This document includes a federal contract opportunity solicitation for infrastructure upgrades at the Tomah Veterans Affairs Medical Center in Wisconsin. The solicitation seeks a general contractor to expand an existing building by approximately 5,000 square feet to incorporate a new data center and address other facility needs. The upgrades are intended to meet electronic health record modernization requirements and correct deficiencies related to accessibility, the main computer room, and telecommunications infrastructure. The solicitation was issued by the Department of Veterans Affairs Technology Acquisition Center located in Austin, Texas. Interested offerors are invited to respond with pricing and capability statements for furnishing all required labor, materials, and equipment for the expansion and upgrades by the specified due date.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINISH FLOOR
100' - 0"
BASE
95' - 2"
EXTG. FIRST FLOOR
104' - 8"
B.O.S 118' - 0"
T.O.F 91' - 2"
CBA
T.O.S. FRAMING
PLAN
128' - 0"
2ND FLR FRAMING
PLAN
112' - 0"
S300
S200
C12 STRIN
GER
C12 STRINGER
C12 STRINGER
W12x14 W12x14 W12x14
W18X35
S1.2
S1.1A
(1
R
IS
E
R S
.2
(8
R
IS
E
R S
.0
(9
R
IS
E
R S
.4
(8) TREADS @ 11" = 7'-4"
(7) TREADS @ 11" = 6'-5"
(12) TREADS @ 11" = 11'-0"
L
IF
T B
E A
M B
.O .S
C
O O
R D
IN
A
T E w E
L E
V A
T O
R C
O N
T R
2" SOAP
STARTER
COURSE
S500
S500
S500
W12x14
S500
1 SIM.
4" (4000PSI) CONC. SLAB w/ 6x6 - W2.9xW2.9 W.W.F. OVER
6 MIL VAPOR BARRIER AND
6" COMPACTED GRANULAR FILL
3" CONC. TOPP.
OVER METAL PAN
3" CONC. TOPP.
OVER METAL PAN
3" CONC. TOPP.
OVER METAL PAN
23' - 9 1/2"
ROOF TRUSSES @ 24" O.C.
HIP TRUSSES
SEE PLAN
HIP TRUSSES
SEE PLAN
SUMP
15" CONC. WALL
SEE PLAN
#5 @ 12" O.C., EACH WAY
#5 DWL @ 16" O.C.
#5 E.W. @ 18" O.C.
8" CONC. WALL
SEE PLAN
(2) #5 CONT.
T. & B.
#5 DWL @ 16" O.C.
WF36
15" CONC. WALL
SEE PLAN
(2) #5 CONT.
T. & B.
#5 DWL @ 16" O.C.
#5 VERT. @ 16" O.C.
B.B. w/ (2) #5 CONT.
B.B. w/ (2) #5 CONT.B.B. w/ (2) #5 CONT.
S500
2" CONC. PAN, TYPICAL
95' - 2"
BASE
104' - 8"
EXISTING 1ST FLOOR
91' - 2" T.O.F.
118' - 0" B.O.S.
B.B. w/ (2) #5 CONT.
COORDINATE EXISTING CONDUITS w/
ELECTICAL SHT. ET101 & CONTR. FOR
ALL WALL TELECOM PENETRATIONS
3 1/2" / 1 '-0"
3 1/2" / 1'-0"
WATER PROOF MEMBRANEWATER PROOF MEMBRANE
FIRST FLOOR
100' - 0"
EXTG. FIRST FLOOR
104' - 8"
T.O.F 91' - 2"
EXISTING BASEMENT
95' - 2"
S300
S200
H S
S x4 x /4
H S
S x4 x /4
C8X11.5 W6x15
H S
S x4 x /4
H S
S x4 x /4
HSS6X2X1/4
4' - 10" (FIELD VERIFY) 5' - 2" (F.V.)
(F.V.)
1' - 3 1/2" 5' - 5" (F.V.)
(2) 3/4"Ø A325 BOLTS
w/ 3/8" SHEAR TAB
CONNECTION
(2) 3/4"Ø A325 BOLTS
w/ 3/8" SHEAR TAB
CONNECTION
EXISTING CONCRETE
STRUCTURAL FLOOR SYSTEM
EXISTING BLOCK WALL
W6x15
COPE TOP
FLANGE @
ANGLE
L6x6x5/16 SEAT ANGLE
WELDED TO COLUMN
w/ NON-SHINK GROUT
@ BEARING POINT
L2x2x3/16 SEAT ANGLE
WELDED TO COLUMN,
TYPICAL EA. END
FIELD CUT EXISTING
CONCRETE STRUCTURAL
FLOOR BEAM AS REQUIRED
FOR MECHANICAL CHASE.
SEE SHT'S P101, P102, EP101
EXISTING CONCRETE BEAMEXISTING CONCRETE BEAM
EXISTING
FLOOR SLAB
EXISTING
BLOCK WALL
AND VENEER
EXISTING
FDN. WALL
EXISTING
FOOTING
EXISTING
BLOCK WALL
AND VENEER
EXISTING
FDN. WALL
EXISTING
FOOTING
NEW
DOOR
OPENING
NEW
DOOR
OPENING
F
IE
L D
V E
R
IF
Y B
O T
T O
M O
F B
E A
M H
IE
G
H T
(F .V
B E
A M
D E
P T
H
4" (4000PSI) CONC. SLAB INFILL w/ 6x6 - W2.9xW2.9 W.W.F. OVER
6 MIL VAPOR BARRIER AND
6" COMPACTED GRANULAR FILL
COORDINATE EXISTING/NEW CONDUITS
w/ ELECTICAL SHT. ET101 & CONTR. FOR
ALL WALL TELECOM PENETRATIONS
S301
L6x6x5/16 SEAT ANGLE
WELDED TO COLUMN
w/ NON-SHINK GROUT
@ BEARING POINT
EXTG. FIRST FLOOR
104' - 8"
EXISTING BASEMENT
95' - 2"
S301
S500
EXISTING 1-WAY
SLAB STRUCTURE
W6x15 BEAM
H S
S x x /4
C O
L U
M N
1/2"x5"x0'-10" BASE PLATE w/ (4) 3/4"Ø ANCHOR RODS
AND 5" MIN. EMBEDMENT
CMU PARTITION WALL
SEE ARCH. PLANS
3/8"x4"x0'-5" SHEAR TAB w/
(2) 3/4"Ø A325 BOLTS,
TYPICAL EACH END
NON-SHRINK GROUT
AS REQUIRED AT
BEARING POINTS
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY SPRINKLEREDFULLY SPRINKLERED
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL TOMAH. WI
FEB. 4, 2022 JDR TSK
S301S301
FINAL BID DOCUMENTS
676-21-701STRUCTURAL
STAIR/BUILDING SECTIONS
3/8" = 1'-0"S301
1 STAIR CROSS-SECTION
3/8" = 1'-0"S301
2 EXISTING BASEMENT ELEVATION
1/2" = 1'-0"S301
3 EXISTING FLR SUPPORT SECTION
EXISTING CONDITIONSEXISTING CONDITIONSEXISTING CONDITIONSEXISTING CONDITIONS
FIELD VERIFY ALL DIMENSIONS, FIELD VERIFY ALL DIMENSIONS, FIELD VERIFY ALL DIMENSIONS, FIELD VERIFY ALL DIMENSIONS, ELEVATIONS AND CONDITIONS ELEVATIONS AND CONDITIONS ELEVATIONS AND CONDITIONS ELEVATIONS AND CONDITIONS
PRIOR TO CONSTRUCTION PRIOR TO CONSTRUCTION PRIOR TO CONSTRUCTION PRIOR TO CONSTRUCTION
No. Description Date
3/8" STIFFENER
ENCASE BEAM
IN MASONRY
PARTIAL HGT. COURSE AS REQ`D
GROUT CORES SOLID
CMU PIER-SEE PLAN FOR PIER SIZE
& REINFORCING REQUIREMENTS
SEE SCHEDULE
FOR BRG PLATE
T/ BEAM EL.
SEE PLAN
BOND BEAM
SEE PLAN
1/4
1/4
@ SIMILAR TWO BEAMS SHARE BEARING PLATE
STRUCTURAL STEEL COLUMN
SHEAR TAB CONNECTION
STRUCTURAL STEEL BEAM,
SEE PLAN
A325 BOLTS TYP.
SHEAR TAB SCHEDULE
BEAM
SIZE
BOLTS SHEAR TAB SIZE
W12
W18
(3) 3/4"Ø A325
(5) 3/4"Ø A325
3/8"x12"x0'-9" THROUGH PLATE
3/8"x12"x1'-3" THROUGH PLATE
1/4
1/4
TYP
ALLOWABLE
16.3 kips
36.3 kips
CMU WALL, SEE PLAN
WF BEAM, SEE SCHEDULE
BOTTOM PLATE
SEE LINTEL SCHEDULE
1/4 4-12
1/4" PLATE STIFFENER
@ 16" O.C.
BOARD INSULATION
SEE PLAN
VENEER, SEE PLAN
OPENING, SEE PLAN
L4x4x1/4 LEDGER ANGLE FASTEN TO BLOCK w/
1/2"x3" SLEEVE ANCHORS @ 32" O.C.
FLOOR DECK
SEE PLAN
CONT. CMU BOND
BEAM w/ [2]-#5
BARS CONT.
CMU WALL
BUILDING PAPER
CONCRETE FILL
SPECIAL CONTROL
JOINT UNITS
RAKE AND CAULK
SPECIAL CONTROL
JOINT UNITS
RAKE AND CAULK
RAKE AND CAULK
PREFORMED GASKET
SASH UNITS
NOTE:
CMU CONTROL JOINTS
SPACED 24'-0" MAX. & 10'
FROM CORNERS
L5x3 1/2x1/4 EDGE ANGLE FASTEN TO BLOCK w/
1/2"x3" EXP. ANCHORS @ 32" O.C.
COMPOSITE DECK
SEE PLAN
CONT. CMU BOND
BEAM w/ [2]-#5
BARS CONT.
CMU WALL
5" CONCRETE
SEE PLAN
STEEL BEAM
SEE PLAN
SHEAR TAB CONNECTION
SEE SCHEDULE
STEEL BEAM
SEE PLAN
A325 BOLTS TYP.
