Attachment 0038_Technical Review Criteria.docx

DOCX document 22 KB Posted

Attached to
Water Storage Distribution System (Solicitation) Federal contract opportunity
Solicitation number
W56HZV21R0011
Issued by
Department of the Army Materiel Command TACOM Life Cycle Management Command

About this file

This solicitation is for the procurement of Water Storage Distribution Systems to provide potable water storage and distribution capabilities to the U.S. Army. The Army Contracting Command - Detroit Arsenal intends to award five IDIQ contracts for the delivery of pump assemblies to be used for testing. The test results will inform the downselect to a single IDIQ holder responsible for producing up to 123 Water Storage Distribution Systems with capacities of 100,000 gallons or split 50,000 gallon units, as well as up to 150 spare fluid distribution pumps. The resulting IDIQ contracts will have a five year base period and two one-year options, with orders to be placed as firm fixed price. This is a 100% small business set-aside procurement. Products required include collapsible fabric water tanks, pumps, meters, hoses, fittings, nozzles, and hypochlorination units. Interested parties should contact the named buyer by phone to obtain further details on response dates and requirements. The Department of the Army Materiel Command Life Cycle Management Command is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Water Storage Distribution System (Solicitation), newest first.
File Type Posted
WSDS QA 91-95.pdf PDF
Attachment 0010 SESAME.xlsx XLSX spreadsheet
W56HZV21R0011-0002.pdf PDF
WSDS VENDOR QA (10 June) (questions 36-90) Final.pdf PDF
Attachment 0009 WSDS FDSC Certified 16 Apr 21.pdf PDF
Attach 0009 WSDS FDSC Certified 16 Apr 21.pdf PDF
Attachment_0042_Pricing_Workbookv2 (4 Jun 21).xlsx XLSX spreadsheet
Attachment_0040_Pricing_Workbookv2 (4 Jun 21).xlsx XLSX spreadsheet
Attachment_0042_Pricing_Workbookv2.xlsx XLSX spreadsheet
Notice to Offerors.pdf PDF
Attachment_0040_Pricing_Workbookv2.xlsx XLSX spreadsheet
Attachment_0042_Pricing_Workbookv2.xlsx XLSX spreadsheet
WSDS VENDOR QA (as of 25 May 2021).pdf PDF
Instructions.docx DOCX document
Copy of Attachment 0042 - Updated Pricing Workbook.xlsx XLSX spreadsheet
Attachment 0039 - Copyright Release Letter Template.docx DOCX document
Attachment 0037 PKG1_LPD Coded Data Products Packaging.docx DOCX document
Attachment 0026-IADS Dataset_TOC File Template.docx DOCX document
Attachment 0017- AMPS Procedures for Users and Administrators.pdf PDF
Copy of Attachment 0010-SESAME.xlsx XLSX spreadsheet
Attachment 0007 - WSDS Technical Data Package (TDP).zip ZIP file
Attachment 0006- CARC Paint Drawing 12585018.pdf PDF
Attachment 0024-TPG 2016-01 Rev 1 Source Data.pdf PDF
Attachment 0034- Additional Guidelines for Controlled Unclassified Information.docx DOCX document
Attachment 0033- Department of Defense Guide to Item Unique Identification Quality Assurance.doc DOC document
Attachment 0029- Provisioning Requirements Worksheet.docx DOCX document
Attachment 0011- LPD Attribute Selection Sheet.pdf PDF
Copy of Attachment 0005- HMMR Format.XLSX XLSX spreadsheet
Attachment 0004- Request for Use of Prohibited Materials.doc DOC document
Attachment 0002-PEO CSCSS OPSEC Program.pdf PDF
Attachment 0028-SSI.DOCX DOCX document
Attachment 0027-ATPD 2232 Packaging.pdf PDF
Attachment 0025-TM Crosswalk Form.xls XLS spreadsheet
Copy of Attachment 0015-LORA.xlsx XLSX spreadsheet
Attachment 0013-GMTK CL.pdf PDF
Attachment 0003 - ATPD-2425 WSDS.pdf PDF
Solicitation WSDS.pdf PDF
Attachment 0009- Failure Definition and Scoring Criteria (FDSC).docx DOCX document
Attachment 0018-DE Style Guide 1-26-18.pdf PDF
Copy of Attachment 0041 - Use of Existing Government-Furnished Property.xlsx XLSX spreadsheet
Copy of Attachment 0040 - Pricing Workbook revised 4 20 2021.xlsx XLSX spreadsheet
Attachment 0036- Incoming Transaction Format Packaging.docx DOCX document
Attachment 0035- MOS Operator and Maintenance Tasks 92W-91J.docx DOCX document
Attachment 0032- IUID Data Plate Examples.docx DOCX document
Attachment 0031-Microscan UID Compliance Results.pdf PDF
Attachment 0030 - Pump Reliability and Mobility PQT Plan WSDS-v16.docx DOCX document
Attachment 0023-General Publications Requirements for Page-Based Manuals.doc DOC document
Attachment 0022-TABLE A-VII-NMWR Requirements Matrix.docx DOCX document
Attachment 0020-TABLE A-IV - TM Requirements Matrix -23.docx DOCX document
Attachment 0021-TABLE A-VI - TM Requirements Matrix -23P RPSTL.DOCX DOCX document
Show all 50

