOKE/ FIRE BARRIERS
B
SCALE: NONE
SEMI-RECESSED PENDENT SPRINKLER (QR)
C
Revisions Date
C3-B-2
CORRIDOR-2
01 - DEDUCT ALTERNATE 01:
OMIT ALL NEW WORK RELATED TO THE
OPEN OFFICES AND CHAPEL.
SPACE WILL BE UNFINISHED STORAGE.
H.A.C.
CLOSET
OH
CHAPEL
OPEN
OFFICE
OPEN
OFFICE
OPEN
OFFICE
LOBBY
SPACE
HEALTHY
TEACHING
KITCHEN
02 - DEDUCT ALTERNATE 02:
OMIT ALL NEW WORK RELATED TO THE
ELECTRICAL SHOP.
SPACE WILL BE UNFINISHED STORAGE.
OH
MECHANICAL
ROOM
ELECTRICAL
SHOP
401A
OFFICE
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
Project Schedule Date
Schematic Design 15% 02.16.2021
Schematic Design 35% 04.16.2021
Design Development 65% 09.24.2021
Construction Documents 95% 10.26.2023
Bid Documents 100% 12.15.2023
Design Development 65% (Re-submittal) 11.15.2021
/1 /2
:0
:4
P M
Construct Private In-Patient Rooms & Primary Clinics
12/15/2023
BID DEDUCT ALTERNATE 01 & 02
F002
RLCEWL
506-334
Ann Arbor, Michigan (506)
B01W
JEFF MEANS
BID DOCUMENTS 100%
20014.00
Scale: 1/8" = 1'-0"1
BID DEDUCT 01 - REMOVE THIRD FLOOR OFFICES AND
CHAPEL
Scale: 1/8" = 1'-0"2
BID DEDUCT 02 - REMOVE FOURTH FLOOR
ELECTRICAL SHOP
03 - DEDUCT ALTERNATE 03:
OMIT ALL NEW WORK RELATED TO THE
TEACHING KITCHEN.
EXISTING OFFICE CONSTRUCTION
TO REMAIN.
SPACE WILL BE UNFINISHED STORAGE.
OH
04 - DEDUCT ALTERNATE 04:
OMIT ALL NEW WORK RELATED TO THE
NEW LOUNGE AND LOCKER ROOMS.
EXISTING LOCKERS, HAC, SOILED
UTILITY AND OFFICE TO REMAIN.
04 - DEDUCT ALTERNATE 04:
EXISTING OFFICE TO BECOME CLEAN
LINEN ROOM.
OH
524A
BATH
1 BR
PATIENT
ROOM #8 525
1 BR
PATIENT
ROOM #9
525A
BATH
C5-52
CORRIDOR
1 BR
PATIENT
ROOM #7
523A
BATH
NS-502
NURSE
STATION
NS-503
NURSE
STATION
LOUNGE
1BR
PATIENT
ROOM #6
519A
BATH
517A
BATH
1BR
PATIENT
ROOM #5
C5-50
CORRIDOR
SPACE
1BR
PATIENT
ROOM #4
515A
BATH
1BR
PATIENT
ROOM #2
507A
BATH
NS-501
NURSE
STATION
MED ROOM
CLEAN
UTILITY
C5-51
CORRIDOR
SOILED
HOLD
505A
BATH
1BR
ISOLATION
ROOM #1
A513
2BR
505B
ANTE
OFFICE
EQUIPMENT
ALCOVE
NS-500
NURSE
STATION
NUTRITION
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
Project Schedule Date
Schematic Design 15% 02.16.2021
Schematic Design 35% 04.16.2021
Design Development 65% 09.24.2021
Construction Documents 95% 10.26.2023
Bid Documents 100% 12.15.2023
Design Development 65% (Re-submittal) 11.15.2021
/1 /2
:0
:5
P M
Construct Private In-Patient Rooms & Primary Clinics
12/15/2023
BID DEDUCT ALTERNATE 03 & 04
F003
RLCEWL
506-334
Ann Arbor, Michigan (506)