SHEAR TAB SCHEDULE
BEAM
SIZE
BOLTS SHEAR TAB SIZE
W12
W18
(3) 3/4"Ø A325
(5) 3/4"Ø A325
3/8"x4"x0'-9" PLATE
3/8"x4"x1'-3" PLATE
1/4
1/4
TYP
/2
STEEL BEAM
SEE PLAN
/2 "3
1 1/2"
GAP
1/2"
STEEL BEAM
SEE PLAN
SHEAR TAB CONNECTION
SEE SCHEDULE
A325 BOLTS TYP.
SHEAR TAB SCHEDULE
BEAM
SIZE
BOLTS SHEAR TAB SIZE
C8
(2) 3/4"Ø A325 3/8"x4"x0'-6" PLATE
1/4
1/4
TYP
STEEL
CHANNEL
SEE PLAN
1 1/2"
SECOND FLOOR
112' - 0"
A
W12x14
W14X22
W12x14
5" TOPPING OVER
1.5 CF 22 ga.
COMPOSITE DECK
5" TOPPING OVER
1.5 CF 22 ga.
COMPOSITE DECK
FINISH FLOOR
EL. = 113'-0"
5/16"x7" TOP PLATE
3/8"x4"x0'-9" SHEAR TAB w/ (3) 3/4"Ø A325 BOLTS
1 1/2"
L5x3 1/2x1/4" EDGE ANGLE CONT.
CUT BLOCK AND GROUT SOLID
(F .V
/4
L5x3 1/2x1/4 EDGE ANGLE CONT.
CUT VENEER BLOCK AS REQUIRED EXTERIOR WALL
SEE ARCH. PLANS
10 1/2"
B.B. w/ (2) #5 CONT.
1/2"Ø x 2 1/4" LG.
SLEEVE ANCHORS
@ 24" O.C.
EXISTING 2x6 RAFTER REINFORCED w/ 2x6 SPF #1
& (2) 10d NAILS @ 12" O.C., TYPICAL
NEW CRICKET WITH ASPHALT
SINGLES ON 1/2" SHEATHING
OVER 2x6 P.T. SPF#1 @ 24" O.C.
OVER-FRAMING
L6x6x5/16 LEDGER ANGLE w/ 1/2"Ø x 2 1/4" LG. EPOXY
ANCHORS @ 32" O.C.
BRICK VENEER
CMU VENEER
BOND BEAM
EL. 120'-0"
DEMO RAFTER OVERHANG
& SHEATHING UNDER
CRICKET AREA
STAIR
S1
EXISTING BUILDING
2x6 RIDGE BOARD
FASTEN RAFTER TO
RIDGE w/ METAL HANGER
EXTG. FIRST FLOOR
104' - 8"
CMU PARTITIAN WALL
EXISTING CONCRETE
STRUCTURAL FLOOR SYSTEM
COMPRESSABLE FILLER
M
IN
L4x4x1/4x0'-8" CLIP ANGLE @ 48" O.C. w/ (3) 1/4"Ø x 2 1/4 LG.
TAPCON FASTENERS
5" COMPOSITE
CONC. DECK
TSB TRACK W/
(2) HILTI SCREWS
DO NOT ATTACH STUDS
TO CONC. DECK
/2
M
IN
#8-18 HILTI SCREW @ 16" O.C.
LONG LEG VERTICAL SLIP TRACK (TSC)
SEE ARCHITECTURAL WALL DETAILS
FOR SIZE AND GAUGE
STEEL STUDS @ 16" O.C.
SEE ARCH DETAILS FOR STUD SIZE
5" COMPOSITE
CONC. DECK
TSB TRACK W/
(2) HILTI SCREWS
DO NOT ATTACH STUDS
TO CONC. DECK
#8-18 HILTI SCREW @ 16" O.C.
LONG LEG VERTICAL SLIP TRACK (TSC)
SEE ARCHITECTURAL WALL DETAILS
FOR SIZE AND GAUGE
STEEL STUDS @ 16" O.C.
SEE ARCH DETAILS FOR STUD SIZE
PERPENDICULAR TO DECKING PARALLEL TO DECKING
T.O.S. FRAMING
PLAN
128' - 0"
W12x14
W8X24
/8
L2 LINTEL
C12x20.7x0'-6" BEAM SEAT
5/8"x5"x0'-8 SPACER PLATE
1/4
1/4
1/4
1/4
2ND FLR FRAMING
PLAN
112' - 0"
" 2
/2
2"
C8X11.5
5" TOPPING OVER
1.5 CF 22 GA.
COMPOSITE DECK
B.B. w/ (2) #5 CONT.
GROUT CORES SOLID
(2) - 3/4"Ø x 2-1/4" EPOXY ANCHORS
L4x3x1/4 CLIP ANGLE w/ (2) 3/4"Ø A325 BOLTS
EXTERIOR WALL
SEE ARCH. PLANS
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY SPRINKLEREDFULLY SPRINKLERED
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL TOMAH. WI
FEB. 4, 2022 JDR TSK
S500S500
FINAL BID DOCUMENTS
676-21-701STRUCTURAL
FRAMING DETAILS
3/4" = 1'-0"S500
1 BEAM BRG. DETAIL
1" = 1'-0"S500
2 COLUMN BEAM CONNECTION DETAIL
1" = 1'-0"S500
3 (L2) LINTEL SECTION
3/4" = 1'-0"S500
4 LEDGER ANGLE DETAIL
1/2" = 1'-0"S500
5 Control Joints
3/4" = 1'-0"S500
6 EDGE ANGLE DETAIL
1" = 1'-0"S500
7 BEAM-BEAM CONNECTION DETAIL
1" = 1'-0"S500
8 CHANNEL-BEAM CONNECTION DETAIL
3/4" = 1'-0"S500
12 LOW ROOF/WALL DETAIL
1/2" = 1'-0"S500
9 CRICKET @ STAIR DETAIL
1" = 1'-0"S500
10 SLIP CONNECTION DETAIL
1" = 1'-0"S500
11 LGSF SLIP CONNECTION DETAIL
1" = 1'-0"S500
13 BEAM/L2 CONN. DETAIL
1" = 1'-0"S500
14 CHANNEL/CMU CONN. DETAIL
OS
H
INTERIOR PARTITION WALL
SMOKE PARTITION WALL
PLAN
3-5/8" METAL STUDS
@ 16" OC
(1) LAYER 5/8" GYP
BD EACH SIDE
TAPE ALL JOINTS
ANCHOR TOP RUNNER
TO STRUCTURE ABOVE
SEAL TRACK
BATT INSULATION
WALL BASE AS SCHEDULED
STEEL RUNNER ANCHORED
TO FLOOR STRUCTURE
A1
EXTERIOR WALL
FIRE RESISTANCE: 2 HR
RESISTANCE UL# U905
PLAN
W2
3 5/8" 3" 7 5/8"
BRICK VENEER
AIR SPACE
2 1/2" RIGID
INSULATION (R13.3
MIN)
CONCRETE
MASONRY UNIT
EXTERIOR WALL
FIRE RESISTANCE: 2 HR
RESISTANCE UL# U905
PLAN
3-5/8" METAL STUDS
@ 16" OC
(1) LAYER 5/8" GYP
BD TAPE ALL JOINTS
ANCHOR TOP RUNNER
TO STRUCTURE ABOVE
SEAL TRACK
FULL WIDTH
BATT INSULATION
WALL BASE AS SCHEDULED
STEEL RUNNER ANCHORED
TO FLOOR STRUCTURE
W1
3 5/8" 3 3/4" 7 5/8" 3 5/8"
BRICK VENEER
AIR SPACE
RIGID INSULATION
(R13.3 MIN)
CONCRETE
MASONRY UNIT
1' - 2 1/4"
3 5/8"
INTERIOR WALL
FIRE RESISTANCE: 1 HR
RESISTANCE UL# U905
PLAN
7 5/8"
CONCRETE
MASONRY UNIT
INTERIOR WALL
FIRE RESISTANCE: 1 HR
RESISTANCE UL# U905
PLAN
7 3/4" 2 1/2" 5/8"
CONCRETE
MASONRY UNIT
2 1/2" METAL STUDS @
16" O.C
(1) LAYER 5/8" GYP
BD TAPE ALL JOINTS
ANCHOR TOP RUNNER
TO STRUCTURE ABOVE
SEAL TRACK
BATT INSULATION
WALL BASE AS SCHEDULED
STEEL RUNNER ANCHORED
TO FLOOR STRUCTURE
A3A2
1' - 7 1/4"
CONTINUOUS AIR & VAPOR
BARRIER & RETURN HORIZONTALLY
AT BOTTOM OF STEEL PLATE
10 7/8"
INTERIOR WALL
FIRE RESISTANCE: 1 HR
RESISTANCE UL# U905
PLAN
5/8"
2 1/2" 7 3/4" 3 5/8"
5/8"
BOND BEAM - SEE
STRUCTURAL PLAN
3-5/8" METAL STUDS
@ 16" OC W/ 5/8" GYP
ANCHOR TOP RUNNER
TO STRUCTURE ABOVE
SEAL TRACK
BATT INSULATION
WALL BASE AS SCHEDULED
STEEL RUNNER ANCHORED
TO FLOOR STRUCTURE
A4
1' - 3 1/8"
2-1/2" METAL STUDS
@ 16" OC W/ 5/8" GYP
INTERIOR PARTITION WALL
PLAN
2-1/2" METAL STUDS
@ 16" OC
(1) LAYER 5/8" GYP
BD
TAPE ALL JOINTS
ANCHOR TOP RUNNER
TO STRUCTURE ABOVE
SEAL TRACK
FULL WIDTH
BATT INSULATION
WALL BASE AS SCHEDULED
STEEL RUNNER ANCHORED
TO FLOOR STRUCTURE
SECTION SECTION
SECTION SECTION SECTION
SECTION SECTION
A5
AIR & VAPOR
BARRIER
SLIP TRACK
SLIP TRACK
SLIP TRACK
ANGLE BOTH SIDES - SEE
STRUCTURAL PLAN
SLIP TRACK
SLIP TRACK
BOND BEAM - SEE
STRUCTURAL PLAN
1A1
PROVIDE FIRE STOPPING
ASSEMBLY ON TOP OF FIRE
RATED WALL
PROVIDE FIRE STOPPING
ASSEMBLY ON TOP OF FIRE
RATED WALL
PROVIDE FIRE STOPPING
ASSEMBLY ON TOP OF FIRE
RATED WALL
/8
/8
SEALANT
SEALANT
/8
" SEALANT
PROVIDE 1 HR FIRE
STOPPING ASSEMBLY
/8
SEALANT
PROVIDE 2 HR FIRE
STOPPING ASSEMBLY
/8
PROVIDE 2 HR FIRE
STOPPING ASSEMBLY
INTERIOR PARTITION WALL
PLAN
3-5/8" METAL STUDS
@ 16" OC
(1) LAYER 1/2" PLYWOOD BOTH
SIDES
STEEL RUNNER ANCHORED
TO FLOOR STRUCTURE
SECTION
A6
/8
" SEALANT
1/2" PLYWOOD CAP
1. VERIFY EXISTING CONDITIONS AND LOCATIONS IN FIELD PRIOR TO SUBMITTING PROPOSAL.
FAILURE TO DO SO SHALL NOT RELIEVE THIS CONTRACTOR FROM PERFORMING THE WORK
REQUIRED UNDER THIS CONTRACT.
