Tech Questions from Site Visit - Tomah T2 - 4-20-22.pdf

PDF 103 KB Posted

Attached to
Y1EZ--EHRM Infrastructure Upgrades Tier 2 Construction - Tomah VAMC 676-21-701
Solicitation number
36C77622B0025
Issued by

About this file

This document contains technical questions and responses related to a construction project at the Tomah VA Medical Center. The project involves expanding building 32 to incorporate a new data center and correct facility deficiencies. There will be 6 employees on site during construction, with 3 upstairs and 3 downstairs. The IT systems must remain operational with minimal disruptions scheduled mid-week. The fire alarm system is radio operated separately from the campus and is dust sensitive, requiring coordination for work in the existing data center. Standard contractor badges and VA escorts are required for the data center. Connectivity must be maintained to building 23 during tramway construction.

View the file

Other files

File Type Posted
36C77622B0025 0006.pdf PDF
C102 - Contractor Markup for Question 35.pdf PDF
P001 - COR Markup for Response 35.pdf PDF
36C77622B0025 0005.pdf PDF
Reference Pictures for Question 29.pdf PDF
Tech Questions - Tomah T2 - 5-12-22.pdf PDF
EP100.pdf PDF
36C77622B0025 0004.pdf PDF
Att 9 - DBA Wage Rates - Monroe County - 04-29-22.pdf PDF
Updated Drawings - ELECTRICAL_ADD1.pdf PDF
36C77622B0025 0003.pdf PDF
Updated Drawings - CIVIL ADD1.pdf PDF
Tech Questions - Tomah T2 - 5-5-22.pdf PDF
Updated Specs - 055000 Metal Fabrications.pdf PDF
36C77622B0025 0002.pdf PDF
Tech Questions - Tomah T2 - 4-28-22.pdf PDF
36C77622B0025 0001.pdf PDF
Site Visit Sign-in Sheet - Tomah Tier 2.pdf PDF
Tomah Tier 2 IFB 36C77622B0025 - 4-6-22.pdf PDF
Att 9 - DBA Wage Rates - Monroe County - 03-18-22.pdf PDF
Att 3 - Final Drawings 1 of 4.pdf PDF
Att 7 - VHA Supp Contract Reqs COVID-19 - 12-14-21.pdf PDF
Att 8 - Limitations on Subcontracting - Construction.docx DOCX document
Att 6 - Final Drawings 4 of 4.pdf PDF
Att 11 - Tomah VAMC - EHRM Tier 2 - Site Visit Map.pdf PDF
Att 10 - Contractor Safety - Enviro Record Eval Form.docx DOCX document
Att 5 - Final Drawings 3 of 4.pdf PDF
Att 1 - Final Specifications Vol 1.pdf PDF
Att 4 - Final Drawings 2 of 4.pdf PDF
Att 2 - Final Specifications Vol 2.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND

RESPONSES TRACKING SHEET

SOLICITATION #

36C77622B0025

PROJECT TITLE

Tomah EHRM Tier 2 Construction Project

# RECEIVED

DATE

ANSWERED

DATE

CONTRACTOR QUESTIONS VA RESPONSES TO QUESTIONS

1 4/19/22 4/20/22 How many employees will be in the space during construction?

There will be 6 employees total - 3 upstairs and 3 downstairs.

2 4/19/22 4/20/22 Is there backup for the IT systems? There is no backup for IT systems - must stay up for duration of project with minimum disruptions and scheduled outages. All scheduled outages should be mid-week to accommodate IT coordination.

3 4/19/22 4/20/22 Does facility fire alarm system run through B32? No - fire alarm system is radio operated from a separate facility on campus.

Fire alarm system in Data centers is dust sensitive. Cutting or creating dust in existing data center must be coordinated with fire department and IT to ensure fire system does not activate during construction.

4 4/19/22 4/20/22 How is access for Data Center during construction? A standard contractor badge is required along with a VA-provided escort while in data center.

5 4/19/22 4/20/22 How is connectivity during construction between B 32 and 23 during tramway construction?

The contractor must maintain connectivity to B23.