Atch 13 22-215Y BD Dwgs _Part3.pdf
PDF 2 MB Posted
- Solicitation number
- 36C24926R0064
About this file
These are architectural bid documents for a Video Surveillance Security improvement project at Alvin C. York Campus (3400 Lebanon Road, Murfreesboro, TN 37129), a U.S. Department of Veterans Affairs facility. The project, identified as VA Project Number 22-215 with ACG Project Number 626A4-22-104, involves the installation of new security camera systems and associated infrastructure across multiple buildings. The scope includes removal of existing cameras and cabling, installation of new cameras with 4-pair UTP cabling runs from cameras to new POE switches located in telecom rooms, and routing of multimode fiber (MMF) from telecom rooms to racks in Building 5's server room. The contractor must repair or replace surfaces affected by equipment removal and installation, including damaged ceiling tiles and grid systems at no additional cost to the government.
The security plans cover multiple buildings (Buildings 2, 3, 4, and associated structures like Buildings 117 and 149) with ground and first floor configurations specified. General construction requirements include running CCTV cabling on J-hooks at 2-foot on-center spacing above ceilings in corridors, using minimum 3/4-inch conduit sized per the National Electrical Code, and employing fiber optic cable for camera-to-rack distances exceeding 295 feet. All work must coordinate with the Contracting Officer Representative (COR) and OIT representative prior to rough-in, implement ICRA containment measures per Sheet G-100, and utilize mobile containment carts in corridors. The documents, prepared by Apogee Consulting Group P.A. and dated June 13, 2024, are designated as fully sprinklered bid documents for contractor pricing and execution.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 2 3 4
TR ROOM G20B:
5 PR SPARE MMF
6 PR SPARE SMF
2RM 'G20B'
RM 'G20B'
RM 'G20B'
RM 'G20B'
RM 'G20B'
RM 'G20B'
RM 'G20A'
RM 'G20B'
RM 'G20B'
RM 'G20B'
RM 'G20B'
RM 'G20B'
H6 N #29
N #27
H5A FE
N #25
N #28
H6 N #30
SW
N #35
H5A DH
N #23
H5A DH
N #24
H6 N #31
H6 N #32
H5A FE
N #26
B U
IL
D
IN
G
B U
IL
D
IN
G
BUILDING 2
BUILDING 117
H6 N #33
RM 'G20B'
H6 N #34
RM 'G20B'
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/2
/2
:2
:3
P
M C
U s e rs
\l s ta rn e s \D o c u m e n ts
\E -2
-2
Y
-V A
Y o rk
-V id e o S e c I m p ro v -T
N ls ta rn e s C
B U
M B
.r v t
2.T-101
BULDING 2 GROUND FLOOR SECURITY
PLAN
6 26LAS
VIDEO SURVEILLANCE
SECURITY YORK
ALVIN C. YORK CAMPUS
3400 LEBANON ROAD
MURFREESBORO, TN 37129 JUNE 13, 2024
BID DOCUMENTS
626A4-22-10422-215
JVE
Scale: 1/8" = 1'-0"
BUILDING 2 GROUND FLOOR SECURITY PLAN
1 REMOVE EXISTING CAMERAS AND CABLING
BACK TO SOURCE. REPAIR/REPLACE
EXISTING SURFACES AFFECTED BY
REMOVAL OF CAMERA EQUIPMENT TO
MATCH SIMILAR EXISTING CONDITIONS.
2 INSTALL NEW CAMERAS. PROVIDE NEW 4 PR
UTP CABLING FROM CAMERA TO NEW POE
SWITCH IN TELECOM ROOM. REPAIR/
REPLACE SURFACES AFFECTED BY CAMERA
EQUIPMENT INSTALLATION TO MATCH
SIMILAR/EXISTING CONDITIONS.
CONTRACTOR TO REPLACE DAMAGED
CEILING TILE AND GRID ASSOCIATED WITH
WORK AT NO ADDITIONAL COST TO
GOVERNMENT.
3 PROPOSED LOCATION OF NEW CISCO 9300
SWITCH AND PATCH PANEL. VERIFY
LOCATION WITH COR AND OIT
REPRESENTATIVE.