2. WHILE THE SIZE AND LOCATION OF NEW WORK AND EQUIPMENT IN THE EXISTING AREA HAS
BEEN INDICATED ON THE DRAWINGS AS ACCURATELY AS POSSIBLE, CONTRACTOR
SHALL ADJUST HIS WORK AS REQUIRED TO AVOID EXISTING UTILITIES, FIRE ALARM, ROOF
DRAINS, ACCESS COVERS, AND OTHER STRUCTURES NOT PARTICULARLY SHOWN ON PLAN
AT NO EXTRA COST. BEFORE CONSTRUCTION, INSPECT PREMISES AND MAKE A DETAILED
EXAMINATION OF ALL LOCATIONS WHERE NEW WORK IS TO BE INSTALLED. EXAMINE
EXISTING PIPING, CONDUITS, STRUCTURAL SUPPORTING BEAMS, AND OTHER CONDITIONS.
3. ACCESS TO ALL BUILDINGS AND PARKING AREAS MUST BE MAINTAINED THROUGHOUT THE
PROJECT.
4. CONTRACTOR SHALL COORDINATE ALL WORK WITH THE VA'S CONTRACTING OFFICER'S
REPRESENTATIVE (COR).
5. CONTRACTOR SHALL MAINTAIN FULL OPERATION OF EXISTING BUILDING'S MECHANICAL,
ELECTRICAL AND SECURITY SYSTEMS. COORDINATE WITH THE VA COR AND PROVIDE (14) DAY
ADVANCE NOTIFICATION PRIOR TO SHUT DOWN. REQUIRED SHUT DOWNS SHALL BE
SCHEDULED AT THE VA'S CONVENIENCE. PREMIUM OR OVERTIME COSTS REQUIRED SHALL BE
INCLUDED IN THE BASE BID. FAILURE TO PROCEED WITHOUT PROPER PRIOR NOTIFICATION
MAY RESULT IN THE ASSESSMENT OF A CREDIT TO THE CONTRACT.
6. CONTRACTOR SHALL STRICTLY ADHERE TO STATE AND FEDERAL OCCUPATIONAL SAFETY A
HEALTH ADMINISTRATION (OSHA) STANDARDS
7. CONTRACTOR SHALL PARK ONLY IN THE DESIGNATED PARKING AREAS AND ARE NOT TO
PARK ON THE LAWN AREAS.
8. CONTRACTOR SHALL SAFEGUARD THEIR TOOLS AND EQUIPMENT. TOOLS AND EQUIPMENT
SHALL NOT BE LEFT UNATTENDED AND SHALL BE SECURED AT ALL TIMES WHEN THE
CONTRACTOR IS NOT PRESENT.
9. CONTRACTOR SHALL CONTROL DEMOLITION AND CONSTRUCTION DUST FROM FACILITY BY
ERECTING A DUST BARRIER AND VENTILATION WITH HEPA FILTERS. IF VENTING TO
OUTSIDE, THE CONTRACTOR SHALL INSURE NEGATIVE AIR PRESSURE IS MAINTAINED IN
ENCAPSULATED WORK AREA. WHEN TRANSPORTING DEBRIS, WET DOWN SUFFICIENTLY TO
PREVENT DUST SPREADING.
10. IF SCAFFOLDING IS USED, IT SHALL BE USED IN ACCORDANCE WITH (OSHA AND VA)
REGULATIONS AND SHALL BE ENCLOSED FOR THE FIRST EIGHT FEET ABOVE GROUND AT END
OF EACH WORKING DAY, UNTIL DISMANTLED. LADDERS SHALL BE REMOVED AND LOCKED UP
AT THE END OF EACH WORKING DAY TO PREVENT UNAUTHORIZED PERSONS FROM HAVING
ACCESS.
11. ALL CRANE LIFT OPERATIONS SHALL HAVE A LIFT PLAN DRAWING AND AN OUTAGE
SCHEDULE TO ALLOW THE VA TO EVACUATE TWO FLOORS BELOW LIFT SWING ARC.
12. PROTECT ALL EXISTING SURFACES FROM DAMAGE. ANY DAMAGED SURFACES SHALL BE
REPLACED TO MATCH ORIGINAL ITEM, OR REPAIRED TO MATCH EXISTING OR ADJACENT
MATERIAL AS APPROVED BY THE VA COR.
13. CONTRACTOR SHALL REPAIR AND REPLACE ANY DAMAGED LAWN. THE RESTORATION SHALL
BE SOD AND SHALL BE PERFORMED BY A LANDSCAPE CONTRACTOR. TOPSOIL SHALL BE
TILLED AND GRADED TO A SMOOTH MATCHING GRADE OF UNDAMAGED LAWN. SOD SHALL BE
THOROUGHLY SATURATED WITH WATER UPON PLACEMENT. THE CONTRACTOR SHALL WATER
NEW SOD UNTIL PROJECT ACCEPTANCE BY THE COR.
14. CLEAN AND REMOVE DEBRIS FROM CONSTRUCTION SITE TO THE SATISFACTION OF THE VA
COR.
15. WORK HOURS: DAYTIME - NORMAL WORK THAT DOES NOT CREATE VIBRATION, LOUD
NOISE OR ODORS OR REQUIRE LOADING DOCK / TRUCK SPACE.
8PM-6AM - WORK REQUIRING OUTAGES, TRUCK SPACE / CRANES.
WEEKENDS - WORK THAT CREATES LOUD NOISE, VIBRATIONS, ODORS, OUTAGES AND/OR
TRUCK SPACE / CRANE.
16. CONTRACTOR SHALL PROVIDE "SUBMITTAL EXCHANGE" SECURE ONLINE SYSTEM FOR
EXCHANGING, REVIEWING AND ARCHIVING SUBMITTALS, RFI'S, AND OTHER CONSTRUCTION
COMMUNICATIONS ELECTRONICALLY.
GENERAL ARCHITECTURAL
A/E ARCHITECT/ENGINEER
A AIR (MEDICAL)
AC ACOUSTICAL CEILING
ACS DR ACCESS DOOR
ACS PNL ACCESS PANEL
ACST ACOUSTIC
ACT ACOUSTIC CEILING TILE
ADA AMERICAN WITH DISABILITIES ACT
ADDL ADDITIONAL
ADH ADHESIVE
ADO AUTOMATIC DOOR OPERATOR
ADJ ADJACENT, ADJOINING, OR ADJUSTABLE
AFF ABOVE FINISHED FLOOR
AHJ AUTHORITY HAVING JURISDICTION
AHU AIR HANDLING UNIT
ALT ALTERNATE
ALUM ALUMINUM
AMT AMOUNT
ANOD ANODIZED
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE
APPROX APPROXIMATELY
ARCH ARCHITECT
ASB ASBESTOS
ATTD ATTACHED
AUTO AUTOMATIC
AUX AUXILIARY
AVG AVERAGE
AWT ACOUSTICAL WALL TREATMENT
B BASE
BD BOARD
BEJ BRICK EXPANSION JOINT
BF BARRIER FREE
BITUM BITUMINOUS
BKG BACKING
BLDG BUILDING
BLKT BLANKET
BM BEAM OR BENCHMARK
BOT BOTTOM
BRCG BRACING
BRG BEARING
BRKT BRACKET
BSMT BASEMENT
BTWN BETWEEN
CAB CABINET
CB CATCH BASIN OR CORNER BEAD
CCTV CLOSED CIRCUIT TELEVISION
CCW COUNTERCLOCKWISE
CD CONSTRUCTION DOCUMENTS OR CONTRACT DOCUMENTS
CF CONTRACTOR FURNISHED
CF/CI CONTRACTOR FURNISHED/CONTRACTOR INSTALLED
CF/OI CONTRACTOR FURNISHED/OWNER INSTALLED
CFM CUBIC FEET PER MINUTE
CFMF COLD-FORMED METAL FRAMING
CG CORNER GUARD
CHK CHECK
CIP CAST IN PLACE
CIR CIRCLE
CJ CONTROL JOINT
CL CENTER LINE
CLDG CLADDING
CLG CEILING
CLOS CLOSET
CLR CLEAR
CLR HT CLEAR HEIGHT
CMU CONCRETE MASONRY UNIT
CNR CORNER
CNTR COUNTER
COL COLUMN
COMB COMBINATION, COMBINED
COMM COMMUNICATION
CONC CONCRETE
COND CONDITION
CONF CONFERENCE
CONN CONNECT
CONT CONTINUOUS
CONTR CONTRACTOR
COORD COORDINATE
CORR CORRIDOR
CPT CARPET
CR CARD READER
CRS COURSE
CSG CASING
CSWK CASEWORK
CT CERAMIC TILE
CTR CENTER
CTRL CONTROL
CURT CURTAIN
CYL CYLINDER
DBL DOUBLE
DEG DEGREE
DEMO DEMOLITION
DEPT DEPARTMENT
DET DETAIL
DIA DIAMETER
DIAG DIAGONAL
DIM DIMENSION
DISP DISPENSER
DN DOWN
DOC DOCUMENT
DR DOOR
DR FR DOOR FRAME
DR OPNG DOOR OPENING
DS DOWNSPOUT
DWG DRAWING
DWG DOWEL
E EAST
EA EACH
EJ EXPANSION JOINT
EL ELEVATION
ELEC ELECTRICAL
ELEV ELEVATOR
EMER EMERGENCY
ENCL ENCLOSURE
ENGR ENGINEER
EP ELECTRICAL PANEL
EPDM ETHYLENE PROPYLENE DIENE MONOMER
EQ EQUAL
EQUIP EQUIPMENT
EQUIV EQUIVALENT
EXH EXHAUST
EXIST EXISTING
EXP EXPANSION OR EXPOSED
EXT EXTERIOR
FA FIRE ALARM
FD FLOOR DRAIN
FDC FIRE DEPARTMENT CONNECTION
FDTN FOUNDATION
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FESR FIRE EXTINGUISHER, SEMI-RECESSED
FF FINISH FACE, FINISH FLOOR
FF EL FINISH FLOOR ELEVATION
FF&E FURNITURE, FIXTURE, AND EQUIPMENT
FHP FULL HEIGHT PARTITION
FIN FINISH
FIXT FIXTURE
FLASH FLASHING
FLR FLOOR
FO FINISH OPENING
FP FIRE PROTECTION OR FIREPROOF
FR FIRE RATING, FIRE RESISTANT, OR FRAME
FRP FIBER REINFORCED POLYESTER, OR FIBERGLASS
REINFORCED PLASTIC
FT FEET
FTG FOOTING
FURN FURNISH, FURNISHED OR FURNITURE
GA GAUGE
GALV GALVANIZED
GB GRAB BAR
GC GENERAL CONTRACTOR
GEN GENERAL
GL GLASS
GR GROUT
GYP BD GYPSUM BOARD
H HIGH OR HEIGHT
HAZ MAT HAZARDOUS MATERIALS
HB HOSE BIBB
HC HOLLOW CORE
HD HUB DRAIN
HDWR HARDWARE
HEPA HIGH EFFICIENCY PARTICULATE AIR (FILTER)
HM HOLLOW METAL
HR HANDRAIL
