This document is a set of architectural and engineering drawings for the EHRM Infrastructure Upgrades project at the Jack C. Montgomery VA Medical Center in Muskogee, Oklahoma, with a project number of 623-21-700. The comprehensive drawing set, dated 05/24/2024, includes detailed floor plans, demolition plans, and phasing plans for multiple buildings (Buildings 1, 18, 22, 24, and 53) across basement and multiple floor levels. The project involves extensive infrastructure modifications, including telecommunications room (TR) upgrades, electrical system improvements, and selective demolition and reconstruction of interior spaces.

The drawings outline a three-phase construction approach with specific infection control risk assessment (ICRA) precautions for each phase. Phase 1 focuses on building out telecommunications rooms and adjacent impacted areas with Class IV precautions. Phase 2 involves pulling new cables from TR racks down main corridors during night and weekend work with Class II precautions. Phase 3 entails providing cable drops in designated rooms, also performed during night and weekend work under Class II precautions. The project team includes Seven Generations Architecture and Engineering, DAV Energy Solutions, and other specialized consultants, with the work to be performed at the VA Medical Center located at 1011 Honor Heights Dr, Muskogee, OK 74401.

View the file

Other files

File Type Posted
36C77625R0046 0009.pdf PDF
Attachment 21 - Tech Questions Tracker - FINAL07162025.pdf PDF
Attachment 21 - Tech Questions Tracker - FINAL_07142025.pdf PDF
36C77625R0046 0008.pdf PDF
Attachment to Tech Questions- ASI-001 Mechanical Ductwork Drawings- 20250714.pdf PDF
36C77625R0046 0007.pdf PDF
Attachment 21 - Tech Questions Tracker - 07082025.pdf PDF
Attachment 21 - Tech Questions Tracker - 07022025.pdf PDF
36C77625R0046 0006.pdf PDF
36C77625R0046 0005.pdf PDF
Attachment 16 Muskogee County Wage Rates_06272025.pdf PDF
Attachment 20 - Spec 01 31 00.01 Project Management and Coordination.pdf PDF
36C77625R0046 0004.pdf PDF
Attachment 21 - Tech Questions Tracker - 20250623 Partial.pdf PDF
36C77625R0046 0003.pdf PDF
Attachment 19 Site Visit Sign In Sheet 62323700.pdf PDF
36C77625R0046 0002.pdf PDF
36C77625R0046 0001.pdf PDF
Attachment 05 Drawings 4 of 13 Muskogee 623-21-700.pdf PDF
Attachment 17- Limitations on Subcontracting - Muskogee EHRM.pdf PDF
Attachment 08 Drawings 7 of 13 Muskogee 623-21-700.pdf PDF
Attachment 01 - 623-21-700 - Muskogee - Updated Combined Specifications-20250501.pdf PDF
Attachment 03 Drawings 2 of 13 Muskogee 623-21-700.pdf PDF
36C77625R0046_1.pdf PDF
Attachment 04 Drawings 3 of 13 Muskogee 623-21-700.pdf PDF
Attachment 18 Site Map.pdf PDF
Attachment 16 Muskogee County Wage Rates.pdf PDF
Attachment 07 Drawings 6 of 13 Muskogee 623-21-700.pdf PDF
Attachment 06 Drawings 5 of 13 Muskogee 623-21-700.pdf PDF
Attachment 12 Drawings 11 of 13 Muskogee 623-21-700.pdf PDF
Attachment 14 Drawings 13 of 13 Muskogee 623-21-700.pdf PDF
Attachment 10 Drawings 9 of 13 Muskogee 623-21-700.pdf PDF
Attachment 13 Drawings 12 of 13 Muskogee 623-21-700.pdf PDF
Attachment 11 Drawings 10 of 13 Muskogee 623-21-700.pdf PDF
Attachment 09 Drawings 8 of 13 Muskogee 623-21-700.pdf PDF
Attachment 15- PCRA for EHRM 623-700.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Building No.

Drawing Number

Project Number

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

Department of

Veteran Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Project Title

ARCHITECT/ENGINEERS:

A/E:

STAMP:CONSULTANTS:

321 4 5 6 7 8 9 10

DAV ENERGY SOLUTIONS

2207 GARNET AVE, SUITE I

SAN DIEGO, CA 92109

619-770-8552

WWW.DAVENERGY.COM

Floor No.

th re e i n c h e s o n e fo o t o n e i n c h o n e fo o t o n e a n d o n e h a lf i n c h e s o n e fo o t th re e q u a rt e rs i n c h o n e fo o t o n e h a lf i n c h o n e fo o t th re e e ig h th s i n c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th i n c h o n e fo o t Dwg. of

G-001

COVER SHEET

SEVEN GENERATIONS ARCHITECTURE AND ENGINEERING

600 E. MICHIGAN AVE. STE B

KALAMAZOO, MI 49007

296.927.0144

JACK C. MONTGOMERY VA MEDICAL CENTER

05/24/2024 JRB SCC

EHRM INFRASTRUCTURE UPGRADES -

JACK C. MONTGOMERY VA MC

623-21-700

MUSKOGEE, OKLAHOMA

NORTH

LOCATION MAP

PROJECT TEAM

MECHANICAL ENGINEERING:

ARCHITECTURE:

PHONE: 269.927.0144

SEVEN GENERATIONS A+E

KALAMAZOO, MI 49007

600 E. MICHIGAN AVENUE - SUITE B

WEB: WWW.7GENAE.COM

PHONE: 619.770.8552

DAV ENERGY SOLUTIONS

SAN DIEGO, CA 92109

2207 GARNET AVE. SUITE I

623-21-700 EHRM INFRASTRUCTURE UPGRADES FOR:

1011 HONOR HEIGHTS DR, MUSKOGEE, OK 74401

JACK C. MONTGOMERY

VA MEDICAL CENTER

PROJECT SITE

ELECTRICAL/FIRE PROTECTION ENGINEERING:

PHONE: 206.590.2118

SPEES DESIGN BUILD

SEATTLE, WA 98104

625 1ST AVE, STE 301

LOW VOLTAGE:

PHONE: 585.377.1850

ECC TECHNOLOGIES

PENFIELD, NY 14526

2163 FIVE MILE LINE ROAD

Revisions: 35% Schematic Design Date: 02/24/2023

Revisions: 65% Design Development Date: 09/21/2023

Revisions: 95% Construction Documents Date: 02/12/2024

STRUCTURAL:

PHONE: 213.271.2000

SIMPSON GUMPERTZ & HEGER

LOS ANGELES, CA 90015

1150 S. OLIVE STREET, SUITE 1600

Revisions: 10% Diamond Drawings Date: 09/30/2022

Revisions: 100% Bid Documents Date: 05/24/2024

Building No.

Drawing Number

Project Number

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

Department of

Veteran Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Project Title

ARCHITECT/ENGINEERS:

A/E:

STAMP:CONSULTANTS:

321 4 5 6 7 8 9 10

DAV ENERGY SOLUTIONS

2207 GARNET AVE, SUITE I

SAN DIEGO, CA 92109

619-770-8552

WWW.DAVENERGY.COM

Floor No.

th re e i n c h e s o n e fo o t o n e i n c h o n e fo o t o n e a n d o n e h a lf i n c h e s o n e fo o t th re e q u a rt e rs i n c h o n e fo o t o n e h a lf i n c h o n e fo o t th re e e ig h th s i n c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th i n c h o n e fo o t Dwg. of

G-002

SHEET INDEX

SEVEN GENERATIONS ARCHITECTURE AND ENGINEERING

600 E. MICHIGAN AVE. STE B

KALAMAZOO, MI 49007

296.927.0144

JACK C. MONTGOMERY VA MEDICAL CENTER

05/24/2024 JRB SCC

EHRM INFRASTRUCTURE UPGRADES -

JACK C. MONTGOMERY VA MC

623-21-700

DRAWING SHEET INDEX

DESCRIPTIONSHEET ISSUE DATE

TN-114 BUILDINGS 53, 56, 60 - DETAILS - NEW WORK 05/24/24

TN-115 BUILDINGS 11, 18, 38 - KEY PLAN - NEW WORK 05/24/24

TN-116 BUILDING 18 - SUB BASEMENT - NEW WORK 05/24/24

TN-117 BUILDINGS 18 - BASEMENT - NEW WORK 05/24/24

TN-118 BUILDINGS 11, 18, 38 - FIRST FLOOR - NEW WORK 05/24/24

TN-119 BUILDINGS 11, 18, 38 - DETAILS - NEW WORK 05/24/24

TN-120 NEW FIBER OPTIC RISER DIGRAM 05/24/24

TN-121 NEW COPPER RISER DIAGRAM 05/24/24

TN-122 NETWORK DETAILS 05/24/24

TN-18 BUILDING 52, 53 - MEZZANNE - DEMOLITION 05/24/24

TN-19 BUILDING 1 - FIRST FLOOR - AREA A - DEMOLITION 05/24/24

TN-20 BUILDING 1 - FIRST FLOOR - AREA B - DEMOLITION 05/24/24

TN-21 BUILDING 53 - FIRST FLOOR - AREA C - DEMOLITION 05/24/24

TN-22 BUILDING 53, 60 - FIRST FLOOR - AREA D - DEMOLITION 05/24/24

TN-23 BUILDING 1 - FIRST FLOOR - AREA E - DEMOLITION 05/24/24

TN-24 BUILDING 24 - FIRST FLOOR - AREA F - DEMOLITION 05/24/24

TN-25 BUILDING 22 - FIRST FLOOR - AREA G - DEMOLITION 05/24/24

TN-26 BUILDING 1 - SECOND FLOOR - AREA A - DEMOLITION 05/24/24

TN-27 BUILDING 1 - SECOND FLOOR - AREA B - DEMOLITION 05/24/24

TN-28 BUILDING 53 - SECOND FLOOR - AREA C - DEMOLITION 05/24/24

TN-29 BUILDING 53 - SECOND FLOOR - AREA D - DEMOLITION 05/24/24

TN-30 BUILDING 24 - SECOND FLOOR - AREA E - DEMOLITION 05/24/24

TN-31 BUILDING 22 - SECOND FLOOR - AREA F - DEMOLITION 05/24/24

TN-32 BUILDING 1 - THIRD FLOOR - AREA A - DEMOLITION 05/24/24

TN-33 BUILDING 1 - THIRD FLOOR - AREA B - DEMOLITION 05/24/24

TN-34 BUILDING 53 - THIRD FLOOR - AREA C - DEMOLITION 05/24/24

TN-35 BUILDING 53 - THIRD FLOOR - AREA D - DEMOLITION 05/24/24

TN-36 BUILDING 22,24 - THIRD FLOOR - AREA E - DEMOLITION 05/24/24

TN-37 BUILDING 1 - FOURTH FLOOR - AREA A - DEMOLITION 05/24/24

TN-38 BUILDING 53 - FOURTH FLOOR - AREA B - DEMOLITION 05/24/24

TN-39 BUILDING 53 - FOURTH FLOOR - AREA C - DEMOLITION 05/24/24

TN-40 BUILDING 1 - FIFTH FLOOR - AREA A - DEMOLITION 05/24/24

TN-41 BUILDING 53 - FIFTH FLOOR - AREA B - DEMOLITION 05/24/24

TN-42 BUILDING 53 - FIFTH FLOOR - AREA C - DEMOLITION 05/24/24

TN-43 BUILDING 1 - SIXTH FLOOR - AREA A - DEMOLITION 05/24/24

TN-44 BUILDING 53 - SIXTH FLOOR - AREA B - DEMOLITION 05/24/24

TN-45 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-46 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-47 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-48 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-49 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-50 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-51 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-52 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-53 BUILDINGS 1, 22, 24, 53 - DETAILS - DEMOLITION 05/24/24