B01W
JEFF MEANS
BID DOCUMENTS 100%
20014.00
Scale: 1/8" = 1'-0"1
BID DEDUCT 03 - REMOVE THIRD FLOOR TEACHING
KITCHEN
Scale: 1/8" = 1'-0"2
BID DEDUCT 04 - RETAIN EXISTING FIFTH FLOOR
LOCKERS AND RESTROOMS
F S
S
F S
S
FS S
B01W
B01E
A C
F G I J LE
OH
STAIR #1
STANDPIPE
1EXISTING ZONE
CONTROL VALVE
EXISTING ZONE
CONTROL VALVE
1-3-4
EXISTING ZONE
CONTROL VALVE
1-3-2
EXISTING ZONE
CONTROL VALVE
1-3-1
STAIR #2
STAIR #3
OH
ELEC
A311
DATA
A370
ELEC
A335
ELEC
A373
LAV
A372
LAV
A371
DATA
B310B
ELEC
B312
ELEC
B303
CORRIDOR
C3-2A
CORRIDOR
C3-304
CORRIDOR
C3-305
OPEN OFFICE
LOBBY
B314
CHAPEL
OPEN OFFICE
CORRIDOR
C3-B
CORRIDOR
C3-B
HAC
OH
OH
STORAGE
307A
A. REFER TO SHEET F001 FOR ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS.
B. EXISTING CORRIDORS AND/ OR ROOMS TO REMAIN OPERATIONAL AT ALL TIMES
DURING BUSINESS HOURS. AUTOMATIC SPRINKLER SYSTEM(S) SHALL BE MAINTAINED
IN FULLY OPERATIONAL CONDITION (PER NFPA 241, SPRINKLER SYSTEMS WILL BE
OPERATIONAL, BUT IMPAIRED WHILE CEILINGS ARE REMOVED). SPRINKLER SYSTEM
MAY BE TAKEN OFF-LINE FOR UP TO 8 HOURS, AS REQUIRED, TO MAKE MODIFICATIONS/
CONNECTIONS TO EXISTING SYSTEM.
C. WHEN CEILINGS ARE REMOVED DURING RENOVATION OF AN EXISTING SPACE OR
STRUCTURE, THE SPRINKLERS SYSTEM SHALL BE MAINTAINED BY INSTALLING
UPRIGHT SPRINKLERS TO PROVIDE SUFFICIENT COVERAGE AND A QUICKER
RESPONSE TIME.
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
Project Schedule Date
Schematic Design 15% 02.16.2021
Schematic Design 35% 04.16.2021
Design Development 65% 09.24.2021
Construction Documents 95% 10.26.2023
Bid Documents 100% 12.15.2023
Design Development 65% (Re-submittal) 11.15.2021
/1 /2
:0
:5
P M
Construct Private In-Patient Rooms & Primary Clinics
12/15/2023
PARTIAL THIRD FLOOR PLAN
FX103
RLCEWL
506-334
Ann Arbor, Michigan (506)
B01W
JEFF MEANS
BID DOCUMENTS 100%
20014.00
N Scale: 1/8" = 1'-0"
PARTIAL THIRD FLOOR PLAN
1. EXISTING AREA, PIPING OR PIECE OF EQUIPMENT (TYPE AS INDICATED) TO REMAIN.
2. LIMITS OF RENOVATED AREA REQUIRING EXISTING SPRINKLER SYSTEM
MODIFICATIONS. MODIFICATIONS INCLUDE, BUT ARE NOT LIMITED TO, REPLACING
ALL SPRINKLERS, PIPE BRANCHES, AND PIPE MAINS TO CONFORM TO NEW
ARCHITECTURAL LAYOUTS AND NEW MEPT UTILITIES AS NECESSARY.
3. HARD CEILING IN THIS LOCATION (GYPSUM BOARD/ PLASTER/ WOOD). REFER TO
ARCHITECTURAL DRAWINGS FOR ADDITIONAL INFORMATION.
4. PROVIDE NEW WET-PIPE FIRE SUPPRESSION SPRINKLER SYSTEM (PER HYDRAULIC
CALCULATIONS) TO CONFORM TO NEW LAYOUT INSIDE INDICATED AREA.