HO HOLD OPEN
HORIZ HORIZONTAL
HOSP HOSPITAL
HSKPG HOUSEKEEPING
HPC HIGH PERFORMANCE COATING
HR HOUR
HSS HOLLOW STRUCTURAL SECTION
HT HEIGHT
HVAC HEATING, VENTILATING, AIR CONDITIONING
IBC INTERNATIONAL BUILDING CODE
ID IDENTIFICATION
IG INSULATING GLASS
INCL INCLUDED, INCLUDING
INSTL INSTALLED
INSUL INSULATION
INT INTERIOR
IRWC IMPACT RESISTANT WALL COVERING
JAN JANITOR
JT JOINT
KD KNOCKED-DOWN
KO KNOCK(ED)-OUT
L ANGLE
LAM LAMINATE(D)
LAM GL LAMINATED GLASS
LAV LAVATORY
LD BRG LOAD-BEARING
LED LIGHT EMITTING DIODE
LH LEFT HAND
LIN LINEAR
LKR LOCKER
LKR RM LOCKER ROOM
LRG LARGE
LT LIGHT
LTWT LIGHTWEIGHT
LTG LIGHTING
LVR LOUVER
LYR LAYER
MACH MACHINE
MAINT MAINTENANCE
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MEMB MEMBRANE
MEZZ MEZZANINE
MFR MANUFACTURER
MICRO MICROWAVE
MIN MINIMUM
MIRR MIRROR
MISC MISCELLANEOUS
MLWK MILLWORK
MO MASONRY OPENING
MON MONITOR
MR MOISTURE RESISTANT
MTD MOUNTED
MTG MOUNTING
MTL METAL
MTR METER
N NORTH
NA NOT APPLICABLE
NEG NEGATIVE
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
NIC NOT IN CONTRACT
NO NUMBER
NOM NOMINAL
NRC NOISE REDUCTION COEFFICIENT
NRP NON REMOVABLE
NTS NOT TO SCALE
O OXYGEN
OC ON CENTER
OD OUTSIDE DIAMETER, OUTSIDE DIMENSION
OF/CI OWNER FURNISHED/CONTRACTOR INSTALLED
OFD OVERFLOW DRAIN
OFF OFFICE
OF/OI OWNER FURNISHED/OWNER INSTALLED
OPNG OPENING
OPP OPPOSITE
OPR OPERABLE
OPT OPTIONAL
ORD OVERFLOW ROOF DRAIN
ORIG ORIGINAL
ORN ORNAMENTAL
OSHA OCCUPATIONAL SAFETY AND HEALTH
ADMINISTRATION
PART PARTIAL
PASS PASSAGE
PB PUSHBUTTON
PE POURED EPOXY
PERF PERFORATED
PERIM PERIMETER
PL PLATE
PLAM PLASTIC LAMINATE
PLBG PLUMBING
PLYWD PLYWOOD
PNL PANEL
PP PUSH PLATE
PPT PARAPET
PR PAIR
PRCST PRECAST
PREFAB PREFABRICATED
PREFIN PREFINISHED
PREP PREPARATION
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT PAINT
PTD PAPER TOWEL DISPENSER
PTN PARTITION
PWR POWER
QTR QUARTER
QTY QUANTITY
R RADIUS OR RISER
RB RESILIENT BASE
RD ROOF DRAIN
RCP REFLECTED CEILING PLAN
REC RECESSED
RECPT RECEPTACLE
REF REFRIGERATOR OR REFERENCE
REINF REINFORCED, REINFORCEMENT
REPL REPLACE
REQD REQUIRED
REV REVISION
RF RESILIENT FLOORING
RFG ROOFING
RH RIGHT HAND
RLG RAILING
RM ROOM
RO ROUGH OPENING
RT RESILIENT TILE
RV ROOF VENT
SC SHARPS CONTAINER, SPECIAL COATING
SCHD SCHEDULE
SCONC SEALED CONCRETED
SCWD SOLID CORE WOOD DOOR
SD SOAP DISPENSER
SECT SECTION
SEP SEPARATE
SF SQUARE FOOT (FEET)
SHT SHEET
SGL SINGLE
SHR SHOWER
SHV SHELVING
SIM SIMILAR
SLD SOLID SURFACE
SLNT SEALANT
SM SHEET METAL
SND SANITARY NAPKIN DISPENSER/DISPOSAL
SPEC SPECIFICATION
SPKLR SPRINKLER
SPKR SPEAKER
SPLY SUPPLY
SQ SQUARE
SST STAINLESS STEEL
SSM SOLID SURFACING MATERIAL
ST STONE
STC SOUND TRANSMISSION CLASS
STD STANDARD
STL STEEL
STN STAIN
STOR STORAGE
STRUCT STRUCTURE OR STRUCTURAL
SURF SURFACE
SUSP SUSPENDED
SV SHEET VINYL
T TREAD
TEL TELEPHONE
TEMP TEMPERED OR TEMPORARY
TH THICK(NESS)
THERM THERMAL
TLT TOILET
TOB TOP OF BEAM
TOF TOP OF FOOTING
TOM TOP OF MASONRY
TOS TOP OF SLAB OR TOP OF STEEL
TOW TOP OF WALL
TPD TOILET PAPER DISPENSER
TRTD TREATED
TS TUBE STEEL
TV TELEVISION OR TV OUTLET
TWC TACKABLE WALL COVERING
TYP TYPICAL
U HEAT TRANSFER COEFFICIENT
UC UNDERCOUNTER OR CABINET
UL UNDERWRITERS LABORATORIES
UNEXC UNEXCAVATED
UNFIN UNFINISHED
UNO UNLESS NOTED OTHERWISE
W WIDE OR WEST
W/ WITH
W/0 WITHOUT
WC WALL COVERING OR WATER CLOSET
WD WOOD
WDW WINDOW
WDWK WOODWORK
WF WIDE FLANGE
WLD WELDED
WM WIRE MESH
WT WEIGHT
WWF WELDED WIRE FABRIC
X BRACE CROSS BRACE
XPS EXTRUDED POLYSTYRENE BOARD
YD YARD
VAR VARIES
VCT VINYL COMPOSITION TILE
VENT VENTILATION
VERT VERTICAL
VEST VESTIBULE
VIF VERIFY IN FIELD
VTR VENT THROUGH ROOF
VWC VINYL WALL COVERING
T
.0
0'-0"
SHT
DTL
SHT
DTL
SHT
DTL
CHR1
EXISTING WALLS TO REMAIN
EXISTING WALLS TO BE REMOVED
EXISTING ITEM TO REMAIN
EXISTING ITEM TO BE REMOVED
EXISTING DOOR AND FRAME TO BE REMOVED
EXISTING DOOR AND FRAME TO REMAIN
LEGEND
WALL TYPE / PARTITION TYPE
DETAIL REFERENCE
SECTION REFERENCE
NEW WALL / PARTITION
NEW DOOR AND FRAME
EQUIPMENT TAG
INTERIOR ELEVATION
CARD READER
INTERCOM
DOOR OPERATOR PUSH PLATE (FURNISHED BY
DIVISION 08, INSTALLED AND WIRED BY ELECTRICAL CONTRACTOR)
CONSTRUCTION LIMITS
2'-0" x 2'-0" SUSPENDED EXPOSED GRID ACOUSTIC CEILING TILE SYSTEM
RETURN, TRANSFER, EXHAUST GRILLE
2'-0" x 2'-0" RECESSED TROFFER LIGHT
2'-0" x 4'-0" RECESSED TROFFER LIGHT
SUPPLY GRILLE
1'-0" x 4'-0" RECESSED TROFFER LIGHT
PENDANT LIGHT
RECESSED DOWN LIGHT
INDUSTRIAL STRIP LIGHT
2'-0" x 2'-0" AUDIO SPEAKER
SMOKE DETECTOR
HEAT DETECTOR
KEYED NOTE
CEILING HEIGHT
CEILING RECESSED TV BRACKET
GYPSUM BOARD CEILING OR BULKHEAD
EXIT LIGHT
PP
CR
IC
CORNER GUARD
12 x 12 ACCESS PANEL
HR
CG
HANDRAIL
24 x 24 ACCESS PANEL
S
OCCUPENCY SENSOR
SPRINKLER HEAD
XX
EXISTING CMU WALL
NEW CMU WALL
FLAT ROOF CONSTRUCTION
R1
SINGLE MEMBRANE
TAPERED POLY ISO RIGID INSULATION (30)
3 1/2" CONCRETE
TOPPING OVER 1 1/2"
METAL DECKING
ROOF CONSTRUCTION
R2
TRUSS - SEE STRUCTURAL
5" POLY ISO RIGID INSULATION (R30)
1/2" PLYWOOD SHEATHING
COMPOSITE SLATE ROOF TILE SYSTEM
CRICKET ROOF CONSTRUCTION
R3
OVER FRAMING ON EXISTING
ROOF STRUCTURE
1/2" PLYWOOD SHEATHING
ASPHALT SHINGLES
TRAMWAY ROOF CONSTRUCTION
R4
VAPOR RETARDER
EPDM SHEET ROOFING
15 # FELT UNDERLAYMENT
FLUID APPLIED AIR & VAPOR RETARDER
FLUID APPLIED AIR & VAPOR RETARDER
15# FELT UNDERLAYMENT
PROVIDE VALLEY FLASHING W/ 3'-0"
WIDE ICE & WATER SHIELD
3 1/2" CONCRETE
TOPPING OVER 1 1/2"
METAL DECKING
3 1/2" CONCRETE
TOPPING OVER 1 1/2"
METAL DECKING
TAPERED POLY ISO RIGID
INSULATION (R30)
FLOOR CONSTRUCTIONF1
4" CONCRETE SLAB
VAPOR BARRIER
6" COMPACTED DRAINAGE
FILL -SEE STRUCTURAL
DRAWINGS
3 1/2" CONCRETE
TOPPING OVER 1 1/2"
METAL DECKING
SECOND FLOOR CONSTRUCTIONF2
4" FINE GRANULAR FILL
1 HR UL # DL916
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT
LEADER:
Department of Veterans Affairs
CONSULTANTS
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS
TOMAH, WI 54660
MEDICAL CENTER
VETERANS
FULLY
500 E VETERANS
TOMAH, WI 54660
MEDICAL CENTER
VETERANS
FULLY
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY FULLY
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
A001A001
FINAL BID DOCUMENTS
676-21-701ARCHITECTURAL
LEGENDS, ABBREVIATIONS AND
WALL TYPES
1" = 1'-0"A001
1 WALL PARTITION TYPES
1" = 1'-0"A001
2 ROOF TYPES
1" = 1'-0"A001
3 FLOOR TYPES
DN
MDP
ATS-208-EQ
ATS-208-CR
B
P/1
MDP-208-EQ
KILL
SWITCHFIRE
SYS
UPS UPS
BIX
PNL A
POWER COND
'A'
UPS
PNL
BYPASS
FLOW
IPX IPX IPX
LIGHTNING
PROTECTION
RACK
SERVER
SERVER FIBER
FEED
LIEBERT
DS
PA ???