TN-54 BUILDINGS 11, 18, 38 - KEY PLAN - DEMOLITION 05/24/24

TN-55 BUILDING 18 - SUB BASEMENT - DEMOLITION 05/24/24

TN-56 BUILDING 18 - BASEMENT- DEMOLITION 05/24/24

TN-57 BUILDINGS 11, 18, 38 - FIRST FLOOR - DEMOLITION 05/24/24

TN-58 BUILDINGS 11, 18, 38 - DETAILS - DEMOLITION 05/24/24

TN-59 EXISTING FIBER OPTIC RISER DIAGRAM 05/24/24

TN-60 EXISTING COPPER BACKBONE RISER 05/24/24

TN-61 SITE PLAN - NEW WORK 05/24/24

TN-62 BUILDINGS 56, 52, 53 - SUB BASEMENT - KEY PLAN - NEW WORK 05/24/24

TN-63 BUILDINGS 22, 24, 53 - BASEMENT - KEY PLAN - NEW WORK 05/24/24

TN-64 MEZZANINE - KEY PLAN - NEW WORK 05/24/24

TN-65 BUILDINGS 1, 22, 24, 53 - FIRST FLOOR - KEY PLAN - NEW WORK 05/24/24

TN-66 BUILDINGS 1, 22, 24, 53 - SECOND FLOOR - KEY PLAN - NEW WORK 05/24/24

TN-67 BUILDINGS 1, 22, 24, 53 - THIRD FLOOR - KEY PLAN - NEW WORK 05/24/24

TN-68 BUILDINGS 1, 22, 24, 53 - THIRD FLOOR INTERST. - KEY PLAN - NEW

WORK

05/24/24

TN-69 BUILDINGS 1, 53 - FOURTH FLOOR - KEY PLAN - NEW WORK 05/24/24

TN-70 BUILDINGS 53 - FOURTH FLOOR INTERST. - KEY PLAN - NEW WORK 05/24/24

TN-71 BUILDINGS 1, 53 - FIFTH FLOOR - KEY PLAN - NEW WORK 05/24/24

TN-72 BUILDING 53 - FIFTH FLOOR INTERST. - KEY PLAN - NEW WORK 05/24/24

TN-73 BUILDINGS 1, 53 - SIXTH FLOOR - KEY PLAN - NEW WORK 05/24/24

TN-74 BUILDING 22 - SUB BASEMENT - NEW WORK 05/24/24

TN-75 BUILDING 24 - SUB BASMENT - NEW WORK 05/24/24

TN-76 BUILDINGS 52, 53 - SUB BASMENT - NEW WORK 05/24/24

TN-77 BUILDING 22 - BASEMENT - NEW WORK 05/24/24

TN-78 BUILDING 24 - BASEMENT - NEW WORK 05/24/24

TN-79 BUILDING 53 - BASEMENT - NEW WORK 05/24/24

TN-80 MEZZANINE - NEW WORK 05/24/24

TN-81 BUILDING 1 - FIRST FLOOR - AREA A - NEW WORK 05/24/24

TN-82 BUILDING 1 - FIRST FLOOR - AREA B - NEW WORK 05/24/24

TN-83 BUILDING 53 - FIRST FLOOR - AREA C - NEW WORK 05/24/24

TN-84 BUILDING 53, 60 - FIRST FLOOR - AREA D - NEW WORK 05/24/24

TN-85 BUILDING 1 - FIRST FLOOR - AREA E - NEW WORK 05/24/24

TN-86 BUILDINGS 22, 24 - FIRST FLOOR - AREA D - NEW WORK 05/24/24

TN-87 BUILDING 1 - SECOND FLOOR - AREA A - NEW WORK 05/24/24

TN-88 BUILDING 1 -SECOND FLOOR - AREA B - NEW WORK 05/24/24

TN-89 BUILDING 53 - SECOND FLOOR - AREA C - NEW WORK 05/24/24

TN-90 BUILDING 53 - SECOND FLOOR - AREA D - NEW WORK 05/24/24

TN-91 BUILDING 24 - SECOND FLOOR - AREA E - NEW WORK 05/24/24

TN-92 BUILDING 22 - SECOND FLOOR - AREA F - NEW WORK 05/24/24

TN-93 BUILDING 1 - THIRD FLOOR - AREA A - NEW WORK 05/24/24

TN-94 BUILDINGS 1, 53 - THIRD FLOOR - AREA B - NEW WORK 05/24/24

TN-95 BUILDING 53 - THIRD FLOOR - AREA C - NEW WORK 05/24/24

TN-96 BUILDING 22, 24 - THIRD FLOOR - AREA D - NEW WORK 05/24/24

TN-97 BUILDING 53 - THIRD FLOOR INTERST. - NEW WORK 05/24/24

TN-98 BUILDING 1 - FOURTH FLOOR - AREA A - NEW WORK 05/24/24

TN-99 BUILDING 53 -FOURTH FLOOR - AREA B - NEW WORK 05/24/24

TN-100 BUILDING 53 - FOURTH FLOOR - AREA C - NEW WORK 05/24/24

TN-101 BUILDING 53 - FOURTH FLOOR INTERST. - NEW WORK 05/24/24

TN-102 BUILDING 1 - FIFTH FLOOR - AREA A - NEW WORK 05/24/24

TN-103 BUILDING 53 - FIFTH FLOOR - AREA B - NEW WORK 05/24/24

TN-104 BUILDING 53 - FIFTH FLOOR - AREA C - NEW WORK 05/24/24

TN-105 BUILDING 53 - FIFTH FLOOR INTERST. - NEW WORK 05/24/24

TN-106 BUILDING 1 - SIXTH FLOOR - AREA A - NEW WORK 05/24/24

TN-107 BUILDING 53 - SIXTH FLOOR - AREA B - NEW WORK 05/24/24

TN-108 BUILDINGS 53, 56, 60 - DETAILS - NEW WORK 05/24/24

TN-109 BUILDINGS 53, 56, 60 - DETAILS - NEW WORK 05/24/24

TN-110 BUILDINGS 53, 56, 60 - DETAILS - NEW WORK 05/24/24

TN-111 BUILDINGS 53, 56, 60 - DETAILS - NEW WORK 05/24/24

TN-112 BUILDINGS 53, 56, 60 - DETAILS - NEW WORK 05/24/24

TN-113 BUILDINGS 53, 56, 60 - DETAILS - NEW WORK 05/24/24

01EP101 BLDG 01 - LEVEL 01 - ELECTRICAL PLAN 05/24/24

18EP100B BLDG 18 - LEVEL 00B - ELECTRICAL PLAN 05/24/24

18&11EP101 BLDG 18&11 - LEVEL 01 - ELECTRICAL PLAN 05/24/24

22EP100S BLDG 22 - LEVEL 00S - ELECTRICAL PLAN 05/24/24

22EP100B BLDG 22 - LEVEL 00B - ELECTRICAL PLAN 05/24/24

22EP100B 22EP101 - BLDG 22 - LEVEL 01 - ELECTRICAL PLAN 05/24/24

24EP100B BLDG 24 - LEVEL 00B - ELECTRICAL PLAN 05/24/24

24EP101 BLDG 24 - LEVEL 01 - ELECTRICAL PLAN 05/24/24

52EP102 BLDG 52 - MEZZANINE - ELECTRICAL PLAN 05/24/24

53EP100S BLDG 53 - LEVEL 00S - ELECTRICAL PLAN 05/24/24

53EP100B BLDG 53 - LEVEL 00B - ELECTRICAL PLAN 05/24/24

53EP101 BLDG 53 - LEVEL 01 - ELECTRICAL PLAN 05/24/24

53EP102 BLDG 53 - LEVEL 02 - ELECTRICAL PLAN 05/24/24

53EP103 BLDG 53 - LEVEL 03 - ELECTRICAL PLAN 05/24/24

53EP104 BLDG 53 - ROOF - ELECTRICAL PLAN 05/24/24

01EP401a BLDG 01 - LEVEL 01 - ENLARGED ELECTRICAL PLANS 05/24/24

01EP401b BLDG 01 - LEVEL 01 - ENLARGED ELECTRICAL PLANS 05/24/24

01EP402a BLDG 01 - LEVEL 02 - ENLARGED ELECTRICAL PLANS 05/24/24

01EP402b BLDG 01 - LEVEL 02 - ENLARGED ELECTRICAL PLANS 05/24/24

01EP403 BLDG 01 - LEVEL 03 - ENLARGED ELECTRICAL PLANS 05/24/24

01EP404 BLDG 01 - LEVEL 04 - ENLARGED ELECTRICAL PLANS 05/24/24

01EP405 BLDG 01 - LEVEL 05 - ENLARGED ELECTRICAL PLANS 05/24/24

01EP406 BLDG 01 - ROOF - ENLARGED ELECTRICAL PLAN 05/24/24

01EP406 BLDG 01 - R18&11EP401 - BLDG 18&11 - LEVEL 01 - ENLARGED

ELECTRICAL PLANS

OOF - ENLARGED ELECTRICAL PLAN

05/24/24

22EP400B BLDG 22 - LEVEL 00B - ENLARGED ELECTRICAL PLANS 05/24/24

22EP401 BLDG 22 - LEVEL 01 - ENLARGED ELECTRICAL PLANS 05/24/24

24EP400B BLDG 24 - LEVEL 00B - ENLARGED ELECTRICAL PLANS 05/24/24

24EP401 BLDG 24 - LEVEL 01 - ENLARGED ELECTRICAL PLANS 05/24/24

24EP402 BLDG 24 - LEVEL 02 - ENLARGED ELECTRICAL PLANS 05/24/24

52EP402 BLDG 52 - MEZZANINE - ENLARGED ELECTRICAL PLANS 05/24/24

53EP400B BLDG 53 - LEVEL 00B - ENLARGED ELECTRICAL PLANS 05/24/24

53EP401 BLDG 53 - LEVEL 01 - ENLARGED ELECTRICAL PLANS 05/24/24

53EP403 BLDG 53 - LEVEL 03 - ENLARGED ELECTRICAL PLANS 05/24/24

53EP404 BLDG 53 - LEVEL 04 - ENLARGED ELECTRICAL PLANS 05/24/24

