This document package includes construction drawings and specifications for infrastructure upgrades at the St. Cloud Veterans Affairs Health Care System facility in Minnesota. The project involves renovating and expanding existing space to construct an Adult Day Health Care center, including electrical, data, telecommunications, security, and HVAC infrastructure upgrades. Work includes installing new and upgrading existing fiber optic cabling both within buildings and between campus buildings, as well as data center physical security enhancements. Hazardous materials abatement is also required. The contractor will furnish all labor, materials, tools and equipment necessary to complete the infrastructure improvements in accordance with the contract drawings and specifications.

View the file

Other files for this federal contract opportunity

Other files attached to Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud, newest first.
File Type Posted
Atch 41 - Construction Wage Rates - Stearns 7-29-22.pdf PDF
Atch 3 - Specifications Volume 3 - Asbestos addendum.pdf PDF
Atch 4 - General 1 of 2 addendum.pdf PDF
Atch 6 - BLDG 1 - 1 of 2 addendum.pdf PDF
Atch 8 - BLDG 2 addendum.pdf PDF
Atch 9 - BLDG 3 addendum.pdf PDF
Atch 12 - BLDG 6 addendum.pdf PDF
Atch 13 - BLDG 7 and 13 addendum.pdf PDF
Atch 27 - BLDG 96 addendum.pdf PDF
Atch 30 - BLDG 111 addendum.pdf PDF
Atch 31 - BLDG 112 addendum.pdf PDF
Atch 5 - General 2 of 2 addendum.pdf PDF
Atch 14 - BLDG 8 addendum.pdf PDF
Atch 15 - BLDG 9 addendum.pdf PDF
Atch 20 - BLDG 29 addendum.pdf PDF
Atch 22 - BLDG 49 addendum.pdf PDF
Atch 24 - BLDG 51 addendum.pdf PDF
Atch 25 - BLDG 54 and 69 addendum.pdf PDF
Atch 32 - BLDG 115 addendum.pdf PDF
OIT Design Requirements - St. Cloud - Backbone Cabling.zip ZIP file
Atch 10 - BLDG 4 addendum.pdf PDF
Atch 21 - BLDG 48 addendum.pdf PDF
36C77622B0035 0001.pdf PDF
36C77622B0035 - 6-9-22.pdf PDF
Atch 6 - BLDG 1 - 1 of 2.pdf PDF
Atch 16 - BLDG 10.pdf PDF
Atch 19 - BLDG 28.pdf PDF
Atch 22 - BLDG 49.pdf PDF
Atch 1 - Specifications Volume 1.pdf PDF
Atch 7 - BLDG 1 - 2 of 2.pdf PDF
Atch 12 - BLDG 6.pdf PDF
Atch 15 - BLDG 9.pdf PDF
Atch 18 - BLDG 14.pdf PDF
Atch 21 - BLDG 48.pdf PDF
Atch 25 - BLDG 54 and 69.pdf PDF
Atch 26 - BLDG 95 and 88.pdf PDF
Atch 28 - BLDG 108.pdf PDF
Atch 30 - BLDG 111.pdf PDF
Atch 32 - BLDG 115.pdf PDF
Atch 36 - Parking Structure.pdf PDF
Atch 40 - Limitations on Subcontracting - Construction.docx DOCX document
Atch 43 - Site Visit Instructions.pdf PDF
Atch 20 - BLDG 29.pdf PDF
Atch 4 - General 1 of 2.pdf PDF
Atch 5 - General 2 of 2.pdf PDF
Atch 8 - BLDG 2.pdf PDF
Atch 23 - BLDG 50.pdf PDF
Atch 24 - BLDG 51.pdf PDF
Atch 27 - BLDG 96.pdf PDF
Atch 31 - BLDG 112.pdf PDF
Show all 50

Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXISTING FIBER - INSIDE

VFY EXIST

EXISTING FIBER - OUTSIDE

VFY EXIST

FIBER ROUTE - INSIDE

SEE TELECOM

FIBER ROUTE - OUTSIDE

SEE CIVIL

BUILDING OUTLINE

VFY EXIST

CORRIDOR OUTLINE

VFY EXIST

LEGEND

TO 8TH ST WEST ONLYTO 8TH ST EAST & WEST

44TH AVE.