Water Storage Distribution System (Solicitation) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Water Storage and Distribution System (WSDS) Technical Review Criteria

Pump Critical Design Review (CDR)/ Test Readiness Review (TRR)

Entrance Criteria

1
Pump CDR meeting agenda
2
Pump assembly design established
3
Assessment of long lead items and availability of critical pump assembly components
4
Risk assessment completed (safety, performance, RAM)
5
Training materials available
6
Test support package list developed
7
Field Service Representative (FSR) support identified
8
Test plan completed and approved

Exit Criteria

1
Action items identified and responsibility assigned
2
Risks identified and mitigation plans in place where required
3
Critical safety issues mitigated to acceptable level
4
Post Pump CDR assessment complete

System Critical Design Review (CDR)/ Test Readiness Review (TRR)

Entrance Criteria (System CDR/TRR)

1
System CDR meeting agenda
2
Product Baseline established for the system (proposed changes to Gov’t TDP)
3
Assessment of long lead items and availability of critical components
4
Prototype fabrication plan
5
Test support plan
6
Risk assessment
7
Safety Assessment Report (SAR)
8
Human Factors Engineering (HFE) assessment
9
Hazardous Materials Management Plan (HMMP)
10
Configuration Management Plan (CMP)
11
Training Materials available
12
Test support package list developed
13
Field Service Representative (FSR) support identified
14
Test plan completed and approved

Exit Criteria (System CDR/TRR)

1
Actions items identified and responsibility assigned
2
Risks identified and mitigation plans in place where required
3
Critical safety issues mitigated to acceptable level
4
Post System CDR assessment complete

Production Readiness Review (PRR)

Entrance Criteria (PRR)

1
PRR meeting agenda
2
PQT complete
3
System Technical Data Package updated with Engineering Change Proposals (ECPs) resulting from test
4
Pump and Hypochlorinator Technical Data Package (TDP) delivered
5
Updated Risk assessment
6
Updated SAR
7
Updated HFE
8
Updated HMMP
9
Contractor properly staffed (engineering, production, quality, manufacturing)
10
Manufacturing processes and quality control system in place
11
Acceptance system including test procedures in place
12
Production facilities ready and required personnel trained
13
Supply chain is stable and adequate to support production

Exit Criteria (PRR)

1
Actions items identified and responsibility assigned
2
Risks identified and mitigation plans in place where required
3
Critical safety issues mitigated to acceptable level
4
Post PRR assessment complete

Physical Configuration Audit (PCA)

Entrance Criteria (PRR)

1
PCA plan complete
2
Technical Data Package (TDP) and all Engineering Change Proposals (ECPs) available
3
Detailed schedule for review complete

Exit Criteria (PRR)

1
Actions items identified and responsibility assigned
2
Risks identified and mitigation plans in place where required
3
Critical safety issues mitigated to acceptable level
4
Configuration audit summary report complete

File details come from the government source that posted it. Updated .