53EP405 BLDG 53 - LEVEL 05 - ENLARGED ELECTRICAL PLANS 05/24/24

EP501 ELECTRICAL DETAILS 05/24/24

EP502 ELECTRICAL DETAILS 05/24/24

EP503 ELECTRICAL DETAILS 05/24/24

EP504 ELECTRICAL DETAILS 05/24/24

EP505 ELECTRICAL DETAILS 05/24/24

EP506 ELECTRICAL DETAILS 05/24/24

EP507 ELECTRICAL DETAILS 05/24/24

EG601 TELECOMMUNICATIONS BONDING RISER DIAGRAM 05/24/24

01EP602 BLDG 01 - PARTIAL ONE-LINE DIAGRAM - DEMOLITION 05/24/24

01EP611 BLDG 01 - ONE-LINE DIAGRAM - PART 1 OF 4 05/24/24

01EP612 BLDG 01 - ONE-LINE DIAGRAM - PART 2 OF 4 05/24/24

01EP613 BLDG 01 - ONE-LINE DIAGRAM - PART 3 OF 4 05/24/24

01EP614 BLDG 01 - ONE-LINE DIAGRAM - PART 4 OF 4 05/24/24

18&11EP611 BLDG 18&11 - ONE-LINE DIAGRAM 05/24/24

22EP611 BLDG 22 - ONE-LINE DIAGRAM 05/24/24

24EP601 BLDG 24 - ONE-LINE DIAGRAM - DEMOLITION 05/24/24

24EP611 BLDG 24 - ONE-LINE DIAGRAM 05/24/24

52EP602 BLDG 52 - PARTIAL ONE-LINE DIAGRAM - DEMOLITION 05/24/24

52EP611 BLDG 52 - ONE-LINE DIAGRAM - PART 1 OF 2 05/24/24

52EP612 BLDG 52 - ONE-LINE DIAGRAM - PART 2 OF 2

52EP612 - BLDG 52 - ONE-LINE DIAGRAM - PART 2 OF 2

05/24/24

53EP601 BLDG 53 - PARTIAL ONE-LINE DIAGRAM - DEMOLITION 05/24/24

53EP602 BLDG 53 - PARTIAL ONE-LINE DIAGRAM - DEMOLITION 05/24/24

53EP611 BLDG 53 - ONE-LINE DIAGRAM - PART 1 OF 6 05/24/24

53EP612 BLDG 53 - ONE-LINE DIAGRAM - PART 2 OF 6 05/24/24

53EP613 BLDG 53 - ONE-LINE DIAGRAM - PART 3 OF 6 05/24/24

53EP614 BLDG 53 - ONE-LINE DIAGRAM - PART 4 OF 6 05/24/24

53EP615 BLDG 53 - ONE-LINE DIAGRAM - PART 5 OF 6 05/24/24

53EP616 BLDG 53 - ONE-LINE DIAGRAM - PART 6 OF 6 05/24/24

EP701 ELECTRICAL SCHEDULES 05/24/24

EP702 ELECTRICAL SCHEDULES 05/24/24

01EP701 BLDG 01 - ELECTRICAL SCHEDULES 05/24/24

01EP70 BLDG 01 - ELECTRICAL SCHEDULES 05/24/24

01EP703 BLDG 01 - ELECTRICAL SCHEDULES 05/24/24

18&11EP701 BLDG 18 - ELECTRICAL SCHEDULES 05/24/24

22EP701 BLDG 22 - ELECTRICAL SCHEDULES 05/24/24

24EP701 BLDG 24 - ELECTRICAL SCHEDULES 05/24/24

24EP702 BLDG 24 - ELECTRICAL SCHEDULES 05/24/24

52EP701 BLDG 52 - ELECTRICAL SCHEDULES 05/24/24

53EP701 BLDG 53 - ELECTRICAL SCHEDULES 05/24/24

53EP702 BLDG 53 - ELECTRICAL SCHEDULES 05/24/24

TN-1 SYMBOLS AND ABBREVIATIONS 05/24/24

TN-2 SITE PLAN - DEMOLITION 05/24/24

TN-3 BUILDINGS 22, 24, 52, 53 - SUB BASEMENT - KEY PLAN - DEMOLITION 05/24/24

TN-4 BUILDINGS 22, 24, 52, 53 - SUB BASEMENT - KEY PLAN - DEMOLITION 05/24/24

TN-5 BUILDINGS 52, 53 - MEZZANINE - DEMOLITION 05/24/24

TN-6 BUILDINGS 1, 22, 24, 53 - FIRST FLOOR PLAN - KEY PLAN- DEMOLITION 05/24/24

TN-7 BUILDINGS 1, 22, 24, 53 - SECOND FLOOR PLAN - KEY PLAN -

DEMOLITION

05/24/24

TN-8 BUILDINGS 1, 22, 52, 53 - THIRD FLOOR PLAN - KEY PLAN - DEMOLITION 05/24/24

TN-9 BUILDINGS 1, 53 - FOURTH FLOOR - KEY PLAN - DEMOLITION 05/24/24

TN-10 BUILDINGS 1, 53 - FIFTH FLOOR - KEY PLAN - DEMOLITION 05/24/24

TN-11 BUILDINGS 1, 53 - SIXTH FLOOR - KEY PLAN - DEMOLITION 05/24/24

TN-12 BUILDING 22 - SUB BASEMENT - DEMOLITION 05/24/24

TN-13 BUILDING 24 - SUB BASEMENT - DEMOLITION 05/24/24

TN-14 BUILDING 52, 53 - SUB BASEMENT AND BUILDING 56 FIRST FLOOR -

DEMOLITION

05/24/24

TN-15 BUILDING 22 - BASEMENT - DEMOLITION 05/24/24

TN-16 BUILDING 24 - BASEMENT - DEMOLITION 05/24/24

TN-17 BUILDING 53 - BASEMENT - DEMOLITION 05/24/24

G-001 COVER & DRAWING INDEX 05/24/24

G-002 SHEET INDEX 05/24/24

G-003 ARCHITECTURAL SYMBOLS & ABBREVIATIONS 05/24/24

G-100 ICRA AND PHASING GENERAL NOTES

18G-201 BUILDING 18 - LEVEL 01 - ICRA AND PHASING PLAN 05/24/24

22G-200 BUILDING 22 - LEVEL 00 - ICRA AND PHASING PLAN 05/24/24

24G-200 BUILDNG 24 - LEVEL 00 - ICRA AND PHASING PLAN 05/24/24

53G-200 BUILDING 53 - LEVEL 00 - ICRA AND PHASING PLAN 05/24/24

G-201 BUILDING 1/22/24/53 - LEVEL 01 - ICRA AND PHASING PLAN 05/24/24

G-202 BUILDING 1/22/24/53 - ICRA AND PHASING PLAN 05/24/24

G-203 BUILDING 1/53 - LEVEL 03 - ICRA AND PHASING PLAN 05/24/24

G-204 BUILDING 1/53 - LEVEL 04 - ICRA AND PHASING PLAN 05/24/24

G-205 BUILDING 1/53 - LEVEL 05 - ICRA AND PHASING PLAN 05/24/24

S-001 STRUCTURAL GENERAL NOTES 05/24/24

S-010 STRUCTURAL TYPICAL CONCRETE DETAILS 05/24/24

S-400 STRUCTURAL CONCRETE DETAILS 05/24/24

G-300 WALL TYPES, FINISH KEY, AND DETAILS 05/24/24

18A-101 BUILDING 18 - LEVEL 01 - OVERALL 05/24/24

22A-100 BUILDING 22 - LEVEL 00 - OVERALL 05/24/24

24A-100 BUILDING 24 - LEVEL 00 - OVERALL 05/24/24

53A-100 BUILDING 53 - LEVEL 00 - OVERALL 05/24/24

A-101 BUILDING 01/22/24/53 - LEVEL 01 - OVERALL 05/24/24

A-102 BUILDING 1/22/24/53 - LEVEL 02 - OVERALL 05/24/24

A-103 BUILDING 1/53 - LEVEL 03 - OVERALL 05/24/24

A-104 BUILDING 1/53 - LEVEL 04 - OVERALL 05/24/24

A-105 BUILDING 1/53 - LEVEL 05 - OVERALL 05/24/24

01A-201 BUILDING 01 - LEVEL 01 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

01A-202 BUILDING 01 - LEVEL 02- ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

01A-203 BUILDING 01 - LEVEL 03 - ENLARGED DEMO, FLOOR PLAN & RCPS 05/24/24

01A-204 BUILDING 01 - LEVEL 04 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

01A-205 BUILDING 01 - LEVEL 05 - ENLARGED DEMO, FLOOR PLAN & RCPS 05/24/24

18A-201 BUILDING 18 - LEVEL 01 - ENLARGED DEMO, FLOOR PLAN & RCPS 05/24/24

22A-200 BUILDING 22 - LEVEL 00 - ENLARGED DEMO, FLOOR PLANS, & RCPS 05/24/24

22A-201 BUILDING 22 - LEVEL 01 - ENLARGED DEMO, FLOOR PLANS, & RCPS 05/24/24

24A-200 BUILDING 24 - LEVEL 00 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

24A-201 BUILDING 24 - LEVEL 01 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

24A-202 BUILDING 24 - LEVEL 02 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

52A-202 BUILDING 52 - LEVEL 02 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

53A-200 BUILDING 53 - LEVEL 00 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

53A-201 BUILDING 53 - LEVEL 01 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