TRAIL 1

TRAIL 2

TRANSFER

SWITCH

CAPACITOR

BANK (3)

SWITCH

(2)

15KV

MAIN

SW

BATT

35 KV

TO

15 KV

TRANSFORMER

35KV

FUSED

SWITCH

METER 35KV

SWITCH

GRAVEL

GRAVEL

GRAVEL

EXISTING

ROAD

CHAIN LINK FENCE

CHAIN LINK FENCE

16' GATE

GRAVEL

ELECTRICAL

SUBSTATION

G E N E R A T O R

FUEL LINES

CONDU ITS TO TU NNEL

M V

D U

C T

B A

N K

1 1 2 W

PHARMACY ADDITION

11 2 E

G E N E R A T O R

B

CORRIDOR LINK

A

C T

TR

A

IL

ER

174 s .f.

256 s .f.

185 s .f.

149 s ..f.

155 s .f.

104 s .f.

70 s. .f .

72 s .f.

110 s .f.

276 s .f.

112 s .f.

99 s .f.

57 s .f.

146 s .f.

434 s .f.

R A

MP

U P

1:

M A X

R A

MP

U P

1:

M A X

RA

M P

UP

1:2 0 M

AX

TRANSFER

SWITCH

CAPACITOR

BANK (3)

SWITCH

(2) 15KV

MAIN

SW

BATT

35 KV

TO

15 KV

TRANSFORMER

35KV

FUSED

SWITCH

METER 35KV

SWITCH

.3

TRANSFORMER

BUILD ING

#91

5,000 GAL.

UNDERGROUND

DIESEL FUEL TANK

EXISTIN G G AS SU P P LY EQ U IP M EN T TO R EM AIN

O P ER ATIO N AL DU R IN G D EM O LITIO N AN D N EW

C O N STR U C TIO N. P R O TEC T EQU IP M EN T AN D

P IP ELIN ES IN AC C O R D AN C E W ITH G AS SU P P LIER 'S

R EC O M M EN D ATIO N S

N EW G AS SU P P LY M AIN

IN TO B U ILD IN G

SP AR E

P H O N E LIN E

EXTEN D S TO

E XISTIN G

P H O N E IN

B O ILER R O O M

P ER P LAN .

SP AR E

P H O N E

LIN E TO

M ETER

TU N N EL

E XTEN D S

A D D ITIO N AL

2'- 0" U N D ER

B U ILD IN G

FUEL LINE

VENT LINE

1,000 GAL.

UNDERGROUND

DIESEL FUEL

TANK

1,000/5,000 GAL.

UNDERGROUND

DIESEL FUEL TANK

1,000 GAL.

UNDERGROUND

DIESEL FUEL TANK

1,000 GAL.

UNDERGROUND

DIESEL FUEL TANK

S 1

LIG H T

N EW G AS SU P P LY

(C O O R D IN ATE W ITH SU P P LIER )

12"D

10"D

"D

TP TP

EXIST. BUILDING

EXIST.

BUS STOP

CC

L O

O P

16"

20"

12"

3"

8"

DN

0.

0’

BIRDCAGE

B

IR

D C

A G

E

NSP ELECTRICAL

FOR HWY DEPT

T101

I.T.

CHILLER

C O

NC

. B

LO

CKS

PAT

I O

C O

NC

. B

LO

CKS

PAT

I O

C O

NC

. B

LO

CKS

PAT

I O

C O

NC

. B

LO

CKS

PAT

I O

C O

NC

. B

LO

CKS

PAT

I O

C O

NC

. B

LO

CKS

PAT

I O

C O

NC

. B

LO

CKS

PAT

I O

C O

NC

. B

LO

CKS

PAT

I O

VESTIBULE

DN

DN

DN

FD

DN

F B

F

B

F B

F

B

F B

F

B

SOUTH

VESTIBULE

PASS

THROUGH

LINK TO

BUILDI NG 51

6 3. 32 56

1 13 5. 35 78

PARKING

NO

PARKING

93 49

37 6

109 5

1A

S M

O K

E B

L D

G

SMOKE

BLDG

SMOKE

BLDG

S M

O K

E B

L D

G

SMOKE

BLDG

M.H.