4 ROUTE MMF FROM TELECOM ROOM TO
RACKS IN BUILDING 5 SERVER ROOM.
N O
R T
H
0 4 8 16
A. REFERENCE SHEET TS101 AND TS102 FOR
EXTERIOR CAMERA LOCATIONS.
B. ALL EXISTING CONDITIONS ARE BASED ON THE
BEST AVAILABLE INFORMATION AT THE TIME
OF SURVEY.
C. NEW CCTV CABLING TO BE RUN ON J-HOOKS 2'
OC ABOVE CEILING IN CORRIDORS.
D. ALL CONDUIT SHALL BE 3/4" MINIMUM.
ELECTRICAL CONTRACTOR TO SIZE CONDUIT.
PER THE MOST CURRENT EDITION OF THE NEC.
E. WHERE LENGTH FROM CAMERA TO RACK
EQUIPMENT EXCEEDS 295' (90M) CONTRACTOR
SHALL USE FIBER OPTIC CABLE.
F. COORDINATE AND CONFIRM ALL ROUTING
WITH COR PRIOR TO ROUGH-IN.
G. SEE SHEET G-100 FOR ICRA MEASURES.
H. USE MOBILE CONTAINMENT CART (6/G-100)
ALONG CORRIDORS.
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
Docusign Envelope ID: B9B77CD2-F0C1-4BAA-8538-6B315B443E44
7/24/2024
TR ROOM G03A
3 PR SPARE MMF
6 PR SPARE SMF
1 2 3 4
1 2
1 1
1 21 2
1 2
1 1
RM 'G03A'
H6SL
N #61
H6 N #50
H5A FE
N #43
H6 N #51
H5A FE
N #44
H5A FE
N #45
H6 N #52
H5A FE
N #46
H6 N #210
N #203
H6 N #212
H6 N #53
H5A FE
N #47H6
N #54
FIXED
RVFIXED
RV
FIXED
RV
H6
RP
#55
H6
RP
#56
H6
RP
#57
H6
RP
#58
FIXED
RV
FIXED
RV
FIXED
RV
FIXED
RV
FIXED
RV
FIXED
RV
H6 N #59
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
B U
IL
D
IN
G
B U
IL
D
IN
G
BUILDING 149
BUILDING 117
BUILDING 117
BUILDING 3
RM 'G03A'
FIXED
RV
H5A FE
N #48
H6 N #60
RM 'G03A'
H5A FE
N #49
RM 'G03A'
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/2
/2
:2
:5
P
M C
U s e rs
\l s ta rn e s \D o c u m e n ts
\E -2
-2
Y
-V A
Y o rk
-V id e o S e c I m p ro v -T
N ls ta rn e s C
B U
M B
.r v t
3.T-101
BUILDING 3 GROUND FLOOR SECURITY
PLAN
7 26LAS
VIDEO SURVEILLANCE
SECURITY YORK
ALVIN C. YORK CAMPUS
3400 LEBANON ROAD
MURFREESBORO, TN 37129 JUNE 13, 2024
BID DOCUMENTS
626A4-22-10422-215
JVE
Scale: 1/8" = 1'-0"
BUILDING 3 GROUND FLOOR SECURITY PLAN
1 REMOVE EXISTING CAMERAS AND CABLING
BACK TO SOURCE. REPAIR/REPLACE
EXISTING SURFACES AFFECTED BY
REMOVAL OF CAMERA EQUIPMENT TO
MATCH SIMILAR EXISTING CONDITIONS.
2 INSTALL NEW CAMERAS. PROVIDE NEW 4 PR
UTP CABLING FROM CAMERA TO NEW POE
SWITCH IN TELECOM ROOM. REPAIR/
REPLACE SURFACES AFFECTED BY CAMERA
EQUIPMENT INSTALLATION TO MATCH
SIMILAR/EXISTING CONDITIONS.
CONTRACTOR TO REPLACE DAMAGED
CEILING TILE AND GRID ASSOCIATED WITH
WORK AT NO ADDITIONAL COST TO
GOVERNMENT.