53A-203 BUILDING 53 - LEVEL 03 - ENLARGED DEMO, FLOOR PLAN & RCPS 05/24/24

53A-204 BUILDING 53 - LEVEL 04 - ENLARGED DEMO, FLOOR PLANS & RCPS 05/24/24

53A-205 BUILDING 53 - LEVEL 05 - ENLARGED DEMO, FLOOR PLAN & RCPS 05/24/24

01F-101a BUILDING 01 -LEVEL 01 -DEMO, FLOOR PLANS & RCPS 05/24/24

01F-101b BUILDING 01 -LEVEL 01 -DEMO, FLOOR PLANS & RCPS 05/24/24

01F-102a BUILDING 01 -LEVEL 02-DEMO, FLOOR PLANS & RCPS 05/24/24

01F-102b BUILDING 01 -LEVEL 02-DEMO, FLOOR PLANS & RCPS 05/24/24

01F-103 BUILDING 01 -LEVEL 03 -DEMO, FLOOR PLANS & RCPS 05/24/24

01F-104 BUILDING 01 -LEVEL 04 -DEMO, FLOOR PLANS & RCPS 05/24/24

01F-105 BUILDING 01 -LEVEL 05 -DEMO, FLOOR PLANS & RCPS 05/24/24

18 & 11F-101 BUILDING 18 -LEVEL 01 -DEMO, FLOOR PLANS & RCPS 05/24/24

22F-101a BUILDING 22 -LEVEL 01 -DEMO, FLOOR PLANS & RCPS 05/24/24

22F-101b BUILDING 22 -LEVEL 01 -DEMO, FLOOR PLANS & RCPS 05/24/24

22F-102 BUILDING 22 -LEVEL 02 -DEMO, FLOOR PLANS & RCPS 05/24/24

24F-100 BUILDING 24 -LEVEL 00 -DEMO, FLOOR PLANS, & RCPS 05/24/24

24F-101 BUILDING 24 -LEVEL 01 -DEMO, FLOOR PLANS, & RCPS 05/24/24

24F-102 BUILDING 24 -LEVEL 02 -DEMO, FLOOR PLANS, & RCPS 05/24/24

52F-102 BUILDING 52 -LEVEL 02 -DEMO, FLOOR PLANS & RCPS 05/24/24

53F-100 BUILDING 53 -LEVEL 00 -DEMO, FLOOR PLANS & RCPS 05/24/24

53F-101 BUILDING 53 -LEVEL 01 -DEMO, FLOOR PLANS & RCPS 05/24/24

53F-103 BUILDING 53 -LEVEL 03 -DEMO, FLOOR PLANS & RCPS 05/24/24

53F-104 BUILDING 53 -LEVEL 04 -DEMO, FLOOR PLANS & RCPS 05/24/24

53F-105 BUILDING 53 -LEVEL 05 -DEMO, FLOOR PLANS & RCPS 05/24/24

M-001 MECHANICAL COVER SHEET 05/24/24

M-100 BUILDINGS 22, 24, 53 COMBINED BASEMENT LEVEL LAYOUT 05/24/24

M-100A BUILDINGS 22, 24, 53 BASEMENT FLOOR ROOM DETAILS 05/24/24

M-101 BUILDINGS 1, 22, 24, 53 COMBINED LEVEL 1 LAYOUT 05/24/24

M-101A BUILDINGS 1, 22, 24, 53 FIRST FLOOR ROOM DETAILS 05/24/24

M-101B BUILDINGS 1, 22, 24, 53 FIRST FLOOR ROOM DETAILS 05/24/24

M-101C BUILDINGS 1, 22, 24, 53 FIRST FLOOR ROOM DETAILS 05/24/24

M-101D BUILDINGS 1, 22, 24, 53 FIRST FLOOR ROOM DETAILS 05/24/24

M-102 BUILDINGS 1, 22, 24 COMBINED LEVEL 2 LAYOUT 05/24/24

M-102A BUILDINGS 1, 22, 24, 53 SECOND FLOOR ROOM DETAILS 05/24/24

M-102B BUILDINGS 1, 22, 24, 53 SECOND FLOOR ROOM DETAILS 05/24/24

M-103 BUILDINGS 1, 53 COMBINED LEVEL 3 LAYOUT 05/24/24

M-103A BUILDINGS 1, 53 THIRD FLOOR ROOM DETAILS 05/24/24

M-104 BUILDINGS 1, 53 COMBINED LEVEL 4 LAYOUT 05/24/24

M-104A BUILDINGS 1, 53 FOURTH FLOOR ROOM DETAILS 05/24/24

M-105 BUILDINGS 1, 53 COMBINED LEVEL 5 LAYOUT 05/24/24

M-105A BUILDINGS 1, 53 FIFTH FLOOR ROOM DETAILS 05/24/24

M-106 BUILDING 18 FIRST FLOOR DETAILS 05/24/24

M-107A BUILDING 1 ROOF PLAN 05/24/24

M-107B BUILDING 53 ROOF PLAN 05/24/24

M-401 MECHANICAL SCHEDULES 05/24/24

M-501 MECHANICAL DETAILS 05/24/24

M-502 MECHANICAL DETAILS 05/24/24

M-503 MECHANICAL DETAILS 05/24/24

EPG001 ABBREVIATIONS, GENERAL NOTES, AND SHEET INDEX 05/24/24

EPG002 ELECTRICAL LEGENDS 05/24/24

Revisions: 35% Schematic Design Date: 02/24/2023

DESCRIPTIONSHEET ISSUE DATE DESCRIPTIONSHEET ISSUE DATE DESCRIPTIONSHEET ISSUE DATE

Revisions: 65% Design Development Date: 09/21/2023

Revisions: 35% Schematic Design Date: 02/24/2023

Revisions: 95% Construction Documents Date: 02/12/2024

Revisions: 10% Diamond Drawings Date: 09/30/2022Revisions: 100% Bid Documents Date: 05/24/2024

A300

A320

ARCHITECTURAL SYMBOLS & PLAN INDICATORS

ABBREVIATIONSBARRIER-FREE DESIGN INFORMATION

ROOMNAME

XXX

A

A

A

A

8'-0"

TOP OF STEEL

ELEV. 10'-0"

A200

TITLE

SCALE X" = 1'-0"

TYP. BARRIER FREE TOILET ROOM FIXTURES

SCALE: NONE

TYP. BARRIER FREE TOILET ROOM FIXTURES

SCALE: NONE

OBSTRUCTED APPROACH

UNOBSTRUCTED APPROACH

TYP. BARRIER FREE SHOWER PLAN

SCALE: NONE

TYP. BARRIER FREE TRANSFER SHOWER

SCALE: NONE

TYP. CODE REGULATED MOUNTING HEIGHTS

SCALE: NONE

TYP. EQUIPMENT MOUNTING HEIGHTS

SCALE: NONE

ELEVATION INDICATION

SHEET NO.

ELEVATION NUMBER

SECTION INDICATOR

ENLARGED PLAN OR

ELEVATION

PROPOSED SPOT

EXISTING SPOT

ELEVATION

100.57'

100.57'

STRUCTURAL SPAN

ROOF TRUSSES

FLOOR JOIST OR

RAMP

@ 16" O.C.

2 x 12

1" per 12"

SLOPE UP

REVISION TAG W/

REVISION NUMBER

KEYNOTE TAG

WINDOW TAG W/

WINDOW TYPE

INDICATOR

WALL SECTION CUT

COLUMN LINE

WALL TYPES

ELEVATION

BUILDING SECTION CUT

SHEET LOCATION

DETAIL NUMBER

TYPICAL

DIMENSIONING

SET-BACK LINE

PROPERTY LINE

EXISTING

CONTOUR

TOPOGRAPHY

CONTOUR

100'

100'

TOPOGRAPHY

PROPOSED

SECTIONS & DETAILS

TYPICAL TITLE FOR

DOOR NUMBER

DOOR TAG W/

ROOM NUMBER

ROOM NAME/

NORTH ARROW

60" DIAMETER CLEAR

WHEELCHAIR TURNING

SPACE - REFER TO PLAN

- REFER TO PLAN

AND GROUND SPACE

30" x 48" CLEAR FLOOR

CEILING HEIGHT TAG

MIRRORGRAB

BARS

TOILET PAPER

GRAB BARS

5'-0" DIA.

CLEAR FLOOR SPACE

60" WIDE BY 59" DEEP

CLEAR FLOOR AREA AT

WATER CLOSET

2'-6" x 4'-0" CLEAR

FLOOR AREA AT

LAVATORY

SEAT WALL

BACK WALL

CONTROL WALL

3'-0" x 4'-0"

CLEAR AREA

'L' SHAPE FOLDING

SHOWER SEAT SHALL

COMPLY WITH SECTION

610.3 OF ICC/ANSI A117.1

GRAB BAR TO BE

ACROSS CONTROL

AND MEASURE 18"

FROM CONTROL WALL

SHOWER SPRAY UNIT W/

59" HOSE AND 24" HEIGHT

ADJUSTABLE BAR

GRAB

BARS

CONTROLS SHALL BE

LOCATED WITHIN 15" OF

EITHER SIDE OF SHOWER SEAT

CENTER LINE. PROVIDE MAX

WATER TEMP OF 120°

ACCESSIBLE SHOWER

COMPARTMENTS SHALL

COMPLY WITH SECTION

608 OF ICC/ANSI A117.1

'L' SHAPE FOLDING SHOWER

SEAT AND SHALL COMPLY

WITH SECTION 610.3 OF

ICC/ANSI A117.1

* DIMENSION IS TO BOTTOM

OF REFLECTIVE SURFACE

RECEPTACLE

LIGHT

SWITCH

HVAC

CONTROLS

FIRE

ALARM

FEC

LESS THAN 40#

FEC

GREATER THAN 40#

TEL

PUSH PAD

RH/CH

GBX

SH1

CL

OT

SPH

CRK SND

PT

SD

HS

XR COM4 MR

CRBG

WP

TP SNR

4'-4"

TV

XXXNORTH

M A

X

M

IN

/3

" 4

" 5

M A

X

0' - 6" 3' - 0"

1' - 6 1/32"3' - 5 31/32"

MIN

1' - 3"

MIN

1' - 6"

M

A X

M

IN

M

IN

M A

X

/3

M

IN

3' - 0"

C

LR

4' - 0"

3' - 0" CLR.

1' - 6"

5' - 0"

M

IN

0' - 6" 3' - 0"

M A

X

3' - 6" 1' - 0"

M

IN

M

A X

M

IN

M

IN

M A

X

SIDE FRONT

M

A X

M

A X

20" - 25"

M

A X

FRONT

M

A X

20" MAX

SIDE

SIDE FRONT

M

IN

M

A X

M

IN

M

A X

@ AT

A/C AIR CONDITIONING/AIR CONDITIONER

ACOUS ACOUSTICAL

AD AREA DRAIN, AUTOMATIC DAMPER

ADJ ADJUST, ADJUSTABLE

ALUM ALUMINUM

AP ACCESS PANEL

ACT ACOUSTICAL CEILING

B BASE

BAR BARRIER

BD BOARD

BF BARRIER FREE

BKT BRACKET

BLDG BUILDING

BLKG BLOCKING

BOTT BOTTOM

C TO C CENTER TO CENTER

CAB CABINET

CE COLUMN ENCLOSURE

CIR CIRCLE

CIR CIRCUIT

CL CENTER LINE, CLEARANCES

CLG CEILING

CJ CONTROL JOINT

CLKG CAULKING

CLO CLOSET

CMT CERAMIC MOSAIC TILE

CMU CONCRETE MASONRY UNIT

CO CLEANOUT

COL COLUMN

CONC CONCRETE

CONT CONTINUOUS

CORR CORRIDOR

CPT CARPET

CSS CLINICAL SERVICE SINK

CT CERAMIC TILE

CTR CENTER

CUH CABINET UNIT HEATER

DEMO DEMOLITION, DEMOLISH

DEPT DEPARTMENT

DF DRINKING FOUNTAIN

DIA, D DIAMETER

DIM DIMENSION

DN DOWN

DR DRAIN

DS DOWNSPOUT

ELECT ELECTRICAL

ELEV ELEVATION

ENTR ENTRANCE

EQ EQUAL

EP ELECTRICAL PANEL

EXH EXHAUST

EXP EXPOSED

EXIST EXISTING, EXSIST'G

EXT EXTERIOR

EW EACH WAY

FA FIRE ALARM

FD FIRE DAMPER OR FLOOR DRAIN

FE FIRE EXTINGUISHER

FEC FIRE EXTINGUISHER CABINET

FIN FINISH

FL, FLR FLOOR FINISH

FLG, FLRG FLOORING, FLOOR'G

FURN FURNITURE, FURNACE

FWC FABRIC WALL COVERING

FT FEET, FOOT

GALV GALVANIZE(D)