1. DO NOT BEGIN DEMOLITION WORK UNTIL HAZARDOUS ABATEMENT
WORK HAS BEEN COMPLETED - SEE HA DRAWING
2. GENERAL CONTRACTOR IS RESPONSIBLE FOR THE COORDINATION OF
ALL DEMOLITION WORK WITH NEW CONSTRUCTION WORK.
3. GENERAL CONTRACTOR TO REVIEW MECHANICAL, ELECTRICAL,
4. PLUMBING, AND FIRE PROTECTION PLANS FOR ADDITIONAL DEMOLITION
WORK. DEMOLITION OF WALL, CEILING, AND FLOOR ASSEMBLIES
NECESSARY TO FACILITATE MEP SYSTEM DEMOLITION IS PART OF
CONTRACTOR'S SCOPE OF WORK.
5. ALL DEMOLISHED MATERIAL BECOMES THE PROPERTY AND
RESPONSIBILITY OF THE CONTRACTOR, WITH THE EXCEPTION OF
SPECIFIED ITEMS DESIGNATED EITHER IN THE PLANS OR VERBALLY
REQUESTED BY THE COR TO BE RETAINED BY THE VA. OFFSITE
DISPOSAL OF THE DEMOLISHED ITEMS IS THE RESPONSIBILITY OF THE
CONTRACTOR.
6. MAINTAIN CONTINUOUS UTILITY SERVICE TO ALL SPACES IN THE
BUILDING NOT AFFECTED BY THIS WORK. COORDINATE WITH VA COR
ANY DISRUPTION IN SERVICES REQUIRED TO PERFORM WORK.
7. FIELD VERIFY AND COORDINATE LOCATIONS OF NEW VENT AND FAN
ROOF OPENING TO AVOID CONFLICT WITH EXISTING ROOF STRUCTURE
AND UTILITIES.
8. MAINTAIN THE WARRANTY OF THE INTEGRITY OF EXISTING ROOFING
ASSEMBLY.
DEMO GENERAL NOTES
DEMO PLAN - KEYNOTES
1 REMOVE PORTION OF WALL, CEILING AND ROOFING TO ACCOMMODATE NEW
OPENING. PATCH AND REPAIR TO MATCH EXISTING FINISHED.
2 REMOVE EXISTING SMOKING ENCLOSURE, CONCRETE AND
FOOTINGS
3 LOCATION OF EXISTING MANHOLE AND TELECOMM VAULT - SEE CIVIL DRAWINGS
COMPLETELY REMOVE PORTION OF EXISTING TRAMWAY
INCLUDING FOUNDATION/FOOTINGS
5 REMOVE EXISTING CONCRETE PAD- SEE CIVIL DRAWINGS
6 RELOCATE EXISTING MECHANICAL EQUIPMENT- SEE MECHANICAL DRAWINGS
7 EXISTING STEAM TUNNEL - SEE CIVIL DRAWINGS FOR MODIFICATIONS
8 REMOVE COLUMN AFTER CEILING STRUCTURE MODIFICATIONS ARE
COMPLETED - SEE STRUCTURAL DRAWINGS
9 REMOVE EXISTING RADIATOR
10 REMOVE EXISTING WINDOWS AND FRAMES - SEE ABATEMENT DRAWINGS
11 REMOVE EXISTING DOOR AND FRAME TO ACCOMMODATE NEW CONSTRUCTION.
12 REMOVE EXISTING CONCRETE FLOORING, STRUCTURE, ENCLOSURE, CEILING
ASSEMBLY, LIGHT FIXTURES AND EXISTING FINISHES
13 REMOVE EXISTING SUMP PUMP - SEE PLUMBING DRAWINGS
CUT BACK EXISTING ROOF STRUCTURE TO REMOVE OVERHANG AND
GUTTER. REMOVE ROOF DECK SHEATHING AND SHINGLES. REQUIRED FOR
NEW CONSTRUCTION.
REMOVE CONCRETE WINDOW WELLS AND WINDOW AWNING.
16 REMOVE AND RELOCATE DOWNSPOUT
SAWCUT AND REMOVE CONCRETE FLOOR SLAB. PROTECT EXISTING
STRUCTURE. AS REQUIRED FOR PLUMBING REMOVAL & INSTALLATION WORK.
COORDINATE W/ PLUMBING CONTRACTOR & SEE PLUMBING DRAWINGS.
18 DOWNSPOUT TO BE RELOCATED
REMOVE PORTION OF FOUNDATION WALL FOR NEW CONDUITS - SEE CIVIL
DRAWINGS C104 FOR MORE INFORMATION
20 REMOVE ROOF CONSTRUCTION
CUT BACK EXISTING ROOF STRUCTURE, ROOF DECK SHEATHING AND
SHINGLES. REQUIRED FOR NEW CONSTRUCTION.
EX. TELEPHONE
EQUIPMENT RM
EX. TRAMWAY
EX. STRUCTURE
EX. STEAM
TUNNEL
V .I .F
EX.
CONCRETE
PAD
EX. MECHANICAL RM
EX.OFFICE
EX.TLT
EX.STORAGE
V.I.F
8' - 7 7/8"
V .I .F
/2
V .I .F
V.I.F
6' - 0"
S E
E C
IV
IL
S E
E C
IV
IL
SEE CIVIL
4' - 0"
SEE CIVIL
7' - 9"
EX. ADP CHIEF
EX. TRAINING RMEX.
UNSECURED
SUPPLY RM
EX.
SECURED
SUPPLY RM
EX.
MECHANICAL
RM
EX. TOILET
EX. TOILET EX. TECH
STAFF
EX. COMPUTER
RM
EX. LOBBY
V .I .F
/2
V.I.F
14' - 0"
20 20
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY SPRINKLEREDFULLY SPRINKLERED
KEY PLAN N
BLDG 32
T R
A M
W A
Y
BLDG 401
BLDG 32
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
AD101AD101
FINAL BID DOCUMENTS
676-21-701ARCHITECTURAL
FLOOR PLANS - DEMOLITION
1/8" = 1'-0"AD101
1 EXISTING BASEMENT FLOOR DEMOLITION
1/8" = 1'-0"AD101
2 EXISTING FIRST FLOOR DEMOLITION PLAN
1/8" = 1'-0"AD101
3 EXISTING ROOF DEMOLITION PLAN
UPEX. TELEPHONE EQUIPMENT RM
V .I .F
2' - 8" 8' - 0" 8"
63' - 4"
/2
/2
39' - 2"
/8
1072 SF
MECHANICAL
ROOM
13215
377 SF
CORRIDOR
13211
240 SF
CORRIDOR
13210
STAIR
S1
ELEV.