3 PROPOSED LOCATION OF NEW CISCO 9300
SWITCH AND PATCH PANEL. VERIFY
LOCATION WITH COR AND OIT
REPRESENTATIVE.
4 ROUTE MMF FROM TELECOM ROOM TO
RACKS IN BUILDING 5 SERVER ROOM.
N O
R T
H
0 4 8 16
A. REFERENCE SHEET TS101 AND TS102 FOR
EXTERIOR CAMERA LOCATIONS.
B. ALL EXISTING CONDITIONS ARE BASED ON THE
BEST AVAILABLE INFORMATION AT THE TIME
OF SURVEY.
C. NEW CCTV CABLING TO BE RUN ON J-HOOKS 2'
OC ABOVE CEILING IN CORRIDORS.
D. ALL CONDUIT SHALL BE 3/4" MINIMUM.
ELECTRICAL CONTRACTOR TO SIZE CONDUIT.
PER THE MOST CURRENT EDITION OF THE NEC.
E. WHERE LENGTH FROM CAMERA TO RACK
EQUIPMENT EXCEEDS 295' (90M) CONTRACTOR
SHALL USE FIBER OPTIC CABLE.
F. COORDINATE AND CONFIRM ALL ROUTING
WITH COR PRIOR TO ROUGH-IN.
G. SEE SHEET G-100 FOR ICRA MEASURES.
H. USE MOBILE CONTAINMENT CART (6/G-100)
ALONG CORRIDORS.
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
RM 'G03A'
BUILDING 117
BUILDING 3
BUILDING 117
BUILDING 3
H6SL
N #67
H6 N #66
H6SL
N #68
H5A FE
N #63
SW
N #69
N #65
H5A DH
N #62
N #64
SW
N #70
RM 'G03A'
RM 'G03A'
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/2
/2
:2
:5
P
M C
U s e rs
\l s ta rn e s \D o c u m e n ts
\E -2
-2
Y
-V A
Y o rk
-V id e o S e c I m p ro v -T
N ls ta rn e s C
B U
M B
.r v t
3.T-102
BUILDING 3 FIRST FLOOR SECURITY
PLAN
8 26LAS
VIDEO SURVEILLANCE
SECURITY YORK
ALVIN C. YORK CAMPUS
3400 LEBANON ROAD
MURFREESBORO, TN 37129 JUNE 13, 2024
BID DOCUMENTS
626A4-22-10422-215
JVE
Scale: 1/8" = 1'-0"
BUILDING 3 FIRST FLOOR SECURITY PLAN
2 INSTALL NEW CAMERAS. PROVIDE NEW 4 PR
UTP CABLING FROM CAMERA TO NEW POE
SWITCH IN TELECOM ROOM. REPAIR/
REPLACE SURFACES AFFECTED BY CAMERA
EQUIPMENT INSTALLATION TO MATCH
SIMILAR/EXISTING CONDITIONS.
CONTRACTOR TO REPLACE DAMAGED
CEILING TILE AND GRID ASSOCIATED WITH
WORK AT NO ADDITIONAL COST TO
GOVERNMENT.
N O
R T
H
0 4 8 16
A. REFERENCE SHEET TS101 AND TS102 FOR
EXTERIOR CAMERA LOCATIONS.
B. ALL EXISTING CONDITIONS ARE BASED ON THE
BEST AVAILABLE INFORMATION AT THE TIME
OF SURVEY.
C. NEW CCTV CABLING TO BE RUN ON J-HOOKS 2'
OC ABOVE CEILING IN CORRIDORS.
D. ALL CONDUIT SHALL BE 3/4" MINIMUM.
ELECTRICAL CONTRACTOR TO SIZE CONDUIT.
PER THE MOST CURRENT EDITION OF THE NEC.
E. WHERE LENGTH FROM CAMERA TO RACK
EQUIPMENT EXCEEDS 295' (90M) CONTRACTOR
SHALL USE FIBER OPTIC CABLE.
F. COORDINATE AND CONFIRM ALL ROUTING
WITH COR PRIOR TO ROUGH-IN.