GL GLASS

GSB GYPSUM SHEATHING BOARD

GWB GYPSUM WALLBOARD

GYP. BD GYPSUM BOARD

ID INSIDE DIAMETER

INSUL INSULATION

IN INCH(ES)

JAN JANITOR'S CLOSET

HM HOLLOW METAL

HORIZ HORIZONTAL

HR HANDRAIL

HT HEIGHT

HW HEADWALL

LAM LAMINATED

LF LINEAL FEET

MAS MASONRY

MAT'L MATERIAL

MAX MAXIMUM

MECH MECHANICAL

MANUF MANUFACTURED, MANUFACTURER

MIN MINIMUM

MLD'G MOLDING

MTL METAL

N NORTH

NAT NATURAL

NIC NOT IN CONTRACT

NORM NORMAL

NTS NOT TO SCALE

O.C. ON CENTER

OPN'G OPENING

O, O2 OXYGEN

PLAST PLASTIC

PNT PAINT

PREFAB PREFABRICATED

PLYWD PLYWOOD, PLYW'D

R RADIUS

RA RETURN AIR

REQ'D REQUIRED

RM ROOM

S SINK, SOUTH, SHINGLE

SA SUPPLY AIR

SAN SANITARY

SMKD SMOKE DAMPER

SECT SECTION

SHWR SHOWER

SIM SIMILAR

SPEC SPECIFICATION

SQ SQUARE

SS SERVICE SINK, STAINLESS STEEL

STD STANDARD

STOR STORAGE

SUSP SUSPEND(ED)

SYM SYMBOL, SYMMETRICAL

TOIL TOILET

TYP TYPICAL

UNFIN UNFINISHED

UTIL UTILITY

VAC VACUUM

VAV VARIABLE AIR VOLUME

VCT VINYL COMPOSITION TILE

VD VOLUME DAMPER

VERT VERTICAL

V.I.F. VERIFY IN FIELD

VT VINYL TILE

VWC VINYL WALL COVERING

W/ WITH

WC WATER CLOSET

WD WOOD

WNDW WINDOW

W. HTR WATER HEATER

W/O WITHOUT

WP WALL PROTECTION

A420

A320

M

A X

M

IN

18" MAX.

16" MIN.

IF

B A

R R

IE

R

F R

E E

M

A X

M

IN

M

IN

DRINKING FOUNTAIN REQUIREMENTS

SCALE: NONE

HIGH LOW WATER COOLER

W/ BOTTLE FILLER

FRONT

SIDE

/4

0' - 6 1/32" MIN11" MIN

0' - 9 7/32"

1' - 7"

/2

/3

/3

VERT. GRAB BAR

GENERAL NOTES:

ACCESSIBLE CONTROLS, OPERATING

MECHANISMS & HARDWARE SHALL COMPLY

WITH SECTION 1109.13 OF THE IBC AND

SECTION 309OF ICC/ANSI A117.1.

ACCESSIBLE SIGNAGE TO BE FURNISHED BY

OWNER, SHALL COMPLY WITH SECTIONS

1110 OF THE IBC AND SECTION 703 OF

ICC/ANSI A117.1.

PORTABLE FIRE EXTINGUISHERS TO BE

PROVIDED IN ACCORDANCE WITH THE 2000

ICC INTERNATIONAL FIRE CODE IBC (906.1).

REFER TO FLOOR PLAN SHEETS FOR

LOCATIONS OF FIRE EXTINGUISHER CABINETS

(FEC).

MOUNTING HEIGHT GENERAL NOTES:

1. REFER TO AI100A - AI100C FOR EQUIPMENT

ABBREVIATIONS AND LOCATIONS.

2. REFER TO INTERIOR ELEVATIONS FOR

ADDITIONAL INFORMATION.

3. ITEMS INCLUDED ON THIS SHEET ARE NOT

NECESSARILY INCLUDED IN THIS PROJECT.

4. CONTRACTOR TO VERIFY ALL EQUIPMENT

MOUNTED HEIGHTS WITH ARCHITECT AND

OWNER'S CONTRACTING OFFICER PRIOR TO

INSTALLATION.

5. REFER TO MECHANICAL/ELECTRICAL

DRAWINGS FOR DEVICE MOUNTING HEIGHTS.

FINISH FLOOR FINISH FLOOR

Building No.

Drawing Number

Project Number

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

Department of

Veteran Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Project Title

ARCHITECT/ENGINEERS:

A/E:

STAMP:CONSULTANTS:

321 4 5 6 7 8 9 10

DAV ENERGY SOLUTIONS

2207 GARNET AVE, SUITE I

SAN DIEGO, CA 92109

619-770-8552

WWW.DAVENERGY.COM

Floor No.

th re e i n c h e s o n e fo o t o n e i n c h o n e fo o t o n e a n d o n e h a lf i n c h e s o n e fo o t th re e q u a rt e rs i n c h o n e fo o t o n e h a lf i n c h o n e fo o t th re e e ig h th s i n c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th i n c h o n e fo o t Dwg. of

G-003

ARCHITECTURAL SYMBOLS & ABBREVIATIONS

SEVEN GENERATIONS ARCHITECTURE AND ENGINEERING

600 E. MICHIGAN AVE. STE B

KALAMAZOO, MI 49007

296.927.0144

JACK C. MONTGOMERY VA MEDICAL CENTER

05/24/2024 JRB SCC

EHRM INFRASTRUCTURE UPGRADES -

JACK C. MONTGOMERY VA MC

623-21-700

GENERAL NOTES

1. THIS PROJECT SHALL BE CONSTRUCTED IN CONFORMANCE WITH ALL FEDERAL,

STATE AND LOCAL REGULATIONS AND BUILDING CODES. CONSTRUCTION TO

BE PERFORMED IN ACCORDANCE WITH APPLIACABLE VA DESIGN GUIDES

AND INTERNATIONAL BUILDING CODES.

2. CONTRACTOR SHALL BE RESPONSIBLE TO OBTAIN ALL ASSOCIATED PERMITS

FOR CONSTRUCTION AND SHALL DO ALL NECESSARY ITEMS FOR

PROCUREMENT OF A CERTIFICATE OF OCCUPANCY. ANY COSTS DERIVED

FROM OBTAINING SAID PERMITS SHALL BE BORNE BY CONTRACTOR.

3. CONTRACTOR SHALL SUPPLY AND ASSIST OWNER IN APPLYING FOR ANY

UTILITIES REQUIRED FOR THE COMPLETION OF THE WORK UNLESS SPECIFIED

OTHERWISE IN WRITING. ALL COSTS ASSOCIATED WITH TEMPORARY POWER,

PHONE OR GAS SHALL BE PART OF THIS CONTRACT.

4. DRAWINGS AND SPECIFICATIONS ARE SUPPLEMENTARY. ANYTHING SHOWN

IN ONE SHALL BE CONSIDERED IN BOTH. ANY SHEET OF THE CONTRACT

DOCUMENTS IS VOID UNLESS USED IN CONJUNCTION WITH THE REST OF THE

CONTRACT DOCUMENTS.

5. IT IS THE RESPONSIBILITY OF CONTRACTOR TO COORDINATE THE WORK OF ALL

TRADES. ANY CONFLICTING WORK TO BE REPORTED TO THE OWNER'S

CONTRACTING OFFICER PRIOR TO THE INSTALLATION OF ANY WORK.

6. CONTRACTOR SHALL NOTIFY ARCHITECT IMMEDIATELY IF ANY UNFORESEEN

STRUCTURAL OR UTILITY RELATED ISSUES ARISE DURING DEMOLITION OR

EXCAVATION.

7. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO OBTAIN CLARIFICATION OF

ANY DISCREPANCIES FOUND ON DRAWINGS OR SPECIFICATIONS PRIOR TO

BID DATE.

8. PRIOR TO ANY EXCAVATION WORK, ALL UTILITY COMPANIES ARE TO BE

NOTIFIED TO LOCATE UTILITIES ON SITE THAT MAY CONFLICT WITH

EXCAVATION WORK.

9. CONTRACTOR(S) TO VERIFY ALL DIMENSIONS IN FIELD. ANY DISCREPANCIES

SHALL BE REPORTED TO THE OWNER'S CONTRACTING OFFICER PRIOR TO THE

INSTALLATION OF ANY WORK.

10. DO NOT SCALE DRAWINGS. USE INDICATED DIMENSIONS ONLY.

11. CONTRACTOR(S) TO VISIT THE SITE AND FAMILIARIZE THEMSELVES WITH THE

EXISTING CONDITIONS TO UNDERSTAND THE NATURE AND SCOPE OF THE

WORK. THE BASE BID SHALL REFLECT MODIFICATIONS TO SYSTEMS AND

DEVICES REQUIRED BY STATE AND LOCAL CODES WHETHER INDICATED OR

NOT ON THE CONTRACT DOCUMENTS. THE SUBMISSION OF A BID WILL BE

EVIDENCE THAT SUCH AN EXAMINATION AND COMPLIANCE WITH

GOVERNING CODES/ REQUIREMENTS HAVE BEEN MADE. LATER CLAIMS FOR

LABOR, EQUIPMENT OR MATERIALS REQUIRED, OR FOR DIFFICULTIES

ENCOUNTERED WHICH COULD HAVE BEEN FORSEEN HAND AN EXAMINATION

AND CODE REQUIREMENT REVIEW WILL NOT BE ALLOWED. ALL OF THE ABOVE

SHALL BE PROVIDED AT THE CONTRACTOR’S EXPENSE.

12. ARCHITECT WILL NOT BE RESPONSIBLE FOR ANY DEVIATIONS FROM THESE

DOCUMENTS OR DEVIATIONS FOR SPECIFIED PRODUCTS, UNLESS APPROVED

BY OWNER'S CONTRACTING OFFICER.

ADA NOTE:

THIS PROJECT IS TO MEET THE ADA STANDARDS IN EFFECT AT THE TIME OF THE

PROJECT. IF A MATERIAL OR SYSTEM HAS BEEN SPECIFIED OR DRAWN THAT DOES

NOT MEET THE STANDARDS, THE ARCHITECT REQUESTS THAT THE CONTRACTOR,

SUPPLIER OR MATERIAL MANUFACTURER ADVISE AND ASSIST THE ARCHITECT TO

PROVIDE THE PRODUCT OR SYSTEM. ALL PRODUCTS OR SYSTEMS WILL NEED

ACCEPTANCE OF THE OWNER AND THE ARCHITECT.

GENERAL NOTES – SITE

1. CONTRACTOR TO REQUEST LOCATION OF ALL UTILITIES BY CONTACTING MISS

DIG.

2. ALL EXCESS/ UNSUITABLE MATERIAL SHALL BECOME THE PROPERTY OF THE

CONTRACTOR AND WHO SHALL BE RESPONSIBLE FOR THE PROPER DISPOSAL OF

MATERIAL.