E1
9' - 3"12' - 0 3/4" 30' - 1 3/4"
8' - 3 1/2"
/8
2' - 8" 8' - 0" 2' - 8" 2' - 8" 3' - 4" 14' - 4" 3' - 8" 2' - 8" 3' - 8" 7' - 4" 3' - 8" 2' - 4" 3' - 8" 4' - 8 1/2" 7' - 3" 2' - 0 1/2"
4' - 0" 3' - 8" 2' - 8" 3' - 8" 7' - 8" 3' - 8" 2' - 8" 3' - 8" 7' - 0" 3' - 8" 2' - 6" 3' - 8" 3' - 4"
453 SF
CORRIDOR
13212
A301
8' - 6"
2"
2"
74' - 8"
3' - 10 1/4" 9' - 3"
EXISTING NEW CONSTRUCTION
11' - 6"
/4
1 HR.
V .I .F
A302
A302
A501
EX. BUILDING 401
EX. TRAMWAY
EX. STRUCTURE
A501
120 SF
ELECTRICAL
ROOM
13215A
C
B
A
14' - 9 1/2" 19' - 6"
E Q
E Q
8' - 6"
/4
W1
W1
W1
W1 W1
W1
A1
A1
1A1
1A1
A1
A3
W2
A3
A3W1
A2
13210
S1.1A
13215A
13212A
13212B
B
B
A A A
AAAAAA
A504
FIRST FLOOR
ELEV: 100'-0"
EXTG. BASEMENT
ELEV: 95'-2"
FIRST FLOOR
ELEV: 100'-0"
FIRST FLOOR
ELEV: 100'-0"
EXTG. BASEMENT
ELEV: 95'-2"
A505
A505
DS
DS
DS
DS
1A1
FEC
A505
A2
EX.
MECHANICAL
RM
A701
A7012
S im
S im
A505
13215
A502
V .I .F
V .I .F
/8
8 8
8 8 8
/2
A505
FEC
FEC
R
IS
E
R S
/4
2' - 7 3/4"
S1.0
A505
A5
8' - 0"
V .I ,F
/1
A701 5
A503
DN
FD
FD HD
TELECOMM
CONDUITS
SPACE
TELECOMM
CONDUITS
SPACE
TELECOMM
CONDUITS
SPACE
DS
A5
A5
FCO
A5
23 24
DS
CG
CG
CG
CG CG
CG
CG
DS
DS
R
IS
E
R S
A3
CG
FCO
FD
V I.
F
V I.
F
/4
V I.
F
/4
V .I .F
VI.F
10"
VI.F
3' - 0"
VI.F
2' - 5"
A4
ELEV. PIT
ELEV: 91'-2"
CG
CG
14' - 7"
1. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR THE
COORDINATION OF ALL CONSTRUCTION WORK.
2. GENERAL CONTRACTOR SHALL REVIEW MECHANICAL, ELECTRICAL,
PLUMBING, AND FIRE PROTECTION PLANS FOR ADDITIONAL WORK.
3. MAINTAIN CONTINUOUS UTILITY SERVICE TO ALL SPACES IN THE
BUILDING NOT AFFECTED BY THIS WORK. COORDINATE WITH
VA COR ANY DISRUPTION IN SERVICES REQUIRED TO PERFORM WORK.
4. FIELD VERIFY AND COORDINATE LOCATIONS OF NEW VENT AND FAN
ROOF OPENING TO AVOID CONFLICT WITH EXISTING ROOF STRUCTURE
AND UTILITIES.
5. MAINTAIN THE WARRANTY OF THE INTEGRITY OF EXISTING ROOFING
ASSEMBLY.
6. ALL INTERIOR DIMENSIONS TAKEN FROM FINISHED WALL TO FINISHED
WALL
GENERAL NOTES
EXPANSION JOINT - SEE DETAIL SHEET A504
FLOOR PLAN- KEYNOTES
2 NEW WALL OPENING
3 MODIFY EXISTING MANHOLE - SEE CIVIL PLAN
4 FILL IN OPENING, MATCH EXISTING WALL CONSTRUCTION.
REFER TO STRUCTURAL DRAWINGS. PATCH AND REPAIR TO
MATCH EXISTING FINISHES.
5 MECHANICAL FLOOR OPENING - SEE MECHANICAL PLAN
6 PLUMBING CORED FLOOR OPENING - SEE PLUMBING PLAN
7 ROOF ACCESS LADDER
8 CARTS PROVIDED BY VA
9 MECHANICAL EQUIPMENT - SEE MECHANICAL PLAN
10 4" CONCRETE MECHANICAL EQUIPMENT PAD - SEE STRUCTURAL PLAN
11 EXISTING TELECOMM VAULT - SEE CIVIL AND STRUCTURAL PLAN
12 NEW TELECOMM EQUIPMENT - SEE ELECTRICAL PLAN
13 CRAC UNIT - SEE MECHANICAL PLAN
14 UPS UNITS - SEE ELECTRICAL PLAN
15 STAINLESS STEEL SECURITY MESH SCREENING ON EXTERIOR SIDE OF
WINDOW
16 ELECTRICAL EQUIPMENT - SEE ELECTRICAL PLAN
17 CLEAN AGENT TANKS - SEE FIRE PROTECTION PLAN
AREA TO BE MODIFIED BY GC. COORDINATE W/ ELECTRICAL CONTRACTOR
FOR REQUIRED OPENING SIZE.
19 METAL SAFETY CURB - SEE STRUCTURAL PLAN
20 RELOCATED DOWNSPOUT
21 NEW SUMP PUMP - SEE PLUMBING PLAN
22 PIV CARD READER WITH KEYPAD
23 PIV CARD READER WITH NO KEYPAD
24 PUSH BUTTON
25 PUSH BUTTON, CARD READER, PHONE
26 EXPANSION JOINT PLATE COVER
27 PATCH AND REPAIR EXISTING FINISHES WHEN DISTURBED BY DEMO
WORK. MATCH EXISTING
28 UNUSED
29 24X24 ACCESS PANEL - SEE PLUMBING PLAN
30 LOUVER - SEE MECHANICAL PLAN
31 42" HIGH SELF CLOSING SAFETY ACCESS GATE WITH "NO
EXIT" SIGN
32 PITCHED CONCRETE SLAB - SEE STRUCTURAL PLAN
33 STATIONARY ELEVATOR PIT LADDER. FOR LOCATION, COORDINATE WITH
ELEVATOR INSTALLER.
34 INFILL OLD SUMP PUMP WITH GRAVEL
35 FL FLOOR TYPE. OVER LAP AND SEAL NEW TO EXISTING VAPOR RETARDER.
36 3/4" FIRE RATED PLYWOOD W/ WALL BLOCKING - SEE ELECTRICAL
DRAWING ET102
37 FEC FOR CLEAN AGENT FIRE EXTINGUISHER
38 PROVIDE MACHINE ROOM LESS (MRL) HYDRAULIC ELEVATOR. SEE
SPECIFICATIONS.
1 HR FIRE RATED WALL
2 HR FIRE RATED WALL
FIRE RATED
SMOKE TIGHT
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT
LEADER:
Department of Veterans Affairs
CONSULTANTS
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS
TOMAH, WI 54660
MEDICAL CENTER
VETERANS
FULLY
500 E VETERANS
TOMAH, WI 54660
MEDICAL CENTER
VETERANS
FULLY
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY FULLY
KEY PLAN N
BLDG 32
T R
A M
W A
Y
BLDG 401
BLDG 32
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
AS101AS101
FINAL BID DOCUMENTS
676-21-701ARCHITECTURAL
FIRST FLOOR PLAN - NEW WORK
1/4" = 1'-0"AS101
1 FIRST FLOOR PLAN
1. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR THE
COORDINATION OF ALL CONSTRUCTION WORK.
2. GENERAL CONTRACTOR SHALL REVIEW MECHANICAL, ELECTRICAL,
PLUMBING, AND FIRE PROTECTION PLANS FOR ADDITIONAL WORK.
3. MAINTAIN CONTINUOUS UTILITY SERVICE TO ALL SPACES IN THE
BUILDING NOT AFFECTED BY THIS WORK. COORDINATE WITH
VA COR ANY DISRUPTION IN SERVICES REQUIRED TO PERFORM WORK.
4. FIELD VERIFY AND COORDINATE LOCATIONS OF NEW VENT AND FAN
ROOF OPENING TO AVOID CONFLICT WITH EXISTING ROOF STRUCTURE
AND UTILITIES.
5. MAINTAIN THE WARRANTY OF THE INTEGRITY OF EXISTING ROOFING
ASSEMBLY.
6. ALL INTERIOR DIMENSIONS TAKEN FROM FINISHED WALL TO FINISHED
WALL
GENERAL NOTES
EXPANSION JOINT - SEE DETAIL SHEET A504
FLOOR PLAN- KEYNOTES
2 NEW WALL OPENING
3 MODIFY EXISTING MANHOLE - SEE CIVIL PLAN
4 FILL IN OPENING, MATCH EXISTING WALL CONSTRUCTION.
REFER TO STRUCTURAL DRAWINGS. PATCH AND REPAIR TO
MATCH EXISTING FINISHES.
5 MECHANICAL FLOOR OPENING - SEE MECHANICAL PLAN
6 PLUMBING CORED FLOOR OPENING - SEE PLUMBING PLAN
7 ROOF ACCESS LADDER
8 CARTS PROVIDED BY VA
9 MECHANICAL EQUIPMENT - SEE MECHANICAL PLAN
10 4" CONCRETE MECHANICAL EQUIPMENT PAD - SEE STRUCTURAL PLAN
11 EXISTING TELECOMM VAULT - SEE CIVIL AND STRUCTURAL PLAN
12 NEW TELECOMM EQUIPMENT - SEE ELECTRICAL PLAN
13 CRAC UNIT - SEE MECHANICAL PLAN
14 UPS UNITS - SEE ELECTRICAL PLAN
15 STAINLESS STEEL SECURITY MESH SCREENING ON EXTERIOR SIDE OF
WINDOW
16 ELECTRICAL EQUIPMENT - SEE ELECTRICAL PLAN
17 CLEAN AGENT TANKS - SEE FIRE PROTECTION PLAN
AREA TO BE MODIFIED BY GC. COORDINATE W/ ELECTRICAL CONTRACTOR
FOR REQUIRED OPENING SIZE.