G. SEE SHEET G-100 FOR ICRA MEASURES.
H. USE MOBILE CONTAINMENT CART (6/G-100)
ALONG CORRIDORS.
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
TR ROOM G112A:
7 PR MMF
3 PR SMF1
N #80
H6 N #81
H6 N #82
H6 N #83
H6 N #84
H6 N #85
SW
N #87
RM 'G112A' RM 'G112A'
RM 'G112A'
RM 'G112A'
RM 'G112A'
RM 'G112A'
RM 'G112A'
H6SL
N #86
RM 'G112A'
RM 'G112A'
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/2
/2
:2
:5
P
M C
U s e rs
\l s ta rn e s \D o c u m e n ts
\E -2
-2
Y
-V A
Y o rk
-V id e o S e c I m p ro v -T
N ls ta rn e s C
B U
M B
.r v t
4.T-101
BULIDING 4 GROUND FLOOR SECURITY
PLAN
9 26LAS
VIDEO SURVEILLANCE
SECURITY YORK
ALVIN C. YORK CAMPUS
3400 LEBANON ROAD
MURFREESBORO, TN 37129 JUNE 13, 2024
BID DOCUMENTS
626A4-22-10422-215
JVE
Scale: 1/8" = 1'-0"
BUILDING 4 GROUND FLOOR SECURITY PLAN
1 REMOVE EXISTING CAMERAS AND CABLING
BACK TO SOURCE. REPAIR/REPLACE
EXISTING SURFACES AFFECTED BY
REMOVAL OF CAMERA EQUIPMENT TO
MATCH SIMILAR EXISTING CONDITIONS.
2 INSTALL NEW CAMERAS. PROVIDE NEW 4 PR
UTP CABLING FROM CAMERA TO NEW POE
SWITCH IN TELECOM ROOM. REPAIR/
REPLACE SURFACES AFFECTED BY CAMERA
EQUIPMENT INSTALLATION TO MATCH
SIMILAR/EXISTING CONDITIONS.
CONTRACTOR TO REPLACE DAMAGED
CEILING TILE AND GRID ASSOCIATED WITH
WORK AT NO ADDITIONAL COST TO
GOVERNMENT.
3 PROPOSED LOCATION OF NEW CISCO 9300
SWITCH AND PATCH PANEL. VERIFY
LOCATION WITH COR AND OIT
REPRESENTATIVE.
4 ROUTE MMF FROM TELECOM ROOM TO
RACKS IN BUILDING 5 SERVER ROOM.
NORTH
0 84 16
A. REFERENCE SHEET TS101 AND TS102 FOR
EXTERIOR CAMERA LOCATIONS.
B. ALL EXISTING CONDITIONS ARE BASED ON THE
BEST AVAILABLE INFORMATION AT THE TIME
OF SURVEY.
C. NEW CCTV CABLING TO BE RUN ON J-HOOKS 2'
OC ABOVE CEILING IN CORRIDORS.
D. ALL CONDUIT SHALL BE 3/4" MINIMUM.
ELECTRICAL CONTRACTOR TO SIZE CONDUIT.
PER THE MOST CURRENT EDITION OF THE NEC.
E. WHERE LENGTH FROM CAMERA TO RACK
EQUIPMENT EXCEEDS 295' (90M) CONTRACTOR
SHALL USE FIBER OPTIC CABLE.
F. COORDINATE AND CONFIRM ALL ROUTING
WITH COR PRIOR TO ROUGH-IN.
G. SEE SHEET G-100 FOR ICRA MEASURES.
H. USE MOBILE CONTAINMENT CART (6/G-100)
ALONG CORRIDORS.
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
| 22-215YELEC |
| Sheets |
| 2.T-101 - BULDING 2 GROUND FLOOR SECURITY PLAN |
| 3.T-101 - BUILDING 3 GROUND FLOOR SECURITY PLAN |
| 3.T-102 - BUILDING 3 FIRST FLOOR SECURITY PLAN |
| 4.T-101 - BULIDING 4 GROUND FLOOR SECURITY PLAN |
File details come from the government source that posted it. Updated .