3. ALL STRUCTURES LOCATED ON PROPERTY, SHOWN DASHED, TO BE REMOVED IN

ITS ENTIRETY.

4. ALL TREES SHOWN ARE TO REMAIN. ANY TREES NOT SHOWN ARE TO BE

REMOVED IN ITS ENTIRETY. CONTRACTOR TO VERIFY ALL EXISTING TREE

REMOVAL WITH OWNER AND ARCHITECT PRIOR TO EXTRACATION.

5. TREES SHALL BE PROTECTED BY THE CONTRACTOR. DAMAGED TREES SHALL BE

RESTORED TO THE ORIGINAL CONDITION AT THE CONTRACTORS EXPENSE. ALL

TREES DAMAGED BEYOND SAVING AS DETERMINED BY THE ARCHITECT SHALL BE

REMOVED AND REPLACED WITH A NURSERY GROWN TREE AS SPECIFIED BY THE

ARCHITECT.

6. CONTRACTOR SHALL VISIT THE SITE AND EXAMINE THE PREMISES AND EXISTING

CONDITIONS TO COORDINATE NEW INSTALLATIONS.

7. CAP OFF EXISTING UNDERGROUND UTILTIES BEYOND EXTENT OF NEW BUILDING

LOCATION FOR POSSIBLE RECONNECTION.

Revisions: 35% Schematic Design Date: 02/24/2023Revisions: 35% Schematic Design Date: 02/24/2023

Revisions: 65% Design Development Date: 09/21/2023

Revisions: 95% Construction Documents Date: 02/12/2024

Revisions: 10% Diamond Drawings Date: 09/30/2022

INFECTION CONTROL GENERAL NOTES

1. REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS

OUTLINED BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL

INFORMATION.

2. REFER TO DRAWINGS AND SPECIFICATIONS FOR ADDITIONAL

INFORMATION.

3. PROJECT SHALL BE COMPLETED IN 3 PHASES.

4. COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS

AND FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE

OF ABOVE CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR

PLATE OF THE PROJECT BOUNDARY.

5. COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC)

BARRIER WALL CONSTRUCTION AND INFECTION CONTROL (IC)

MEASURES WITH COR AND PATIENT SAFETY/ INFECTION CONTROL

REPRESENTATIVE. TEMPORARY IC BARRIER WALL CONSTRUCTION

LOCATIONS IN DRAWINGS ARE APPROXIMATE. CONTRACTOR SHALL

PROVIDE DRAWING TO COR AND PATIENT SAFETY/ INFECTION

CONTROL REPRESENTATIVE ONCE ICRA PROTOCOLS AND PLAN IS

APPROVED.

6. SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY

COR AND NURSING STAFF BEFORE CONSTRUCTION MAY BEGIN.

PROVIDE PHASING INFORMATION FOR ABOVE CEILING WORK IN THE

CONTRACTOR PROVIDED CMP SCHEDULE FOR WORK ALSO REQUIRED

ABOVE AND BELOW THE FLOOR PLATE OF THE PROJECT BOUNDARY.

7. ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF

5:00 PM AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK

WHERE CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED

AND STORED IN A SAFE MANNER UNTIL CEILING TILES CAN BE

REINSTALLED. DAMAGED AND BROKEN CEILING TILES SHALL BE

REPLACED BY CONTRACTOR.

8. EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE

MAINTAINED DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION

FOR HOURS OF OPERATION.

9. WORK REQUIRING VIBRATION OR LOUD NOISE SHALL TAKE PLACE

BETWEEN THE HOURS OF 8:00 AM AND 5:00 PM. EVERY EFFORT SHALL

BE MADE TO KEEP NOISE AND VIBRATION TO A MINIMUM.

10. PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36"

STICKY WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY

DOOR LOCATION. MAT SHALL BE REPLACED OR CLEANED AS

NECESSARY

11. PROVIDE THE VA OSHA REQUIRED TEMPORARY SIGNAGE AT EACH

TEMPORARY DOOR LOCATION.

12. CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP

VAC, MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON

AGGRESSIVE LIQUIDS UP TO 30 GALLONS.

13. ALL NEW MATERIAL MOVED THROUGH THE FACILITY SHALL BE

COVERED WITH 4 MIL. POLY SHEET.

14. ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT

BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA

APPROVED ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH

PURPOSED WITH A LID.

15. ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE

PROPERLY STORED IN DESIGNATED AREAS AND IN APPROVED

CONTAINERS. FLAMMABLE MATERIALS SHALL NOT BE STORED IN THE

FACILITY.

16. PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE

PROJECT BOUNDARY.

CLASS OF PRECAUTIONS

PATIENT RISK GROUP

LOW: NON-PATIENT CARE AREAS

• PUBLIC HALLWAYS AND GATHERING AREAS NOT ON CLINICAL UNITS.

• OFFICE AREAS NOT ON CLINICAL UNITS.

• BREAKROOMS NOT ON CLINICAL UNITS.

• BATHROOMS OR LOCKER ROOMS NOT ON CLINICAL UNITS.

• MECHANICAL ROOMS NOT ON CLINICAL UNITS.

• EVS CLOSETS NOT ON CLINICAL UNITS.

MEDIUM: PATIENT CARE SUPPORT AREAS

• WAITING AREAS.

• CLINICAL ENGINEERING.

• MATERIALS MANAGEMENT.

• STERILE PROCESSING DEPARTMENT - DIRTY SIDE.

• KITCHEN, CAFETERIA, GIFT SHOP, COFFEE SHOP, AND FOOD KIOSKS.

HIGH: PATIENT CARE AREAS

• PATIENT CARE ROOMS AND AREAS

• ALL ACUTE CARE UNITS

• EMERGENCY DEPARTMENT

• EMPLOYEE HEALTH

• PHARMACY - GENERAL WORK ZONE

• MEDICATION ROOMS AND CLEAN UTILITY ROOMS

• IMAGING SUITES: DIAGNOSTIC IMAGING LABORATORY.

HIGHEST: INVASIVE, STERILE OR HIGHLY COMPROMISED CARE

• ALL TRANSPLANT AND INTENSIVE CARE UNITS.

• ALL ONCOLOGY UNITS.

• OR THEATERS AND RESTRICTED AREAS.

• PROCEDURAL SUITES.

• PHARMACY COMPOUNDING.

• STERILE PROCESSING DEPARTMENT - CLEAN SIDE.

• TRANSFUSION SERVICES.

• DEDICATED ISOLATION WARDS/UNITS.

• IMAGING SUITES: INVASIVE IMAGING.

TYPE OF ACTIVITY

TYPE A: NON-INVASIVE

INCLUDES BUT IS NOT LIMITED TO:

• REMOVAL OF CEILING TILE FOR VISUAL INSPECTION-LIMITED TO 1 TILE

PER 50 SQUARE FEET WITH LIMITED EXPOSURE TIME.

• LIMITED BUILDING SYSTEM MAINTENANCE (E.G., PNEUMATIC TUBE

STATION, HVAC SYSTEM, FIRE SUPPRESSION SYSTEM, ELECTRICAL AND

CARPENTRY WORK TO INCLUDE PAINTING WITHOUT SANDING) THAT

DOES NOT CREATE DUST OR DEBRIS.

• CLEAN PLUMBING ACTIVITY LIMITED IN NATURE.

TYPE B: SMALL-SCALE, SHORT DURATION

INCLUDES BUT IS NOT LIMITED TO:

• WORK CONDUCTED ABOVE THE CEILING (E.G., PROLONGED

INSPECTION OR REPAIR OF FIREWALLS AND BARRIERS, INSTALLATION OF

CONDUIT AND/OR CABLING, AND ACCESS TO MECHANICAL AND/OR

ELECTRICAL CHASE SPACES).

• FAN SHUTDOWN/STARTUP.

• INSTALLATION OF ELECTRICAL DEVICES OR NEW FLOORING THAT

PRODUCES MINIMAL DUST AND DEBRIS.

• THE REMOVAL OF DRYWALL WHERE MINIMAL DUST AND DEBRIS IS

CREATED.

• CONTROLLED SANDING ACTIVITIES (E.G., WET OR DRY SANDING) THAT

PRODUCE MINIMAL DUST AND DEBRIS.

TYPE C: LARGE-SCALE, LONGER DURATION

INCLUDES BUT IS NOT LIMITED TO:

• REMOVAL OF PREEXISTING FLOOR COVERING, WALLS, CASEWORK OR

OTHER BUILDING COMPONENTS.

• NEW DRYWALL PLACEMENT.

• RENOVATION WORK IN A SINGLE ROOM.

• NONEXISTENT CABLE PATHWAY OR INVASIVE ELECTRICAL WORK

ABOVE CEILINGS.

• THE REMOVAL OF DRYWALL WHERE A MODERATE AMOUNT OF DUST

AND DEBRIS IS CREATED.

• DRY SANDING WHERE A MODERATE AMOUNT OF DUST AND DEBRIS IS

CREATED.

• WORK CREATING SIGNIFICANT VIBRATION AND/OR NOISE.

• ANY ACTIVITY THAT CANNOT BE COMPLETED IN A SINGLE WORK SHIFT.

TYPE D: MAJOR DEMOLITION, CONSTRUCTION

INCLUDES BUT IS NOT LIMITED TO:

• REMOVAL OR REPLACEMENT OF BUILDING SYSTEM COMPONENT(S).

• REMOVAL/INSTALLATION OF DRYWALL PARTITIONS.

• INVASIVE LARGE-SCALE NEW BUILDING CONSTRUCTION.

• RENOVATION WORK IN TWO OR MORE ROOMS.

TYPE A TYPE B TYPE C TYPE D

LOW

MEDIUM

HIGH

HIGHEST

I II II III

I II III IV

I III IV V

III IV V V

PHASE 1

BUILD OUT TR AND ADJACENT ROOMS IMPACTED AS

SHOWN IN DRAWINGS. REFER TO ARCHITECTURAL,

ELECTRICAL, MECHANICAL, AND LOW VOLTAGE

DRAWINGS FOR TR ROOM DESIGN REQUIREMENTS.

(ICRA CLASS IV PRECAUTIONS, SEE G-100)

PHASE 2

PULL NEW CABLE FROM TR RACKS DOWN MAIN

CORRIDORS. REFER TO LOW VOLTAGE DRAWINGS

FOR CABLE PATHWAYS. NOTE: ALL WORK IN THIS

PHASE TO BE NIGHT AND WEEKEND WORK. (ICRA

CLASS II PRECAUTIONS, SEE G-100)

PHASE 3

PROVIDE CABLE DROPS IN ALL ROOMS SHOWN. REFER

TO LOW VOLTAGE DRAWINGS FOR EXACT DROP

LOCATIONS. NOTE: ALL WORK IN THIS PHASE TO BE

NIGHT AND WEEKEND WORK. (ICRA CLASS II

PRECAUTIONS, SEE G-100)

PHASING LEGEND

1. PROJECT AREAS ARE TO BE OCCUPIED BY STAFF AND

VETERANS THROUGHOUT CONSTRUCTION.