19 METAL SAFETY CURB - SEE STRUCTURAL PLAN
20 RELOCATED DOWNSPOUT
21 NEW SUMP PUMP - SEE PLUMBING PLAN
22 PIV CARD READER WITH KEYPAD
23 PIV CARD READER WITH NO KEYPAD
24 PUSH BUTTON
25 PUSH BUTTON, CARD READER, PHONE
26 EXPANSION JOINT PLATE COVER
27 PATCH AND REPAIR EXISTING FINISHES WHEN DISTURBED BY DEMO
WORK. MATCH EXISTING
28 UNUSED
29 24X24 ACCESS PANEL - SEE PLUMBING PLAN
30 LOUVER - SEE MECHANICAL PLAN
31 42" HIGH SELF CLOSING SAFETY ACCESS GATE WITH "NO
EXIT" SIGN
32 PITCHED CONCRETE SLAB - SEE STRUCTURAL PLAN
33 STATIONARY ELEVATOR PIT LADDER. FOR LOCATION, COORDINATE WITH
ELEVATOR INSTALLER.
34 INFILL OLD SUMP PUMP WITH GRAVEL
35 FL FLOOR TYPE. OVER LAP AND SEAL NEW TO EXISTING VAPOR RETARDER.
36 3/4" FIRE RATED PLYWOOD W/ WALL BLOCKING - SEE ELECTRICAL
DRAWING ET102
37 FEC FOR CLEAN AGENT FIRE EXTINGUISHER
38 PROVIDE MACHINE ROOM LESS (MRL) HYDRAULIC ELEVATOR. SEE
SPECIFICATIONS.
8' - 0"
1828 SF
COMPUTER
ROOM
33215
336 SF
CORRIDOR
33210
STAIR
S1
ELEV.
E1
2"
11' - 4" 4' - 8" 3' - 8" 2' - 0" 3' - 8" 7' - 8" 3' - 8" 2' - 8" 3' - 8" 7' - 0" 3' - 8" 2' - 6" 3' - 8" 5' - 6" 3' - 8" 5' - 8"
74' - 8"
/2
10' - 0 5/8"
1 HR.
V .I .F
V .I .F
2' - 8" 8' - 0" 2' - 8" 2' - 8" 3' - 8" 2' - 8" 3' - 8" 7' - 8" 3' - 8" 2' - 8" 3' - 8" 7' - 0" 3' - 8" 2' - 8" 3' - 8" 5' - 4" 3' - 8" 5' - 0"
2"
A302
A302
A501
A501
ROOF ACCESS
ROOM
33210A
ROOF OVERHANG
ROOF OVERHANG
R O
O F
O V
E R
H A
N G
C
B
A
W1
A3
W1
W1
A3W1
W1
W1
A2
A1
A1
A1
S1.2
B
B
B
A A A A A A A
AAAAAAA
A504
SECOND FLOOR
ELEV: 112'-0"
EX. ADP CHIEF
EX. ADP CHIEF
/8
/4
14' - 9 1/2" 19' - 6"
TELECOMM
CONDUITS
SPACE
/4
/4
5' - 10 5/8" 46' - 5 3/4"
E Q
E Q
S1.1B
A1A1A1
A1
A1
A1
1 HR
A502
74' - 8"
13 13
FEC
R
IS
E
R S
151515151515
15 15 151515
EXISTING BUILDING 401
A701
A503
EXISTING NEW CONSTRUCTION
HD
EXTG. FIRST FLOOR
ELEV: 104'-0"
TELECOMM
CONDUITS
SPACE
TELECOMM
CONDUITS
SPACE
DN
HD
A7013 4
DS
DS
DS
DS
DS
DS
DS
DS
EXISTING ROOF TO REMAIN.
HD HD
CG-1
CG-1
CG-1
CG-1
A3
A4
FEC
A6
5' - 5"
A6
5' - 1" 8' - 0"
/4
A6
1 HR FIRE RATED WALL
2 HR FIRE RATED WALL
FIRE RATED
SMOKE TIGHT
1/4" = 1'-0"AS102
1 SECOND FLOOR PLAN
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT
LEADER:
Department of Veterans Affairs
CONSULTANTS
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS
TOMAH, WI 54660
MEDICAL CENTER
VETERANS
FULLY
500 E VETERANS
TOMAH, WI 54660
MEDICAL CENTER
VETERANS
FULLY
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY FULLY
KEY PLAN N
BLDG 32
T R
A M
W A
Y
BLDG 401
BLDG 32
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
AS102AS102
FINAL BID DOCUMENTS
676-21-701ARCHITECTURAL
SECOND FLOOR PLAN - NEW
WORK
KEYED NOTES
1 ROOF HATCH
2 TAPERED INSULATION SADDLE/EDGE STRIP
3 HEAT CABLE ON NEW AND EXISTING ROOF
4 COMPOSITE SLATE ROOF TILE SYSTEM - R2
ROOF TYPE
5 HIP VENT
6 WALKWAY PROTECTION PAD
ASPHALT SHINGLES - R4 ROOF TYPE
INTERLOCK NEW SHINGLES WITH EXISTING
8 VTR - SEE PLUMBING DRAWINGS
9 DAVIT CRANE 1000LB LIFT CAPACITY
REACH 27.5 TO 42 IN - SEE
STRUCTURAL FOR ANCHORING
INSTALL
10 36" x 36" EXTERIOR ACCESS PANEL
VALLEY FLASHING W/ 3'-0" WIDE ICE &
WATER SHIELD
A302
EQ 51' - 6 3/8" EQ
E Q
/4
E
Q
EXISTING ROOF TO REMAIN.
EXISTING ROOF TO REMAIN
A505
A505
A505
AS103
AS103
ROOF TOP UNIT -
SEE MECHANICAL
DRAWINGS
ROOF TOP UNIT -
SEE MECHANICAL
DRAWINGS
R.D
OVERFLOW
DS
DS
DS
DS
4 4
NEW ROOF
INTAKE HOOD -
SEE MECHANICAL
DRAWINGS
AS103
6 6
6 6 6 6 6 6 6 6 6 6 6
5 5
A503
EXISTING NEW CONSTRUCTION
DS
/4
/F
T
/4
/F
T
VTR
VTR
VTR
DS
DS
5" / 1'-0" 5" / 1'-0"
'-0
'-0
A505
A505
1/4" /FT
1/4" /FT
E Q
E Q
7' - 0"
7' - 0"
7' - 0"
7' - 0"
10 10
33210B
AIR & VAPOR BARRIER BEHIND
COMPOSITE FLASHING
THROUGH - WALL COMPOSITE FLASHING
W/ METAL DRIP EDGE AND END DAMS
EXTEND ROOF VAPOR RETARDER
4" ABOVE TOP OF ROOF AND SEAL
TO AIR & VAPOR BARRIER W/ NON
HARDENING SEALANT
R3
W1
BOND BEAM -
SEE
STRUCTURAL
DRAWINGS
M
IN
PROVIDE WEEPS/VENTS @ 24" O.C
SHEET MEMBRANE OVER 1/2" EXTERIOR
GRADE PLYWOOD SHEATHING OVER 6"
METAL STUD
WRAP UP AND OVER PARAPET WALL
ROOF HATCH
ALUMINUM COPING
2X WOOD BLOCKING
ALUMINUM FASCIA
R1
R2
A1
A1FIXED ROOF LADDER
PROVIDE WALL
BLOCKING AS REQUIRED
EXTENSION LADDER
ROOF RAIL
DAVIT CRANE
B.O.S 118' - 0"
T.O.M 128' - 0"
STEP FLASHING
DOWNSPOUT
EXISTING WALL
R2
R3
ROOF DRAIN
OVERFLOW
3" MIN INSULATION
THICKNESS @
DRAIN
SEAL ROOF VAPOR
RETARDER TO TOP OF
ROOF SUMP PAN W/
NON-HARDENING
SEALANT
R1
2 1/4"
CANT STRIP
COUNTERFLASHING
2X TREATED WOOD NAILER
ROOF MEMBRANE
M
IN
V
A R
IE
S
PRE MANUFACTURED ROOF CURB
RIGID INSULATION
ROOF TOP UNIT
R1
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY SPRINKLEREDFULLY SPRINKLERED
KEY PLAN N
BLDG 32
T R
A M
W A
Y
BLDG 401
BLDG 32
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
AS103AS103
FINAL BID DOCUMENTS
676-21-701ARCHITECTURAL
ROOF PLAN - NEW WORK
1/4" = 1'-0"AS103
1 ROOF PLAN
N
1 1/2" = 1'-0"AS103
2 ROOF CONNECTION DETAIL
1" = 1'-0"AS103
3 DETAIL @ ROOF HATCH
1/4" = 1'-0"AS103
4 ROOF ELEVATION
1 1/2" = 1'-0"AS103
5 ROOF DRAIN DETAIL
1 1/2" = 1'-0"AS103
6 ROOF CURB DETAIL
S
S S S
S
S
S
S
S
S
S S
S
S
S
S
S
SS
C
B
A
CORRIDOR
13211
CORRIDOR
13212
ELECTRICAL
ROOM
13215A
MECHANICAL
ROOM
13215
CORRIDOR
13210
STAIR
S1
ELEV.
E1
EXPOSED CEILING
9'-0"
9'-0"
MECHANICAL
OPENINGS - SEE
MECHANICAL
PLAN
9'-0"
EXPOSED CEILING
EXISTING NEW CONSTRUCTION
EXPOSED CEILING
GYP
MECHANICAL
OPENINGS - SEE
MECHANICAL
PLAN
PLUMBING
OPENINGS - SEE
PLUMBING PLAN
1. REFER TO SHEET GC102 FOR PHASING PLANS. ALL WORK TO BE DONE IN
ACCORDANCE WITH THE PHASES IDENTIFIED.
2. GENERAL CONTRACTOR SHALL REVIEW MECHANICAL, ELECTRICAL,
PLUMBING AND FIRE PROTECTION PLANS FOR ADDITIONAL
CONSTRUCTION WORK.
3. GENERAL CONTRACTOR IS RESPONSIBLE FOR THE COORDINATION OF
ALL CONSTRUCTION WORK.
4. MAINTAIN CONTINUOUS UTILITY SERVICE TO ALL SPACES IN THE
BUILDING NOT AFFECTED BY THIS WORK. COORDINATE WITH VA COR
ANY DISRUPTION IN SERVICES REQUIRED TO PERFORM WORK.
5. PATCH ALL SURFACES DISTURBED BY DEMOLITION TO CREATE A
SMOOTH AND CONSISTENT FINISH WITH ADJACENT MATERIALS. TYPICAL
AT FLOORS, WALLS, AND CEILINGS.