STOR.

SMOKE

BLDG

SMOKE

BLDG

SMOKE

BLDG

SMOKE

BLDG

SMOKE

BLDG

STOR.

BIO-

HAZ.

SAUK RIVER

GP

HOLDING POND

ADHC

I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly Licensed Architect under the laws of the State of

Minnesota.

Name:

Date: License Number: MN# 18157

Typed or Printed Name: Tom Olesak

OWNER AND

CONSULTANTS:

CONTACT:

ADDRESS:

MIKE ENGMARK

ST CLOUD VA MEDICAL CENTER

4801 VETERANS DRIVE

ST. CLOUD, MN 56303

NAME:

ADDRESS:

CONTACT:

ADVANCED STRUCTURAL TECHNOLOGIES

7301 OHMS LANE; SUITE 215

EDINA, MN 55439

ZACHARY CRAIG

PHONE:

NAME:

ADDRESS:

CONTACT:

SPECIALIZED ENGINEERING SOLUTIONS

10360 ELLISON CIRCLE

OMAHA, NE 68134

KRIS BURNHAM

PHONE: 402-991-5520

NAME:

ADDRESS:

CONTACT:

PHONE:

NAME:

ADDRESS:

CONTACT:

PHONE:

NAME:

ADDRESS:

CONTACT:

PHONE:

ANDERSON ENGINEERING OF MN, LLC

13605 1ST AVE NORTH, SUITE 100

PLYMOUTH, MN 55441

IAN WEBER

763-412-4000

ARCHITECT:

ANDERSON ENGINEERING OF MN, LLC

13605 1ST AVE NORTH, SUITE 100

PLYMOUTH, MN 55441

EDWARD MARKFORT

763-412-4000

952-854-9302

SPECIALIZED ENGINEERING SOLUTIONS

10360 ELLISON CIRCLE

OMAHA, NE 68134

KRIS BURNHAM

402-991-5520

No DATEREVISION

DRAWING TITLE

CHECKED BY

ST.CLOUD, MN 56303

VA MEDICAL CENTER

BUILDING No

LOCATION

DRAWING NO.DRAWN

DWG. OF

PROJECT TITLE

PLOT SCALE

PROJECT NO.

COVER

DATE:

APPROVED: APPROVED: PROJECTS SECTION MANAGER

APPROVED: OIT MANAGER DATE: APPROVED: ASSISTANT CHIEF ENGINEER DATE:

APPROVED: SAFETY MANAGER

APPROVED: CHIEF OF POLICE

APPROVED: PATIENT SAFETY

DATE:

DATE:

DATE: APPROVED: EMS MANAGER

APPROVED: M/O MANAGER

DATE:

DATE:

DATE:DATE:

APPROVED: MEDICAL CENTER DIRECTOR

APPROVED: PROJECT COR DATE:

APPROVED: INFECTION CONTROL NURSE DATE:

APPROVED: SERVICE LINE DIRECTOR

APPROVED: GEMS COORDINATOR DATE:

DATE:

APPROVED: NURSE EXECUTIVE

APPROVED: CHIEF OF STAFF DATE:

APPROVED: DIRECTOR FMS

APPROVED: ASSOCIATE DIRECTOR

DATE:

DATE:

DATE:

DATE:APPROVED: DATE:

APPROVED: DATE:

APPROVED: DATE:

Main Campus, St. Cloud, Minnesota St. Cloud VA Health Care System

N

CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP

FULLY

SPRINKLERED

VICINITY MAP:

A

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PHONE: 320-252-1670

CIVIL ENGINEER:

VA COR:

TELECOMMUNICATIONS ENGINEER:

CONTACT:

ADDRESS:

JONATHAN WEST

ST CLOUD VA MEDICAL CENTER

4801 VETERANS DRIVE

ST. CLOUD, MN 56303

PHONE: 504-250-2699

PROGRAM MANAGER:

EMAIL: Jonathan.West@vciint.com

STRUCTURAL ENGINEER:

MECH/ELEC/PLUMB/FIRE ENGINEER:

C

U s e rs

\P u b li c \D o c u m e n ts \R e v it

P ro je c ts

\1 -C

O N

S T

R U

C T

A D

H C

-R E

M a rk fo rt

.r v t

/2

/2

:5 :1

P

M

FB1-GI000

CONSTRUCT ADULT DAY

HEALTH CARE COVER SHEET

& SHEET INDEX

EHRM INFRASTRUCTURE

UPGRADES

656‐21‐235

03/30/2022

EM EM

16305

CONSTRUCT ADHC - EHRM INFRASTRUCTURE UPGRADES

FB#1

03/30/2022

0APPROX 150' 300'75'

SHEET INDEX - ADHC

ADHC SHEET TITLE

FB1-GI000 CONSTRUCT ADULT DAY HEALTH CARE COVER SHEET & SHEET INDEX

FB1-AS110 FIRST FLOOR - OVERALL PLAN

SEE CAMPUS SHEETS FOR ADDITIONAL INFORMATION

ROOM SCHEDULE

NO. NAME C

A

B

LI

N G

P A

T C

H P

A N

E L

F

IB

E R

P O

W E

R

B O

N D

IN

G

U P

S

D E

D

IC

A T

E D

C O

O

LI

N G

T E

M P

E R

A T

U R

E

H U

M

ID

IT

Y

R A

C K

S E

N S

O R

S P

A C

E

AREA

WIDTH

(FT)

LENGTH

(FT) REMARKS

FIRST FLOOR

PLACEHOLDER ADHC 10 SF SEE TELECOM DRAWINGS

HAZARDOUS MATERIAL SCHEDULE

LEVEL

ROOM

NO. ROOM NAME

QUESTIONABLE HAZARDOUS

ELEMENT POSSIBLE ABATEMENT ACTION

FIRST FLOOR PLACEHOLDER ADHC NONE NONE

HAZARDOUS MATERIALS MAY BE ENCOUNTERED THROUGHOUT THE DISTRIBUTION ROUTING THROUGH CEILING PLENUMS AND UTILITY TUNNELS. INSTALLATION OF DISTRIBUTION SHALL NOT

DISTURB QUESTIONABLE HAZARDOUS MATERIAL.

LEAK PREVENTION / DIVERTER SCHEDULE

LEVEL

ROOM

NO. ROOM NAME OVERHEAD LEAK DIVERTER AND DRAIN PIPING LEAK PREVENTION BARRIER WATERPROOFING

FIRST FLOOR PLACEHOLDER ADHC

SEE GENERAL NOTES SHEET FOR DETAIL. MWP = MEMBRANE WATERPROOFING. MASONRY = FLUID-APPLIED WATERPROOFING. INT = INTERIOR. EXT = EXTERIOR

ICRA PHASE CONSTRUCTION ROOM SCHEDULE

LEVEL

ROOM

NO. ROOM NAME

CAI BLDG NAME /

FUNCTION

CONSTRUCTION

PROJECT ACTIVITY

INFECTION CONTROL

RISK GROUP

CONTROL

PROCEDURE CLASS SECTION

CONSTRUCTION ZONE /

OCCUPIED CONSTR

DAY /

NIGHT

FIRST FLOOR PLACEHOLDER ADHC ADHC WEST OCCUPIED CONSTRUCTION NIGHT

SEE GENERAL NOTES SHEET FOR CONSTRUCTION INFECTION CONTROL RISK ASSESSMENT (ICRA) DESCRIPTIONS. TYPE, GROUP AND CLASS SELECTED TO BEST OF DESIGN TEAM'S KNOWLEDGE.

FINAL DETERMINATION BY THE VA WILL BE MADE AT A LATER DATE.

TYP.