2. PHASES NOTED AS AFTER HOURS: CORRIDOR WORK TO

BE COMPLETED DURING NIGHT SHIFTS, 5:00 PM TO 5:00

AM. COORDINATE WITH COR. ALL WORK TO BE

COMPLETED AND OPEN FOR PUBLIC USE AT THE END

OF EACH NIGHT'S WORK.

3. CONSTRUCTION WORK BEHIND TEMPORARY

CONSTRUCTION PARTITIONS SHALL BE COMPLETED

DURING DAY SHIFTS.

4. REFER TO SPECIFICATION 01 00 00 FOR INFORMATION

ON WORK DURATION FOR EACH PHASE AND AREA OF

WORK.

5. COORDINATE WITH MEP PHASING PLANS FOR

SIMULTANEOUS WORK TO BE COMPLETED.

INFECTION CONTROL RISK ASSESSMENT NOTES - CLASS V

1. CONSTRUCT AND COMPLETE CRITICAL BARRIERS MEETING NFPA 241

REQUIREMENTS. BARRIERS MUST EXTEND TO THE CEILING OR IF CEILING

TILE IS REMOVED, TO THE DECK ABOVE.

2. ALL (PLASTIC OR HARD) BARRIER CONSTRUCTION ACTIVITIES MUST BE

COMPLETED IN A MANNER THAT PREVENTS DUST RELEASE. PLASTIC

BARRIERS MUST BE EFFECTIVELY AFFIXED TO GROUND AND CEILING

AND SECURE FROM MOVEMENT OR DAMAGE. APPLY TAPE THAT WILL

NOT LEAVE A RESIDUE TO SEAL GAPS BETWEEN BARRIERS, CEILING OR

FLOOR.

3. SEAL ALL PENETRATIONS IN CONTAINMENT BARRIERS, ANTEROOM

BARRIERS, INCLUDING FLOORS AND CEILING USING APPROVED

MATERIALS (UL SCHEDULE FIRESTOP IF APPLICABLE FOR BARRIER TYPE).

4. CONSTRUCT ANTEROOM LARGE ENOUGH FOR EQUIPMENT STAGING,

CART CLEANING, WORKERS. THE ANTEROOM MUST BE CONSTRUCTED

ADJACENT TO ENTRANCE OF CONSTRUCTION WORK AREA.

5. PERSONNEL WILL BE REQUIRED TO WEAR COVERALLS AT ALL TIMES

DURING CLASS V WORK ACTIVITIES. COVERALLS MUST BE REMOVED

BEFORE LEAVING THE ANTEROOM.

6. REMOVE OR ISOLATE RETURN AIR DIFFUSERS TO AVOID DUST ENTERING

THE HVAC SYSTEM.

7. REMOVE OR ISOLATE THE SUPPLY AIR DIFFUSERS TO AVOID POSITIVE

PRESSURIZATION OF THE SPACE.

8. NEGATIVE AIRFLOW PATTERN MUST BE MAINTAINED FROM THE ENTRY

POINT TO THE ANTEROOM AND INTO THE CONSTRUCTION AREA. THE

AIRFLOW MUST CASCADE FROM OUTSIDE TO INSIDE THE

CONSTRUCTION AREA. THE ENTIRE CONSTRUCTION AREA MUST REMAIN

NEGATIVELY PRESSURIZED.

9. MAINTAIN NEGATIVE PRESSURIZATION OF THE ENTIRE WORKSPACE

USING HEPA EXHAUST AIR SYSTEMS DIRECTED OUTDOORS. EXHAUST

DISCHARGED DIRECTLY TO THE OUTDOORS THAT IS 25 FEET OR GREATER

FROM ENTRANCES, AIR INTAKES AND WINDOWS DOES NOT REQUIRE

HEPA-FILTERED AIR.

10. IF EXHAUST IS DIRECTED INDOORS, THEN THE SYSTEM MUST BE HEPA

FILTERED. PRIOR TO START OF WORK, HEPA FILTRATION MUST BE

VERIFIED BY PARTICULATE MEASUREMENT AS NO LESS THAN 99.97%

EFFICIENCY AND MUST NOT ALTER OR CHANGE AIRFLOW/PRESSURE

RELATIONSHIPS IN OTHER AREAS.

11. EXHAUST INTO SHARED OR RECIRCULATING HVAC SYSTEMS, OR OTHER

SHARED EXHAUST SYSTEMS (BATHROOM EXHAUST) IS NOT ACCEPTABLE.

12. INSTALL DEVICE (DIGITAL MONITORING) ON EXTERIOR OF WORK

CONTAINMENT TO CONTINUALLY MONITOR NEGATIVE

PRESSURIZATION. THE “BALL IN THE WALL” OR SIMILAR APPARATUS ARE

NOT ACCEPTABLE.

13. CONTAIN ALL TRASH AND DEBRIS IN THE WORK AREA.

14. NONPOROUS/SMOOTH AND CLEANABLE CONTAINERS (WITH A HARD

LID) MUST BE USED TO TRANSPORT TRASH AND DEBRIS FROM THE

CONSTRUCTION AREAS. THESE CONTAINERS MUST BE DAMP-WIPED

CLEANED AND FREE OF VISIBLE DUST/DEBRIS BEFORE LEAVING THE

CONTAINED WORK AREA.

15. WORKER CLOTHING MUST BE CLEAN AND FREE OF VISIBLE DUST

BEFORE LEAVING THE WORK AREA ANTEROOM.

16. WORKERS MUST WEAR SHOE COVERS PRIOR TO ENTRY INTO THE WORK

AREA. SHOE COVERS MUST BE CHANGED PRIOR TO EXITING THE

ANTEROOM TO THE OCCUPIED SPACE (NON-WORK AREA). DAMAGED

SHOE COVERS MUST BE IMMEDIATELY CHANGED.

17. INSTALL A STICKY (DUST COLLECTION) MAT AT ENTRANCE OF

CONTAINED WORK AREA BASED ON FACILITY POLICY. STICKY MATS

MUST BE CHANGED ROUTINELY AND WHEN VISIBLY SOILED.

18. IN THE EVENT THAT THERE IS A DEVIATION IN PLACE TO DISCHARGE THE

EXHAUST AIR INTO OCCUPIED SPACE (AND NOT OUTSIDE), THEN

CONSIDER PARTICULATE SAMPLING TO HELP IDENTIFY CONTAMINANTS

THAT MAY ENTER PATIENT CARE AREAS.

DURING CONSTRUCTION PROJECT UPON COMPLETION OF PROJECT

CONSTRUCTION AREAS MUST BE INSPECTED BY AN INFECTION

PREVENTIONIST OR DESIGNEE AND ENGINEERING REPRESENTATIVE FOR

DISCONTINUATION OR DOWNGRADING OF ICRA PRECAUTIONS.

WORK AREA CLEANING:

1. CLEAN WORK AREAS INCLUDING ALL ENVIRONMENTAL SURFACES,

HIGH HORIZONTAL SURFACES AND FLOORING MATERIALS.

2. CHECK ALL SUPPLY AND RETURN AIR REGISTERS FOR DUST

ACCUMULATION ON UPPER SURFACES AS WELL AS AIR DIFFUSER

SURFACES.

REMOVAL OF CRITICAL BARRIERS:

1. CRITICAL BARRIERS MUST REMAIN IN PLACE DURING ALL WORK

INVOLVING DRYWALL REMOVAL, CREATION OF DUST AND

ACTIVITIES BEYOND SIMPLE TOUCH-UP WORK. THE BARRIER MAY

NOT BE REMOVED UNTIL A WORK AREA CLEANING HAS BEEN

PERFORMED.

2. ALL (PLASTIC OR HARD) BARRIER REMOVAL ACTIVITIES MUST BE

COMPLETED IN A MANNER THAT PREVENTS DUST RELEASE. USE THE

FOLLOWING PRECAUTIONS WHEN REMOVING HARD BARRIERS:

3. CAREFULLY REMOVE SCREWS AND PAINTER TAPE.

4. IF DUST WILL BE GENERATED DURING SCREW REMOVAL, USE HAND-

HELD HEPA VACUUM.

5. DRYWALL CUTTING IS PROHIBITED DURING REMOVAL PROCESS.

6. CLEAN ALL STUD TRACKS WITH HEPA VACUUM BEFORE REMOVING

OUTER HARD BARRIER.

7. USE A PLASTIC BARRIER TO ENCLOSE AREA IF DUST COULD BE

GENERATED.

NEGATIVE AIR REQUIREMENTS:

1. THE USE OF NEGATIVE AIR MUST BE DESIGNED TO REMOVE

CONTAMINATES FROM THE WORK AREA.

2. NEGATIVE AIR DEVICES MUST REMAIN OPERATIONAL AT ALL TIMES

AND IN PLACE FOR A PERIOD AFTER COMPLETION OF DUST

CREATING ACTIVITIES TO REMOVE CONTAMINANTS FROM THE

WORK AREA AND BEFORE REMOVAL OF CRITICAL BARRIERS.

3. MAINTAIN MINIMUM NEGATIVE AIR PRESSURE, 0.01 INCHES OF

WATER GAUGE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR

FILTRATION UNITS AND CONTINUOUSLY MONITORED WITH A DIGITAL

DISPLAY, RECORDING AND ALARM INSTRUMENT, WHICH MUST BE

CALIBRATED ON INSTALLATION, MAINTAINED WITH PERIODIC

CALIBRATION, AND MONITORED.

HVAC SYSTEMS:

1. UPON REMOVAL OF CRITICAL BARRIERS, REMOVE ISOLATION OF

HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

2. VERIFY THAT HVAC SYSTEMS ARE CLEAN AND OPERATIONAL.

3. VERIFY THE HVAC SYSTEMS MEETS ORIGINAL AIRFLOW AND AIR

EXCHANGE DESIGN SPECIFICATIONS.

INFECTION CONTROL RISK ASSESSMENT NOTES - CLASS IV

1. CONSTRUCT AND COMPLETE CRITICAL BARRIERS MEETING NFPA 241

REQUIREMENTS. BARRIERS MUST EXTEND TO THE CEILING OR IF CEILING

TILE IS REMOVED, TO THE DECK ABOVE.

2. ALL (PLASTIC OR HARD) BARRIER CONSTRUCTION ACTIVITIES MUST BE

COMPLETED IN A MANNER THAT PREVENTS DUST RELEASE. PLASTIC

BARRIERS MUST BE EFFECTIVELY AFFIXED TO GROUND AND CEILING

AND SECURE FROM MOVEMENT OR DAMAGE. APPLY TAPE THAT WILL

NOT LEAVE A RESIDUE TO SEAL GAPS BETWEEN BARRIERS, CEILING OR

FLOOR.

3. SEAL ALL PENETRATIONS IN CONTAINMENT BARRIERS, INCLUDING

FLOORS AND CEILING, USING APPROVED MATERIALS (UL SCHEDULE

FIRESTOP IF APPLICABLE FOR BARRIER TYPE).

