Atch 8 General Conditions Breakout.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Z1DA--Project 626A4-22-104_Video Surveillance Security TVHS VAMC - Alvin C. York Campus
Solicitation number
36C24926R0064
Issued by

About this file

This is a General Conditions Breakout template for construction contract pricing submissions, required by the Veterans Affairs Acquisition Regulation (VAAR) 852.243-70 for construction contract changes. The document establishes that contractors must provide a detailed breakdown of General Conditions costs when submitting a Schedule of Values, with the contractual restriction that overhead and fee percentages must include insurance, supervisory personnel, security, small tools, job burdens, and home office expenses with no separate allowances permitted.

The template categorizes General Conditions costs into three primary sections: Project Management (including superintendent, safety manager, CPM scheduler, quality assurance, project managers, field office staff, and project expeditor positions); Bonds and Insurance (builder's risk insurance, general liability insurance, and security/payment/performance bonds); and Site Conditions (encompassing temporary utilities, SWPPP measures, security systems, temporary structures, protective measures, and documentation requirements such as pre-construction and progress photography). All line items in the template are currently set to zero dollars, indicating this is a blank form to be completed by the contractor with actual cost estimates for the specific construction project.

View the file

Other files

File Type Posted
S06 AMEND_7 36C24926R0064 0007-York Campus.pdf PDF
S02 AMEND-6_36C24926R0064 0006 MUR.pdf PDF
S02 36C24926R0064 0005 VIDEO -YORK.pdf PDF
Atch 24 JA Brand Name Avigilon VIDEO 626A4-22-104 MUR_Redacted.pdf PDF
S02 AMEND_4 36C24926R0064 0004.pdf PDF
S02 AMEND 36C24926R0064 0003 Protest.pdf PDF
Atch 1 Video camera design changes- York.pdf PDF
S02 AMEND 36C24926R0064 0002 VIDEO-York.pdf PDF
S02 AMEND 36C24926R0064 0002 VIDEO-York.pdf PDF
Atch 1 Video camera design changes.pdf PDF
Atch 1 Site Visit Sign In Sheet 626A4-22-104 _York.pdf PDF
S02 AMEND_1 36C24926R0064 0001 VIDEO York.pdf PDF
S02 36C24926R0064_1 VIDEO 626A4-22-104 YORK.pdf PDF
Atch 18 22-215Y BD Dwgs _Part8.pdf PDF
Atch 14 22-215Y BD Dwgs _Part4.pdf PDF
Atch 13 22-215Y BD Dwgs _Part3.pdf PDF
Atch 11 22-215Y BD Dwgs _Part1.pdf PDF
Atch 9 Price Breakout Schedule.xlsx XLSX spreadsheet
Atch 2 WD SCA 2015-4647 REV31 _05.13.2026 Rutherford-Davidson.docx DOCX document
36C24926R0064_1.docx DOCX document
Atch 23 SF1442 36C24926R0064_2.pdf PDF
Atch 19 HotWorkPermit.pdf PDF
Atch 16 22-215Y BD Dwgs _Part6.pdf PDF
Atch 7 Contractor EMR Certification Form.docx DOCX document
Atch 6 Calc. of Self Performed Work.xlsx XLSX spreadsheet
Atch 4 UEI _ TAX ID.docx DOCX document
Atch 22 JA Brand Name JCI VIDEO 626A4-22-104 MUR_1_Redacted.pdf PDF
Atch 17 22-215Y BD Dwgs _Part7.pdf PDF
Atch 12 22-215Y BD Dwgs _Part2.pdf PDF
Atch 10 22-215Y BD Specs.pdf PDF
Atch 5 RFI Form.docx DOCX document
Atch 21 JA Brand Name Avigilon VIDEO 626A4-22-104 MUR_2_Redacted.pdf PDF
Atch 20 Fire-Smoke Barrier Permit.doc DOC document
Atch 15 22-215Y BD Dwgs _Part5.pdf PDF
Atch 3 Past Performance Questionnaire York.docx DOCX document
Atch 1 WD DBA-TN20260187 BUILDING MOD-0 01.02.2026 - MUR.docx DOCX document
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GC Breakout

GENERAL CONDITIONS BREAKOUT
When entering a line item for General Conditions costs on Schedule of Values, a breakout of the General Conditions costs must be provided. Per VAAR 852.243-70 Construction Contract Changes-Supplement, paragraph (c)(1), the following contractual restrictions apply: Overhead and Contractor's fee percentages shall be considered to include insurance other than mentioned herein, field and office supervisors and assistants, security police, use of small tools, incidental job burdens, and general home office expenses and no separate allowance will be made. Assistants to office supervisors include all clerical, stenographic and general office help. Incidental job burdens include, but are not necessarily limited to, office equipment and supplies, temporary toilets, telephone and conformance to OSHA requirements. Items such as, but not necessarily limited to, review and coordination, estimating and expediting relative to contract changes are associated with field and office supervision and are considered to be included in the Contractor's overhead and/or fee percentage.
General Condition DescriptionValue
Project Management:$ - 0
Superintendent(s)$ - 0
Safety Manager$ - 0
CPM Scheduler$ - 0
Quality Assurance/Quality Control$ - 0
Project Manager (s)$ - 0
Project Executive$ - 0
Field Office Engineer$ - 0
Field Office Support Staff$ - 0
Project Expeditor$ - 0
Assistant Superintendent (s)$ - 0
Project Manager Subtotal:$ - 0
Bonds and Insurance (excluding any for Subcontractors):$ - 0
Builder’s Risk Insurance$ - 0
General Liability Insurance$ - 0
Security, Payment & Performance Bonds$ - 0
Bonds and Insurance Subtotal:$ - 0
Site Conditions:$ - 0
Temporary Power Consumption (Offices)$ - 0
Temporary Power Consumption (General Site Use)$ - 0
Temporary Water and Sewer Consumption$ - 0
Temporary Water Hookup, Distribution & Meters$ - 0
Temporary Electrical Hookup, Distribution & Meters$ - 0
Temporary Telephone & Network System Installation$ - 0
Temporary Telephone & Internet Consumption Fees$ - 0
Temporary Fire Protection$ - 0
Temporary Heating & Cooling$ - 0
Temporary Fencing$ - 0
Temporary Covered Walkways$ - 0
SWPPP Measures$ - 0
Temporary Entries and Truck Washes$ - 0
Street Cleaning (by G.C.)$ - 0
Traffic Control Measures$ - 0
Temporary Barricades & Signage$ - 0
Temporary Roads & Walkways (install & maintenance)$ - 0
Temporary Lighting$ - 0
Temporary Partitions & Covered Floor Openings$ - 0
Temporary Toilets/Sanitary Measures$ - 0
Temporary Laydown (prep and restoration)$ - 0
Security System/Watchman$ - 0
Pre-construction Photo Documentation$ - 0
Progress Photos$ - 0
Temporary Protection (in place work/adjacent structures)$ - 0
$ - 0
$ - 0
$ - 0
General Conditions Total$ - 0