AREA OF

FUTURE STAIR #2

UPDN

A H

U

BATHING RR #2

126A

MECHANICAL

STAFF RR

STAIR #1

MALE STAFF

LOCKERS

KITCHENETTE

MEDICATION

ROOM

OFFICE SUPPLY

STORAGE

NURSE WORK

AREA

ADHC

ENCOUNTER #1

ADHC

ENCOUNTER #2

ADHC

ENCOUNTER #3

ADHC

TOILET #1

119A

ADHC

TOILET #2

ADHC

TOILET #3

ADHC

TOILET #4

ADHC

TOILET #5

ADHC

TOILET #6

ADHC

TOILET #7

ADHC

TOILET #8

UNISEX

RESTROOM

CLEAN

SUPPLY

ADHC

CORRIDOR

C130

OXYGEN

STORAGE

CLEAN

LINEN

LAUNDRY

SOILED

HOLDING

MULTIPURPOSE

ROOM

HSKP

CORRIDOR

C112

SCOOTER

STORAGE

WHEELCHAIR

STORAGE

RECEPTION

WORKSTATION

COAT

STORAGE

CORRIDOR

C100

BATHING

ROOM #1

BATHING

ROOM #2

VESTIBULE

BATHING RR #1

127A

CART

HOLDING

141B

SCALE

ALCOVE

141A

DINING/

ACTIVITY AREA

PROGRAM SUPPLY

EQUIP. RM

EQUIP ALCOVE

C129

ENGINEERING

UTILITY

PARTICIPANT

QUIET RM

ELEC.

ROOM

EXERCISE ROOM

FEMALE STAFF

LOCKERS

STAFF

LOUNGE

FUTURE

ELEVATOR

#2

FUTURE

ELEVATOR

#1

DATA

ROOM

MULTIPURPOSE

STORAGE

128B

TREATMENT

ROOM

ADHC

CORRIDOR

C130

CORRIDOR

C112

I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly Licensed Architect under the laws of the State of

Minnesota.

Name:

Date: License Number: MN# 18157

Typed or Printed Name: Tom Olesak

No DATEREVISION

DRAWING TITLE

CHECKED BY

ST.CLOUD, MN 56303

VA MEDICAL CENTER

BUILDING No

LOCATION

DRAWING NO.DRAWN

DWG. OF

PROJECT TITLE

PLOT SCALE

PROJECT NO.

DATE:

CONSULTANT ARCHITECT/ENGINEER OF RECORD STAMP

FULLY

SPRINKLERED

A

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10 C

U s e rs

\P u b li c \D o c u m e n ts \R e v it

P ro je c ts

\1 -C

O N

S T

R U

C T

A D

H C

-R E

M a rk fo rt

.r v t

/2

/2

:5 :2

P

M

FB1-AS110

FIRST FLOOR - OVERALL PLAN

EHRM INFRASTRUCTURE

UPGRADES

656‐21‐235

03/30/2022

EM EM

16305

FB#1

03/30/2022

N

0 4' 8'2'

FL20 TELECOM EQUIPMENT, SEE TELECOM DRAWINGS.

1/8" = 1'-0"

FIRST FLOOR - OVERALL PLAN

_SHEET NOTES

1. SEE GENERAL NOTES AND CAMPUS DRAWINGS FOR GENERAL

INFORMATION, LIFE SAFETY, ICRA, AND PHASING

2. ALL EXISTING CONDITIONS MUST BE FIELD VERIFIED BY THE

CONTRACTOR PRIOR TO DEMOLITION OR CONSTRUCTION. EXISTING

CONDITIONS THAT DIFFER FROM THOSE SHOWN MUST BE BROUGHT TO

THE ATTENTION OF THE C.O.R. TO INFORM THE ARCHITECTS AND

ENGINEERS.

3. THE INFORMATION SHOWN ON THE DRAWINGS IS BASED ON DRAWINGS

AND PHOTOGRAPHS PROVIDED BY THE C.O.R. COMBINED WITH

OBSERVATIONS AND SURVEYED DATA FROM THE ARCHITECTS AND

ENGINEERS.

4. SEE CIVIL, STRUCTURAL, TELECOM, ELECTRICAL, MECHANICAL, AND

PLUMBING DRAWINGS AND SPECIFICATIONS FOR ADDITIONAL

DEMOLITION AND CONSTRUCTION REQUIREMENTS.

5. PORTABLE FIRE EXTINGUISHERS (CO2 OR HALOGENATED TYPE AS

DETERMINED BY THE VA) WITH WALL MOUNT BRACKET AND CODE

REQUIRED SIGNAGE SHALL BE PROVIDED BY THE CONTRACTOR WITHIN

TELECOM ROOMS.

File details come from the government source that posted it. Updated .