6. PERIMETER CEILING TILES SHALL NOT BE LESS THAN 4" WIDE.
7. LOCATE ALL SPRINKLER HEADS, SMOKE DETECTORS, AUDIO SPEAKERS,
AND HEAT SENSORS IN THE CENTER OF CEILING TILE.
8. DESIGN-BUILD FIRE PROTECTION CONTRACTOR SHALL PROVIDE THE
REQUIRED NUMBER OF SPRINKLER HEADS FOR FULL ROOM COVERAGE.
GENERAL NOTES
PATCH AND REPAIR CEILING WHERE DISTURBED BY DEMO WORK.
MATCH EXISTING
KEYED NOTES
ACCESS PANEL - SEE MECHANICAL DRAWINGS2
5/8" GYP BOARD SOFFIT ON 2
1/2"" METAL FRAMING
GWB SOFFIT
7'-0" AFF
A.C.T
9'-0" AFF
ACCESS PANEL - SEE
MECHANICAL
DRAWINGS
ACOUSTIC CEILING TILE
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY SPRINKLEREDFULLY SPRINKLERED
KEY PLAN N
BLDG 32
T R
A M
W A
Y
BLDG 401
BLDG 32
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
AC101AC101
FINAL BID DOCUMENTS
676-21-701ARCHITECTURAL
REFLECTED CEILING PLAN - FIRST
FLOOR
1/4" = 1'-0"AC101
1 REFLECTED CEILING PLAN - FIRST FLOOR
1" = 1'-0"AC101
2 SOFFIT DETAIL
S
C
B
A
COMPUTER
ROOM
33215
STAIR
S1
ELEV.
E1
ROOF ACCESS
ROOM
33210A
CORRIDOR
33210
10'-0"
EXPOSED CEILING
EXPOSED CEILING
EX. BUILDING 401
EXISTING ROOF
EXISTING NEW CONSTRUCTION
ROOF OVERHANG
PLUMBING
OPENINGS -
SEE
PLUMBING
PLAN
MECHANICAL
OPENINGS -
SEE
MECHANICAL
PLAN
16X8 METAL SOFFIT VENT16X8 METAL SOFFIT VENT16X8 METAL SOFFIT VENT16X8 METAL SOFFIT VENT
16X8 METAL SOFFIT VENT 16X8 METAL SOFFIT VENT 16X8 METAL SOFFIT VENT 16X8 METAL SOFFIT VENT
X M
E T
A L S
O F
F
IT
V E
N T
X M
E T
A L S
O F
F
IT
V E
N T
X M
E T
A L S
O F
F
IT
V E
N T
X M
E T
A L S
O F
F
IT
V E
N T
2' - 0"
2' - 0"
LINEAR METAL SOFFIT
L
IN
E A
R M
E T
A L
S O
F F
IT
L
IN
E A
R M
E T
A L
S O
F F
IT
L
IN
E A
R M
E T
A L
S O
F F
IT
LINEAR METAL SOFFIT LINEAR METAL SOFFIT
1. REFER TO SHEET GC102 FOR PHASING PLANS. ALL WORK TO BE DONE IN
ACCORDANCE WITH THE PHASES IDENTIFIED.
2. GENERAL CONTRACTOR SHALL REVIEW MECHANICAL, ELECTRICAL,
PLUMBING AND FIRE PROTECTION PLANS FOR ADDITIONAL
CONSTRUCTION WORK.
3. GENERAL CONTRACTOR IS RESPONSIBLE FOR THE COORDINATION OF
ALL CONSTRUCTION WORK.
4. MAINTAIN CONTINUOUS UTILITY SERVICE TO ALL SPACES IN THE
BUILDING NOT AFFECTED BY THIS WORK. COORDINATE WITH VA COR
ANY DISRUPTION IN SERVICES REQUIRED TO PERFORM WORK.
5. PATCH ALL SURFACES DISTURBED BY DEMOLITION TO CREATE A
SMOOTH AND CONSISTENT FINISH WITH ADJACENT MATERIALS. TYPICAL
AT FLOORS, WALLS, AND CEILINGS.
6. PERIMETER CEILING TILES SHALL NOT BE LESS THAN 4" WIDE.
7. LOCATE ALL SPRINKLER HEADS, SMOKE DETECTORS, AUDIO SPEAKERS,
AND HEAT SENSORS IN THE CENTER OF CEILING TILE.
8. DESIGN-BUILD FIRE PROTECTION CONTRACTOR SHALL PROVIDE THE
REQUIRED NUMBER OF SPRINKLER HEADS FOR FULL ROOM COVERAGE.
GENERAL NOTES
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY SPRINKLEREDFULLY SPRINKLERED
KEY PLAN N
BLDG 32
T R
A M
W A
Y
BLDG 401
BLDG 32
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
AC102AC102
FINAL BID DOCUMENTS
676-21-701ARCHITECTURAL
REFLECTED CEILING PLAN -
SECOND FLOOR
1/4" = 1'-0"AC102
1 REFLECTED CEILING PLAN - SECOND FLOOR
LEGEND
RIGID VINYL WALL COVERING
4' CORNER GUARD
RWC-1
CG-1
LVT-1 LUXURY VINYL TILE
LVT-2 LUXURY VINYL TILE
RES-3 RESINOUS EPOXY FLOORING
8' STAINLESS STEEL
CORNER GUARDCG-2
RF-1 - RUBBER FLOORING
HANDRAIL
HR-1
C
B
A
ELEV.
E1
STAIR
S1
MECHANICAL
ROOM
13215
CORRIDOR
13211
ELECTRICAL
ROOM
13215A
CORRIDOR
13210
CORRIDOR
13212
CG-2
RWC -1
CG-2
CG-1
CG-1
CG-1
CG-1
CG-1
RWC -1RWC -1
RWC -1
R W
C
R W
C
RES-3
LVT-1
LVT-2
LVT-2
LVT-1
LVT-2
RF-1
RF
EPY
EPY
CG-1
CG-2
CG-2
H R
-1
H R
-1
H R
-1
H R
-1
1' - 0"1' - 0"
RF-1
1. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR THE
COORDINATION OF ALL CONSTRUCTION WORK.
2. GENERAL CONTRACTOR SHALL REVIEW MECHANICAL, ELECTRICAL,
PLUMBING, AND FIRE PROTECTION PLANS FOR ADDITIONAL WORK.
3. MAINTAIN CONTINUOUS UTILITY SERVICE TO ALL SPACES IN THE
BUILDING NOT AFFECTED BY THIS WORK. COORDINATE WITH
VA COR ANY DISRUPTION IN SERVICES REQUIRED TO PERFORM WORK.
4. PROTECT EXISTING FINISHES TO REMAIN.
5. PROVIDE REQUIRED CONCRETE FLOOR LEVELING FOR SMOOTH FINISH.
6. LOCATE FLOOR FINISH TRANSITION TO CENTER OF DOOR SLAB.
GENERAL NOTES
PATCH FLOOR TO MATCH EXISTING
KEYED NOTES
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
Office of Facilities
Management
B
A
C
D
E
F
97 8654321
F
E
D
C
B
A
1 2 3 4 5 6 87 9
FULLY SPRINKLEREDFULLY SPRINKLERED
KEY PLAN
BLDG 32
T R
A M
W A
Y
BLDG 401
BLDG 32
EHRM INFRASTRUCTURE
UPGRADES TIER 2
VA MEDICAL CENTER TOMAH, WI
FEB. 4, 2022 HB GR
AF101AF101
FINAL BID DOCUMENTS
676-21-701
FIRST FLOOR FINISHES PLAN
1/4" = 1'-0"AF101
1 FIRST FLOOR FINISHED PLAN
C
B
A
COMPUTER
ROOM
33215
CORRIDOR
33210
ROOF ACCESS
ROOM
33210ASTAIR
S1
ELEV.
E1
CG-1
CG-1
CG-1
CG-1
RWC -1
LVT-1
LVT-2
LVT-2
LVT-2
LVT-2
LVT-2
R W
C
R W
C
RF-1
RF-1
SDT
A505
1' - 0"1' - 0"
1. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR THE
COORDINATION OF ALL CONSTRUCTION WORK.
2. GENERAL CONTRACTOR SHALL REVIEW MECHANICAL, ELECTRICAL,
PLUMBING, AND FIRE PROTECTION PLANS FOR ADDITIONAL WORK.
3. MAINTAIN CONTINUOUS UTILITY SERVICE TO ALL SPACES IN THE
BUILDING NOT AFFECTED BY THIS WORK. COORDINATE WITH
VA COR ANY DISRUPTION IN SERVICES REQUIRED TO PERFORM WORK.
4. PROTECT EXISTING FINISHES TO REMAIN.
5. PROVIDE REQUIRED CONCRETE FLOOR LEVELING FOR SMOOTH FINISH.
6. LOCATE FLOOR FINISH TRANSITION TO CENTER OF DOOR SLAB.
GENERAL NOTES
LEGEND
RIGID VINYL WALL COVERING
4' CORNER GUARD
RWC-1
CG-1
LVT-1 LUXURY VINYL TILE
LVT-2 LUXURY VINYL TILE
RES-3 RESINOUS EPOXY FLOORING
8' STAINLESS STEEL
CORNER GUARDCG-2
RF-1 - RUBBER FLOORING
HANDRAIL
HR-1
PATCH FLOOR TO MATCH EXISTING
KEYED NOTES
3770 S. PENNSYLVANIA AVENUE, UNIT 8
ST. FRANCIS, WISCONSIN 53235
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked By
Building Number
Project Number
Drawing Number
Drawn By
PROJECT LEADER:
Department of Veterans Affairs
CONSULTANTS:
o n e e ig h th in ch o n e f o o t th re e in ch e s o n e f o o t o n e a n d o n e h a lf in ch e s o n e f o o t o n e in ch o n e f o o t th re e q u a rt e rs in ch o n e f o o t o n e h a lf in ch o n e f o o t th re e e ig h th s in ch o n e f o o t o n e q u a rt e r in ch o n e f o o t
VA FORM 08-6231, OCT 1978
500 E VETERANS ST
TOMAH, WI 54660
MEDICAL CENTER
VETERANS AFFAIRS
FULLY SPRINKLERED
500 E VETERANS ST
TOMA…