KEYPLAN
S
F S
S
FS S
B01W
B01E
A C
F G I J LE
OH
OH
2 2
1EXISTING ZONE
CONTROL VALVE
1-4-2
EXISTING ZONE
CONTROL VALVE
1-4-1 1
EXISTING ZONE
CONTROL VALVE
1-4-4
STAIR #1
STAIR #2
STAIR #3
HAC
A477
VEST
B400A
DATA
A470
ELEC
A433
ELEC
VEST
A410
MECHANICAL
ROOM
ELECTRICAL
SHOP
401A
OFFICE
GENERAL NOTES
A. REFER TO SHEET F001 FOR ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS.
B. EXISTING CORRIDORS AND/ OR ROOMS TO REMAIN OPERATIONAL AT ALL TIMES
DURING BUSINESS HOURS. AUTOMATIC SPRINKLER SYSTEM(S) SHALL BE MAINTAINED
IN FULLY OPERATIONAL CONDITION (PER NFPA 241, SPRINKLER SYSTEMS WILL BE
OPERATIONAL, BUT IMPAIRED WHILE CEILINGS ARE REMOVED). SPRINKLER SYSTEM
MAY BE TAKEN OFF-LINE FOR UP TO 8 HOURS, AS REQUIRED, TO MAKE MODIFICATIONS/
CONNECTIONS TO EXISTING SYSTEM.
C. WHEN CEILINGS ARE REMOVED DURING RENOVATION OF AN EXISTING SPACE OR
STRUCTURE, THE SPRINKLERS SYSTEM SHALL BE MAINTAINED BY INSTALLING
UPRIGHT SPRINKLERS TO PROVIDE SUFFICIENT COVERAGE AND A QUICKER
RESPONSE TIME.
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
Project Schedule Date
Schematic Design 15% 02.16.2021
Schematic Design 35% 04.16.2021
Design Development 65% 09.24.2021
Construction Documents 95% 10.26.2023
Bid Documents 100% 12.15.2023
Design Development 65% (Re-submittal) 11.15.2021
/1 /2
:0
:0
P M
Construct Private In-Patient Rooms & Primary Clinics
12/15/2023
PARTIAL FOURTH FLOOR PLAN
FX104
RLCEWL
506-334
Ann Arbor, Michigan (506)
B01W
JEFF MEANS
BID DOCUMENTS 100%
20014.00
N Scale: 1/8" = 1'-0"
PARTIAL FOURTH FLOOR PLAN
KEYPLAN
PLAN NOTES
1. EXISTING AREA, PIPING OR PIECE OF EQUIPMENT (TYPE AS INDICATED) TO REMAIN.
2. PROVIDE NEW WET-PIPE FIRE SUPPRESSION SPRINKLER SYSTEM (PER HYDRAULIC
CALCULATIONS) TO CONFORM TO NEW LAYOUT INSIDE INDICATED AREA.