4. CONTAINMENT UNITS OR ENVIRONMENTAL CONTAINMENT UNITS

(ECUS) APPROVED FOR CLASS IV PRECAUTIONS IN SMALL AREAS

TOTALLY CONTAINED BY THE UNIT AND THAT HAS HEPA-FILTERED

EXHAUST AIR.

5. REMOVE OR ISOLATE RETURN AIR DIFFUSERS TO AVOID DUST ENTERING

THE HVAC SYSTEM.

6. REMOVE OR ISOLATE THE SUPPLY AIR DIFFUSERS TO AVOID POSITIVE

PRESSURIZATION OF THE SPACE.

7. NEGATIVE AIRFLOW PATTERN MUST BE MAINTAINED FROM THE ENTRY

POINT TO THE ANTEROOM AND INTO THE CONSTRUCTION AREA. THE

AIRFLOW MUST CASCADE FROM OUTSIDE TO INSIDE THE

CONSTRUCTION AREA. THE ENTIRE CONSTRUCTION AREA MUST REMAIN

NEGATIVELY PRESSURIZED.

8. MAINTAIN NEGATIVE PRESSURIZATION OF THE ENTIRE WORKSPACE BY

USE OF HEPA EXHAUST AIR SYSTEMS DIRECTED OUTDOORS. EXHAUST

DISCHARGED DIRECTLY TO THE OUTDOORS THAT IS 25 FEET OR GREATER

FROM ENTRANCES, AIR INTAKES AND WINDOWS DOES NOT REQUIRE

HEPA-FILTERED AIR.

9. IF EXHAUST IS DIRECTED INDOORS, THEN THE SYSTEM MUST BE HEPA

FILTERED. PRIOR TO START OF WORK, HEPA FILTRATION MUST BE

VERIFIED BY PARTICULATE MEASUREMENT AS NO LESS THAN 99.97%

EFFICIENCY AND MUST NOT ALTER OR CHANGE AIRFLOW/PRESSURE

RELATIONSHIPS IN OTHER AREAS.

10. EXHAUST INTO SHARED OR RECIRCULATING HVAC SYSTEMS, OR OTHER

SHARED EXHAUST SYSTEMS (E.G., BATHROOM EXHAUST) IS NOT

ACCEPTABLE.

11. INSTALL DEVICE (DIGITAL MONITORING) ON EXTERIOR OF WORK

CONTAINMENT TO CONTINUALLY MONITOR NEGATIVE

PRESSURIZATION. THE “BALL IN THE WALL” OR SIMILAR APPARATUS ARE

NOT ACCEPTABLE.

12. CONTAIN ALL TRASH AND DEBRIS IN THE WORK AREA.

13. NONPOROUS/SMOOTH AND CLEANABLE CONTAINERS (WITH A HARD

LID) MUST BE USED TO TRANSPORT TRASH AND DEBRIS FROM THE

CONSTRUCTION AREAS. THESE CONTAINERS MUST BE DAMP-WIPED

CLEANED AND FREE OF VISIBLE DUST/DEBRIS BEFORE LEAVING THE

CONTAINED WORK AREA.

14. WORKER CLOTHING MUST BE CLEAN AND FREE OF VISIBLE DUST

BEFORE LEAVING THE WORK AREA. HEPA VACUUMING OF CLOTHING

OR USE OF COVER SUITES IS ACCEPTABLE.

15. WORKERS MUST WEAR SHOE COVERS PRIOR TO ENTRY INTO THE WORK

AREA. SHOE COVERS MUST BE CHANGED PRIOR TO EXITING THE

ANTEROOM TO THE OCCUPIED SPACE (NON-WORK AREA). DAMAGED

SHOE COVERS MUST BE IMMEDIATELY CHANGED.

16. INSTALL A STICKY (DUST COLLECTION) MAT AT ENTRANCE OF

CONTAINED WORK AREA BASED ON FACILITY POLICY. STICKY MATS

MUST BE CHANGED ROUTINELY AND WHEN VISIBLY SOILED.

17. IN THE EVENT THAT THERE IS A DEVIATION IN PLACE TO DISCHARGE THE

EXHAUST AIR INTO OCCUPIED SPACE (AND NOT OUTSIDE), THEN

CONSIDER PARTICULATE SAMPLING TO HELP IDENTIFY CONTAMINANTS

THAT MAY ENTER PATIENT CARE AREAS.

DURING CONSTRUCTION PROJECT UPON COMPLETION OF PROJECT

CONSTRUCTION AREAS MUST BE INSPECTED BY AN INFECTION

PREVENTIONIST OR DESIGNEE AND ENGINEERING REPRESENTATIVE FOR

DISCONTINUATION OR DOWNGRADING OF ICRA PRECAUTIONS.

WORK AREA CLEANING:

1. CLEAN WORK AREAS INCLUDING ALL ENVIRONMENTAL SURFACES,

HIGH HORIZONTAL SURFACES AND FLOORING MATERIALS.

2. CHECK ALL SUPPLY AND RETURN AIR REGISTERS FOR DUST

ACCUMULATION ON UPPER SURFACES AS WELL AS AIR DIFFUSER

SURFACES.

REMOVAL OF CRITICAL BARRIERS:

1. CRITICAL BARRIERS MUST REMAIN IN PLACE DURING ALL WORK

INVOLVING DRYWALL REMOVAL, CREATION OF DUST AND

ACTIVITIES BEYOND SIMPLE TOUCH-UP WORK. THE BARRIER MAY

NOT BE REMOVED UNTIL A WORK AREA CLEANING HAS BEEN

PERFORMED.

2. ALL (PLASTIC OR HARD) BARRIER REMOVAL ACTIVITIES MUST BE

COMPLETED IN A MANNER THAT PREVENTS DUST RELEASE. USE THE

FOLLOWING PRECAUTIONS WHEN REMOVING HARD BARRIERS:

3. CAREFULLY REMOVE SCREWS AND PAINTER TAPE.

4. IF DUST WILL BE GENERATED DURING SCREW REMOVAL, USE HAND-

HELD HEPA VACUUM.

5. DRYWALL CUTTING IS PROHIBITED DURING REMOVAL PROCESS.

6. CLEAN ALL STUD TRACKS WITH HEPA VACUUM BEFORE REMOVING

OUTER HARD BARRIER.

7. USE A PLASTIC BARRIER TO ENCLOSE AREA IF DUST COULD BE

GENERATED.

NEGATIVE AIR REQUIREMENTS:

1. THE USE OF NEGATIVE AIR MUST BE DESIGNED TO REMOVE

CONTAMINATES FROM THE WORK AREA.

2. NEGATIVE AIR DEVICES MUST REMAIN OPERATIONAL AT ALL TIMES

AND IN PLACE FOR A PERIOD AFTER COMPLETION OF DUST

CREATING ACTIVITIES TO REMOVE CONTAMINANTS FROM THE

WORK AREA AND BEFORE REMOVAL OF CRITICAL BARRIERS.

3. MAINTAIN MINIMUM NEGATIVE AIR PRESSURE, 0.01 INCHES OF

WATER GAUGE WITHIN WORK SITE UTILIZING HEPA EQUIPPED AIR

FILTRATION UNITS AND CONTINUOUSLY MONITORED WITH A DIGITAL

DISPLAY, RECORDING AND ALARM INSTRUMENT, WHICH MUST BE

CALIBRATED ON INSTALLATION, MAINTAINED WITH PERIODIC

CALIBRATION, AND MONITORED.

HVAC SYSTEMS:

1. UPON REMOVAL OF CRITICAL BARRIERS, REMOVE ISOLATION OF

HVAC SYSTEM IN AREAS WHERE WORK IS BEING PERFORMED.

2. VERIFY THAT HVAC SYSTEMS ARE CLEAN AND OPERATIONAL.

3. VERIFY THE HVAC SYSTEMS MEETS ORIGINAL AIRFLOW AND AIR

EXCHANGE DESIGN SPECIFICATIONS.

Building No.

Drawing Number

Project Number

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

Department of

Veteran Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Project Title

ARCHITECT/ENGINEERS:

A/E:

STAMP:CONSULTANTS:

321 4 5 6 7 8 9 10

DAV ENERGY SOLUTIONS

2207 GARNET AVE, SUITE I

SAN DIEGO, CA 92109

619-770-8552

WWW.DAVENERGY.COM

Floor No.

th re e i n c h e s o n e fo o t o n e i n c h o n e fo o t o n e a n d o n e h a lf i n c h e s o n e fo o t th re e q u a rt e rs i n c h o n e fo o t o n e h a lf i n c h o n e fo o t th re e e ig h th s i n c h o n e fo o t o n e q u a rt e r in c h o n e fo o t o n e e ig h th i n c h o n e fo o t Dwg. of

G-100

ICRA AND PHASING GENERAL NOTES

SEVEN GENERATIONS ARCHITECTURE AND ENGINEERING

600 E. MICHIGAN AVE. STE B

KALAMAZOO, MI 49007

296.927.0144

JACK C. MONTGOMERY VA MEDICAL CENTER

05/24/2024 JRB SCC

EHRM INFRASTRUCTURE UPGRADES -

JACK C. MONTGOMERY VA MC

623-21-700

Revisions: 35% Schematic Design Date: 02/24/2023

Revisions: 65% Design Development Date: 09/21/2023

Revisions: 95% Construction Documents Date: 02/12/2024

Revisions: 10% Diamond Drawings Date: 09/30/2022

PHASING LEGEND

PHASE 1

BUILD OUT TR AND ADJACENT ROOMS IMPACTED AS

SHOWN IN DRAWINGS. REFER TO ARCHITECTURAL,

ELECTRICAL, MECHANICAL, AND LOW VOLTAGE

DRAWINGS FOR TR ROOM DESIGN REQUIREMENTS.

(ICRA CLASS IV PRECAUTIONS, SEE G-100)

PHASE 2

PULL NEW CABLE FROM TR RACKS DOWN MAIN

CORRIDORS. REFER TO LOW VOLTAGE DRAWINGS

FOR CABLE PATHWAYS. NOTE: ALL WORK IN THIS

PHASE TO BE NIGHT AND WEEKEND WORK. (ICRA

CLASS II PRECAUTIONS, SEE G-100)

PHASE 3

PROVIDE CABLE DROPS IN ALL ROOMS SHOWN. REFER

TO LOW VOLTAGE DRAWINGS FOR EXACT DROP

LOCATIONS. NOTE: ALL WORK IN THIS PHASE TO BE

NIGHT AND WEEKEND WORK. (ICRA CLASS II

PRECAUTIONS, SEE G-100)

1. PROJECT AREAS ARE TO BE OCCUPIED BY STAFF AND

VETERANS THROUGHOUT CONSTRUCTION.

2. PHASES NOTED AS AFTER HOURS: CORRIDOR WORK TO

BE COMPLETED DURING NIGHT SHIFTS, 5:00 PM TO 5:00

AM. COORDINATE WITH COR. ALL WORK TO BE

COMP…