S
F S
S
FS S
B01W
B01E
A C
F G I J LE
OH
OH
OH
4 4
EXISTING ZONE
CONTROL VALVE
1-5-2
EXISTING ZONE
CONTROL VALVE
1-5-1 1
EXISTING ZONE
CONTROL VALVE
1-5-4
STAIR #1
STAIR #2
STAIR #3
OH
ELECTRICAL
A578
DATA
A575
LAV
A576
LAV
A577
ELEC
A527
ELEC
A511
FEC
A510
FEC
A574
FEC
A541
MED
B521A
LAV
B523
DATA
B525A
DATA
B525
ELEC
B520
4 4
524A
BATH
1 BR
PATIENT
ROOM #8
1 BR
PATIENT
ROOM #9
525A
BATH
C5-52
CORRIDOR
1 BR
PATIENT
ROOM #7
523A
BATH
NS-502
NURSE
STATION
NS-503
NURSE
STATION
LOUNGE
1BR
PATIENT
ROOM #6
519A
BATH
517A
BATH
1BR
PATIENT
ROOM #5
C5-50
CORRIDOR
SPACE
STAFF
LOUNGE
522C
LOCKERS
522A
LOCKERS
522D
FEMALE
LAV
522B
MALE LAV
1BR
PATIENT
ROOM #4
515A
BATH
1BR
PATIENT
ROOM #2
507A
BATH
NS-501
NURSE
STATION
MED ROOM
CLEAN
UTILITY
CLEAN
LINEN
C5-51
CORRIDOR
SOILED
HOLD
505A
BATH
1BR
ISOLATION
ROOM #1
A513
2BR
505B
ANTE
OFFICE
EQUIPMENT
ALCOVE
NS-500
NURSE
STATION
NUTRITION
BATH
509A
GENERAL NOTES
A. REFER TO SHEET F001 FOR ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS.
B. EXISTING CORRIDORS AND/ OR ROOMS TO REMAIN OPERATIONAL AT ALL TIMES
DURING BUSINESS HOURS. AUTOMATIC SPRINKLER SYSTEM(S) SHALL BE MAINTAINED
IN FULLY OPERATIONAL CONDITION (PER NFPA 241, SPRINKLER SYSTEMS WILL BE
OPERATIONAL, BUT IMPAIRED WHILE CEILINGS ARE REMOVED). SPRINKLER SYSTEM
MAY BE TAKEN OFF-LINE FOR UP TO 8 HOURS, AS REQUIRED, TO MAKE MODIFICATIONS/
CONNECTIONS TO EXISTING SYSTEM.
C. WHEN CEILINGS ARE REMOVED DURING RENOVATION OF AN EXISTING SPACE OR
STRUCTURE, THE SPRINKLERS SYSTEM SHALL BE MAINTAINED BY INSTALLING
UPRIGHT SPRINKLERS TO PROVIDE SUFFICIENT COVERAGE AND A QUICKER
RESPONSE TIME.
VA Project No.
RDC/JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
Project Schedule Date
Schematic Design 15% 02.16.2021
Schematic Design 35% 04.16.2021
Design Development 65% 09.24.2021
Construction Documents 95% 10.26.2023
Bid Documents 100% 12.15.2023
Design Development 65% (Re-submittal) 11.15.2021
/1 /2
:0
:0
P M
Construct Private In-Patient Rooms & Primary Clinics
12/15/2023
PARTIAL FIFTH FLOOR PLAN
FX105
RLCEWL
506-334
Ann Arbor, Michigan (506)
B01W
JEFF MEANS
BID DOCUMENTS 100%
20014.00
N Scale: 1/8" = 1'-0"
PARTIAL FIFTH FLOOR PLAN
PLAN NOTES
1. EXISTING AREA, PIPING OR PIECE OF EQUIPMENT (TYPE AS INDICATED) TO REMAIN.
2. LIMITS OF RENOVATED AREA REQUIRING EXISTING SPRINKLER SYSTEM
MODIFICATIONS. MODIFICATIONS INCLUDE, BUT ARE NOT LIMITED TO, REPLACING
ALL SPRINKLERS, PIPE BRANCHES, AND PIPE MAINS TO CONFORM TO NEW
ARCHITECTURAL LAYOUTS AND NEW MEPT UTILITIES AS NECESSARY.
3. LOCATION OF PATIENT LIFT. NO SPRINKLERS SHALL BE LOCATED BETWEEN SIDE
RAILS, BELOW MOVEABLE LIFT RAIL OR MOTOR.
4. HARD CEILING IN THIS LOCATION (GYPSUM BOARD/ PLASTER/ WOOD). REFER TO
ARCHITECTURAL DRAWINGS FOR ADDITIONAL INFORMATION.
5. NEGATIVELY PRESSURIZED SPACE. SEAL ALL PENETRATIONS IN WALL AND/ OR
CEILING AS REQUIRED TO MAINTAIN PRESSURIZATION.
6. PROVIDE NEW WET-PIPE FIRE SUPPRESSION SPRINKLER SYSTEM (PER HYDRAULIC
CALCULATIONS) TO CONFORM TO NEW LAYOUT INSIDE INDICATED AREA.
7. ALL RENOVATION WORK IN THIS AREA TO BE COMPLETED AFTER THE NEW FIFTH
FLOOR WORK IS COMPLETE AND TURNED OVER TO THE VA.
KEYPLAN
File details come from the government source that posted it. Updated .